You are on page 1of 21

DATA RATES- P AND M WORKS

C. LABOUR: Sl No 1 2 3 4

Description

Unit Day Day Day Day

Quantity 1.00 3.00 2.00 2.00

Maistry Stone chiseller Cl- I Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 148.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 445.50 264.00 261.00 1112.00 11.12 111.20 166.80 55.60 1456.72

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour TOTAL

Rs: Rs: Rs: Rs:

909.32 0.00 1456.72 2366.04

Add for enabling works @ Total cost for

0.00% 10.00 Nos. Rate per Each Rate approved per Each

Rs: Rs: Rs: Rs:

0.00 2366.04 237.00 237.00

NOTE:For providing 300 mm thick compacted murum bed in B.C soil area including additional excavation for thickness of murum bedding add per Each Rs: 5.00 SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11 ITEM No: 14

ITEM: Providing and fixing 200 x 200 x 750 mm size permanent bench mark stone in CC 1 :3 : 6 block of size 900 x 900 x 1200 mm using 40 mm down size graded coarse aggregate and providing 350 mm thick 300 mm high UCR masonry in CM 1 : 5 proportion protective wall alround the BM stone, including cost of all materials, labour, dressing top surface of stone, engraving BM data on top surface, excavation, finishing, curing etc., complete with lead upto 50 m and all lifts. DATA: For 1 permanent bench mark stone : Quantity of excavation ( 0.9 x 0.9 x 1.2 ) say : 1.00 cum Quantity of concrete 1 : 3 : 6 propn. 1 - ( 0.2 x 0.2 x 0.75 ) say : 0.95 cum Quantity of UCR masonry in CM 1 : 5 propn. (4 x 0.55 x 0.35 x 0.3) say : 0.25 cum 0.5 stone chiseller Cl- I for dressing top surface and engraving BM data for 1 stone. 1 Mason Cl- II and 2 Heavy mazdoors for excavation of pit, laying concrete, fixing BM stone and constructing protective masonry wall for 1 BM stone. 1 light mazdoor for handling concrete / masonry materials for 1 BM stone. 1 light mazdoor for curing at 1 hour daily for 2 weeks. Consider dressing, engraving BM data and fixing 1 stones in concrete including constructing protective masonry wall for rate analysis. 1. Requirement of materials : 200 x 200 x 750 mm stones

: 1 No.

40

DATA RATES- P AND M WORKS

Cement for concrete for fixing 1 stone Cement for UCR masonry Cement for finishing C A 40-20 mm size for concrete C A 20-10 mm size for concrete C A 10-4.75 mm size for concrete Rubble stones for masonry Stone chips for masonry Sand for concrete Sand for masonry and finishing 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Maistry Stone chiseller Cl-I Mason CL- II Heavy mazdoor Light mazdoor

( 0.95 x 238 x 1.01 ) ( 0.25 x 115 x 1.01 ) (LS) ( 0.95 x 0.5 x 1.02 ) ( 0.95 x 0.3 x 1.02 ) ( 0.95 x 0.2 x 1.02 ) ( 0.25 x 1 ) ( 0.25 x 0.15 ) ( 0.95 x 0.45 x 1.02 )

: : : : : : : : : :

228 kg 29 kg 13 kg 0.51 cum 0.31 cum 0.20 cum 0.25 cum 0.04 cum 0.44 cum 0.16 cum

: : : : :

1 No. 0.5 No. 1 No. 2 Nos. 3 Nos.

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Perticulars Unit Each kg cum cum cum cum cum cum Quantity

UNIT :

1.00 Nos. Rate in Rs. 13.00 4.00 381.00 520.00 669.00 200.00 240.00 199.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 13.00 1080.00 194.31 161.20 133.80 50.00 9.60 119.40 1761.31 17.61 176.13 88.07 0.00 0.00 2043.12

4 5 6

Rough stones 200 x 200 x 750 mm Cement Coarse aggregate 40-20 mm Coarse aggregate 20-10 mm Coarse aggregate 10-4.75 mm Rubble stone at quarry Stone chips at quarry Sand ( screened ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on stone @ Add Royalty charges on murum @

1.00 270.00 0.51 0.31 0.20 0.25 0.04 0.60

1% 10% 5% ( Included in material rate ) ( Included in material rate ) Total cost of Materials :

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery :

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

41

DATA RATES- P AND M WORKS

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit Day Day Day Day Day

Quantity 1.00 0.50 1.00 2.00 3.00

Maistry Stone chiseller Cl- I Mason Cl- II Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 148.50 148.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 74.25 148.50 264.00 391.50 1019.75 10.20 101.98 152.96 50.99 1335.87

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery

Rs: Rs:

2043.12 0.00

C. Cost of Labour TOTAL Add for enabling works @ Total cost for 0.00% 1.00 Nos. Rate per Each Rate approved per Each YEAR: 2010-11

Rs: Rs: Rs: Rs: Rs: Rs:

1335.87 3378.99 0.00 3378.99 3379.00 3379.00 ITEM No: 15

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment including stacking all materials separately as directed with initial lead upto 50 m and all lifts. DATA: Total thickness of rivetment Thickness of sand layer Thickness of 10 mm down CA layer Thickness of 40 mm CA layer Thickness of rough stone layer including stone chips Consider 100 sqm rivetment area: Quantity of materials to be removed: Rough stones and stone chips 40 mm down filter backing 10 mm down filter backing sand filter backing : : : : : 1.05 m 150 mm 150 mm 150 mm 600 mm

: 60.00 cum : 15.00 cum : 15.00 cum : 15.00 cum Total : 105.00 cum Consider removal of 105 cum materials for 100 sqm rivetment and filter for rate analysis. 1. Requirement of materials : No materials required. 2. Requirement of machinery : No machinery proposed for the work.

