You are on page 1of 6

Activity ID

Activity Description

Orig Dur

Early Start

Early JANF M A M Finish

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

MILESTONES
MILESTONES
MS00010 MS00020 MS00030 MS00050 MS00070 MS00090 MS00100 MS00140 MS00150 MS00160 MS00170 MS00180 ZERO DATE RELIABILITY RUN COMPLETION (CCPP) START OF CIVIL WORKS GT/GTG & AUX. FOUNDATION COMPLETION HRSG & AUX FOUNDATION COMPLETION GTG/ STG BLDG READINESS FOR ERN START STG DECK READINESS GT/GTG ERECTION START GT ERECTION COMPLETION GT RACHETING GT FSNL GT SYNCRONISATION HRSG ERECTION START HRSG DRUM LIFTING (HP+LP+IP) HRSG HYDRO TEST HRSG ERN COMPLETION PRE BOILER SYSTEM FLUSHING HRSG GAS IN EDTA CLEANING STEAM BLOWING START STEAM BLOWING & SVF COMPLETION CONDENSER ERECTION START ST ERECTION START STG BOX UP ST OIL FLUSHING STG BARRING GEAR STG SYNCHRONISATION 0 23JAN08 0 0 11AUG08 0 0 0 08MAY09 0 0 23JUN09 0 0 0 0 0 23NOV08 0 0 0 0 0 0 0 25FEB10 0 0 23MAY09 0 23JUN09 0 0 0 0 15JAN10 14FEB10 22FEB10 23MAR10 10MAR10 22SEP09 22NOV09 21JAN10 06FEB10 10FEB10 17FEB10 23DEC09 23JAN10 10FEB10 23FEB10 12MAY09 12APR09 07JAN09 22APR10

CIVIL WORKS

GAS TURBINE

HRSG
MS00190 MS00200 MS00210 MS00220 MS00230 MS00240 MS00250 MS00260 MS00270

STG
MS00280 MS00290 MS00300 MS00310 MS00320 MS00340

CIVIL WORKS
CIVIL WORKS
CVL00001 CVL00003 CVL00005 CVL00010 CVL00020 CVL00040 CVL00050
Start Date Finish Date Data Date Run Date

SPEC PREP, TENDERING AND ORDERING OF CIVIL WORKS SITE MOBILISATION AND START OF CIVIL WORKS GTG/ STG BUILDING PILING & FOUNDATION GTG/STG BLDG STR- FABRICATION GTG/STG BLDG SUPER STR, CIVIL, ARCH,FINISH WORKS GT - GTG & AUX PILING & FOUNDATIONS ST - STG PILING & FOUNDATION
23JAN08 22APR10 23JAN08 22JUL08 16:08 Early Bar Progress Bar Critical Activity

140 08MAR08 16 26JUL08 195 31AUG08 210 10OCT08 410 09NOV08 210 15SEP08 150 15SEP08
HZL2

25JUL08 10AUG08 13MAR09 07MAY09 23DEC09 12APR09 11FEB09


Sheet 1 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID CVL00060 CVL00070 CVL00080 CVL00090 CVL00100 CVL00110 CVL00120 CVL00130 CVL00140 CVL00150 ST - STG DECK SLAB

Activity Description HRSG & AUX FDN AND STEEL STACK PILING & FDN OTHER MAJOR EQPMNT PILING & FDN ALL AUX FACILITIES/ BLDG INCL. CONTROL BLDG TRFO YARD, FENCING, OWS ETC RW,CWPH, FOREBAY, CW DUCT, DM TANK CVL WORKS PIPE/CABLE RACKS FOUNDATIONS PIPE/CABLE RACK STRUCTURAL FAB AND ERECTION GEN CIVIL WORKS - PLANT ROADS, DRAIN, FENCING SWITCHYARD CIVIL WORKS

