This article is to explain Project Management Concept as a quick reference through step by step guidance using MS Project 2013 The targeted audience is a beginner to the project management and experienced with MS Project in early version, such 2007 or 2010

Author: Ong-Art S. Factory AVP

Table of Contents
1. 2. 3. 4. 5. 6. 7. 8. 9. Start Project Plan the Tasks Assign resources Project Baseline set up Update progress Forecast Information Step by Step to S-Curve Step by Step Export Data to Excel (Visual Report) Close Project
4

Author: Ong-Art S. Factory AVP

Step-1: Start Project


Prior to start the project planning, Project manager should be identified, who can set up a project plan in MS project 2013
1. Create a new Project File To create a new blank project in Project, click the file tab. Click new

Author: Ong-Art S. Factory AVP

Step-1: Start Project


2. Set project start date Go to Project tab. Click Project information

Author: Ong-Art S. Factory AVP

Step-1: Start Project


3. Define Project Calendar Go to Project tab. Click Change Working time

Author: Ong-Art S. Factory AVP

Step-1: Start Project


4. Save the Project file Go to Tab file, select save as with Project Name or Job Order running number

Author: Ong-Art S. Factory AVP

Step-2: Plan the Tasks


In the planning stage, we need to achieved projects goals. To do this, we have to identify the projects milestone, deliverables and tasks. This plan can be use work breakdown structure (WBS).

Author: Ong-Art S. Factory AVP

Step-2: Plan the Tasks


1. Enter Task Click View tab. In the Task View groups, click Gantt Chart. In the Task Name fields, enter tasks.

Author: Ong-Art S. Factory AVP

10

Step-2: Plan the Tasks


2. Decide how you want to Schedule Task In Project 2013, we can schedule tasks manually or automatically. Select schedule method after enter a new tasks by clicking in the Task Mode column:Note: New Tasks manually set by default in Option Tab

Author: Ong-Art S. Factory AVP

11

Step-2: Plan the Tasks


3. Outline Tasks Create task hierarchy including tasks and milestones under summary task, which can be represent phase or other work divisions. Click the Task tab. In the Schedule group select Indent or Outdent button Tip: if you created a summary task with duration, start or finish date, then the tasks that fall under the summary task will not be rolled up to this summary tasks.

Author: Ong-Art S. Factory AVP

12

Step-2: Plan the Tasks


4. Enter Durations Click the Duration field for a task and enter a Duration. Two way to entering a duration: Mutually Schedule task A number or text like Tomorrow or Next after roll shell etc. Auto Schedule task Number only, 3d=3 Days, 0d=milestone, 6? is an estimate duration. Note: Both can selected in the Task Mode
Author: Ong-Art S. Factory AVP 13

Step-2: Plan the Tasks


5. Link Tasks to show relationships Click the Task tab, in the View Group click Gantt Chart. Select the tasks that you want to link then click the Link Tasks button in the Schedule group, or move a mouse to bar chart press and drack down to tasks that you want to link. To change the default Finish-to-Start (FS), double click the link line and change.

Author: Ong-Art S. Factory AVP

14

Step-3: Assign Resources


Assignments are the associations between specific tasks and the resources needed to completed them. We can assign more than one resources to a tasks. We can assign work resources (People), material (pipe/shell etc.) and cost (THB) to tasks.

Author: Ong-Art S. Factory AVP

15

Step-3: Assign Resources


1. Add Resources Click the Task Tab, in the Views dropdown to Project list select Resources Sheet. In the Resources Name filed, type the name of resources that well use in this project.

Author: Ong-Art S. Factory AVP

16

Step-3: Assign Resources


2. Assign Resources to Tasks In the Resources Tab, Click Assign Resources the click resources name then click assign

Author: Ong-Art S. Factory AVP

17

Step-3: Assign Resources


3. Enter the Work After assign a resources to the Tasks, work Hours spending hours automatically show in a Work. If PM on Tasks prefer control a Working hours, it can be change in in Work Field. Entering Work reflects real world scheduling. Go to Gantt Chart, right click on column then click Insert Columns type "WORK to select the Work Columns