42

DATA RATES- P AND M WORKS

3. Requirement of workforce : For removing, conveying and stacking stone / chips ( 1 heavy mazdoor 4 cum / day) Masom Class-II : 6 Nos Heavy mazdoor ( 15 for 60 cum stones and 3 for loading 9 cum chips ) : : 18 Nos. Maistry : 1 No. Light mazdoor for stone chips : 3 Nos. For removing, conveying and stacking 40-20 mm CA ( 1 heavy and 1 light 4 cum / day). Heavy mazdoor : 4 Nos. Light mazdoor : 4 Nos. For removing, conveying and stacking 10 mm down CA ( 1 heavy and 1 light 4 cum / day). Heavy mazdoor : 4 Nos. Light mazdoor : 4 Nos. For removing, conveying and stacking sand ( 1 heavy and 1 light 4 cum / day). Heavy mazdoor : 4 Nos. Light mazdoor : 4 Nos.

RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity

UNIT :

105.00 cum Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 1% 10% 5% Total cost of Materials :

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day Day Day

Quantity 1.00 6.00 30.00 15.00 1% 10% 15%

Maistry Mason Class-II Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @

Rate in Rs. 141.50 148.50 132.00 130.50 Total Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 891.00 3960.00 1957.50 6950.00 69.50 695.00 1042.50

43

DATA RATES- P AND M WORKS

Add for Contractor's Overheads @

5% Total cost of Labour :

Rs: Rs:

347.50 9104.50

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 105.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

0.00 0.00 9104.50 9104.50 0.00 9104.50 87.00 87.00 ITEM No: 16

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Re-constructing 600 mm thick hand packed rough stone revetment with through stones at

1.5 m c / c over a backing of 450 mm thick graded filter media consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 150 mm thick each using sand from approved quarry and stones and filter aggregates obtained from revetment removed for re-construction including cost of all machinery, labour, laying filter and stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts. DATA: Total thickness of revetment Thickness of sand layer Thickness of 10 mm down CA layer Thickness of 40 mm CA layer Thickness of rough stone layer Consider 100 sqm revetment area for rate analysis: 1. Requirement of materials : Rough stones 30 to 45 cm long ( available ) Through stones 65 to 75 cm long @ 1.5 m interval ( available ) Stone chips @ 15 percent of stone ( available ) 40 mm down filter backing ( available ) 10 mm down filter backing ( available ) Sand filter backing frm quarry ( 100 x 0.15 x 1.02 ) 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : For assessing labour average height between berms is considered. For conveying and laying sand ( 1 heavy and 1 light 5 cum / day). Heavy mazdoor Light mazdoor For conveying and laying 10 mm down CA ( 1 heavy and 1 light 5 cum / day). Heavy mazdoor Light mazdoor For conveying and laying 40-20 mm CA ( 1 heavy and 1 light 5 cum / day). Heavy mazdoor Light mazdoor For conveying and laying stone / chips Masom Class-II Heavy mazdoor : : : : : 1.05 m 150 mm 150 mm 150 mm 600 mm

: : : : : :

57.60 cum 44 Nos 9.00 cum 15.00 cum 15.00 cum 15.30 cum

: 3 Nos. : 3 Nos. : 3 Nos. : 3 Nos. : 3 Nos. : 3 Nos. : 5 Nos. : 15 Nos.

44

DATA RATES- P AND M WORKS

Maistry RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Perticulars Unit cum cum cum cum cum Nos Quantity 15.30 15.00 15.00 9.00 57.60 44.00 1% UNIT :

: 1 No. 100.00 sqm Rate in Rs. 154.00 0.00 0.00 0.00 0.00 0.00 Total Rs: Rs: Contd Amount in Rs. 2356.20 0.00 0.00 0.00 0.00 0.00 2356.20 23.56

Sand ( unscreened ) ( from quarry ) Coarse aggregate 10 mm ( available) Coarse aggr. 40-20 mm ( available ) Stone chips ( available ) Rough stones ( available ) Through stones ( available ) Add for small Tools and Plants @

A. MATERIALS ( Contd ) : Sl No Perticulars

Unit

Quantity

Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on sand @

10% 5% ( Included in material rate ) Total cost of Materials :

Rate in Rs. Contd Rs: Rs: Rs: Rs:

