ID

Task Name

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER


B.O.T.) FROM B.A.R.C. JUNCTION(CH 140/690) TO KALAMBOLI
JUNCTION (CH 115/800) - SECTION A,C AND D

1
2

Duration

LEFT HAND SIDE CARRIAGEWAY CONSTRUCTION


SECTION A: CH 126.140 - CH 128.200(APPROX 2.060KM)
START OF SECTION 2 TO NEW SHIRVANE VEHICULAR
UNDERPASS APPROACH THANE END
NEW CROSS DRAINAGE STRUCTURES

441.25
days

Start

29 Dec '11

Finish

29 Jun '13

429.25 29 Dec '11 14 Jun '13


days
419 days

09 Jan '12

12 Jun '13

114 days

16 Jan '12

05 Jun '12

BOX CULVERT AT CH 126.310

84 days

16 Jan '12

28 Apr '12

BOX CULVERT AT CH 126.510

84 days

24 Jan '12

07 May '12

BOX CULVERT AT CH 126.700

84 days

01 Feb '12

16 May '12

BOX CULVERT AT CH 126.800

84 days

01 Feb '12

16 May '12

BOX CULVERT AT CH 127.015

84 days

21 Feb '12

05 Jun '12

180 days

16 Jan '12

25 Aug '12

ADJACENT TO EXISTING NERUL FLYOVER - CH 127.100 180 days


TO CH 127.800( 2LANE X 700MTR RIGID PAVEMENT)

16 Jan '12

25 Aug '12

282 days

01 Feb '12

17 Jan '13

130 days

01 Feb '12

12 Jul '12

130 days

12 Jul '12

20 Dec '12

131 days

07 Aug '12

17 Jan '13

205 days

01 Oct '12

12 Jun '13

205 days

01 Oct '12

12 Jun '13

9
10

11
12
13
14
15
16

NEW SLIP ROAD

NEW PEDESTRIAN UNDERPASS


PEDESTRIAN UNDERPASS AT CH 126.400
PEDESTRIAN UNDERPASS AT CH 127.270(BELOW
EXISTING NERUL FLYOVER)
PEDESTRIAN UNDERPASS AT CH 127.400(BELOW
EXISTING NERUL FLYOVER)
NEW VEHICULAR UNDERPASS
SHIRAVNE VEHICULAR UNDERPASS FROM CH 127.860
TO CH 128.195(335MTR WITH 2 CELL BOX FOR
UNDERPASS TRAFFIC)

CLIENT
PWD(SPECIAL PROJECT CELL)
GOVT. OF MAHARASHTRA
ID
17

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.)


FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)
SECTION 2: CH 126.140 TO CH 140.700
SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

Task Name

Duration

CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5


FOR TRAFFIC DIVERSION BEFORE TAKING UP CC
PAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

Start

Finish

91 days

09 Jan '12

30 Apr '12

D
-1

J
1

F
2

M
3

A
4

M
5

J
6

J
7

A
8

CONCESSIONAIRE
SION PANVEL TOLLWAY PVT LTD
EPC CONTRACTOR
J.KUMAR INFRAPROJECTS LTD
S
9

O
10

N
11

D
12

18
19

C.C. PAVEMENT WORKS - ALL FIVE LANES

208 days

01 Mar '12

15 Nov '12

20

NEW FOOT OVER BRIDGES

205 days

01 Oct '12

12 Jun '13

21

FOOT OVER BRIDGE AT CH 126.800

205 days

01 Oct '12

12 Jun '13

22

NEW STORM WATER DRAIN & FOOTPATH

144 days

15 Nov '12

14 May '13

23

MEDIAN REINSTATEMENT

237 days

08 Jun '12

30 Mar '13

24

SIGNAGES, LANDSCAPING & FINISHING WORKS

91 days

19 Feb '13

12 Jun '13

394 days

29 Dec '11

02 May '13

73 days

29 Dec '11

28 Mar '12

73 days

29 Dec '11

28 Mar '12

366 days

01 Feb '12

02 May '13

186 days

01 Feb '12

20 Sep '12

210 days

02 Mar '12

19 Nov '12

242 days

16 Apr '12

11 Feb '13

90 days

20 Nov '12

12 Mar '13

90 days

20 Nov '12

12 Mar '13

156 days

12 Sep '12

26 Mar '13

25

26
27
28
29
30
31
32
33
34

SECTION C: CH 130.450 - CH 133.900(APPROX 3.45KM)


