Stage Payment Schedule

Rear Extension & Alterations at 6 Athoke Croft,


Hook
Based on the projected build program the following stage payments will become due. Any
changes to the build program may affect the payment profile.
Start date 17th November 2014
8 Weeks project
Date

Excluding VAT

Including VAT

Build phase(s) partially/entirely included

17/11/2014

8,027.26

9,632.71

Scaffolding, Enabling Works, Excavations &


Foundations, Foundation Masonry, Ground Floor

24/11/2014

14,564.42

17,477.30

Brickworks, Window, External Door, Bi Folding


Door & Roof Lantern, Structural Works and PC
Sum for Bi Folding Door Blinds and Lantern Vent.

08/12/2014

3,999.00

4,798.80

Gutters & Rainwater Pipes, Carpentry & Joinery,


Built up Flat roofs, Plastering & Insulation

22/12/2014

3,336.38

4,003.65

Electrical, Heating, Plumbing First Fix, Painting &


Decorating, Sundry Fixings & Fasteners. Minus 5%
retainer of contract project value.

1575.10

1,890.12

5% of project value kept as retainer, paid on


satisfactory completion of project.

31,502.16

37,802.59

Total Cost