Author: Ong-Art S. Factory AVP

18

Step-3: Assign Resources


4. Know the Work After Assign a resources to Tasks, MS Tasks Type Project determine how to schedule the tasks based on the tasks type.(Manually tasks dont use task type) durations may change as we assign resources to tasks. How tasks types work Work, duration and unit are determined by formula:Work =Duration x Units

Author: Ong-Art S. Factory AVP

19

Step-3: Assign Resources


In a
Fixed units tasks Fixed work tasks Fixed duration tasks

If we revised Work
Duration changes Duration changes Units change

If we revised Duration
Work changes Units change Work changes

If we revised units
Duration changes Duration changes Work changes

To set a default task type for the entire project, click the options. Go to Schedule group, in the default task type box shown fixed units as a default, we can change to Fixed Duration or Fixed Work To change the task type for an individual, go to tasks tab in properties group click information or to tasks name double click it will appear.
Author: Ong-Art S. Factory AVP 20

Step-3: Assign Resources


5. Identify factors We can use MS Project 2013 to help for effecting task understanding how changes one task can schedules effect the rest of the project. Click the task tab then in the Schedule group click Inspect Task. A pane opens on the left showing the factors that affect the scheduling of selected task. Or double click in tasks name.

Author: Ong-Art S. Factory AVP

21

Step-4: Set the Project Baseline


Create a baseline or interim plan is to compare between plan and actual. Saving baseline plan enables to identify and solve discrepancy and plan more accurately for similar future projects.

Author: Ong-Art S. Factory AVP

22

Step-4: Set the Project Base Line


1. Save the baseline plan After the plan is solidly in place for the finish date, budget and scope, we can submit a plan for approval. Once it has been approved, save the baseline plan. Click the Project tab, in Schedule group click Set Baseline

Author: Ong-Art S. Factory AVP

23

Step-4: Set the Project Base Line


2.View baseline data in Gantt Chart views
Name
Base Plan (Custom)

In Gantt chart view, move a mouse to gantt area, right click and select Bar Style.
Show for Task
Select Normal

Appearance
Select bar shave and color

Row
2 or 3

From
Baseline Start

To
Baseline finish

Author: Ong-Art S. Factory AVP

24

Step-4: Set the Project Base Line


3. View Baseline in a Table Go to View tab, in Data group click to Table and select Variance or insert columns with custom field.

Author: Ong-Art S. Factory AVP

25

Step-5: Update Progress


Updating the progress is the only way to ensure it stays on tracks as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress and communicating project information. MS Project 2013 tracks 3 sets of date: Current, Baseline and Actual. When we set the baseline, current = baseline. when a task is 100% complete, current=actual.
Author: Ong-Art S. Factory AVP 26

Step-5: Update Progress


1. Manage Change Managing changes involves modifying duration, date, dependencies, resource assignment or tasks based on requested changes or new information. Keep the current fields up to date and compare to baseline.

Author: Ong-Art S. Factory AVP

27

Step-5: Update Progress


2. Track actual Its the best to decide on a single method date and duration for tracking progress. We can enter percentage complete, actual start and finish dates, actual remaining durations or actual and remaining work. Click the Task tab, select the task that we want to enter actual progress. In the Schedule group select the amount of progress done on the tasks. Default: 0%, 25%, 50%, 75%, 100% Note: we can put a number direct to %Complete field
Author: Ong-Art S. Factory AVP 28

Step-5: Update Progress


3. Track Actual Hours and Cost If we want to enter actual and remaining work hours or costs, use tracking table. Click View tab, in Data group point Table and select Tracking. Enter progress data in the Act. Work or Act. Cost field for the task. Program is determine if we put the actual start and actual finish or % Complete.

Author: Ong-Art S. Factory AVP

29

Step-6: View Report Information


MS Project 2013 provide many ways of built in report, but for us we have to create a customize report by using S-Curve Reports.

Author: Ong-Art S. Factory AVP

30

Step-6: View Report Information


1. Select a View MS Project 2013 has old and new views to help you to see project information and report it to others. Click the View Tab, in either the Task Views group or Resources Views group, select the view you want to use. Therere many view but most usful ones include: Team planner View Timeline View Gantt Chart View Calendar View
31

Author: Ong-Art S. Factory AVP

Step-6: View Report Information


2. Customize a View Select the view you want to customize and then on the Format tab click the type of view element you want to change, such as the bar style on the Gantt Chart or gridlines and time scales of any views. Tips & Tricks, if you want to filter, sort or group tasks prior to printing, click the View tab and then in the Data group, click sort, Filter or Group options.

