You are on page 1of 6

Page : 1 of 19

KLM Technology Group


Project Engineering Standard

Rev: 01 August 2013

www.klmtechgroup.com

KLM Technology Group #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)


TABLE OF CONTENT

1.0 INTRODUCTION 2.0 SCOPE 3.0 LOCATION 3.1 General 3.2 Safe Distance from Roads 3.3 Wind Direction 3.4 F.D. Fan Location 4.0 CLEARANCE / ACCESSIBILITY 4.1 Bottom Fired Furnaces 4.2 Multi-floor Side Fired Furnaces 4.3 Valves 4.4 Dampers 4.5 Explosion Doors 5.0 BASIC DESIGN CRITERIA 5.1 Configuration 5.2 Materials of Construction 5.3 Heat Flux 5.4 Corrosion Allowance 5.5 Ladders / Platforms 5.6 Personnel Protection 5.7 Peep Holes 6.0 PROCESS SYSTEM 6.1 Pass Flow Control 6.2 Pressure Monitoring 6.3 Temperature Monitoring 7.0 FIRING SYSTEM 7.1 Burner Mounting

4 4 4 4 5 5 5 5 5 5 5 5 6 6 6 6 6 6 7 7 7 7 7 7 7 8 8

Page : 2 of 19

KLM Technology Group


Project Engineering Standard

Rev: 01 August 2013

www.klmtechgroup.com

KLM Technology Group #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)


8 8 8 8 9 9 9 9 10 10 10 11 11 12 12 12 12 12 12 13 13 13 13 13 13 14 14 15 15

7.2 Pilot Burners 7.3 Burner Lighting 7.4 Fuel Gas Control Valve 7.5 Blinding of Fuel Gas / Oil 7.6 Knock-Out Pots 8.0 UTILITY SYSTEM 8.1 Coil Purge 8.2 Box Purge Steam 9.0 SAFETY INSTRUMENTATION 9.1 Indications 9.2 Alarms 9.3 Shutdown System 9.4 Typical 10.0 OPERATING CHECKS 10.1 Pressure Survey 10.2 Safety Audit 11.0 FLOW MEASUREMENT 11.1 Temperature Measurement 11.2 Monitoring of Decoking 11.3 Quench Pot for Decoking 11.4 Tests after Decoking 11.5 Decoking Schematic 12.0 SAFETY IN FURNACE OPERATION 12.1 Display Board 12.2 Check List for Furnace Lighting 12.3 Precautions in Shutdown 12.4 Tube Failures 13.0 GENERAL 13.1 Housekeeping

Page : 3 of 19

KLM Technology Group


Project Engineering Standard

Rev: 01 August 2013

www.klmtechgroup.com

KLM Technology Group #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)


15 15 15 16 16 17 18

13.2 Safety Shower 13.3 Fire Fighting Facilities 14.0 REFERENCES ATTACHMENTS ANNEXURE-I ANNEXURE-II ANNEXURE-III

KLM Technology Group


Project Engineering Standard

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)

Page 4 of 19
Rev: 01

August 2013

1.0

INTRODUCTION

Fired Process Furnaces are usually component parts of process plants. These are primarily used to heat hydrocarbons of all types, from heavy crude oils and asphalt to the lightest hydrocarbon liquids or gases. They may also be used to heat other substances such as air or steam. A fired process furnace consists of three basic parts; a heating coil, a setting and a stack. The heating coil consists of length of tubing connected together which carry the material being heated. The setting is a suitable housing for firing. It is connected to a stack by means of a duct. The furnace may be fired by oil or gas burners. Instruments are generally used to control rate of firing and flow through coils to maintain desired operating conditions. The design, type, size and other similar design aspects of any individual furnace are based on and determined by various factors such as operating process, size of the unit, space available, economics, etc. However, safety and operational efficiency should be the primary factors in design consideration for furnace. 2.0 SCOPE

This document covers safety provisions in fired process furnaces in Petroleum Refinery, Chemical and Natural Gas Industry. These ishall be the minimum requirement and additional safety features have to be provided depending on individual situations. This does not include boilers and direct fired furnaces like direct fired air heater of FCCU and sulfur reaction furnace since they are specialty items.

KLM Technology Group


Project Engineering Standard

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)

Page 5 of 19
Rev: 01

August 2013

3.0

LOCATION

The following factors should be considered while locating a fired process furnace: 3.1 General

Furnace should be located only at edges of the process units to limit the hazard of open flame to only the small part of the plant facing the furnace and also to facilitate easy firefighting operations in case fire breaks out in the furnace. Also the furnace should be at least 15 meters away from the nearest process equipment handling hydrocarbon, with no sewer boxes, sampling points, etc. in between, from where hydrocarbon could emit vapors when the furnace is on. 3.2 Safe Distance from Roads

There should be a minimum distance of 15 meters from the periphery of the furnace to the edge of any road with vehicular traffic. 3.3 Wind Direction

Furnaces should always be located upwind or side wind from the rest of the plant. 3.4 F.D. Fan Location

F.D. fans wherever applicable should be located at grade. Air intake to the FD fan should be from a safe location so that no hydrocarbon can be pulled into them. 4.0 4.1 CLEARANCE / ACCESSIBILITY Bottom Fired Furnaces

There should be a minimum of 1.75 meters of headroom for the bottom fired furnace floor including plenum chamber, if any, above grade for operational conveniences and safety.

KLM Technology Group


Project Engineering Standard

FIRED PROCESS FURNACE BEST PRACTICES (PROJECT STANDARDS AND SPECIFICATIONS)

Page 6 of 19
Rev: 01

August 2013

4.2

Multi Floor Side Fired Furnaces

For multi floor side fired furnaces, 1.0 meter wide platform and 2.0 meter high headroom should be provided. 4.3 Valves

Unless remotely operated, valves on the fire box purge and coil purging steam lines should be located at least 15 meters away from the furnace in the form of a manifold and distinctly marked for easy identification. 4.4 Dampers

Dampers should be operable from ground. Position of damper while in operation should be distinctly visible from ground. 4.5 Explosion Doors

Explosion doors shall be provided for all furnaces to release accidental over pressures. Explosion doors should be located in such a way that the discharge is directed to a safe area. 5.0 5.1 BASIC DESIGN CRITERIA Configuration

The selection of the configuration of furnace, viz. vertical, horizontal, bottom fired, side fired, etc. should be judged from various design consideration like heat duty, service, etc. and safety consideration like layout limitations, accessibility, etc. 5.2 Materials of Construction

The selection of materials for various parts of the furnaces should be done depending on: a) b) c) Temperature Type of process fluid Type of fuel used

You might also like