You are on page 1of 7

TERMINAL PRODUCTIVITY

In pursuit of
productivity
In part one of a two-part article, Alexandre Goussiatiner investigates productivity
rates for multi-spreader quayside cranes compared with single-lift alternatives

ncreased volumes, single 40 ft, 45 ft of 48 ft

I vessel sizes and


service standards
require higher berth
productivity from
terminal operators. It has
become obvious that ever-
increasing crane intensity for
container or twin containers.
When the spreader is
retracted, it can lift single 20
ft containers. Most spreaders
are adjustable: they adjust to
the gap between two 20 ft
containers and can be used to
vessel operations is not perform twin-lifts in any
always the right answer to deck/cell arrangement. Most
the challenge. If we consider of the cranes used in twin-lift
that berth productivity operations have a lifting
demand nowadays and for capacity of 65 tonnes, which
the coming years is at allows them to handle ‘heavy
minimum 200 containers per lifts’.
hour (cont/hr), and that the Currently, the centre of
practical number of cranes attention for many terminal
allocated for the vessel operators has moved to
should not exceed six, than cranes with dual and triple
the sustainable gross rate (all spreaders. Several ports have
delays included) should be at commissioned dual spreader
least 35 cont/hr. cranes manufactured by
The technical Alexandre Goussiatiner Shanghai Zhenhua Port
productivity rate for Machinery Co, Ltd (ZPMC).
conventional cranes is crane manufacturers are 20 ft containers ‘end to end’ About 60 such cranes have
greater than 45 cont/hr, but seeking new ways to boost simultaneously (twin-lift). As been commissioned and an
not many terminals in the their cranes’ productivity. a result, most conventional additional 85 are currently
world have a sustainable Historically, increasing the cranes are now equipped on order, according to
productivity rate at this level, number of 20 ft containers with telescopic spreaders ZPMC.
even if they allocate an on-deck and in 40 ft cells which can handle twin-lifts The most commonly
adequate number of prime under-deck has driven the as well as single lifts. adopted configuration for
movers to the cranes. As move to increase When the spreader is dual spreader cranes consists
result, terminal operators and productivity by handling two extended, the crane can lift a of two independent sets of

38 • CONTAINER MANAGEMENT • August 2007


TERMINAL PRODUCTIVITY

Figure 1. Dual spreader crane configuration Figure 3. Triple-spreader crane configuration

hoists, head blocks and adjacent terminal trucks. connected, the crane is (see Figure 4). A small
telescopic spreaders similar When sets are connected to operationally identical to a number of dual-hoist cranes
to the ones from each other, the crane can conventional single spreader have been built with 120-
conventional cranes (see perform various dual crane. tonne lifting capacity under
Figure 1). spreader (tandem) lifts: two Disconnection/connection two spreaders.
Mechanical linkages 20 ft containers side-by-side takes less than a minute, but Just recently ZPMC has
between the two sets are used with retracted spreaders, two can be performed only while made further advances with a
to adjust to different twins side-by-side with the spreaders are grounded on triple-spreader crane. The first
container heights and to extended spreaders, etc. All the quay surface. The rated three triple-spreader cranes
adjust side-to-side clearances possible lift types are listed capacity of the cranes is 80 were commissioned at Mawan
of two containers quayside in Figure 2. tonnes under two spreaders or Terminal in the Port of
while landing them onto When the sets are not 65 tonnes under one spreader Shenzhen in China in
February 2007. The crane
configuration consists of three
Lift type Description Conventional Dual Triple spreaders, two head blocks
crane spreader spreader and two hoists. Two
crane crane
inseparable spreaders on the
20 Single 20 ft 1-Retracted 1-Retracted 1-Retracted waterside are connected to a
40 Single 40 ft/45 ft 1-Extended 1-Extended 1-Extended third spreader on the landside
(see Figure 3).
2x20 Twin 1-Extended 1-Extended 1-Extended The crane operates using
20_20 Two 20 ft side-by-side 2-Retracted 2-Retracted the following modes:
J Three spreaders mode:
2x20_2x20 Two twins side-by-side 2-Extended 2-Extended
landside spreader is
2x20_40 Twin and 40 ft side-by-side 2-Extended 2-Extended connected.
J Two spreaders mode:
40_40 Two 40 ft/45 ft side-by-side 2-Extended 2-Extended
landside spreader is
20_20_20 Three 20 ft side-by-side 3-Retracted
disconnected and hoisted up.
2x20_40_40 Twin and two 40 ft side-by-side 3-Extended J One spreader mode:

