Professional Documents
Culture Documents
Sl.
No.
Item
Unit
Qty.
Total
Remarks
Span - 60 mtr, 2 DP /
Km
554288.90 Unit rate of 9 mtr Rail
pole has been
extrapolated to 13 mtr
No.
19
24110.00
29173.10
2
3
4
5
6
7
No.
No.
No.
No.
Set
Set
15
15
19
51
12
2
765.00
150.00
75.00
71.00
280.00
2230.00
925.65
181.50
90.75
85.91
338.80
2698.30
13884.75
2722.50
1724.25
4381.41
4065.60
5396.60
Set
1940.00
2347.40
4694.80
Km
No.
3.09
6
30556.00
25.00
36972.76
30.25
114245.83
181.50
Set
18
530.00
641.30
11543.40
Cmt.
12.9
2150.00
2601.50
33559.35
Ltr.
Ltr.
No.
No.
Kg
Kg
LS
4
4
19
17
4.5
30
1
90.00
140.00
120.00
55.00
120.00
41.00
3000.00
108.90
169.40
145.20
66.55
145.20
49.61
3630.00
435.60
677.60
2758.80
1131.35
653.40
1488.30
3630.00
761463.94
8
9
10
11
12
13
14
15
16
17
18
19
20
i)
ii)
iii)
iv)
Centages
Store incedental charges-2.5%
Contingency-5.0%
W/c Establishment-2.5%
T&P-1.5%
19036.60
38073.20
19036.60
11421.96
21 Labour Charges
Transport Chargesupto 50 kms average lead from area
22
stores to construction camp inc. site transport.
51581.09
9280.00
0.00
Labour Charges
Survey
Tree cutting
Approach Clearance
Pit digging
Stay Pit digging
Trasportation of Pole from road side to Pole Pit for a
lead of 1 Km
Shifting of materials (other than pole) to pole pits
9
10
11
12
13
14
15
16
17
18
1
2
3
4
5
6
909893.38
Km
Km
Km
No
No
1
1
1
19
18
600.00
1150.00
255.00
155.00
115.00
726.00
1391.50
308.55
187.55
139.15
726.00
1391.50
308.55
3563.45
2504.70
No
19
345.00
417.45
7931.55
No
15
25.00
30.25
453.75
Set
115.00
139.15
278.30
40.00
545.00
10.00
125.00
35.00
35.00
10.00
6400.00
920.00
55.00
48.40
659.45
12.10
151.25
42.35
42.35
12.10
7744.00
1113.20
66.55
726.00
12529.55
5619.24
2722.50
2668.05
804.65
96.80
7744.00
1113.20
399.30
51581.09
No
15
No
19
Cu-ft 464.4
No
18
No
63
No
19
Ltr
8
Ckt-Km
1
LS
1
No
6
Unit Cost i.r.o. 1 KM Renovation of 11 kV Line by 50 sq. mm. ACSR Rabbit on 13 mtr long 60 kg/mtr. Rail Pole.
1
Sl.
No.
2
Item
3
Unit
Total
Remarks
Span - 60 mtr, 2 DP
/ Km
554288.90
Unit rate of 9 mtr
Rail pole has been
13884.75
2722.50
1724.25
4381.41
4065.60
5396.60
No.
19
24110.00
29173.10
2
3
4
5
6
7
No.
No.
No.
No.
Set
Set
15
15
19
51
12
2
765.00
150.00
75.00
71.00
280.00
2230.00
925.65
181.50
90.75
85.91
338.80
2698.30
Set
1940.00
2347.40
4694.80
Km
No.
3.09
6
30556.00
25.00
36972.76
30.25
114245.83
181.50
Set
18
530.00
641.30
11543.40
Cmt.
12.9
2150.00
2601.50
33559.35
Ltr.
Ltr.
No.
No.
Kg
Kg
LS
4
4
19
17
4.5
30
1
90.00
140.00
120.00
55.00
120.00
41.00
3000.00
108.90
169.40
145.20
66.55
145.20
49.61
3630.00
435.60
677.60
2758.80
1131.35
653.40
1488.30
3630.00
761463.94
8
9
10
11
12
13
14
15
16
17
18
19
609171.15
20
i)
ii)
iii)
iv)
Centages
Store incedental charges-2.5%
Contingency-5.0%
W/c Establishment-2.5%
T&P-1.5%
15229.28
30458.56
15229.28
9137.57
21 Labour Charges
Transport Chargesupto 50 kms average lead from area
22
stores to construction camp inc. site transport.
