You are on page 1of 2

VICO INDONESIA

JOB SAFETY ANALYSIS.

RIG 453
TASK Created NO. 1 FLOW CHECK PROCEDURE WHILE TRIPPING 03/05/1996 STEP INSTALL STABBING VALVE (I.B.O.P.) ON STRING, ENSURING VALVE IS IN THE OPEN POSITION HAZARD EXIT OF DRILLING FLUID AT PRESSURE FROM WORK STRING TASK NO Review Date ADQ04 PAGE 1 OF 2 03/05/1996 CONTROL AFTER INSTALLING I.B.O.P. CLOSE VALVE.

VERIFY CHOKE IS CLOSED

OPEN H.C.R. VALVE

CLOSE ANNULAR PREVENTER

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

VICO INDONESIA
JOB SAFETY ANALYSIS.

RIG 453
TASK Created NO. 5 FLOW CHECK PROCEDURE WHILE TRIPPING 03/05/1996 STEP INFORM TOOLPUSHER AND COMPANY MAN HAZARD TASK NO Review Date ADQ04 PAGE 2 OF 2 03/05/1996 CONTROL

ROUGHNECKS STAY ON FLOOR DRILLER SHUTS IN WELL DERRICKMAN MONITORS SITE AND DOES MUD WEIGHT CHECKS

CIRCULATE KILL MUD AFTER KILL SHEET HAS BEEN DONE AND VERIFICATION OF CORRECT KILL MUD WEIGHT IN MUD PITS

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

You might also like