You are on page 1of 17

GENERAL GUIDELINES FOR THE DESIGN OF

SMALL HOMOGENEOUS EARTHFILL DAMS


Waikato Catchment Board
Technical Report 1987/24
April 1987
WAIKATO VALLEY AUTHORITY TECHNICAL REPORT 1987124
GENERAL GUIDELINES FOR THE DESIGN OF SMALL HOMOGENEOUS EARTHFILL DAMS
prepared by: WMMulholland
Engineering Services unit
POBox 4010
HAMILTON EAST
APRIL 1987
CONTENTS
CONTENTS
LIST OF TABLES
LIST OF FIGURES
1.0 INTRODUCTION
2.0 FOUNDATIONS
2.1 Rock Foundations
2.2 Sand and Gravel Foundations
2.3 Silt and Clay Foundations
2.3.1 Design for Saturated Foundations
2.3.2 Relatively Dry Foundations
3.0 EMBANKMENT STABILITY
4. 0 CREST WIDTH
5.0 EMBANKMENT SEEPAGE
6.0 SPILLWAY DESIGN
7 0 UPSTREAM SLOPE PROTECTION
8.0 COMMENTS ON DAM CONSTRUCTION AND MAINTENANCE
REFERENCES
PAGE
I
II
II
1
1
1
1
1
1
4
4
4
8
8
9
9
1
2
1
2
3
II
LIST OF TABLES
Recommended slopes for stabilising fills on
saturated silt and clay foundations (Taken from
"Design of Small Dams", U.S. Department of the
Interior Bureau of Reclamation 1974)
Recommended slopes for small homogeneous
earthfill dams on stable foundations (Taken
from "Design of Small Dams", U.S. Department of
the Interior Bureau of Reclamation 1974)
LIST OF FIGURES
Design of dam on s a t u r a t ~ d fine grained foundation
Foundation design criteria for relatively dry
fine grained soils
Alternate foundation design criteria for relatively
dry fine grained soils (Adopted from Gibbs 1966)
PAGE
3
5
2
6
7
-1-
1.0 INTRODUCTION
These guidelines outline requirements for small earth darns (height
less than 15 metres) that do not require special design.
2.0 FOUNDATIONS
The essential requirements of a foundation for an earthfill darn are
that it provides stable support for the embankment, and that it
provide sufficient resistance to seepage.
The minimum treatment for any foundation will require the stripping
of the foundation area to remove sod, topsoil with organic content
and other unsuitable material. In all foundations a key trench
should be used to bond the embankment material to the foundation.
2.1 Rock Foundations
Foundations of rock generally do not present any problems of
bearing strength for small darns. Rock foundations should however
be investigated to determine their permeability. If erosive
leakage, excessive uplift pressure or high water losses will occur
through joints, fissures, crevices, permeable strata, or along
fault planes the foundation should be grouted.
2.2 Sand and Gravel Foundations
These require special consideration pertaining to minimising
seepage volumes and forces and are not dealt with here.
2.3
2.3.1
Silt and Clay Foundations
Design for saturated Foundations
The construction of small darns on saturated fine grain soils may
require the addition of stabilising fills to the shoulders of the
darn embankment as shown in Figure 1 and Table 1 depending on the
consistency of the foundation soil and its classification according
to the united Soil Classification System. These requirements are
based on a factor of safety of 1.5 and average embankment
properties.
f

Q -
4( 0 III
"
Blanket drain
Stabilising fill
Slope as determined by Table 2:0.
but not greater than 3:1

Key
Embankment as designed
for stable foundation
H
,
H.W.L.
- Original ground surface
-
)4: 'crr:rrtJ " \\i. "
hI a"i1'@f1
o j - I' _ ..
\1. - a _0" 1IIL:-- ---I' ---"\ /
-'
t<"': u _
Saturated fine
grained foundation
DepthYH

