Internal assessment: Example 1

Annotated student work: Criterion C

Criterion C: Project Schedule

Date

Action

Details

Date
Criterion
completed

Jan
2008

Initial
discussion
with the
ITGS
teacher

Comments and
follow up

After discussion
with my ITGS
teacher my ideas
were approved

Make an
appointment to
talk to Keith

18th Jan
2008

Feb
2008

Initial
discussion
with Keith

4th Feb

24th Apr

18th May

B, D

10th June

15th June

25th June

Apr
2008

May
2008

June
2008

June
2008

June
2008

Keith mentioned he
wanted to advertise
his business and
this may need an
ICT solution

Carry out
research into
similar
situations to
Keith
Go to the web
First
Solution(s)
and look at
Interview
discussed and
similar website
with Keith website was chosen
solutions
First draft designs
Check that
completed and
Second
Keith has the
approved by Keith.
meeting
photos and
We agreed on what
with Keith
other info for
he needs for the
the website
final product.
Checked I had
suitable hardware
Learn how use
and software to
Dreamweaver
Choose the develop the
solution
website. Made sure
and
I could learn what I Contact Keith
feasibility
needed to do in
to get the
study
order to develop
selected photos
the website.
and information
Preferred solution
justified
Project schedule
Agree on a
developed
schedule
indicating key
for
---------milestones in
developing
discussion with
the product
Keith
Detailed product
designs developed
Think about
Design the
in discussion with
how to test the
product
Keith. Agreement
product
signed off by Keith

Information technology in a global society teacher support material

Internal assessment: Example 1

June
2008

Develop
Test plan to be
the product
developed
(start)

Ongoing

Product
developed

Oct
2008

Website
uploaded

Oct
2008

Solution
tested

Nov
2008

Solution
handed
over to
Keith with
training

Dec
2008

Jan
2009

Annotated student work: Criterion C

Discussions with
Keith as required
during the
development of the
product
Product complete
and installed on
web server
Website handed to
Keith and tested to
see if it works
Spent a morning
with Keith in how
to use and edit the
website

Keith completed a
questionnaire to
Feedback
give feedback on
received
whether the
from Keith
product met his
needs
Following the
questionnaire and
any other feedback
Ideas for
from Keith
improving recommendations
the website were made for
further
improvements to
the website.

28th June

24th Sept

Vacation July
Investigate
copyright issue
involved with
the use of
images

5th Oct

----

Make changes
requested by
Keith

18th Oct

-----------

3rd Nov

-----------

2nd Dec
2008

B, C, D,
F

10th Jan
2009

E, F

3 marks
The project schedule refers to the proposed IT solution identified in criterion B. The project
schedule form has been used to complete this criterion and includes dates, actions and details.
A detailed schedule of tasks involved in the planning, designing, developing, testing and
implementing of the IT solution has been provided along with dates of completion and the
criteria that were addressed.