SANPADA FLOVER TO VASHI TOLL PLAZA EXCL. CC
PAVEMENT
NEW SLIP ROAD FOR PROPOSED SANDAPA FLYOVER
CONSTRUCTION
SLIP ROAD ADJACENT TO PROPOSED SANPADA
FLYOVER ON LHS (APPROX 850MTR)
CONSTRUCTION OF LHS SIDE OF SANPADA FLYOVER
BETWEEN CH 130.450 - CH 131.080
FOUNDATION(18 NOS, AVG 3 PILES EACH,18 PILE
CAPS)
SUBSTRUCTURE(18 NOS PIERS & CAPS)
SUPERSTRUCTURE(16 STANDARD SPANS, 1
OBLIGATORY SPAN)
REINFORCED EARTHWORK STRUCTURE IN
APPROACH - TURBHE END
REINFORCED EARTHWORK STRUCTURE IN
APPROACH - SION END
FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSION
JOINTS, WEARING COAT)

Project: SPTPL-BOT PROJECT-SECTION 2


Date: R.1 24TH DEC 11 - VLA

Task

Split

Summary

Critical Task

Milestone

Critical Summary

Page 2 OF 7

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Project Summary

J
13

F
14

M
15

A
16

M
17

J
18

CLIENT
PWD(SPECIAL PROJECT CELL)
GOVT. OF MAHARASHTRA
ID
35
36

37

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.)


FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)
SECTION 2: CH 126.140 TO CH 140.700
SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

Task Name

Duration

MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,


SIGNAGES ETC)
SECTION D: CH 136.350 - CH 139.250(APPROX 2.90KM) VASHI
JAKAT NAKA(BMC) TO MANKHURD VEHICULAR UNDERPASS
NEW CROSS DRAINAGE STRUCTURES

Start

Finish

136 days

14 Nov '12

02 May '13

420 days

10 Jan '12

14 Jun '13

104 days

10 Jan '12

17 May '12

38

BOX CULVERT AT CH 137.380

84 days

10 Jan '12

23 Apr '12

39

BOX CULVERT AT CH 137.610

84 days

18 Jan '12

01 May '12

40

BOX CULVERT AT CH 138.040

84 days

26 Jan '12

10 May '12

41

BOX CULVERT AT CH 138.820

83 days

04 Feb '12

17 May '12

42

BOX CULVERT AT CH 139.190

83 days

04 Feb '12

17 May '12

66 days

10 Jan '12

31 Mar '12

66 days

10 Jan '12

31 Mar '12

332 days

27 Feb '12

15 Apr '13

175 days

27 Feb '12

02 Oct '12

210 days

28 Mar '12

13 Dec '12

210 days

10 May '12

26 Jan '13

90 days

15 Dec '12

05 Apr '13

90 days

15 Dec '12

05 Apr '13

182 days

25 Jul '12

08 Mar '13

162 days

25 Sep '12

15 Apr '13

43
44
45
46
47
48
49
50
51
52

NEW SLIP ROAD FOR PROPOSED CMLR DUPLICATION


FLYOVER
SLIP ROAD ADJACENT TO PROPOSED CMLR
DUPLICATION FLYOVER - APPROX 700MTR
CONSTRUCTION OF DUPLICATION FLYOVER AT CMLR
JUNCTION
FOUNDATION(22 NOS, AVG 3 PILES EACH,22 PILE
CAPS)
SUBSTRUCTURE(22 NOS PIERS & CAPS)
SUPERSTRUCTURE(20 STANDARD SPANS, 1
OBLIGATORY SPAN)
REINFORCED EARTHWORK STRUCTURE IN
APPROACH - VASHI END
REINFORCED EARTHWORK STRUCTURE IN
APPROACH - SION END
FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSION
JOINTS, WEARING COAT)
MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,
SIGNAGES ETC)