51581.09
9280.00
0.00
Labour Charges
Survey
Tree cutting
Approach Clearance
Pit digging
Stay Pit digging
Trasportation of Pole from road side to Pole Pit for a
lead of 1 Km
Shifting of materials (other than pole) to pole pits
9
10
11
12
13
14
15
16
17
18
1
2
3
4
5
6
740086.92
Km
Km
Km
No
No
1
1
1
19
18
600.00
1150.00
255.00
155.00
115.00
726.00
1391.50
308.55
187.55
139.15
726.00
1391.50
308.55
3563.45
2504.70
No
19
345.00
417.45
7931.55
No
15
25.00
30.25
453.75
Set
115.00
139.15
278.30
40.00
545.00
10.00
125.00
35.00
35.00
10.00
6400.00
920.00
55.00
48.40
659.45
12.10
151.25
42.35
42.35
12.10
7744.00
1113.20
66.55
726.00
12529.55
5619.24
2722.50
2668.05
804.65
96.80
7744.00
1113.20
399.30
51581.09
No
15
No
19
Cu-ft 464.4
No
18
No
63
No
19
Ltr
8
Ckt-Km
1
LS
1
No
6
41264.872
10316.218
51581.09
Unit cost for new 11/0.4 kV DTR (CSP type) on 13 mtr. Long 60 kg/mtr Rail Pole
1
Sl.
No.
2
Item
Unit
Qty.
No.
No.
5
Unit Rate (as
per CSEB
2007-08)
125000
Unit Rate
2009-10
Total
Remarks
151250
151250
Unit rate of 9
58346.20 mtr Rail pole
has been
extrapolated to
7877.10
24110.00
29173.10
6510.00
7877.10
2550.00
3085.50
3085.50
280.00
338.80
1016.40
71.00
85.91
257.73
2040.00
2468.40
2468.40
3435.00
4156.35
4156.35
600.00
726.00
726.00
530.00
641.30
2565.20
1.8
2150.00
2601.50
4682.70
Set
1000.00
1210.00
1210.00
Danger board
No.
Earthing (Pipe earthing)
LS
Anti Climbing device
No.
Red Oxide Paint
Ltr.
Aluminium Paint
Ltr.
MS Nuts & Bolts
Kg
1.1 kV unarmoured PVC Cable
3.5C 70 sq.mm. as outgoing
Mtr
3.5C 150 sq.mm. as incomming
Mtr
LT Distribution BOX with MCCB at I/c
22
No.
and Fuse at O/G
1
1
2
1
1
14
55.00
4500.00
120.00
90.00
140.00
41.00
30
10
214.00
416.00
66.55
5445.00
145.20
108.90
169.40
49.61
0.00
258.94
503.36
66.55
5445.00
290.40
108.90
169.40
694.54
0.00
7768.20
5033.60
27500.00
27500.00
Set
13
14
15
16
17
18
19
20
21
24
i)
ii)
iii)
iv)
No.
1
10431.00
12621.51
7433.49
14866.98
7433.49
4460.10
25 Labour Charges
10018.38
12621.51
297339.68
2616.00
344168.12
No
14211.00
17195.31
17195.31
361363.43
Labour Charges
1 Pit digging
2 Stay Pit digging
Trasportation of Pole from road side
3
to Pole Pit for a lead of 1 Km
No
No
2
4
150.00
115.00
181.50
139.15
363.00
556.60
No
115.00
139.15
278.30
Set
115.00
139.15
139.15
No
465.00
562.65
1125.30
No
435.00
526.35
1052.70
Cu-ft
70
10.00
12.10
847.00
No
130.00
157.30
629.20
No
35.00
42.35
84.70
No
25.00
30.25
60.50
No
660.00
798.60
798.60
No
685.00
828.85
828.85
No
175.00
211.75
211.75
7
8
9
10
11
12
13
14
15
16
LS
600.00
726.00
726.00
No
No
1
1
350
1564.65
423.5
1893.227
423.50
1893.23
10018.38
Sl.
No.
Item
Unit
Qty.
16
i)
ii)
iii)
iv)
No.
8
9
5
6
7
Unit Rate (as
Unit Rate Total (for 100 Total for 63 Total for
per CSEB
2009-10
kVA)
kVA
25 kVA
2007-08)
6510.00
7877.10
7877.10
7877.1
7877.1
No.
2550.00
3085.50
3085.50
3085.5
Set
280.00
338.80
1016.40
1016.4
No.
71.00
85.91
257.73
257.73
Set
2040.00
2468.40
2468.40
2468.4
Set
3435.00
4156.35
4156.35
4156.35
LS
No.
Ltr.
Ltr.
