PO-ME-PE102030049 CHEMICAL INJECTION PACKAGES

SEMCO RESPONSE SHEET TO PE DOCUMENT REVIEW COMMENTS


SEMCO TRANSMITTAL
NUMBER

PE PDR NUMBER

DATE

REVIEW
CODE

DOCUMENT No.

DOCUMENT TITLE

REVISION

11-99-90-9975

SITE ACCEPTANCE TEST

PE - REVIEW BY

SEMCO RESPONSE BY

NAME

NAME

POSITION

DISCIPLINE

Aishwarya
Process Engineer

DATE

DATE

21/05/2015

DOCUMENT REVIEW SHEET :


Sl. No.

PE - COMMENTS

SEMCO - RESPONSE

Please mention Paran No 1.1. In Before Start up para, Both


Pneumatic pump and electric driven unloading pump shall be
tested Ok

Noted and incorporated

Please mention in para No 2. In Test para, All the transmitters


and other instruments shall be checked for proper functioning
with respect to operating parameters
Please mention Para No 7, In Functional test for control panel
para, Check the cable and cable trays

Noted and incorporated

PE COMMENT ON SEMCO RESPONSE

STATUS/REMARK

Noted and incorporated

4
5
6

Page 1 of 1

SEMCO CHECKED BY
SASW

DATE
21/05/2015

SIGNATURE

SEMCO APPROVED BY
BBAL

DATE
21/05/2015

SIGNATURE