Project: SPTPL-BOT PROJECT-SECTION 2


Date: R.1 24TH DEC 11 - VLA

D
-1

J
1

F
2

M
3

A
4

Task

Split

Summary

Critical Task

Milestone

Critical Summary

Page 3 OF 7

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

M
5

J
6

J
7

A
8

CONCESSIONAIRE
SION PANVEL TOLLWAY PVT LTD
EPC CONTRACTOR
J.KUMAR INFRAPROJECTS LTD
S
9

O
10

N
11

D
12

Project Summary

J
13

F
14

M
15

A
16

M
17

J
18

CLIENT
PWD(SPECIAL PROJECT CELL)
GOVT. OF MAHARASHTRA
ID
53
54
55

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.)


FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)
SECTION 2: CH 126.140 TO CH 140.700
SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

Task Name

Duration

NEW PEDESTRIAN UNDERPASS


PEDESTRIAN UNDERPASS AT CH 138.950
CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5
FOR TRAFFIC DIVERSION BEFORE TAKING UP CC
PAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

Start

Finish

121 days

01 Oct '12

27 Feb '13

121 days

01 Oct '12

27 Feb '13

66 days

10 Jan '12

31 Mar '12

D
-1

J
1

F
2

M
3

A
4

M
5

J
6

J
7

A
8

CONCESSIONAIRE
SION PANVEL TOLLWAY PVT LTD
EPC CONTRACTOR
J.KUMAR INFRAPROJECTS LTD
S
9

O
10

N
11

D
12

56
57

C.C. PAVEMENT WORKS - ALL FIVE LANES

210 days

22 Mar '12

08 Dec '12

58

NEW STORM WATER DRAIN & FOOTPATH

147 days

10 Dec '12

10 Jun '13

59

NEW FOOT OVER BRIDGES

207 days

01 Oct '12

14 Jun '13

60

FOOT OVER BRIDGE AT CH 136.710

195 days

01 Oct '12

30 May '13

61

FOOT OVER BRIDGE AT CH 139.250

193 days

17 Oct '12

14 Jun '13

62

MEDIAN REINSTATEMENT

181 days

20 Aug '12

01 Apr '13

63

SIGNAGES, LANDSCAPING & FINISHING WORKS

179 days

05 Nov '12

14 Jun '13

64
65
66

67

RIGHT HAND SIDE CARRIAGEWAY CONSTRUCTION


SECTION A: CH 126.140 - CH 128.200(APPROX 2.060KM)
START OF SECTION 2 TO NEW SHIRVANE VEHICULAR
UNDERPASS APPROACH THANE END
NEW CROSS DRAINAGE STRUCTURES

433 09 Jan '12 29 Jun '13


days
433 days

09 Jan '12

29 Jun '13

114 days

16 Jan '12

05 Jun '12

68

BOX CULVERT AT CH 126.310

84 days

16 Jan '12

28 Apr '12

69

BOX CULVERT AT CH 126.510

84 days

24 Jan '12

07 May '12

70

BOX CULVERT AT CH 126.700

84 days

01 Feb '12

16 May '12

Project: SPTPL-BOT PROJECT-SECTION 2


Date: R.1 24TH DEC 11 - VLA

Task

Split

Summary

Critical Task

Milestone

Critical Summary

Page 4 OF 7

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Project Summary

J
13

F
14

M
15

A
16

M
17

J
18

CLIENT
PWD(SPECIAL PROJECT CELL)
GOVT. OF MAHARASHTRA
ID

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.)


FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)
SECTION 2: CH 126.140 TO CH 140.700
SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

Task Name

Duration

Start

Finish

71

BOX CULVERT AT CH 126.800

84 days

01 Feb '12

16 May '12

72

BOX CULVERT AT CH 127.015

84 days

21 Feb '12

05 Jun '12

180 days

16 Feb '12

27 Sep '12

ADJACENT TO EXISTING NERUL FLYOVER - CH 127.100 180 days


TO CH 127.800( 2LANE X 700MTR RIGID PAVEMENT)

16 Feb '12

27 Sep '12

282 days

18 Feb '12

04 Feb '13

130 days

18 Feb '12

30 Jul '12

130 days

30 Jul '12

08 Jan '13

131 days

24 Aug '12

04 Feb '13

205 days

01 Oct '12

12 Jun '13

SHIRAVNE VEHICULAR UNDERPASS FROM CH 127.860


TO CH 128.195(335MTR WITH 2 CELL BOX FOR
UNDERPASS TRAFFIC)
CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5
FOR TRAFFIC DIVERSION BEFORE TAKING UP CC
PAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

205 days

01 Oct '12

12 Jun '13

91 days

09 Jan '12

30 Apr '12

83

C.C. PAVEMENT WORKS - ALL FIVE LANES

208 days

19 Mar '12

03 Dec '12

84

NEW FOOT OVER BRIDGES

205 days

01 Oct '12

12 Jun '13

73
74

75
76
77
78
79
80

81

NEW SLIP ROAD

NEW PEDESTRIAN UNDERPASS


PEDESTRIAN UNDERPASS AT CH 126.400
PEDESTRIAN UNDERPASS AT CH 127.270(BELOW
EXISTING NERUL FLYOVER)
PEDESTRIAN UNDERPASS AT CH 127.400(BELOW
EXISTING NERUL FLYOVER)
NEW VEHICULAR UNDERPASS

D
-1

J
1

F
2

M
3

A
4

M
5

J
6

J
7

A
8

CONCESSIONAIRE
SION PANVEL TOLLWAY PVT LTD
EPC CONTRACTOR
J.KUMAR INFRAPROJECTS LTD
S
9

O
10

N
11

D
12

82

85

FOOT OVER BRIDGE AT CH 126.800

205 days

01 Oct '12

12 Jun '13

86

NEW STORM WATER DRAIN & FOOTPATH

144 days

03 Dec '12

30 May '13

87

MEDIAN REINSTATEMENT

237 days

27 Jun '12

17 Apr '13

Project: SPTPL-BOT PROJECT-SECTION 2


Date: R.1 24TH DEC 11 - VLA

Task

Split

Summary

Critical Task

Milestone

Critical Summary

Page 5 OF 7

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

Project Summary

J
13

F
14

M
15

A
16

M
17

J
18

CLIENT
PWD(SPECIAL PROJECT CELL)
GOVT. OF MAHARASHTRA
ID
88
89

90
91
92
93
94
95
96
97
98
99
100

101

IMPROVEMENT TO SION PANVEL SPECIAL STATE HIGHWAY (UNDER B.O.T.)


FROM B.A.R.C. JUNCTION( CH 140/690) TO KALAMBOLI JUNCTION (CH115/800)
SECTION 2: CH 126.140 TO CH 140.700
SECTION A,C AND D BOTH CARRIAGEWAY(LEFT+RIGHT) PART1 - REV R.1(DETAIL PROGRAM)

Task Name

Duration

SIGNAGES, LANDSCAPING & FINISHING WORKS

Start

Finish

91 days

08 Mar '13

29 Jun '13

416 days

16 Jan '12

15 Jun '13

73 days

16 Jan '12

14 Apr '12

73 days

16 Jan '12

14 Apr '12

384 days

24 Feb '12

15 Jun '13

196 days

24 Feb '12

25 Oct '12

221 days

24 Mar '12

25 Dec '12

SUPERSTRUCTURE(16 STANDARD SPANS, 1


260 days
OBLIGATORY SPAN)
REINFORCED EARTHWORK STRUCTURE IN
90 days
APPROACH - TURBHE END
REINFORCED EARTHWORK STRUCTURE IN
90 days
APPROACH - SION END
FINISHING ITEMS(ANTI CRASH BARRIERS, EXPANSION 156 days
JOINTS, WEARING COAT)
MISCELLANEOUS ITEMS(PAINTING, ELECTRICALS,
136 days
SIGNAGES ETC)
SECTION D: CH 136.350 - CH 138.650(APPROX 2.30KM) VASHI 432 days
JAKAT NAKA(BMC) TO MANKHURD VEHICULAR UNDERPASS