Kg
1
2
1
1
14
4500.00
120.00
90.00
140.00
41.00
Mtr
Mtr
Mtr
30
30
10
46.00
214.00
416.00
5445.00
145.20
108.90
169.40
49.61
0.00
55.66
258.94
503.36
5445.00
290.40
108.90
169.40
694.54
0.00
0.00
7768.20
5033.60
5445
290.4
108.9
169.4
694.54
0
0
7768.2
0
27500.00
21000
No.
No.
No.
1
1
10431.00
12621.51
6466.00
7823.86
6466.00
7823.86
No.
257.73
2468.4
4156.35
5445
290.4
108.9
169.4
694.54
0
1380
0
0
14000
Unit rate
is
including
16% ED &
7823.86 4 % CST
7823.86
1962.33
3924.65
1962.33
1177.40
0.00
6828.41
17 Labour Charges
1016.4
12621.51
78493.03
Centages
Store incedental charges-2.5%
Contingency-5.0%
W/c Establishment-2.5%
T&P-1.5%
3085.5
94348.14
62161.78 48773.58
1554.04
3108.09
1554.04
932.43
0.00
5928.85
1219.34
2438.68
1219.34
731.60
0.00
5928.85
75239.23 60311.39
Labour Charges
Shifting of materials (other than
pole) to pole pits
10
11
12
14
15
16
17
17
17
Set
115.00
139.15
139.15
139.15
No
465.00
562.65
1125.30
1125.3
No
35.00
42.35
84.70
84.7
No
25.00
30.25
60.50
60.5
No
660.00
798.60
798.60
798.6
No
175.00
211.75
211.75
211.75
726
139.15
LS
600.00
726.00
726.00
No
350
423.5
423.50
No
1564.65
1893.227
1893.23
No
969.9
1173.579
0.00
No
969.9
1173.579
0.00
LS
5462.73
1125.3
84.7
60.5
798.6
211.75
423.5
726
423.5
1173.579
0 1173.579
4743.079 4743.079
1365.68
1185.77
1185.77
6828.41
5928.85
5928.85
2007-08
2009-10
205210.69 248304.9
23599.23 28555.07
27585.00 33377.85
4494.00
5437.74
0
260888.92 315675.59
Phase Conversion
1 phase 2 wire to new LT line by ACSR (3 Phase 30 sq.mm +
Street Light 20 sq.mm. + Nutral 20 sq.mm ) on RS Joist 175x85
mm
1 Total supply Cost-80% of New Line
164168.55 198643.9
18879.38 22844.05
22068.00 26702.28
TOTAL COST
6675.57
5517.00
3595.20 4350.192
0
214228.14 259216.04
Item
30 sq.mm. ACSR
20 sq.mm. ACSR
Rate
Qty.
Total
17773.00
3.09
54918.57
11733.00
2.06
24169.98
Total
80 sq.mm. ACSR
45372.00
3.09
140199.48
30 sq.mm. ACSR
17773.00
2.06
36612.38
176811.86
Total
79088.55
97723.31
118733.8217
379622.74
Rate (Rs.)
400.00
225.00
35.00
660.00
Sub total
4 Survey, F&I etc @ 5%
Total
693.00
Rate (Rs.)
805.00
1688.00
253.19
2746.19
Sub total
4 Survey, F&I etc @ 5%
Total
2883.50
Rate (Rs.)
400.00
1800.00
3 Supply of PP Box
1000.00
3200.00
Sub total
4 Survey, F&I etc @ 5%
Total
3360.00
Rate (Rs.)
805.00
7560.00
3 Supply of PP Box
1500.00
9865.00
Sub total
4 Survey, F&I etc @ 5%
Total
10358.25
1
2
3
4
Item
Supply of MRI as per Secures Meter
CST @ 1.00%
Variation w.r.t vendor @ 2.0%
Escalation by 10%
Rate (Rs.)
85000.00
Total
96323.70
Sl.
No.
Item
5 Yard Lighting
Unit
Unit Rate (as per Unit Rate 2009Labour Charges @ Total unit
(Centages-11.5%
CSEB
2007-08)
10 (Supply)
15%
Cost
Qty.
Lot
10600
12826
1474.99
1923.90
16224.89
Lot
115000
139150
16002.25
20872.50
176024.75
Lot
33000
39930
4591.95
5989.50
50511.45
Set
1068
1292.28
148.6122
193.84
1634.73
No
10000
12100
1391.5
1815.00
15306.50
Lot
1.00
50000
60500
--
--
Mtr
1.00
2000
(33% of new)
2420
--
--
--
--
Km
1.00
80000
96800
60500.00
2420.00
96800.00