Professional Documents
Culture Documents
Structure
6.1 6.2 Introduction
Objectives
Transportation of Concrete
6.2.1 6.2.2 6.2.3 6.2.4 Importance of Transportation Precautions in Transporting of Concrete Transporting Operations Safety during Transportation of Concrete
6.3
6.4 6.5
6.6 6.7
6.8 6.9
Formwork Summary
6.1 INTRODUCTION
In previous unit, you have studied the concreting operations like storing of ingredients of concrete, batching of ingredients of concrete and mixing of ingredients of concrete. You have also studied the types of mixer. In this unit, you will study the concreting operations like transportation of concrete, deposition of concrete, compaction of concrete, curing of concrete and finishing of concrete. You will also study the different joints in the concrete work and formwork.
Objectives
After studying this unit, you should be able to appreciate the importance and precautions to be taken during the transportation of concrete, describe the transporting operations, 101
Concrete Technology
appreciate the importance of placing of concrete, explain the steps taken for preparation of surface before placing concrete, discuss the different types of vibrators, appreciate the importance and objectives of curing, describe the methods of curing, duration of curing and effects of delayed curing, explain the finishing operations, and explain the purpose of providing the joints in concrete construction.
(e) (f)
102
(g)
The concrete should be kept agitated in truck mixer in order to prevent it from becoming stiff if more time is likely to be spent during transportation. The permissible duration of transport of concrete should be determined in the laboratory.
(h)
Transport of Concrete by Pans Iron pans are used for transportation of concrete. This method is adopted where the quantity of mix is small and access to the point of placing is restricted. This method is slow as well as costly. Transport of Concrete by Wheelbarrows The capacity of wheelbarrows varies from 70 liters to 80 liters. Steel wheelbarrows with pneumatic tyres are used for moderate distances. Transport of Concrete by Tipping Lorries This method is widely used for the transport of concrete mix and discharging it directly at the position of concreting such as in the construction of air field pavements, dams, concrete floors, canal lining and roads, etc. Tipping lorries are used for transporting ready mixed concrete and for arrangements for receiving, loading and reloading it. The height of mix in the lorries should not be less than 40 cm in order to avoid segregation. The mix delivered in tipping lorries is discharged directly into the structure. If it becomes difficult, then the mix is discharged into skips or tubs, which are then moved to the position of placing by crane. Transport of Concrete in Containers This method exclude the loss of mortar and cement slurry during transportation and also ensure the gradual emptying which is necessary for concreting reinforced structures. This is one of the main methods of delivering ready-mixed concrete from the mixing place to the point of placing without the need for unloading and reloading. For this purpose hoppers, skips and wagon bodies are used. Lorries transport hoppers and skips. Containers are delivered from the transport vehicle to the position of placing the concrete mix by cranes of different types and desired lifting capacity. This method reduces the risk of segregation of concrete and also protects it from atmospheric effects. Transport of Concrete by Belt Conveyors In this method, the belt used has a covering of rubber of width 60 cm and speed not exceeding 1 m/s. The slump of concrete mix should not be more 103
Concrete Technology
than 6 cm in any case. The line of the conveyors should not have any marked breaks in plan. The angle of inclination of the conveyor must not exceed 18 for 4 cm slump and 15 for 4 to 6 cm slump. Flat belts are used only for a distance of 20 m and if the distance is large, the working part of the belt should be trough shaped. When the concrete is unloaded from the conveyor or when it is transferred from one part of the conveyor to another, guide boards should be used to prevent segregation of concrete. Boards should be arranged properly so as to avoid segregation (Figure 6.1). Free falling of concrete from the roller of the conveyor is also not allowed. For getting continuous supply of concrete this method is used. This method is most suitable under summer conditions for concreting structures at a distance of 250 to 500 m from the place of mixing and also in those cases where it is difficult for lorries and other types of transport to reach the structure.
Transport of Concrete by Pumps Concrete pumps are used to deliver concrete for concreting densely reinforced structures, internal structural elements of buildings and large mass concrete structures. These are also used for concreting of tunnel linings. Such pumps cover a horizontal distance of 300 to 400 m and a vertical distance of 40 to 50 m. Pumping is a process of transporting concrete without unloading and reloading in a vertical or horizontal direction and without a harmful effect on its quality.
