What of the following statements are false for a Work package:


Allocating resources must
It should designate a Work manager.
It should set deadlines "definitive "
None of the above is false .
JUM : You should set a timetable definitive .
13.On Work breakdown structure relative to project which of the following statements are
false ? .
Breaks up the project in a " top-down " .
It breaks down the draft as "down -top "
Used to handle large projects.
JUM : used to handle large projects.

8.InanAutomobilefactorywhoisthebestpersontoinspect
a)PetroleumEngineer
b)MechanicalEngineer
c)chemicalEngineer
d)CivilEngineer.

.MajorcriteriainWBD
a)WorkPackage
b)minordeliverable
c)Majordeliverable
d)project

11.Whichistheleastconstraintforaproject
a)cost
b)time
c)people
d)performance.

12.Whichofthefollowingisanacceptablereasoninaprojectdelay
a)Strikeoflabors
b)Delayingettinglicense
c)Badqualitywork
d)

13.Projectmanagementissuitableforallexcept
a)Innovation
b)Repeatability
c)Speed
d)Performance

1. Thefollowingareprojectsexcept
Developinganewsoftwareprogram
Buildinganewsportscomplex
Productionofautomobiletires
2. Backwardpassisusedtofind:
Lateststartdatesofactivities
Criticalpath
Projectduration
Earlystart

26.WhatIthemeaningofresourceleveling:
a)Techniqueusedtoexamineunbalanceduseofresourcesovertime.
b)Techniqueusedtodeterminerequiredresourcesforprojecttasks.
c)Reportgiventoprojectmanageraboutresources.
d)Noneoftheabove
24.FastTrackprojectmeans:
a)Projectthatstartsbeforedesigniscompleted.
b)Costplusfeeproject
c)Startsprojectwithhugemanpower.
d)Noneoftheabove.

25.Whatisthemeaningofcrashinginproject:
a)ToincreaseprojectresourcesinordertoreduceProjecttotalduration.
b)Projectwillnotfinishontime.
c)Projectwillnotachieve
Inpertchartthetimeestimateofactivityiscalculatedby:
a)Normal.
b)Binomial.
c)Logarithmic.
d)Noneoftheabove.
Criticalpathmeans:
a)Longestsequenceofactivitiespathinaproject.
b)Shortestsequenceofactivitiespathinaproject.
c)Thepaththathavethemaximumresourcesassigned.
d)Thepathwiththelongesttasksinproject.
1 Whatisthefirstthingyoudoafteryoutakeaproject:
Arrangeformeeting
Assignstaff
PrepareWBS
2 WhatisWBSusedfor:
Onlyforcomplexproject
Usedforplanning
Toptodownlistofactivities
Downtotopitemsforproject
3 Ethicsmeans:
Goodmannerandbehavior

Goodpracticeinengineeringwhichdependsintheenvironment
OtherstatementsIcantremember
4 InterdisciplineforENGINEERINGbestfitthefollowing:
Allengineersshouldspecializedonallfields
Allengineersshouldstudyallengineersaspects
Engineersshouldcooperatewitheachother
5 Activitycanbedescribedas:
Arrow
Line
Node
All
6 Whatiscriticalpath
Shortestpath
Longestpath

14)CPMNetworkdiagrammergingactivity
15)Totalinternalanglesofhexagon

11)ABETcertificationcoverage
12)WhichengineeringbranchdealswithlayingofnaturalgaslaneinOil&construction

GypsumboardisusedExcept

Lowcost
/Easeofconstruction
/Recycling
/Noneoftheabove


Ministryofurbanplanningneedtoconstructanexhibitioncenterthelocationofthis
centershouldbenextto:
a)Airport
b)Busesstations.
c)Inahighpopulationarea.
d)Inaremotearea.

12.ASHGALresponsiblefor:
a)Responsibleofpublichousing.
b)Responsibleofelectricalandwaterservices.
c)Responsibleofurbanplanning.
d)Noneoftheabove.