Orig Dur

Early Start

Early JANF M A M Finish 12MAY09 07JAN09 25JUN09 17DEC09 04SEP09 03NOV09 01AUG09 04SEP09 26FEB10 16DEC09

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

90 12FEB09 150 11AUG08 229 09NOV08 404 09NOV08 300 09NOV08 360 09NOV08 266 09NOV08 270 09DEC08 400 23JAN09 310 10FEB09

GAS TURBINE
GAS TURBINE
GT00010 GT00020 GT00030 GT00040 GT00050 GT00060 GT00070 GT00080 GT00090 GT00100 GT00110 GT00120 GT00170 GT00180 GT00190 GT00200 GT00210 GT00220 GT00230 GT00240 GT00250 GT00260 GT0275 GT00270 GT00280 GT00290 GT INDENTING & PO PLACEMENT GT ENGG DOCUMENTATION RELEASE GT PROCUREMENT & SITE DELIVERY GT ERECTION GTG STATOR ENGG,MFG & SUPPLY GTG ROTOR ENGG, MFG, & SUPPLY GTG COMPLETING ASSY ENGG, MFG & SUPPLY GTG AUX SYSTEMS ENGG,MFG & SUPPLY GTG PIPING ENGG,MFG & SUPPLY GT GENERATOR ERECTION INC ALIGNMENT OIL FLUSHING & NORMALISATION GT/ GTG PRECOMMISSIONING/ COMMNG. GT AUXILIARIES PO PLACEMENT GT AUX PROCUREMENT & SITE DELIVERY EXHT FRAME BLOWER ERECTION AIR PROCESSING SKID & PIPING INLET AIR DUCT ERECTION INLET AIR FILTER ERECTION VENT FANS INCL. DUCTING BLOWER & VENT FANS CABLING EXPANSION BELLOWS ERECTION EXHAUST DUCT ERECTION FUEL GAS SYSTEM ERECTION GTG HYDROGEN COOLERS & PIPING ERECTION GTG SEAL OIL SYSTEM ERECTION GTG HYDROGEN GAS COOLING SYSTEM ERECTION 91 23JAN08 90 23FEB08 425 23APR08 184 23JUN09 404 23APR08 404 23APR08 434 23APR08 434 23APR08 404 23APR08 184 23JUN09 30 24DEC09 62 24DEC09 180 24APR08 335 23JUL08 31 23JUN09 20 23JUN09 60 23JUN09 60 22AUG09 30 23JUN09 15 23JUL09 15 23JUL09 30 24AUG09 90 24AUG09 62 24JUL09 62 24JUL09 60 24AUG09 22APR08 22MAY08 21JUN09 23DEC09 31MAY09 31MAY09 30JUN09 30JUN09 31MAY09 23DEC09 22JAN10 23FEB10 20OCT08 22JUN09 23JUL09 12JUL09 21AUG09 20OCT09 22JUL09 06AUG09 06AUG09 22SEP09 21NOV09 23SEP09 23SEP09 22OCT09

GAS TURBINE AUX

GENERATOR AUX

HRSG
HRSG SUPPLY & ERECTION
SG00010
Start Date Finish Date Data Date Run Date

FDN & STRUCT MTL ENGG, PROC, MFG & SUPPLY


23JAN08 22APR10 23JAN08 22JUL08 16:08 Early Bar Progress Bar Critical Activity

610 23JAN08
HZL2

23SEP09
Sheet 2 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID SG00020 SG00030 SG00040 SG00050 SG00060 SG00070 SG00080 SG00090 SG00110 SG00120 SG00130 SG00140 SG00150 SG00160 SG00170 SG00180 SG00190 SG00200 SG00210 SG00220 SG00230 SG00250 SG00260 SG00280 SG00290 SG00300