104
In this method, the concrete is charged into the receiving hopper and kept mixed continuously by the paddles in order to retain uniformity of mix and to prevent segregation. The impeller blades through the open suction valve push the concrete into the barrel of the pump. The suction valve closes when the plunger moves to the left. The pressure valve opens which moves the concrete from the barrel into the pipeline. The diameter of the pipeline depends upon the size of the aggregate used but it does not exceed 30 cm in any case. The slump should not be less than 5 cm and more than 8 cm. The water-cement ratio should remain between 0.5 to 0.65. Stiff mixes are not suitable to be delivered by pumps because their pumping properties are not good. Sharp turns and bends should be avoided in the pipeline. The number of bends in a pipeline should be as small as possible.
(b)
(f) (g)
SAQ 1
(a) (b) (c) (d) What do you mean by transportation of concrete? What precautions should be taken during transportation of concrete? Enlist the methods of transportation and explain any one. State the safety measures to be taken during transportation of concrete. 105
Concrete Technology
remove the dust particles from it. After the surface is cleaned, a thin coat of cement paste is applied before placing concrete over the hard surface. In the Case of Specially Prepared Sub-bases In case of brick soling and water bound macadam, base should be made rough with the help of steel brush. Dust and loose particles should be removed from the sub-base before placing the concrete over it. Before placing concrete the water should be sprinkled over the surface. In the Case of Natural Soil Before placing any layer of concrete over natural soil, the soil should be compacted uniformly and its moisture deficiency should be removed initially in order to prevent it from absorbing moisture from beneath the concrete layer. In the Case of Rocky Base In the case of rocky base the sides should be cut in vertical direction and not in sloping direction. All the loose particles should be removed off the rocky base. Before placing concrete the water should be sprinkled over the surface.
SAQ 2
(a) (b) (c) What is meant by placement of concrete? What are the precautions to be taken while placing the concrete? How surface should be prepared before placing of the concrete?
107
Concrete Technology
of compacting operations is to remove the entrapped air and arrange the ingredients uniformly to obtain better quality of concrete. The strength of concrete may reduce by 30% by the presence of only 5% voids. The density, durability and strength of concrete are the factors, which affect the quality of compaction.
In case of mechanical compaction concrete is compacted by vibration during which the vibrator communicates rapid vibrations to the particles thus increasing the mobility of concrete. The particles occupy a more stable position under the force of gravity. The concrete mix fills all the spaces thus forcing air to the surface and making concrete denser. The frequency and duration of vibration, its amplitude depends on the conditions of vibration for compacting the mix. The maximum frequency of vibration depends on the size of the particles and on the mobility of concrete. Following are the advantages of vibratory compaction. (a) (b) (c) (d) (e) (f) (g) (h) A better finish and better quality of concrete is obtained as compared to hand compaction. The concrete produced is more dense and impermeable. Bond between steel and concrete is improved. Laitance is partially reduced. Speed of placing concrete is increased by the ready flow of vibrated concrete into difficult positions. Creep and shrinkage are also reduced due to the possibility of higher aggregate-cement ratio. Concrete with even lower w/c ratio and with lower cement can be compacted effectively. Better compaction can be achieved in heavily reinforced concrete members. Finishing of horizontal surface. Discharging very stiff concrete from mixers. The lack of sufficient vibration at points not immediately in contact with the vibrating equipment thus resulting in segregation. Discharging stiff concrete from lorries and other means of transport.
The following difficulties are encountered in vibratory compaction. (a) (b) (c)
(d)
Compaction by Pressure and Jolting This is one of the effective methods of compacting very dry concrete. This method is used for compacting hollow blocks, cavity blocks and solid concrete blocks. The stiff concrete is vibrated, pressed and also given jolts and due to this the stiff concrete gets compacted to dense form to give good strength. By applying great pressure, a concrete of very low water cement ratio could be compacted to yield very high strength. Generally this method is used in the laboratory. Compaction by Spinning Spinning is one of the recent methods of compaction of concrete and is used for the fabrication of concrete pipes. The plastic concrete when spun at a very high speed, gets well compacted by centrifugal force.