2x20_2x20_40 Two twins and 40 ft side-by-side 3-Extended waterside spreaders are


disconnected and hoisted
2x20_2x20_2x20 Three twins side-by-side 3-Extended up. Only the landside
40_40_40 Three 40 ft side-by-side 3-Extended spreader is utilised. In this
mode, the crane operates
Figure 2. Crane lift types as a conventional crane.

August 2007 • CONTAINER MANAGEMENT • 39


TERMINAL PRODUCTIVITY

Dual-spreader crane Triple-spreader crane operation terminal trucks are hope that by providing
occupying multiple lanes and answers to the following
Under single spreader 65 tonnes 60 tonnes
can block traffic to other questions, a model will be
Under dual spreader 80 tonnes 100 tonnes cranes. provided that can be used for
Under triple spreader 120 tonnes Dual- and triple-spreader impartial estimation of crane
cranes create a higher wheel productivity in a variety of
Figure 4. Rated lifting capacity
load. For example, a dual- operational conditions.
spreader crane with eight 1. What maximum
According to ZPMC, the instance, a dual spreader in wheels per corner creates 165 (minimum) increase in
crane’s rated lifting capacity is four 20 ft container mode can tonnes of wheel load, 37.5% sustainable performance
as follows: be used only when there are more than a conventional should we expect if we
four levelled 20 ft containers crane wheel load. This means replace the conventional
Pluses and minuses available to pick up. that a complete engineering crane with a dual- or
assessment of the wharf triple-spreader crane and
Strengths Yard interface constraints: surface and rails is needed to perform a ‘typical’
The cranes have a Multi-spreader operation make sure that the crane operation?
substantially higher lifting requires that multiple terminal deployment is feasible. 2. What sustainable
capacity than conventional trucks are located under the productivity can the
cranes and can handle more crane at the same time. Even A case study terminal operator expect
containers in a single lift if the terminal operating Various container terminal from the deployment of a
cycle. Still, the hoisting speed system dispatches multiple statistics analyses use a dual- or triple-spreader
remains the same and, despite trucks to arrive at the same number of indicators to crane instead of a
the fact that cycle elapsed time time, there is no guarantee that measure productivity of conventional crane for a
is greater than for a they will arrive concurrently. container cranes. For this particular vessel?
conventional crane, terminal Decoupled operations using article we are going to use the We hope that the article can
operators report significant straddle or shuttle carriers do gross crane rate indicator, answer those questions and
increases in productivity. not have this constraint. which is defined as the total provide a model that can be
number of containers handled used for impartial estimation
Operational constraints Opportunities divided by the gross crane of the crane productivity in a
Certain requirements are Increased crane productivity time. The gross crane rate is a variety of operational
imposed before a multi- suggests that such measure of the productivity of conditions.
spreader mode can be used. configurations can be used the crane and terminal
efficiently for mega-vessel operation as a whole, as all Limitations
Weight constraints: The 80- operations that require a larger delays under control of the Crane productivity depends on
tonne and 120-tonne lifting number of containers to be terminal operator (operating a number of factors, including
capacities allow cranes to handled from fewer numbers delays) are included in the the characteristics of the
handle dual 40 ft and triple 40 of bays. gross crane time. operation, such as vessel
ft containers respectively, but According to ZPMC, a stowage configuration; the teu
do not always allow multiple Areas of concern dual-spreader crane “can boost to containers ratio; average
full 20 ft containers to be Introduction of the dual- and productivity by 50% if loading container weights; containers
handled. If the maximum gross triple-spreader crane raises and unloading techniques are handled in each task; etc. In
weight for a 20 ft container is safety issues for the gear crew improved accordingly”. For a order to estimate the general
30 tonnes, than the ‘heavy lift’ inspecting containers and triple-spreader crane, ZPMC ‘boost’ in productivity, we have
of four 20 ft containers will handling semi-automatic states that: “Compared with used the parameters of a
require a lifting capacity of 120 twistlocks (SATLs) from all the twin 40 ft container cranes, ‘typical’ operation for a middle-
tonnes under two spreaders, four corners of each container. its handling efficiency can be size post-Panamax vessel at the
and six 20 ft containers will To get to the corners, the improved by at least 15-20%”. terminal with benchmarking
require 180 tonnes. workers have to pass through ZPMC also reports that characteristics of the container
a narrow corridor between two dual-spreader cranes at the fleet. Results are therefore not
Stowage constraints: terminal trucks. Port of Dubai have created a universal and can be used for
Multiple spreaders cannot be Multi-spreader crane new world record: 104 teu per comparison purposes only.
used if stowage is uneven, as operation can induce hour. At the same time, while It has been known for
the containers have to be congestion in the apron area, most ports report an increase quite some time in the
levelled and be in position if the terminal is using trucks in performance, their reported industry that the gross crane
side-by-side to each other. For as prime movers. During productivity rates vary. We rate fluctuates significantly,

