Ubicacin: Regin: JUNIN Provincia: TARMA Distrito: TARMA

Lugar : POBLADO DE JACAHUASI 1/4'' 3/8'' 1/2'' 5/8''


Fecha : JULIO DEL 2014 Peso (kg) 0.25 0.58 1.02 1.68
MEDIDAS RESULTADO
Largo Ancho Alto
Area
Peso
Parcial
01 SISTEMA DE ADUCCION Y DISTRIBUCION
01.01 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO MANUAL
TUBERIA PVC C-10 1" -
Distribucin N 01 PVC C10 1" 1.00 51.85 51.85
1.00 86.03 86.03
Distribucin N 02 PVC C10 1" 1.00 63.57 63.57
1.00 15.49 15.49
Distribucin N 03 PVC C10 1" 1.00 32.11 32.11
1.00 36.29 36.29
Distribucin N 04 PVC C10 1" 1.00 23.89 23.89
1.00 44.16 44.16
Distribucin N 05 PVC C10 1" 1.00 22.03 22.03
1.00 37.11 37.11
Distribucin N 06 PVC C10 1" 1.00 18.71 18.71
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 40.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 609.05
01.01.02 TRAZO Y REPLANTEO INICIAL
TUBERIA PVC C-10 1" -
Distribucin N 01 PVC C10 1" 1.00 51.85 51.85
1.00 86.03 86.03
Distribucin N 02 PVC C10 1" 1.00 63.57 63.57
1.00 15.49 15.49
Distribucin N 03 PVC C10 1" 1.00 32.11 32.11
1.00 36.29 36.29
Distribucin N 04 PVC C10 1" 1.00 23.89 23.89
1.00 44.16 44.16
Distribucin N 05 PVC C10 1" 1.00 22.03 22.03
1.00 37.11 37.11
Distribucin N 06 PVC C10 1" 1.00 18.71 18.71
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 40.00
TUBERIA PVC C-7.5 3" -
HOJA DE METRADOS ADICIONAL 01 - AGUA
Nombre : ADICIONAL 01 DE OBRA "MEJORAMIENTO Y AMPLIACIN DE LOS SISTEMAS DE AGUA POTABLE, ALCANTARILLADO E
INSTALACIN DE LA PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES DE LA LOCALIDAD JACAHUASI, DISTRITO DE TARMA, PROVINCIA
DE TARMA - JUNN - I ETAPA
PESO UNITARIO DE LOS ACEROS
ITEM DESCRIPCION DE PARTIDAS Cantidad
Linea de tuberia de 3" 1.00 609.05 609.05
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION EN TERRENO SUELTO
TUBERIA PVC C-10 1" % -
Distribucin N 01 PVC C10 1" 1.00 51.85 90% 46.67
1.00 86.03 90% 77.43
Distribucin N 02 PVC C10 1" 1.00 63.57 90% 57.21
1.00 15.49 90% 13.94
Distribucin N 03 PVC C10 1" 1.00 32.11 90% 28.90
1.00 36.29 90% 32.66
Distribucin N 04 PVC C10 1" 1.00 23.89 90% 21.50
1.00 44.16 90% 39.74
Distribucin N 05 PVC C10 1" 1.00 22.03 90% 19.83
1.00 37.11 90% 33.40
Distribucin N 06 PVC C10 1" 1.00 18.71 90% 16.84
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 90% 36.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 90% 548.15
01.02.02 EXCAVACION DE ZANJAS TERRENO SEMI ROCOSO H=0.80
TUBERIA PVC C-10 1" % -
Distribucin N 01 PVC C10 1" 1.00 51.85 10% 5.19
1.00 86.03 10% 8.60
Distribucin N 02 PVC C10 1" 1.00 63.57 10% 6.36
1.00 15.49 10% 1.55
Distribucin N 03 PVC C10 1" 1.00 32.11 10% 3.21
1.00 36.29 10% 3.63
Distribucin N 04 PVC C10 1" 1.00 23.89 10% 2.39
1.00 44.16 10% 4.42
Distribucin N 05 PVC C10 1" 1.00 22.03 10% 2.20
1.00 37.11 10% 3.71
Distribucin N 06 PVC C10 1" 1.00 18.71 10% 1.87
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 10% 4.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 10% 60.91
01.02.03 REFINE Y NIVELACION ZANJA EN TERRENO NORMAL
TUBERIA PVC C-10 1" % -
Distribucin N 01 PVC C10 1" 1.00 51.85 90% 46.67
1.00 86.03 90% 77.43
Distribucin N 02 PVC C10 1" 1.00 63.57 90% 57.21
1.00 15.49 90% 13.94
Distribucin N 03 PVC C10 1" 1.00 32.11 90% 28.90
1.00 36.29 90% 32.66
Distribucin N 04 PVC C10 1" 1.00 23.89 90% 21.50
1.00 44.16 90% 39.74
Distribucin N 05 PVC C10 1" 1.00 22.03 90% 19.83
1.00 37.11 90% 33.40
Distribucin N 06 PVC C10 1" 1.00 18.71 90% 16.84
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 90% 36.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 90% 548.15
01.02.04 REFINE Y NIVELACION EN TERRENO SEMI ROCOSO
TUBERIA PVC C-10 1" % -
Distribucin N 01 PVC C10 1" 1.00 51.85 10% 5.19