Author: Ong-Art S. Factory AVP

32

Step-6: View Report Information


3. Print a View or Set up the current view that we want it to Report look when printed. Click the File Tab and then click Print. A preview part of the view to see the actual size of the view as it will be printed.

Author: Ong-Art S. Factory AVP

33

Step-6: View Report Information


4. Generate a Report In Report tab has many report to view information of project but were intent to create the S-Curve by using MS Project as a tools, well focus on how to do it. Click the Report tab, go to View reports group, select Customer

Author: Ong-Art S. Factory AVP

34

Step-7: Step by Step to S-Curve


In the field list (right hand) Select Category to Time.

Author: Ong-Art S. Factory AVP

35

Step-7: Step by Step to S-Curve


Then Select Field go to Work, click Actual Work and Cumulative Actual Work only.

Author: Ong-Art S. Factory AVP

36

Step-7: Step by Step to S-Curve


The Click on Baseline, click Baseline Cumulative Work, just only one.

Author: Ong-Art S. Factory AVP

37

Step-7: Step by Step to S-Curve


In chart area Right click to change chart type. Select Chart type to Combo.

Author: Ong-Art S. Factory AVP

38

Step-7: Step by Step to S-Curve


In the Change Chart Type dialog in Series Name choose All Cumulative (Actual & Baseline) Chart type to Line Type. Actual Work chart type to Clustered Column and Click Secondary Axis

Author: Ong-Art S. Factory AVP

39

Step-7: Step by Step to S-Curve


In Field List, in Tasks Tab look at Select Category, click Edit customize time from Days to Weeks and change format as you like.

Author: Ong-Art S. Factory AVP

40

Step-7: Step by Step to S-Curve


In design Tab, choose format color as you like. In Chart Layout select Layout No 5 to show Data

Author: Ong-Art S. Factory AVP

41

Step-7: Step by Step to S-Curve


Final as just Fonts size and others

Author: Ong-Art S. Factory AVP

42

Step-8: Export Data to Excel


1. Visual Report Go to Report tab, select on Visual reports Export. Select template dialog show, go to Task Usage tab, move a mouse on Cash Flow Report template, then click Edit Template. In Visual Report-Field Picker is pop up, in Available Field, select Base line Cumulative Work and Cumulative Actual Work add to selected Fields.

Author: Ong-Art S. Factory AVP

43

Step-8: Export Data to Excel


2. Analyze Data in In PivotTable Fields, select only Actual Pivot Table Work, Baseline Cumulative work and Cumulative Actual Work.

Author: Ong-Art S. Factory AVP

44

Step-8: Export Data to Excel


3. Custom Charts In Pivot Tab Fields, select only Baseline in Excel Cumulative Work, Cumulative Actual Work and Actual Work. In Chart Area Right Click mouse select Combo chart, then All cumulative change type to Line only Actual Work to Clustter Column.

Author: Ong-Art S. Factory AVP

45

Step-8: Export Data to Excel

Author: Ong-Art S. Factory AVP

46

Step-9: Close the Project


Just because your project is almost finished doesnt mean that your work is done. We still need to solve any final project detail and customer acceptance for final deliverables. Conduct a Lessons Learned session, recording information abount areas for improvement and best practices. Make any final update to project plan. Finally archive the project plan according to our organizations guideline.
Author: Ong-Art S. Factory AVP 47

Step-9: Close the Project


1. Create a Final Report Click the Report tab, click Visual Reports to see project data as a Pivot Table report in Excel 2013 or Pivot Diagram view in Visio professional 2013 We can also view basic reports that dont require Excel or Visio. Click Report Tab many report category available to view depend on how we want to views.

Author: Ong-Art S. Factory AVP

48

Step-9: Close the Project


2. Save a Project as a Template After completing a project, we have to leverage what weve learned in the project by making it as a template for future projects. Click the File tab and Save As and then in the Save As Type box click Template.

Author: Ong-Art S. Factory AVP

49

Thanks you