Professional Documents
Culture Documents
In pursuit of
productivity
In part one of a two-part article, Alexandre Goussiatiner investigates productivity
rates for multi-spreader quayside cranes compared with single-lift alternatives
hoists, head blocks and adjacent terminal trucks. connected, the crane is (see Figure 4). A small
telescopic spreaders similar When sets are connected to operationally identical to a number of dual-hoist cranes
to the ones from each other, the crane can conventional single spreader have been built with 120-
conventional cranes (see perform various dual crane. tonne lifting capacity under
Figure 1). spreader (tandem) lifts: two Disconnection/connection two spreaders.
Mechanical linkages 20 ft containers side-by-side takes less than a minute, but Just recently ZPMC has
between the two sets are used with retracted spreaders, two can be performed only while made further advances with a
to adjust to different twins side-by-side with the spreaders are grounded on triple-spreader crane. The first
container heights and to extended spreaders, etc. All the quay surface. The rated three triple-spreader cranes
adjust side-to-side clearances possible lift types are listed capacity of the cranes is 80 were commissioned at Mawan
of two containers quayside in Figure 2. tonnes under two spreaders or Terminal in the Port of
while landing them onto When the sets are not 65 tonnes under one spreader Shenzhen in China in
February 2007. The crane
configuration consists of three
Lift type Description Conventional Dual Triple spreaders, two head blocks
crane spreader spreader and two hoists. Two
crane crane
inseparable spreaders on the
20 Single 20 ft 1-Retracted 1-Retracted 1-Retracted waterside are connected to a
40 Single 40 ft/45 ft 1-Extended 1-Extended 1-Extended third spreader on the landside
(see Figure 3).
2x20 Twin 1-Extended 1-Extended 1-Extended The crane operates using
20_20 Two 20 ft side-by-side 2-Retracted 2-Retracted the following modes:
J Three spreaders mode:
2x20_2x20 Two twins side-by-side 2-Extended 2-Extended
landside spreader is
2x20_40 Twin and 40 ft side-by-side 2-Extended 2-Extended connected.
J Two spreaders mode:
40_40 Two 40 ft/45 ft side-by-side 2-Extended 2-Extended
landside spreader is
20_20_20 Three 20 ft side-by-side 3-Retracted
disconnected and hoisted up.
2x20_40_40 Twin and two 40 ft side-by-side 3-Extended J One spreader mode:
Dual-spreader crane Triple-spreader crane operation terminal trucks are hope that by providing
occupying multiple lanes and answers to the following
Under single spreader 65 tonnes 60 tonnes
can block traffic to other questions, a model will be
Under dual spreader 80 tonnes 100 tonnes cranes. provided that can be used for
Under triple spreader 120 tonnes Dual- and triple-spreader impartial estimation of crane
cranes create a higher wheel productivity in a variety of
Figure 4. Rated lifting capacity
load. For example, a dual- operational conditions.
spreader crane with eight 1. What maximum
According to ZPMC, the instance, a dual spreader in wheels per corner creates 165 (minimum) increase in
crane’s rated lifting capacity is four 20 ft container mode can tonnes of wheel load, 37.5% sustainable performance
as follows: be used only when there are more than a conventional should we expect if we
four levelled 20 ft containers crane wheel load. This means replace the conventional
Pluses and minuses available to pick up. that a complete engineering crane with a dual- or
assessment of the wharf triple-spreader crane and
Strengths Yard interface constraints: surface and rails is needed to perform a ‘typical’
The cranes have a Multi-spreader operation make sure that the crane operation?
substantially higher lifting requires that multiple terminal deployment is feasible. 2. What sustainable
capacity than conventional trucks are located under the productivity can the
cranes and can handle more crane at the same time. Even A case study terminal operator expect
containers in a single lift if the terminal operating Various container terminal from the deployment of a
cycle. Still, the hoisting speed system dispatches multiple statistics analyses use a dual- or triple-spreader
remains the same and, despite trucks to arrive at the same number of indicators to crane instead of a
the fact that cycle elapsed time time, there is no guarantee that measure productivity of conventional crane for a
is greater than for a they will arrive concurrently. container cranes. For this particular vessel?
conventional crane, terminal Decoupled operations using article we are going to use the We hope that the article can
operators report significant straddle or shuttle carriers do gross crane rate indicator, answer those questions and
increases in productivity. not have this constraint. which is defined as the total provide a model that can be
number of containers handled used for impartial estimation
Operational constraints Opportunities divided by the gross crane of the crane productivity in a
Certain requirements are Increased crane productivity time. The gross crane rate is a variety of operational
imposed before a multi- suggests that such measure of the productivity of conditions.