40 • CONTAINER MANAGEMENT • August 2007


TERMINAL PRODUCTIVITY

Model definition
Containers handled
Suppose that during vessel operation the crane was involved in all four operational tasks:
Task 1 2 3 4
Containers handled v1 v2 v3 v4

Then the total containers handled during the operation can be found as follows:
4
Total containers handled: ∑ vi
i=1

Loading spectrum
Suppose that we have portioned all the crane cycles in a task into groups according to the number of containers handled in each cycle:

# Containers 1 2 n
# Lifts s1 s2 sn

Then the loading spectrum of the crane, denoted by, is defined as follows:

Loading spectrum: S = {s1, s1, ...,sn}.

Elapsed time spectra


Suppose that we have portioned all the crane lifts in a task into groups according to the number of containers handled in each lift
cycle and then calculated average gross lift cycle time, measured in seconds, within each group:

# Containers 1 2 n
Average cycle time t2 t2 tn

Then the elapsed time spectrum of the crane, denoted by, is defined as follows:

Elapsed time spectrum: T = {t1, t1, ...,tn}..

Crane gross elapsed time


The crane gross elapsed time for the whole operation can be defined as follows:
4 n
Crane gross elapsed time: ∑ ∑ sjti
i=1 j=1
Crane gross rate
The crane gross rate is total containers handled divided by crane gross elapsed time.
Then the crane gross rate, denoted by G, can be calculated as follows:
4
3600∑ vi
Crane gross rate: i=1 [cont/hr]
4 n
∑ ∑ sjti
i=1 j=1

This formula is applicable for conventional cranes as well as for multi-spreader cranes. We assume that containers handled are
known, and now the question is how to determine load and time spectra.

even for terminals that have Task 1: unloading from the deck
Alexandre Goussiatiner is a container terminal and
similar operating conditions Task 2: unloading from the hold transportation specialist with Sandwell Engineering Inc. in
and identical cranes. The Task 3: loading to the deck Vancouver, Canada. The second part of this article will appear
model presented here is not Task 4: loading to the hold. in the September 2007 issue of Container Management.
intended to predict exact Each task has its own
productivity figures; rather it specifics and its own Sandwell Engineering Inc.
estimates the ‘end points’ of distribution of operational Suite 600 - 885 Dunsmuir Street
the confident interval. delays. The differences are Vancouver, BC V6C 1N5 Canada
At any particular time reflected in the productivity el 604 630 7525 (direct)
tel 604 684 9311
during vessel operation, the statistics. Hence we will
e-mail: agoussiatiner@sandwell.com
crane executes one of the model each task
www.sandwell.com
following tasks: individually. J