Activity Description CHIMNEY ENGG, PROC, MFG & SUPPLY DRUM - LP, IP, HP ENGG, PROC,MFG & SUPPLY MODULES ENGG, PROC, MFG & SUPPLY MODULE LINKS & COMP ENGG, PROC, MFG & SUPPLY DUCT ENGG, PROC, MFG & SUPPLY CASING & SUPP ENGG, PROC, MFG & SUPPLY TANKS, PIPING & FINE FITTINGS ENGG, PROC, MF LINING & INSULATION ENGG, PROC, MFG & SUPPLY COLUMNS, BEAMS & BRACING ERECTION CASING STRUCTURES ERECTION PLATFORMS,GALLARIES STAIRWAYS ERECTION CASING, FIXING COMPONENTS & OUTER CASING MODULES ERECTION PRESSURE PARTS ERECTION TRIM PIPING INLET DUCT ERECTION OUTLET DUCT ERECTION INSULATION OF PR. PARTS & TRIM PIPING INLET DUCT INSULATION OUTLET DUCT INSULATION STEEL STACK (CHIMNEY) ERECTION HRSG HYDRO TEST PRE BOILER SYSTEM FLUSHING EDTA CLEANING STEAM BLOWING & SVF HRSG COMMISSIONING

Orig Dur

Early Start

Early JANF M A M Finish 26JUL09 24AUG09 24AUG09 24AUG09 23SEP09 23SEP09 23OCT09 22NOV09 22JAN09 23MAR09 03NOV09 09OCT09 23SEP09 23OCT09 22NOV09 23OCT09 23OCT09 21JAN10 21JAN10 21JAN10 22AUG09 22NOV09 06FEB10 17FEB10 10MAR10 22MAR10

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

520 23FEB08 520 23MAR08 520 23MAR08 520 23MAR08 550 23MAR08 550 23MAR08 430 20AUG08 460 20AUG08 61 23NOV08 60 23JAN09 285 23JAN09 230 22FEB09 184 24MAR09 122 24JUN09 60 24SEP09 150 27MAY09 120 26JUN09 60 23NOV09 60 23NOV09 60 23NOV09 243 23DEC08 15 08NOV09 16 22JAN10 7 11FEB10 14 25FEB10 60 22JAN10

STEAM TURBINE
ST- STG SUPPLY & ERECTION
STG00010 STG00020 STG00030 STG00040 STG00050 STG00060 STG00070 STG00080 STG00090 STG00100 STG00110 STG00120 STG00130 STG00140 STG00150 STG00160
Start Date Finish Date Data Date Run Date

ST ENGG, PROC, MFG & SITE DELIVERY TG INT. PPG ENGG, PROC, MFG & SUPPLY JACKING, LUB OIL PUMPS, BYPASS SYS SITE DELIVERY STG ENGG, PROCUREMENT & SITE DELIVERY HEAT EXCHANGERS ENGG, PROC, MFG & SUPPLY BFP/CEP/CWP/ACW/ECW/RSW PUMPS SUPPLY ST/ STG AUX ENGG, PROC, & SITE DELIVERY HP PIPING ENGG, PROCUREMENT, MFG & SUPPLY LP PIPING ENGG, PROCUREMENT, MFG & SUPPLY RE JOINTS, B/F VALVES ENGG,PROC, MFG & SUPPLY FLASH TANK/ MISC TANKS ENGG, PROC, MFG & SUPPLY ST CONDENSER ERECTION ST & AUX ERECTION STG & AUX ERECTION TG INTEGRAL PIPING ERECTION HP PIPING ERECTION
23JAN08 22APR10 23JAN08 22JUL08 16:08 Early Bar Progress Bar Critical Activity

486 23FEB08 486 23FEB08 486 23FEB08 486 23FEB08 486 23FEB08 486 23FEB08 486 23FEB08 486 24MAR08 486 23APR08 486 23APR08 455 23APR08 214 23MAY09 206 23JUN09 145 23AUG09 90 21SEP09 174 23JUL09
HZL2