08 May '12

27 Mar '13

26 Dec '12

17 Apr '13

26 Dec '12

17 Apr '13

27 Oct '12

09 May '13

28 Dec '12

15 Jun '13

10 Jan '12

29 Jun '13

104 days

10 Jan '12

17 May '12

SECTION C: CH 130.450 - CH 133.900(APPROX 3.45KM)


SANPADA FLOVER TO VASHI TOLL PLAZA EXCL. CC
PAVEMENT
NEW SLIP ROAD FOR PROPOSED SANDAPA FLYOVER
CONSTRUCTION
SLIP ROAD ADJACENT TO PROPOSED SANPADA
FLYOVER ON LHS (APPROX 850MTR)
CONSTRUCTION OF RHS SIDE OF SANPADA FLYOVER
BETWEEN CH 130.450 - CH 131.080
FOUNDATION(18 NOS, AVG 3 PILES EACH,18 PILE
CAPS)
SUBSTRUCTURE(18 NOS PIERS & CAPS)

NEW CROSS DRAINAGE STRUCTURES

102

BOX CULVERT AT CH 137.380

84 days

10 Jan '12

23 Apr '12

103

BOX CULVERT AT CH 137.610

84 days

18 Jan '12

01 May '12

104

BOX CULVERT AT CH 138.040

84 days

26 Jan '12

10 May '12

105

BOX CULVERT AT CH 138.820

83 days

04 Feb '12

17 May '12

Project: SPTPL-BOT PROJECT-SECTION 2


Date: R.1 24TH DEC 11 - VLA

D
-1

J
1

F
2

M
3

A
4

Task

Split

Summary

Critical Task

Milestone

Critical Summary

Page 6 OF 7

Create PDF files without this message by purchasing novaPDF printer (http://www.novapdf.com)

M
5

J
6

J
7

A
8

CONCESSIONAIRE
SION PANVEL TOLLWAY PVT LTD
EPC CONTRACTOR
J.KUMAR INFRAPROJECTS LTD
S
9

O
10

N
11

D
12

Project Summary

J
13

F
14

M
15

A
16

M
17

J
18

ID
106
107
108
109

Task Name

Duration

BOX CULVERT AT CH 139.190


NEW PEDESTRIAN UNDERPASS
PEDESTRIAN UNDERPASS AT CH 138.950
CONSTRUCTION OF FLEXIBLE PAVEMENT IN LANE 4 & 5
FOR TRAFFIC DIVERSION BEFORE TAKING UP CC
PAVEMENT WORKS IN MAIN CARRIAGEWAY LANE 1,2& 3

Start

Finish

83 days

04 Feb '12

17 May '12

121 days

01 Oct '12

27 Feb '13

121 days

01 Oct '12

27 Feb '13

66 days

10 Jan '12

31 Mar '12

110
111

C.C. PAVEMENT WORKS - ALL FIVE LANES

210 days

09 Apr '12

26 Dec '12

112

NEW STORM WATER DRAIN & FOOTPATH

147 days

26 Dec '12

27 Jun '13

113

NEW FOOT OVER BRIDGES

207 days

01 Oct '12

14 Jun '13

114

FOOT OVER BRIDGE AT CH 136.710

195 days

01 Oct '12

30 May '13

115

FOOT OVER BRIDGE AT CH 139.250

193 days

17 Oct '12

14 Jun '13

116

MEDIAN REINSTATEMENT

181 days

05 Sep '12

18 Apr '13

117

SIGNAGES, LANDSCAPING & FINISHING WORKS

179 days

19 Nov '12

29 Jun '13