Bedrock or other stable foundation
Figure 1:0. Design of dam on saturated fine grained foundation
Table 1:0. Recommended slopes for stabilising fills on saturated silt and
clay foundations. (Taken from "Design of Small Dams",U.S. Department
of the Interior Bureau of Reclamation.)
CONSISTENCY STANDARD PENETRATION FOUNDATION SOIL SLOPE OF STABILISING FILL FOR
OF SOIL TEST "N" VALUE CLASSIFICATION VARIOUS DAM HEIGIITS
(1)
15 m 12 m 9 m 6 m 3 m
soft Less than 4 Special soil tests and analyses required
Medium 4 to 10 SM 4.1:1 4:1 3:1 3:1 3:1
SC 6: 1 5:1 4:1 3:1 3:1
ML 6:1 5:1 4:1 3:1 3:1
CL 6.5:1 5:1 4:1 3:1 3:1
MIl 7:1 5.5:1 4.1:1 3.5:1 3:1
01 13:1 10:1 7:1 4:1 3:1
stiff 11 to 20 SM 4:1 3.5:1 3:1 3:1 3:1
SC 5.5:1 4.5:1 3.5:1 3:1 3:1
ML 5.5:1 4.5:1 3.5:1 3:1 3:1
CL 6:1 4.5:1 3.5:1 3:1 3:1
MIl 6.5:1 5:1 4:1 3:1 3:1
01 11:1 9:1 6:1 3:1 3:1
Hard More than 20 SM 3.5:1 3:1 3:1 3:1 3:1
SC 5:1 4:1 3:1 3:1 3:1
ML 5:1 4:1 3.5:1 3:1 3:1
CL 5:1 4:1 3:1 3:1 3:1
MIl 5.5:1 4:1 3:1 3:1 3:1
01 10:1 8:1 5.5:1 3:1 3:1
(1) United Soil Classification System
NOTE: Stabilisng soils are not needed when embankment slopes listed in Table 2 are less than those listed above.
2.3.2
-4-
Relatively DrY Foundations
Generally unsaturated impermeable soils are satisfactory for
foundations of small dams. There is however a group of soils which
have low densities and may be subject to collapse when saturated by
the reservoir. A typical example of these is loess type soils.
The design of dams on deposits of dry foundations of low density
must take into account the possibility of settlement on saturation
by the reservoir. To determine whether these soils are susceptible
to excessive settlement requires knowledge of the difference
between natural water content and optimum content, and percentage
of the Proctor maximum dry density existing in the natural soil.
An empirical relationship between D (inplace dry density divided by
Proctor maximum dry density) and Wo-W (optimum water content minus
in place water content) is shown in Figure 2. An alternative
criteria in terms of natural dry density and liquid limit for use
in the absence of Proctor test facilities is shown in Figure 3.
For foundations of unsaturated soils that fall into the "no
treatment required" category only the usual foundation stripping
and key trench are required. Soils with inplace water content
considerably greater than Wb should be Checked to determine the
degree of saturation. If they are over 95% saturated they should
,
be considered as saturated and designed accordingly.
3.0 EMBANKMENT STABILITY
The slopes of the embankment must be stable during construction,
and under all conditions of reservoir operation, including rapid
drawdown of the water surface. Recommended embankment slopes for
small homogeneous earthfill dams on stable foundations are shown in
Table 2.
4.0 CREST WIDTH
A minimum crest width should be that width which will provide a
safe percolation gradient through the embankment at the level of a
full reservoir. Because of practical difficulties in determining
this factor the crest width is as a rule determined empirically and
the following formula is recommended for small earth fill dams:
W= HIS + 3 mwhere: W= dam crest width
H = dam height
Table 2:0. Recommended slopp.s for small homogeneous earthfill dams on stable foundarions
(Taken from "Design of Small Dams"U.S. Departmenr of the Interior Bureau of Reclamation.)
SUBJEcr 'f() RAPID SOIL CLASSIFICATION UPSTREAM SLOPE ea-JNSTREAM SLOPE
DR.I\W[lOON (1) , (2 )
No GW, GP, SW, SP Pervious, not suitable
GC, GM, SC, SM 2.5:1 2:1
CL, l1L 3:1 2.5:1
CH,MH 3.5:1 2.5:1
Yes GW, GP, SW, SP Pervious, not suitable
GC, GM, SC, SM 3:1 2:1
CL, ML 3.5:1 2.5:1
01, 1111 4:1 2.5:1
(1) United Soil Classification System
(2) OL and Oll soils are not recommended for major portions of homogeneous earthfill dams and Pt soils are unsuitable.
r
-6-
15 10
%Dry
o 5
Optimum
-10 -5
');Wet
I
I
II
/
.I"
,
/
~ i t t l e or no addItional
... alume change on lafura1'io
/ I11III> I
HO TREAT"'ENT fltEQUIAED
~
(or small t3QT" .... /
J'
/
.'
I
I
-
/ F I
I' I
I ,
...Signt(lC:onr amount t;f
..!

I
vatui'll charge on safurQtiorl I
TIlt!: fM(NT REOUIIIEO -
/
,
.....
/
0
I
/
I I
,
,
:t*;'
,
I
5
/
,
I
,
I
Q
I
7
-15
7
8
85
90
w -w = OPTIMUM WATER CONTENT (% BY DRY WEIGHT)
o
-NATURAL WATER CONTENT (% BY DRY WEIGHT)
100
w
u >-
et: 0::
--' 0
c;
::;:
2::::>
- ::;:
- >- x
I-et:
-::;:
VI
z: 0::
W 0
Cl I-
U
>- 0
0:: cc
Cl c,
"
0-<
Cl
VI
z:
w
o
o
o
~ 95
>-
Figure 2:0. Foundation design criteria for relatively
dry finegrained soils
-7-
10 20 30
LIQUID LIMIT
40 50 60
70
80 90
, Speclflc gravlty 2.10
-'Specific gravity = 2.60
v