22JUN09 22JUN09 22JUN09 22JUN09 22JUN09 22JUN09 22JUN09 22JUL09 21AUG09 21AUG09 21JUL09 22DEC09 14JAN10 14JAN10 19DEC09 12JAN10
Sheet 3 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID STG00170 STG00180 STG00190 STG00210 STG00220 STG00230 STG00240 LP PIPING ERECTION

Activity Description PUMPS ERECTION & COMMNG RE JOINTS, B/F VALVES, TANKS ERECTION STG OIL FLUSHING OIL SYSTEM NORMALISATION & TG ON BARRING GEAR STG ROLLING, TESTING & SYNCHRONISATION STABILISATION & RELIABILITY RUN IN CC MODE

Orig Dur

Early Start

Early JANF M A M Finish 12JAN10 20JAN10 08JAN10 14FEB10 22FEB10 23MAR10 22APR10

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

174 23JUL09 210 25JUN09 170 23JUL09 30 16JAN10 8 15FEB10 4 20MAR10 30 24MAR10

ELECTRICAL & C&I


00EL
EL00090 EL00100 EL00110 EL00115 EL00120 EL00130 EL00140 EL00150 EL00160 EL00170 HRSG ELECTRICAL & C&I ENGG,PROC,MFG & SUPPLY GT/GTG ELECT & C&I ENGG, PROC, MFG & SUPPLY ST/STG ELECT & C&I ENGG, PROC, MFG & SUPPLY DCS ENGG, PROC, MFG & SUPPLY DG SET ENGG, PROCUREMENT, MFG & SUPPLY TRANSFORMERS ENGG, PROC, MFG & SUPPLY BUSDUCT ENGG, PROC, MFG & SUPPLY HT/LT MOTORS ENGG, PROC, MFG & SUPPLY HT SWITCHGEAR ENGG, PROC, MFG & SUPPLY SWITCHYARD EQUIPMENTS ENGG, PROC, MFG & SUPPLY ELECT & C & I ERECTION FOR HRSG ELECT & C & I ERECTION FOR GT/GTG & AUX. ST/STG ELECT & C&I ERECTION DG SET ERECTION TRANSFORMER ERECTION BUSDUCT ERECTION HT/LT MOTORS ERECTION HT SWITCHGEAR ERECTION & COMMNG SWITCHYARD ERECTION & COMMISSIONING 430 23OCT08 434 23APR08 486 23APR08 365 21AUG08 430 23APR08 455 23APR08 455 23APR08 434 22JUL08 456 23APR08 365 23JUN08 210 25MAY09 210 25MAY09 184 23JUL09 180 27JUN09 120 22JUL09 120 22JUL09 150 22JUN09 210 24APR09 180 23JUN09 26DEC09 30JUN09 21AUG09 20AUG09 26JUN09 21JUL09 21JUL09 28SEP09 22JUL09 22JUN09 20DEC09 20DEC09 22JAN10 23DEC09 18NOV09 18NOV09 18NOV09 19NOV09 19DEC09

01EL
EL00010 EL00020 EL00030 EL00040 EL00050 EL00060 EL00070 EL00080 EL00180

BOP PACKAGES
01BO
BOP00010 BOP00011 BOP00013 BOP00014 BOP00015 BOP00020 BOP00021 BOP00022 BOP00023 BOP00024 BOP00030 BOP00031
Start Date Finish Date Data Date Run Date

GTG/STG HALL EOT CRANE HALL BASIC ENGG GTG/STG HALL GTG/STG HALL ORDERING GTG/STG HALL EOT CRANE VENDOR ENGG GTG/STG HALL EOT CRANE MFG, INSP & DELY AT SITE GTG/ STG EOT CRANE ERECTION & COMMNG CWPH EOT CRANE BASIC ENGG CWPH EOT CRANE ORDERING CWPH EOT CRANE VENDOR ENGG CWPH EOT CRANE MFG, ISNPN & DELY AT SITE CWPH EOT CRANE ERECTION & COMMNG RW PTP BASIC ENGG RW PTP ORDERING
23JAN08 22APR10 23JAN08 22JUL08 16:08 Early Bar Progress Bar Critical Activity