1.00 86.03 10% 8.60
Distribucin N 02 PVC C10 1" 1.00 63.57 10% 6.36
1.00 15.49 10% 1.55
Distribucin N 03 PVC C10 1" 1.00 32.11 10% 3.21
1.00 36.29 10% 3.63
Distribucin N 04 PVC C10 1" 1.00 23.89 10% 2.39
1.00 44.16 10% 4.42
Distribucin N 05 PVC C10 1" 1.00 22.03 10% 2.20
1.00 37.11 10% 3.71
Distribucin N 06 PVC C10 1" 1.00 18.71 10% 1.87
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 10% 4.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 10% 60.91
01.02.05 CAMA DE APOYO DE ARENA DE 0.10 M, PARA TUBERIA
TUBERIA PVC C-10 1" -
Distribucin N 01 PVC C10 1" 1.00 51.85 51.85
1.00 86.03 86.03
Distribucin N 02 PVC C10 1" 1.00 63.57 63.57
1.00 15.49 15.49
Distribucin N 03 PVC C10 1" 1.00 32.11 32.11
1.00 36.29 36.29
Distribucin N 04 PVC C10 1" 1.00 23.89 23.89
1.00 44.16 44.16
Distribucin N 05 PVC C10 1" 1.00 22.03 22.03
1.00 37.11 37.11
Distribucin N 06 PVC C10 1" 1.00 18.71 18.71
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 40.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 609.05
01.02.06 RELLENO COMP.ZANJA TERR.NORMAL CON MATERIAL PROPIO
TUBERIA PVC C-10 1" -
Distribucin N 01 PVC C10 1" 1.00 51.85 51.85
1.00 86.03 86.03
Distribucin N 02 PVC C10 1" 1.00 63.57 63.57
1.00 15.49 15.49
Distribucin N 03 PVC C10 1" 1.00 32.11 32.11
1.00 36.29 36.29
Distribucin N 04 PVC C10 1" 1.00 23.89 23.89
1.00 44.16 44.16
Distribucin N 05 PVC C10 1" 1.00 22.03 22.03
1.00 37.11 37.11
Distribucin N 06 PVC C10 1" 1.00 18.71 18.71
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 40.00
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 1.00 609.05 609.05
01.02.07 ELIMINACION DE MATERIAL CON VOLQUETE 10M3, (R=5KM)
TUBERIA PVC C-10 1" -
Distribucin N 01 PVC C10 1" 10% 51.85 0.50 0.90 2.33
10% 86.03 0.50 0.90 3.87
Distribucin N 02 PVC C10 1" 10% 63.57 0.50 0.90 2.86
10% 15.49 0.50 0.90 0.70
Distribucin N 03 PVC C10 1" 10% 32.11 0.50 0.90 1.44
10% 36.29 0.50 0.90 1.63
Distribucin N 04 PVC C10 1" 10% 23.89 0.50 0.90 1.08
10% 44.16 0.50 0.90 1.99
Distribucin N 05 PVC C10 1" 10% 22.03 0.50 0.90 0.99
10% 37.11 0.50 0.90 1.67
Distribucin N 06 PVC C10 1" 10% 18.71 0.50 0.90 0.84
TUBERIA PVC C-7.5 2" -
Ingreso en Pasaje Parte Baja 10% 40.00 0.50 0.90 1.80
TUBERIA PVC C-7.5 3" -
Linea de tuberia de 3" 10% 609.05 0.50 0.90 27.41
01.03 SUMINISTRO E INSTALACION DE TUBERIAS
01.03.01 TUBERIA PVC SAP C-7.5 1"
Distribucin N 01 PVC C10 1" 1.00 51.85 51.85
1.00 86.03 86.03
Distribucin N 02 PVC C10 1" 1.00 63.57 63.57
1.00 15.49 15.49
Distribucin N 03 PVC C10 1" 1.00 32.11 32.11
1.00 36.29 36.29
Distribucin N 04 PVC C10 1" 1.00 23.89 23.89
1.00 44.16 44.16
Distribucin N 05 PVC C10 1" 1.00 22.03 22.03
1.00 37.11 37.11
Distribucin N 06 PVC C10 1" 1.00 18.71 18.71
01.03.02 TUBERIA PVC SAP C-7.5 2" -
Ingreso en Pasaje Parte Baja 1.00 40.00 40.00
01.03.03 TUBERIA PVC SAP C-7.5 3" Linea de tuberia de 3" 1.00 609.05 609.05
01.03.04 PRUEBA HIDRAULICA + DESINFECCION DE TUBERIA 1.00 1,080.29 1,080.29
01.04 SUMINISTRO E INSTALACION DE ACCESORIOS -
01.04.01 SUMINISTRO DE ACCESORIOS. 1.00 1.00
01.05 CONEXIONES DOMICILIARIAS -
01.05.01 CONEXION DOMICILIARIA DE AGUA POTABLE 1.00 1.00
02 FLETES -
02.06 FLETE LOCAL TARMA-JACAHUASI 1.00 1.00
3/4'' 1 ''
2.28 4.34
RESULTADO
Total
1,080.29 m
1,080.29 m
HOJA DE METRADOS ADICIONAL 01 - AGUA
Nombre : ADICIONAL 01 DE OBRA "MEJORAMIENTO Y AMPLIACIN DE LOS SISTEMAS DE AGUA POTABLE, ALCANTARILLADO E
INSTALACIN DE LA PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES DE LA LOCALIDAD JACAHUASI, DISTRITO DE TARMA, PROVINCIA
DE TARMA - JUNN - I ETAPA
PESO UNITARIO DE LOS ACEROS
Unidad
972.26 m
108.03 m
972.26 m
108.03 m
1,080.29 m
1,080.29 m
48.61 m3
431.24 m
40.00 m
609.05 m
1,080.29 m
1.00 u
11.00 u
1.00 u