spreader mode can be used. configurations can be used the crane and terminal
efficiently for mega-vessel operation as a whole, as all Limitations
Weight constraints: The 80- operations that require a larger delays under control of the Crane productivity depends on
tonne and 120-tonne lifting number of containers to be terminal operator (operating a number of factors, including
capacities allow cranes to handled from fewer numbers delays) are included in the the characteristics of the
handle dual 40 ft and triple 40 of bays. gross crane time. operation, such as vessel
ft containers respectively, but According to ZPMC, a stowage configuration; the teu
do not always allow multiple Areas of concern dual-spreader crane “can boost to containers ratio; average
full 20 ft containers to be Introduction of the dual- and productivity by 50% if loading container weights; containers
handled. If the maximum gross triple-spreader crane raises and unloading techniques are handled in each task; etc. In
weight for a 20 ft container is safety issues for the gear crew improved accordingly”. For a order to estimate the general
30 tonnes, than the ‘heavy lift’ inspecting containers and triple-spreader crane, ZPMC ‘boost’ in productivity, we have
of four 20 ft containers will handling semi-automatic states that: “Compared with used the parameters of a
require a lifting capacity of 120 twistlocks (SATLs) from all the twin 40 ft container cranes, ‘typical’ operation for a middle-
tonnes under two spreaders, four corners of each container. its handling efficiency can be size post-Panamax vessel at the
and six 20 ft containers will To get to the corners, the improved by at least 15-20%”. terminal with benchmarking
require 180 tonnes. workers have to pass through ZPMC also reports that characteristics of the container
a narrow corridor between two dual-spreader cranes at the fleet. Results are therefore not
Stowage constraints: terminal trucks. Port of Dubai have created a universal and can be used for
Multiple spreaders cannot be Multi-spreader crane new world record: 104 teu per comparison purposes only.
used if stowage is uneven, as operation can induce hour. At the same time, while It has been known for
the containers have to be congestion in the apron area, most ports report an increase quite some time in the
levelled and be in position if the terminal is using trucks in performance, their reported industry that the gross crane
side-by-side to each other. For as prime movers. During productivity rates vary. We rate fluctuates significantly,
Model definition
Containers handled
Suppose that during vessel operation the crane was involved in all four operational tasks:
Task 1 2 3 4
Containers handled v1 v2 v3 v4
Then the total containers handled during the operation can be found as follows:
4
Total containers handled: ∑ vi
i=1
Loading spectrum
Suppose that we have portioned all the crane cycles in a task into groups according to the number of containers handled in each cycle:
# Containers 1 2 n
# Lifts s1 s2 sn
Then the loading spectrum of the crane, denoted by, is defined as follows:
# Containers 1 2 n
Average cycle time t2 t2 tn
Then the elapsed time spectrum of the crane, denoted by, is defined as follows:
This formula is applicable for conventional cranes as well as for multi-spreader cranes. We assume that containers handled are
known, and now the question is how to determine load and time spectra.
even for terminals that have Task 1: unloading from the deck
Alexandre Goussiatiner is a container terminal and
similar operating conditions Task 2: unloading from the hold transportation specialist with Sandwell Engineering Inc. in
and identical cranes. The Task 3: loading to the deck Vancouver, Canada. The second part of this article will appear
model presented here is not Task 4: loading to the hold. in the September 2007 issue of Container Management.
intended to predict exact Each task has its own
productivity figures; rather it specifics and its own Sandwell Engineering Inc.
estimates the ‘end points’ of distribution of operational Suite 600 - 885 Dunsmuir Street
the confident interval. delays. The differences are Vancouver, BC V6C 1N5 Canada
At any particular time reflected in the productivity el 604 630 7525 (direct)
tel 604 684 9311
during vessel operation, the statistics. Hence we will
e-mail: agoussiatiner@sandwell.com
crane executes one of the model each task
www.sandwell.com
following tasks: individually. J
In pursuit of
productivity 2
T
o determine
loading Vessel capacity
spectra, a In-hold rows 15
special crane In-hold tiers 9
simulation On-deck rows 17
software system called On-deck tiers 6
CraneSpectra has been
In-hold capacity (teu) 3,000
developed. CraneSpectra uses
On-deck capacity (teu) 3,300
a physical model of a vessel
and stowage and generates 20 ft bay to vessel capacity ratio 0.1
discharging and loading
sequences. The containers’ Containers handled
stowage positions, their Handled to capacity ratio 0.6
status and weights are Teu to containers ratio 1.6
randomised. During the
Full to total ratio 0.85
simulation the crane tries to
select moves with the
maximum number of Weights
spreaders. When this is not 20 ft average gross weight (tonnes) 18
possible, the crane 20 ft gross weight variation 0.7
‘disconnects’ spreaders, only 20 ft average tare weight (tonnes) 2.3
to connect them again when 40 ft average gross weight (tonnes) 24
such a move is allowed. The 40 ft gross weight variation 0.4
record of the crane
40 ft average tare weight (tonnes) 3.8
movement is used to
calculate load spectra. Figure 1: Typical operational dimensions
The data presented in
Figure 1 were used to simulate
the ‘typical’ operation. runs (data from 100 runs) are recorded usage of all lift types frequency for each lift type.
The intermediate results of presented in Figure 2. As can during the runs and Based on the recording,
the CraneSpectra simulation be seen, CraneSpectra determined ‘average’ CraneSpectra calculates the
Space