92 23MAR08 92 23JUN08 91 23SEP08 121 23DEC08 61 23APR09 123 23MAY08 91 23SEP08 121 23DEC08 151 23JAN09 92 23JUN09 123 23MAY08 91 23SEP08
HZL2

22JUN08 22SEP08 22DEC08 22APR09 22JUN09 22SEP08 22DEC08 22APR09 22JUN09 22SEP09 22SEP08 22DEC08
Sheet 4 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID BOP00032 BOP00033 BOP00034 BOP00090 BOP00091 BOP00092 BOP00093 BOP00094 BOP00100 BOP00160 BOP00220 BOP00290 BOP00300 BOP00360 BOP00430 BOP00440 BOP00500 BOP00560 BOP00620 BOP00640 BOP00650 BOP00660 BOP00670 BOP00680 BOP00690 BOP00700 BOP00710 BOP00720 BOP00730 BOP00740 BOP00760 BOP00780 BOP00790 BOP00800 BOP00810 BOP00820 BOP00830 BOP00850 BOP00870 BOP00880 BOP00890 BOP00920 BOP00930 BOP00960
Start Date Finish Date Data Date Run Date

Activity Description RW PTP VENDOR ENGG RW PTP MFG,INSP & DELY AT SITE RW PTP ERECTION & COMMNG MISC TANKS(SITE FAB) BASIC ENGG MISC TANKS ORDERING MISC TANKS VENDOR ENGG MISC TANKS MFG, INSP & DELY AT SITE MISC TANKS CIVIL WORKS, FDN & INSTALLATION CW CHEM TREAT SYS ENGG, PROC, MFG, SUPP, E & C COMPR AIR SYS ORDER,VEND ENGG,PROC,MFG,SUPP, E&C AC SYS ORDER, VENDOR ENGG, PROC, MFG, SUPP, E&C ETP ORDER,VENDOR ENGG,PROC,MFG,SUPP,CVL W, E&C FIRE PROT SYS ORDER,VEN ENGG,PROC,MFG,SUPP,E&C VENT SYS ORDER, VENDOR ENGG,PROC,MFG,SUPP, E&C CHLORIN.SYS ORDER,VEN ENGG,PROC,MFG,SUPP, E&C CT ORDER, VEN ENGG, CVL WORK, PROC,MFG,SUPP, E&C STP ORDER,VEN ENGG,PROC,MFG,SUPP,CVL WORKS, E&C ELEVATORS ORDER,V ENGG,PROC,MFG,SUPP, E & C MISC CRANES,HOISTS ETC, ENGG,PROC, SUPP & E&C LP VALVES ORDER,VEN ENGG,PROC,MFG,SUPP, E & C STEAM TRAPS ORDER,VEN ENGG,PROC,MFG,SUPP, E & C AIR TRAPS ORDER,VEN ENGG,PROC,MFG,SUPP, E & C ME BELLOWS ORDER,VEN ENGG,PROC,MFG,SUPP, E & C THERM.INSULN.ORDER,VEN ENGG, PROC,MFG, SUPP, E&C PH EXCH.ORDER,VEN ENGG,PROC,MFG,SUPP, E&C SELF CLEANING FILTERS ORDER,V ENGG,MFG,SUPP,E&C MISC PUMPS(H/V) ORDER,VEN ENGG,PROC,MFG,SUPP,E&C SUMP/SUBM.PUMP ORDER,VEN ENGG,PRC,MFG,SUPP,E&C LT SWGR/BD/NGR ORDR,VEN ENGG,PROC,MFG,SUPP,E&C HT XLPECABLE ORDER,VEN ENGG,PROC,MFG,SUPP, E & C LT XLPE POWER,CONTROL,C&I CABLES ORDER,SUPP, E&C DC BATTERIES & CHARGERS ORDER,ENGG,MFG,SUPP, E&C BELOW GND EARTHING ORDER,ENGG,MFG,SUPPLY, E & C FIRE SEALING SYSTEM ORDER,V ENGG,MFG,SUPP, E&C STN LIGHTING SYS ORDER,V ENGG,MFG,SUPP, E&C EARTHING & LIGHTING SYS ORDER,VENGG,MFG,SUPP,E&C CABLE TRAYS & SUPP. ORDER,VEN ENGG,MFG,SUPP, E&C TERMN.KITS,TRAFL CLAMPS ORDR,V.ENGG,MFG,SUPP,E&C PA SYSTEM ORDER,VEN ENGG,PROC, MFG, SUPP, E & C CONTROL VALVES ORDER,VEN ENGG,PROC,MFG,SUPP, E&C FLOW ELEMENTS ORDER,V ENGG,PROC,MFG,SUPP, E&C GEN.CKT.BRKR ORDER,VEN ENGG,PROC,MFG,SUPP, E&C AUX OIL FILLED TRANSF.ORDER,V ENGG,MFG,SUPP, E&C PLC CONTRL PANEL ORDER,V ENGG,PROC,MFG,SUPP,E&C
23JAN08 22APR10 23JAN08 22JUL08 16:08 Early Bar Progress Bar Critical Activity