August 2007 • CONTAINER MANAGEMENT • 41


TERMINAL PRODUCTIVITY

In the final part of a two-part article, Alexandre Goussiatiner of Sandwell


Engineering Inc. concludes his investigation into productivity rates for multi-spreader
quayside cranes, compared with single-lift alternatives

In pursuit of
productivity 2
T
o determine
loading Vessel capacity
spectra, a In-hold rows 15
special crane In-hold tiers 9
simulation On-deck rows 17
software system called On-deck tiers 6
CraneSpectra has been
In-hold capacity (teu) 3,000
developed. CraneSpectra uses
On-deck capacity (teu) 3,300
a physical model of a vessel
and stowage and generates 20 ft bay to vessel capacity ratio 0.1
discharging and loading
sequences. The containers’ Containers handled
stowage positions, their Handled to capacity ratio 0.6
status and weights are Teu to containers ratio 1.6
randomised. During the
Full to total ratio 0.85
simulation the crane tries to
select moves with the
maximum number of Weights
spreaders. When this is not 20 ft average gross weight (tonnes) 18
possible, the crane 20 ft gross weight variation 0.7
‘disconnects’ spreaders, only 20 ft average tare weight (tonnes) 2.3
to connect them again when 40 ft average gross weight (tonnes) 24
such a move is allowed. The 40 ft gross weight variation 0.4
record of the crane
40 ft average tare weight (tonnes) 3.8
movement is used to
calculate load spectra. Figure 1: Typical operational dimensions
The data presented in
Figure 1 were used to simulate
the ‘typical’ operation. runs (data from 100 runs) are recorded usage of all lift types frequency for each lift type.
The intermediate results of presented in Figure 2. As can during the runs and Based on the recording,
the CraneSpectra simulation be seen, CraneSpectra determined ‘average’ CraneSpectra calculates the

00 • CONTAINER MANAGEMENT • September 2007 September 2007 • CONTAINER MANAGEMENT • 00