Concrete Technology
Internal Vibrator Internal vibrator is also known as needle or immersion or poker vibrator. It consists of a power unit and a long flexible tube at the end of which fitted a vibrating head. These vibrators have higher efficiency since all the energy is directly transmitted to the concrete. As they are portable, therefore, can be readily used in difficult positions. The vibrating element is immersed in the fresh concrete, which transmits vibrations through the vibrator body. It is very important to keep the vibrating head in the concrete while running in order to keep the bearings cool and avoid breakdowns. It should be inserted vertically or nearly so at points 45 cm to 75 cm apart and should be withdrawn slowly at the rate of 7.5 cm/sec. These should not be used for pushing concrete laterally in the formworks because it will cause segregation. The frequency of vibration is about 7000 cycles/mt. Such vibrators are used for compacting large sections of mass concrete in structures, for concrete of beams, columns, foundations, etc.
Screed Vibrator Screed vibrator is also known as surface vibrator. These vibrators are used for compacting plain concrete or one-way reinforced concrete floors, road surfaces, the thickness of which does not exceed 20 cm. This vibrator is set up on the concrete surface after placing the concrete and vibrations are transmitted to concrete through a working platform.
110
Figure 6.4 : Section of a Typical Metal Form for Road Slab Construction
Form Vibrator Form vibrators are also known as external vibrator. It is fastened to the formwork by a clamping device and transmits vibrations to the concrete. External vibrator is clamped at a distance up to 25 cm in depth from the formwork. The vibrator must be firmly clamped to the form as otherwise its efficiency will be reduced. The formwork should be sufficiently strong and rigid to resist the oscillatory action. The time of vibration is from 45 to 90 seconds. The vibrator is switched off for 5 minutes after its continuous working for half an hour in order to allow cooling of motor. If the motor of the vibrator heats up more rapidly, the work should be immediately stopped. The electrician should be called in order to check the motor winding. In this case, more power is required in comparison to internal vibrators. Therefore, emergency vibrators must be kept near the concreting work as replacement for vibrators, which go out of order. Form vibrators are used in concreting of thin components of monolithic structures, heavily reinforced arches and tunnel and tunnel lining, etc. They are also used in the production of different pre-cast reinforced concrete components. Table Vibrator This method is mostly adopted in the laboratories. This is the special case of a formwork vibrator, where the vibrator is clamped to the table. This method is used in making small but precise prefabricated reinforced cement concrete members. In this method, any member kept on the table gets vibrated. Platform Vibrator It is nothing but a table vibrator larger in size. Sometimes, the platform vibrator is also coupled with jerking or shock giving arrangements so that a thorough compaction is given to the concrete. Platform vibrator is used in the manufacture of large prefabricated concrete elements such as railway sleepers, prefabricated roofing elements, electric poles, etc.
111
Concrete Technology
The following steps should be observed in order to obtain good results by compacting concrete with vibrators. (a) (b) (c) Vibrators should be controlled carefully by immersing the internal vibrator for 5 to 15 seconds at points 45 to 75 cm apart. The formworks should be as tight as possible in order to prevent any leakage of mortar. The vibrator should be inserted vertically otherwise it will not be possible to regulate the degree of compaction in all portions of concrete. The lift should not be less than 15 cm in order to avoid air being trapped. The vibrator should be immersed through the full depth of the freshly laid concrete. It should also be immersed into the lower layer if the concrete in that layer is still plastic. The vibrator should be withdrawn very slowly and should be allowed to penetrate of its own accord. The vibrator should not touch the form surface otherwise a sand streak is likely to occur. The surface of the formwork can also be damaged. The vibrator should only be used for compaction purposes. It should not be used for pushing the concrete laterally in the formworks, which would otherwise cause segregation.
(d) (e)
(f) (g)
(h)
2.
Screed
3.
Form
112
components.
SAQ 3
(a) (b) (c) (d) (e) Why concrete is required to be compacted? State the methods of compaction and explain in brief. How you will judge that compaction is proper or not? What should be the duration of compaction? State the factors affecting it. State the different types of vibrator and their usefulness. Explain any one of them in brief.