Orig Dur

Early Start

Early JANF M A M Finish 22APR09 22JUL09 22OCT09 22AUG08 22JAN09 23JUL09 22OCT09 20NOV09 03NOV09 20NOV09 22JAN10 19DEC09 19JAN10 19JAN10 03NOV09 13DEC09 22JAN10 12JAN10 12JAN10 22OCT09 22NOV09 22NOV09 22NOV09 21JAN10 23OCT09 22OCT09 20JAN10 20JAN10 22JAN10 22JAN10 22JAN10 23DEC09 19FEB09 20FEB10 16MAR10 22JAN10 23NOV09 21JAN10 21DEC09 22OCT09 22OCT09 21JAN10 21JAN10 21DEC09

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

121 23DEC08 150 23FEB09 122 23JUN09 153 23MAR08 153 23AUG08 182 23JAN09 214 23MAR09 212 23APR09 500 22JUN08 608 23MAR08 640 23APR08 576 23MAY08 668 23MAR08 668 23MAR08 500 22JUN08 540 22JUN08 580 22JUN08 540 22JUL08 600 23MAY08 488 22JUN08 488 23JUL08 488 23JUL08 488 23JUL08 518 22AUG08 519 23MAY08 548 23APR08 608 23MAY08 608 23MAY08 640 23APR08 640 23APR08 640 23APR08 580 23MAY08 334 23MAR08 456 22NOV08 693 23APR08 640 23APR08 580 23APR08 578 23JUN08 608 23APR08 548 23APR08 548 23APR08 578 23JUN08 578 23JUN08 608 23APR08
HZL2

Sheet 5 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID BOP00980 BOP00990 BOP01000

Activity Description LUB OIL TRANSFER PUMP ORDER,V ENGG,MFG,SUPP,E&C CATHODIC PROTECTION ORDER,V ENGG,MFG,SUPP, E & C ELECT.LAB EQUIPT ORDER, V ENGG,PROC,MFG,SUPP,E&C

Orig Dur

Early Start

Early JANF M A M Finish 20JAN10 20JAN10 21JAN10

2008 J A

O N

F M A M

2009 J J

O N

2010 F M A M

J A

608 23MAY08 425 22NOV08 578 23JUN08

Please enter your text

Start Date Finish Date Data Date Run Date

23JAN08 22APR10 23JAN08 22JUL08 16:08

Early Bar Progress Bar Critical Activity

HZL2

Sheet 6 of 6

BHEL/GSEG Hazira l2 Classic Schedule Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

You might also like