Professional Documents
Culture Documents
BIG JOB
Shells Size comparison
ONE
145 127
57 Olmsted
45
24
Paducah
45 121
Louisville KENTUCKY
5 miles
MAP AREA
The Olmsted Dam on the western end of the Ohio River is being built as precast pieces on land that are then moved to the river for completion in one of the largest construction projects under way in the United States. The Army Corps of Engineers plan is to build its rst dam on a major river without rst building temporary coffer dams to create dry areas on the riverbed for construction workers. Instead, the corps and its contractors are manufacturing 3,500-ton to 5,000ton concrete shells on land, then lifting, moving and lowering them in place, connecting them together like pieces of Lego toys.
Using concrete mixed at the site, reinforcement rods and supporting structures, workers build a series of concrete shells on land. Each will become a piece of the dam. The biggest shells are 125 feet by 102 feet and about 30 feet high.
140 ft.
Sixty four, 36 diameter steel wheels are used to move the cranes
Catamaran barge
2 MOVING A SHELL
Shell lifters
Once a shell is complete, a steel lifting frame is attached. A special crane built just for the Olmsted project rides on rails to move the shell to the top of a skidway, just above the Ohio River. Shell lifters
COST: $19 million (barge alone, does not include assembly or lifting equipment.) PROPULSION: Two 4,500-horsepower push boats LIFTING CAPACITY: 4,500 tons
6-foot tall man
CATAMARAN BARGE
The shell is placed on a wedge-shaped steel cradle with wheels and another piece of equipment slowly lowers the shell down the riverbank, where the catamaran barge waits to pick it up.
Shell lifters
Side view
LOCKS 1
Skidway
Skidway Cradle
As more water is blocked by the wickets of the dam in this area of the river, the water level rises, allowing vessels to pass throughthe locks.
m da n ed io at t G sec
5
ab le da
LOCKS 3
Catamaran barge
DAM
Ohio River
ig av m se ct n io
Supports
Front view
4 ONLINE
To see videos of the Olmsted Dam Project go to: courier-journal.com/olmsteddam
Shell
PLACING A SHELL
Before placing the shell, the bottom of the river is graded and covered with stone, and foundation piles are driven into the river bottom. Using the most precise global positioning equipment, the shells are lowered into the water in sequence, either on top of each other or next to each other, with a margin of error of less than one inch. Shell lifters
Front view
Gates
Locks Wickets
Once each shell is in place, its void is lled with concrete, displacing water.
Supports Shell