SAQ 4
(a) (b) (c) (d) What is vibrator? What is the objective of using vibrators in concreting operation? State the places where different types of vibrator are used. State the precautions to be taken during the use of vibrators. Tick the correct answer. (i) (ii) Vibrators should be penetrated in (horizontal/vertical) direction. Which type of vibrator is generally used for compaction of concrete? (1) (2) Needle vibrator Form vibrator
(iii) For compacting thin reinforced concrete slabs following vibrator is recommended. (1) (2) Immersion vibrator Surface vibrator
(iv) Surface vibrator is effective only when thickness of concrete member does not exceed (1) (2) (v) 200 mm 500 mm
A surface vibrator for compaction of concrete is preferred for (1) (2) Raft footings Columns 113
Concrete Technology
Excellent method of curing is the continuous sprinkling of water. The quantity of water required by this method to cure concrete is much more than other methods. If water is sprinkled in intervals, then the concrete must not be allowed to dry between applications of water. A constant supply of water helps in preventing the formation of cracks caused by alternate wetting and drying. Ponding Methods Ponding method is mainly adopted for surfaces members such as pavements, floors, roofs, slabs and sidewalks, etc. In this method, a small dam of earth or water retaining material is placed around the perimeter of the surface. The surface is firstly covered for 24 hours after placing and compacting concrete. The enclosed area is further divided into a number of rectangles and is kept flooded with water. Water is filled in the rectangles two to three times per day depending upon the climatic conditions. Membrane Curing Membrane curing is used at the places where there is acute shortage of water. In membrane curing a newly laid concrete surface is covered by using chemical or liquid membranes in order to prevent evaporation of moisture from concrete. This method has been found good in maintaining a satisfactory state of wetness in the body of concrete to promote continuous hydration when original w/c ratio used is not less than 0.5. The membranes should be applied immediately after the concrete has been finished. The concrete surface should be kept moist till the membrane is applied. Such compounds should neither be applied when there is free water on the concrete surface nor after the concrete has dried out. The correct time of applying membranes that when water film disappears from the surface of the finished concrete. Curing membranes are plastic films, bitumen emulsions, wax emulsions and waterproof papers, etc. Curing compounds should not be applied in between two courses in order to obtain perfect bonding. The disadvantage of this method is that concrete loses its strength due to less rate of hydration. No supervision is required in this method. Covering Concrete Surfaces with Gunny Bags The exposed surface of concrete is covered with old empty cement bags or hessian, which are kept moist by spraying water frequently. This method is widely used for structural concrete. This method can also be applied for horizontal and vertical members. The surface should not be allowed to dry even for small duration during the period of curing. Shading Concrete Works The object of shading is to avoid the evaporation of water from the surface of concrete after it is placed and compacted. This method is used to protect the newly laid concrete from wind, heat and direct sunrays. In cold weather, it prevents the freezing of concrete under frost condition. This process is mainly suitable for large surfaces such as road slabs. Using canvas and starching them on frames achieve shading over the newly laid concrete. Chemical Curing Chemical curing is accomplished by spraying the sodium silicate solution. About 500 gm sodium silicate mixed with water can cover 1 m2 of surface and forms a hard and insoluble calcium silicate film. It actually acts as case hardener and curing agent. The application of sodium silicate results in a
115
Concrete Technology
thin varnish like film, which also fill pores and surface voids, thus sealing the surface and preventing the evaporation of water. Steam Curing The hydration of cement accelerates with increase in temperature, which leads to faster development and strength. To steam curing, the concrete is subjected to higher temperature by maintaining the required wetness. For concrete mixes with water-cement ratio ranging from 0.3 to 0.7, the increased rate of strength development can be achieved by resorting to steam curing. The mixes with low water-cement ratio respond more favorably to steam curing than mixes with higher water-cement ratio. In steam curing, the heating of the concrete products is caused by steam either at low pressure or high pressure. Steam curing is preferred for precast concrete products. These precast members are passed through the steam chambers. It is also used, when early removal of formwork is required to put the structure in sense without delay. Curing of Concrete by Infrared Radiation It is claimed that a much more rapid gain of strength can be obtained in this method than even with steam curing. The rapid initial rise of temperature does not result in a decrease in the ultimate strength as it does in the case of steam curing. The system is described as particularly applicable to the manufacture of hollow concrete products in which case the heaters are placed in the hollow spaces of the product. The normal operating temperature is 90C. The curing of concrete by infrared radiation has been used in Russia. Electrical Curing of Concrete This method is not used in India. It is more expensive. It is mostly used in very cold climatic regions. Passing alternating current of low voltage can cure concrete products and high amperage through electrodes in the form of plates covering the entire area of two opposite faces of concrete. The potential difference generally adopted is between 30 and 60 V. Evaporation is prevented by using an impermeable rubber membrane on the top surface of the concrete. Initially up to 3 hours, the resistance of concrete to flow of current decreases due to rise in temperature. There is rise in resistance afterwards, due to decrease in the quantity of free water available in the concrete due to hydration and evaporation. This period of rise in temperature should be about 12 hours. The duration of electrical-curing should be about 48 hours at the temperature of 50C or 36 hours at the temperature of 70C. The concrete products are cooled gradually in heatinsulated chambers for a minimum period of 24 hours. By electrical-curing concrete can attain the normal 28 days strength in a period of 3 days.