A
SUSCEPTIBLE TO
V
,
V
0
/
j
NO TREATMENT REQUIRED
0

,
0
/
0

\
..
=
60
12
>-
0::
o
-l 10
""
0::
::::>
f-
"" ""11
u, 70
u
c,
>- 80
f-

VI
z
'C5 9
Case I
'--I At. Voids
I I
.." Solids
Loose
Case n
0:6. Voids
.lSOlids
Voids equal 10 file
_ YOiumear
ihe I'quid Umit
C-se III
[;;;Jt Voi ds
_ .... Solids
Dense
Figure 3:0. Alternate foundation design criteria for
relatively dry fine grained soils
( Adapted from Gibbs 1966 )
-8-
5.0 EMBANKMENT SEEPAGE
Seepage flow through the embankment must be controlled so that no
internal erosion takes place and so that there is no sloughing in
the area where seepage emerges. Specific forms of seepage control
may vary but would normally take the form of a horizontal blanket
drain or a toe drain. Both types of drain should include a filter
to prevent clogging with eroded fines from the dam. Blanket drains
should extend from the tow of the dam to wi thin H + 1. 5 mof the
dam centreline (H = dam height).
Seepage control drains will nor normally be necessary if the
reservoir will not contain water for any significant length of time
(ie. the phreatic surface will not have time to develop). For
example, flood detention dams would fall into this category.
6.0 SPILLWAY DESIGN
The dam spillway should normally be capable of passing a 100 year
flood while maintaining a minimum freeboard on the dam of 300 mm.
For spillways incorporated in the dam embankment velocities over
the crest and on the downstream slope should not be sufficient to
cause erosion. For this reason the crest and downstream slope of
an embankment spillway should be well grassed.
As a typical example design for a spillway with crest 0.5 mbelow
the dam crest and design discharge Q is set out as follows:
Maximum head on spillway H
Critical depth at crest y
Critical flow over crest q
Critical velocity over crest V
Required length of spillway L
= 0.2 m (300 mm freeboard)
= 2/3 x 0.2 = 0.133 m
= 0.152 m
2/sec.
= 1.14 m/sec.
= Q/0.152
Check velocities on downstream slope by Manning equation
Roughness n
Maximum allowable velocity (say)
Maximum flow depth Y = qIV
Maximum slope S
0.05
2.0 m/s
0.152/2.0 = 0.076 m
0.310 (say 1:3)
-9-
For higher heads on a grassed spillway then the slope of the
downstream embankment would need to be decreased to ensure lower
velocities.
7.0 UPSTREIIM SLOPE PROTECTIeN
The upstream slope of the embankment may require protection against
erosion due to wave action if the reservoir is large. This should
take the form of rock rip-rap, rock filled reno mattresses or some
other suitable form of protection and should extend from a safe
distance (several feet) below minimum water level to a similar
distance above normal maximum operating level. Above this level
the embankment should be maintained in grass.
8.0 COMMENTS eN DAM CONSTRUCTIeN AND MAINTENlINCE
It is essential that good construction practices be employed when
compacting fill. Ideally fill should be compacted in shallow
layers close to optimum moisture content. The maximum layer
thickness will depend to a large extent on the characteristics of
the material being compacted, the type of compaction equipment used
and the amount of compactive effort applied. For typical non
specific design situations where no specialist compaction plant is
available a layer thickness of between 150 mm and 300 mm is
considered reasonable. Where fill that has a moisture content
significantly greater than optimum (ie close to saturation water
content) is being placed construction should be undertaken in
stages to allow time for dissipation of excess of pore pressures.
It is important too that the slopes and crest of the embankment are
well vegetated and that the spillway is well maintained. The
embankment, abutments, and visible portions of the foundation
adjacent to the embankment should be checked periodically,
particularly during the first 1-2 years of operation, for evidence
of the development of unfavourable conditions. Observation of the
embankment and the adjacent foundation is most critical at times of
rapid filling or drawing down of water levels. Particular items to
look for include cracks, slides, sloughs, subsidence, impairment of
slope protection, springs, seeps, or boggy areas caused by seepage
from the reservoir.
-10-
The outflow from blanket drains or toe drains should also be
checked from time to time as any sudden increase or decrease in
volumes may provide early warning of problems with seepage control.
Any increase in fine material in the outflow may also warn of
internal erosion.
-11-
REFERENCES
Henderson, F.M. (1966). Open channel flow, New York: Macmillan.
Scott, C.R. (1969). An introduction to soil mechanics and foundations.
Essex, Eng, Applied Science Publishers.
u.S. Department of
small dams.
the Interior,
washington :
Bureau of Reclamation, (1974).
Government printing Office.
Design of

You might also like