TERMINAL PRODUCTIVITY

crane during single- and twin-


Lift Type Task 1 Task 2 Task 3 Task 4
Dual Triple Dual Triple Dual Triple Dual Triple lift operations are similar, so
20' 10 0 12 0 12 0 10 0 we can conclude that the and
parameters of the spectrum
40' 18 36 42 0 88 0 73 36
should be the same for all
2x20' 16 3 12 3 14 0 13 0 cranes.
20_20 94 12 84 0 84 0 94 12 To estimate other elements
2x20_2x20 64 3 57 2 57 0 64 0 of the spectrum we should
2x20_40 0 9 6 0 4 0 3 9 consider two models: a
40_40 360 9 312 7 290 6 331 9 realistic model (R-Model) and
an optimistic model (O-
20_20_20 0 58 0 60 0 60 0 58
Model).
2x20_40_40 0 0 0 5 0 6 0 0
2x20_2x20_40 0 0 0 0 0 0 0 0 R-Model
2z20_2x20_2x20 0 42 0 40 0 42 0 45 Certainly handling more
40_40_40 0 225 0 216 0 216 0 225 containers in a single lift
increases the elapsed time
Figure 2: CraneSpectra simulation runs and it is reasonable to assume
that this is a quasi-linear
and triple-spreader cranes function. The assumption is
Task Containers
using comparative analysis. based on the limited
1 2 3 4 5 6 Supposing that monitoring data and can be
Dual Spreader Crane container/hour is the gross validated further when more
1 28 470 0 64 0 0 rate for the single lift and data become available. The
2 54 408 6 57 0 0 cont/hr is the gross rate for assumption allows us to
3 100 388 4 57 0 0 the twin lift, then the determine the lower
4 83 438 3 64 0 0 elements of the elapsed time boundary of the ‘confidence
Triple Spreader Crane spectra can be calculated as interval’. It is unlikely that
1 36 24 292 3 0 42 following: productivity can fall lower
2 0 10 276 7 0 40 than the level defined by the
3 0 6 276 6 0 42 t2= 3,600/ g2 sec R-Model.
4 36 21 292 0 0 45 t2= 2*3,600/ g2 sec
Figure 3: Loading spectra
O-Model
For instance, if g2 = 30 For the ‘optimistic’ model,
cont/hr (t2 = 120) and g2 = 40 we assume that handling
cranes’ loading spectra (see dual- and triple-spreader (t2 = 180), then conventional more than two containers at
Figure 3). cranes (such as vessel crane spectra are defined as once does not require more
As can be seen, two operational dimensions, follows: time than it takes to perform
containers at a time is the container fleet, yard a twin-lift. The assumption
prevailing case for the double- equipment, etc.) are equal to T= {120, 180} allows us to determine the
spreader crane and three those for the conventional upper boundary of the
containers at a time for the crane. The purpose of this is Hoisting speed characteristics ‘confidence interval’. It is
triple-spreader crane. For to show how to estimate (see Figure 4) and lifting unlikely that productivity can
comparison, about 85% of all elapsed time spectra for dual- capacity for all three types of be higher than the level
lifts performed by
conventional cranes involve
only one container. Conventional Dual Spreader Triple Spreader
Crane Crane Crane
Elapsed time spectra Rated Load Hoist Speed
We assume that conventional
[m/min] 90 90 75
crane gross rates for single-
and twin-lift operations are Empty Hoist Speed [m/min] 180 180 180
known from the terminal Trolley Speed [m/min] 240 250 240
statistics. We also assume that
the operational conditions for Figure 4: Hoisting speed comparison table

00 • CONTAINER MANAGEMENT • September 2007 September 2007 • CONTAINER MANAGEMENT • 00


TERMINAL PRODUCTIVITY

defined by the O-Model.


Dual Spreader Crane Triple Spreader Crane
Based on these models, R-Model O-Model R-Model O-Model
we can estimate the elapsed
time spectra, as shown in Gross Crane Rate [cont/hr] 37.8 40.4 41.5 59.8
Figure 5. Increase over baseline 26% 35% 38% 99%
Gross Crane Rate [TEU/hr] 60.5 64.6 66.4 95.7
Modelling results
Figure 6: Gross crane rates

The elapsed time spectrum, operators should expect a


which is based on the 26% increase in productivity
premise that the gross crane when deploying a dual-
rate for the conventional spreader crane and a 38%
crane is 30 cont/hr for the increase when deploying a
single lift and 40 cont/hr for triple-spreader crane. The
the twin lift, was used to increase is indeed very
produce the final modelling significant. However, it does
results (see Figure 6). not mean that from now on
Figure 7 represents we can recommend only dual
modelling results for the or triple cranes to be
number of lifts counted during purchased and deployed.
the vessel operation. Crane productivity is only
one criteria of many that have
Conclusions to be considered during
Figure 5: Elapsed time spectra
Conservatively, terminal decision-making. J

Alexandre Goussiatiner is a container terminal and


transportation specialist with Sandwell Engineering Inc. in
Vancouver, Canada. The first part of this article appeared
in the August 2007 issue of Container Management.
Sandwell Engineering Inc.
Suite 600 - 885 Dunsmuir Street
Vancouver, BC V6C 1N5 Canada
el 604 630 7525 (direct)
tel 604 684 9311
e-mail: agoussiatiner@sandwell.com
www.sandwell.com
Figure 7: Crane lifts counted for a typical vessel operation

Space

00 • CONTAINER MANAGEMENT • September 2007 September 2007 • CONTAINER MANAGEMENT • 00

You might also like