specimens left in air at 23C for the entire curing period have shown a reduction of 25% in the strength at 7 and 28 days as compared with standard moist-curing. The reduction under field conditions would probably have been greater. Similar adverse curing causes greater relative reduction in strength when Portland blast furnace slag cement and the cements blended with fly ash are used.
SAQ 5 SAQ 5
(a) (b) (c) (d) (e) What is curing? State its importance. What are the objectives of curing? Enlist different methods of curing. Write short note on water curing. What is membrane curing?
SAQ 6
(a) (b) What is steam curing? How are the following structural elements cured? (i) (ii) Test block Columns
(iii) Hume pipe (iv) Bridge slab (v) Pre-cast products 117 (vi) Wall
Concrete Technology
(c) (d)
State the effects of delayed curing. Tick the correct answer. (i) The following method may be used for the curing of concrete (1) (2) (ii) Electrical curing Mechanical curing
The following sealing compounds can be used for the membrane curing (1) (2) Rubber latex emulsions Sodium silicate solution
118
movement. A small quantity of concrete mix should always be kept ahead of the straight edge to fill the voids and maintain a plane surface. Screeds may be of vibrator type or roller type. Vibrators can also be fitted on screeds.
Floating The process of removing the irregularities from the surface of concrete left after screeding is called floating. The process of floating is done with the help of wooden float. Floating helps in leveling the surface and compacting concrete. The wooden float is 1.5 m long and 20 cm wide. A handle is fixed in the center. Moving the wooden float backward and forward performs finishing. Bull float is used if the area of concrete surface is large. It is moved with the help of a handle without the operations getting on the concrete surface.
Trowelling The final operation of finishing is called trowelling. Trowelling is performed where a smooth and dense surface is desired. Trowelling should be delayed as far as possible. In most of the cases, trowelling is performed while the concrete is too soft and plastic. At this stage, excessive trowelling will cause crazing and result in a surface having less wear resistance. The important point is the period at which the trowelling is done and the pressure used by person responsible for the final operation of finishing. Finishing is always carried out with the trowel and the float. After floating surface should be allowed to dry and stiffen till all the excess water has disappeared. Trowelling should be done after water has evaporated from the concrete surface. Spreading dry cement on a wet concrete surface to absorb excess 119
Concrete Technology
water is not a good practice. The occurrence of such wet surfaces should be avoided. The finishing process should be delayed if such spots occur. A gap of some time should be left between successive trowellings in order to permit concrete to increase its set. Initially, an older trowel is preferred to a new trowel. Trowel blade should be kept as flat against the surface as possible. Power float or power trowels are generally used in finishing large surface area such as aircraft hangars or factory floors and is not economical for small areas such as flats or dwelling houses. During trowelling, cement should not be spread, as it is dangerous and liable to produce a neat cement skin, which peels off after some time. Trowelling with power trowels should be delayed till the concrete becomes firm. Trowelling should be finished on the same day as the laying operation. Artificial drying can be very effective by laying cotton sheets on the floor and covering them with 2.5 cm to 5 cm of dry cement. The water is absorbed by the sheets which can be lifted afterwards say 10 or 15 minutes and after this trowelling can proceed for finishing the concrete surface.
SAQ 7
(a) (b) (c) (d) (e) (f) (g) What is finishing? How a good finish can be obtained? Explain the necessity of finishing. State the different methods of finishing of concrete. Explain screeding in brief. What is floating? Explain in brief. What is trowelling? What are the precautions to be taken while trowelling? Tick the correct answer. The final operation of finishing is called ___________________ (floating/screeding/trowelling ).
120
concrete a proper provision is made in the form of a joint. Such joints are called contraction or expansion joints. The concrete joints can be classified as follows : (a) (b) (c) Construction joints, Expansion joints, and Contraction joints.
