2004
29km2 Site
January 2013
Interesting Statistics
Laborers in 2007 Laborers in 2011 Contractors Contracts Engineering, Project, Construction and Cost Personnel Crushed Rock Reclamation Fill Concrete Piles Airfield Asphalt Steel Electrical Cable Fiber Optic Cable Fuel Pipes Curtain Wall Telephones Fencing
13,800 47,000 47 100 900 87,600 tonnes 60,200,000 m3 2,300,000 m3 8,900 2,000,000 m3 140,000 tonnes 17,000,000 m 330,000 m 37,000 m 86, 000 m2 Interesting Statistics 9,000 88,000 m
Master Plan completed in 2003 Runways: 4.8km long 60m wide 2km apart Midfield concept for maximum efficiency 100% A380 Compatibility 100% International Civil Aviation code compliant State-of-the-Art Technology
600,000m2 Terminal 41 Contact Gates 3 Central Utility Plants 29ha Lagoon Iconic Roof Form: Echoes Waves in Gulf 3450 Car Parking System 6900m2 Transportation Facility 100 Limousine Staging Mosque Plaza Landscaped Gardens
25,000m2 Column-Free Space 24m High Ceiling 150 Check-In Stations 5 Islands 14 First Class Check-In Booths 16 Business Class Check-In Desks Information Kiosks Currency Exchange Retail and F&B
Departures Hall
Passenger Terminal Complex
Sunken Gardens
Passenger Terminal Complex
Mirror Image Concourse B 20 Gates with Hold Rooms 270 Seats per Hold Room Code E Aircraft Secondary Screening 30mins Minimum Connect Time Activity Nodes Quiet Rooms Flight Information Displays
Naturally Lit Focal Point Access to Qatar Airways: 1st & Business Lounges Gold & Silver Lounges Al Maha Lounges
Retail Gallery
Passenger Terminal Complex
13 Gates with Hold Rooms 270 Seats per Hold Room Unobstructed Views of the Airfield
Departures Concourse C
Passenger Terminal Complex
Mosque Plaza
Passenger Terminal Complex
Silhouette of Sails 12000m2 Terminal Separate Aircraft Apron 5 Large Aircraft 2 Airbus A380 Positions
Emiri Terminal
Bespoke Interiors
Emiri Terminal
Arrivals Plaza
Emiri Terminal
90m High Visible from Central Doha Tower Cab 75m Above Ground Air Navigation Radar 360 degree Tower Simulator for Advanced Operational Safety and Efficiency
150,000m2 Enclosed Hangar Simultaneous Capacity for: 8 Wide Body Aircraft Maximum 13 Aircraft Including Airbus A380 Safe Access to all Level of Aircraft Flexibility of Tail-First or Nose-First Configuration
50,000m2 1.4 Million tons Annual Capacity Separate Aircraft Parking Apron 11 Wide Body Aircraft Automated Container Storage System 1,200 unit Consignment Handling System Accommodates 5,300 Separate Shipments
Cargo Terminal
Cargo Terminal
65,000m2 Facility 90,000 Meals per Day State-of-the-Art Automated Operations Production capability for Off-Airport Venues Direct Airside Loading
Catering Building
Catering Building
50 Million Passengers
Phase 3A
AVIATION SERVICES AIR TRAFFIC CONTROL TOWER CATERING BUILDING CARGO TERMINAL EMIRI HANGARS AIRCRAFT MAINTENANCE HANGAR RUNWAYS PASSENGER TERMINAL BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
AVIATION SERVICES AIR TRAFFIC CONTROL TOWER CATERING BUILDING CARGO TERMINAL EMIRI HANGARS T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
AVIATION SERVICES AIR TRAFFIC CONTROL TOWER CATERING BUILDING CARGO TERMINAL EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
AVIATION SERVICES AIR TRAFFIC CONTROL TOWER CATERING BUILDING NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
AVIATION SERVICES AIR TRAFFIC CONTROL TOWER CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
AVIATION SERVICES SEA RESCUE CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
MULTI-STOREY PARKING SEA RESCUE CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION T1 EXPANSION BACK-UP APPROACH & TRAINING CENTER
2012 - 2017
Phase 3A
2012 - 2020
Phase 3B
MULTI-STOREY PARKING SEA RESCUE CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION T1 RAIL STATION VISA BUILDING LAND RECLAMATION
2012 - 2020
Phase 3B
MULTI-STOREY PARKING SEA RESCUE CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES T1 APRON EXPANSION WESTERN TAXIWAY & APRON VISA BUILDING LAND RECLAMATION
2012 - 2020
Phase 3B
MULTI-STOREY PARKING SEA RESCUE CAR RENTAL FACILITY NORTH CROSS TAXIWAY EMIRI FLIGHT FACILITIES AVIATION CAMPUS / LAW ENFORCEMENT WESTERN TAXIWAY & APRON VISA BUILDING LAND RECLAMATION
2012 - 2020
Phase 3B
MULTI-STOREY PARKING SEA RESCUE RAIL STATION CAR RENTAL FACILITY PLAZA NORTH CROSS TAXIWAY TERMINAL 2 EMIRI FLIGHT FACILITIES AVIATION CAMPUS / LAW ENFORCEMENT WESTERN TAXIWAY & APRON VISA BUILDING LAND RECLAMATION
2012 - 2020
Phase 3B
2020