February

1-7 Feb 8-14


Filming

Film week

Feb 15-21

Feb 22- 28

any pick up shots eg. Car scens

Sync Assembly

Feb/Mar 29-6 March 7-13


finish filming

Start putting clips together

Rough cut

Start chopping the sync assembly down

fine cut
Music/sound
1 minnute clip

Sound design
1 minute clip
Music

colour grading and effects


We have a budget to use to re-create the sound effects needed in the specific scenes, we have

We have Gimme a break, we are using songs by up coming artist and bands who want to sumbi

At the end of each stage the team will show Simon the upto date version and the completed stage
once the films are in place the team will pick the 5 stills and Aimee will print the new poster

All Scenes filmed by the 8th March

Notes:

Sync Assembly by 9th March

Notes: The sync assembly will be ready to be viewed b

Rough Cut finished within 3 weeks

Notes: once Simon has seen the sync assembly then th

Fine Cut to be completed enough within 3 weeks ready for the colour grading and effects
Sound Design will happen ove r the course of 6 weeks

Notes: once the fine cut in

no recording of foley or A
1 minute clip

Notes: This will be looked at by the team when the editing is coming
and then decide on what we would like to use as a team.

March 14-20 March 21-27 Mar/Apr 28-3

April 4-10

April 11-17

April 18-24

e sync assembly down


once the rough cut is good and simon has seen
Sound design will start once the clips are in places so know what to looks for etc.

as the fine cut comes to an end we can then pick clips we want to u

pecific scenes, we have buzz tracks from all locations, no v/o to record, no foley or ADR to be recorded

nds who want to sumbit their songs

be ready to be viewed by the 22nd Febrruary but only of the scenes filmed w/c 1st Feb then the last scenes will be added w

e sync assembly then the rough cut can be started, then the last scenes will be placed into the timeline within the first wee

rading and effects

otes: once the fine cut in uderway the sound design can be started, at which point the tracks will end and the what sound e

o recording of foley or ADR will be done but the budget is avaible for specific tracks, also all voice overs will be recording du

hen the editing is coming to a finish and then the production is coming clearer so we can look at what we have
se as a team.

April 25-29

we can then pick clips we want to use

be recorded

en the last scenes will be added while the rough cut is started

o the timeline within the first week

cks will end and the what sound effects will be needed,

ll voice overs will be recording during the shoot

ook at what we have