Concrete Technology
recommended that structures exceeding 45 m in length shall be divided by one or more expansion joints.
SAQ 8
(a) (b) (c) (d) (e) (f) Why joints are essential in concrete construction? What are types of joints in concrete? What is construction joint? Explain in brief. Explain the expansion joint in brief. Explain the purposes of providing contraction joint. What is the method of joining the old concrete to new concrete? (Hint : Answer is in Sub-section 6.3.3.)
6.8 FORMWORK
The temporary construction used as a mould for the structure, in which the concrete is placed and in which it hardens is called as formwork. Formwork must be strong enough to withstand the hydrostatic pressure of wet concrete. The method of compaction, size and shape of the formwork also affects the shutter pressure. Formwork should be tight in order to prevent concrete from leaking out. Formwork should be easy to handle so that no time is wasted in assembling and disassembling. Formworks vary both in type and in the method of construction. Another type is the sliding type. In this type, an arrangement is more to rise the form with the placement of concrete. It is generally used where a
122
good surface finish is required. It has two advantages. Firstly, it enables a high speed of construction and secondly, it eliminates the horizontal construction joint.
123
Concrete Technology
beams and column boxes. The sheetings of 3.75 cm to 5 cm are used for the soffits of beams. Joists Joists are commonly 15 cm 5 cm but may vary from 10 cm 5 cm to 22.5 cm 10 cm according to type of work. Posts Posts may be 7.5 cm 10 cm to 12.5 cm 12.5 cm. Studs, Wales, Headtrees, Subsidiary Bearer and Transoms These may vary from 10 cm 5 cm to about 12.5 cm 12.5 cm. Sections about 7.5 cm 5 cm are useful for general bracing and light shuttering. Steel Steel forms can be used for as many number of times as desired and as such are economical. Better finish can be achieved by the use of steel forms, as they are factory made and fit exactly. Steel forms have the following advantages over other types of forms : (a) (b) (c) (d) (e) (f) (g) (h) Quality of work is assured. The wastage of material is eliminated. Handling and transportation costs are reduced. It reduces finishing costs. It reduces friction losses. Smaller number of tie rods is required. These are safer than other material. In order to obtain additional usage of the steel forms, adjustment of various sizes can easily be incorporated in the design of steel forms. Collapsing and stripping is a smooth and gradual operation because it is usually controlled by jacks, etc.
(i)
124
Concrete Technology
beam can safely support its own weight. The slab formwork is supported by the centering to the beam.
126
Concrete Technology
(b) (c)
Removing the supports, which support the formworks. Removing the shuttering boards or panels.
Under normal circumstances when the temperature is 20oC and the cement used is ordinary, the formwork may be stripped after the expiry to the following periods :
(a) (b) (c) Vertical sides of columns, walls, beams and slabs Beam soffits Bottom of slabs (i) (ii) (d) Span of 4.5 m Span of 4.6 m and above, bottom of beams up to span of 6 m, bottom of arch ribs up to a span of 6 m. 7 days 14 days 21days 1 to 2 days 7 days
SAQ 9
(a) Fill in the blanks (i) (ii) __________________ are used in heavy wall construction. __________________ dries out and shrinks.
(iii) ___________________ should be done in order to make the surface of formwork smooth. (iv) Forms require ___________________ study as they account for reasonable percentage of the final cost of concrete. (v) (b) In case of sliding type of formwork, it ____________________ as the concrete is placed.
State True or False (i) (ii) Steel supports minimize the finishing costs. Hard woods are difficult and costly to work.
(iii) Partially seasoned timber is most satisfactory to use for formworks. (iv) Sliding type of formwork enables high speed of construction. (v) (c) (d) (e) (f) (g) (h) 128 The forms should be adequately braced.
What is formwork? What are the requirements of formwork? What are the precautions to be taken before placing concrete in formwork? Enlist the faults in erection of formwork. Discuss the procedure of removal of formwork. Enlist the advantages of steel formwork.
6.9 SUMMARY
In this unit, you have studied concreting operations like transportation, placement or deposition, compaction, curing and finishing of concrete. You also studied different joints in concrete construction and formwork. In the next unit, you will study special types of concrete and concreting methods under extreme environmental conditions.
129