Amount in Rs. 235.62 117.81 0.00 2733.19

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day Day Day

Quantity 1.00 5.00 24.00 9.00

Maistry Mason Class-II Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 148.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 742.50 3168.00 1174.50 5226.50 52.27 522.65 783.98 261.33 6846.72

ABSTRACT: A. Cost of Materials including royalty charges

Rs:

2733.19

45

DATA RATES- P AND M WORKS

B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: YEAR: 2010-11

0.00 6846.72 9579.91 0.00 9579.91 96.00 96.00 ITEM No: 17

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of specified thickness each using sand from approved quarry and stones and filter aggregates obtained from rock-toe removed for re-construction including cost of all machinery, labour, laying filter and

stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts. DATA: Details of Rock-toe: Top width : Side slope upstream side : Side slope down stream side : Height : Cross sectional area ( 1.50 + 10.50 ) x 3 / 2 : Details of Filter behind & below rock-toe: Thickness of sand layers : Thickness of 20 mm down CA layers : Thickness of 80-20 mm CA filter : Consider reconstruction of 100 cum of rock-toe and filter together for rate analysis : 1. Requirement of materials : Quantity of stones to be reused : Quantity of stone chips to be reused : Quantity of 80-20 mm filter to be reused : Quantity of 20 mm down filter to be reused : Quantity of sand to be replaced by fresh sand : Surface finishing required ( 12.40 x 58.20 / 18 ) : 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : For reconstructing rock-toe : Heavy mazdoor for supplying rubble : Light mazdoor for supplying stone chips : Mason Class-II for packing chips and surface finishing : Heavy mazdoor for assisting mason : For relaying filter materials: For conveying and laying sand ( 1 heavy and 1 light mazdoor 5 cum / day ). Heavy mazdoor : Light mazdoor : For conveying and laying 20 mm down CA ( 1 heavy and 1 light 5 cum / day ). Heavy mazdoor : Light mazdoor : For conveying and laying 80-20 mm CA ( 1 heavy and 1 light 5 cum / day ).

1.50 m 1( V ) :1 ( H ) 1( V ) :2 ( H ) 3.00 m 18.00 sqm 200 mm 250 mm 400 mm

58.20 cum 8.70 cum 19.40 cum 12.10 cum 9.80 cum 40 sqm

20 Nos. 3 Nos 7 Nos. 7 Nos.

2 Nos 2 Nos. 3 Nos. 3 Nos.

46

DATA RATES- P AND M WORKS

Heavy mazdoor Light mazdoor Maistry RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 Perticulars Unit cum cum cum cum Quantity 58.20 8.70 19.40 12.10 UNIT :

: 4 Nos. : 4 Nos. : 1 No. 100.00 cum Rate in Rs. 0.00 0.00 0.00 0.00 Contd Amount in Rs. 0.00 0.00 0.00 0.00

Rubble ( available ) Stone chips ( available ) 80-20 mm filter ( available ) 20 mm down filter ( available )

A. MATERIALS ( Contd ) : Sl No Perticulars

Unit

Quantity

Sand ( unscreened )( fresh from quarry ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on sand @

cum

9.80

1% 10% 5% ( Included in material rate ) Total cost of Materials :

Rate in Rs. Contd 154.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 1509.20 1509.20 15.09 150.92 75.46 0.00 1750.67

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day Day Day

Quantity 1.00 7.00 36.00 12.00

Maistry Mason Cl II Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 148.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 1039.50 4752.00 1566.00 7499.00 74.99 749.90 1124.85 374.95 9823.69

ABSTRACT:

47

DATA RATES- P AND M WORKS

A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

1750.67 0.00 9823.69 11574.36 0.00 11574.36 116.00 116.00 ITEM No: 18

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types of slab

lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with lead upto 50 m and all lifts. DATA: Consider removing and resetting of 100 sqm slab lining in CM 1 : 3 for rate analysis. 1. Requirement of materials: Cement mortar 1:3 propn for joints : Cement with 1 percent wastage : Sand with 2 percent wastage : 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Removing / Cleaning disturbed slabs Heavy mazdoor : Resetting and jointing stone slabs Mason Cl I : Assisting mason for relaying stones Heavy mazdoor : Cement mortar mixing and conveying Heavy mazdoor : Cartman with Double bullock cart for conveying water : Curing Light mazdoor : RATE ANALYSIS A. MATERIALS: Sl No 1 2 Perticulars Unit kg cum Quantity 101.00 0.21 UNIT :

0.20 cum 101 kg 0.21 cum

2 Nos. 4 Nos. 2 Nos. 1 No. 1 No. 1 No.

100.00 sqm Rate in Rs. 4.00 199.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 404.00 41.79 445.79 4.46 44.58 22.29 0.00 517.12

Cement 43 Gr Sand ( screened ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on sand @

1% 10% 5% ( Included in material rate ) Total cost of Materials :

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00 1% 10%

Add for small Tools and Plants @ Add for Contractor's Profit on DPOL / Energy @

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00

48

DATA RATES- P AND M WORKS

Add for Contractor's Overheads @

5% Total hire charges of Machinery :

Rs: Rs:

0.00 0.00

C. LABOUR: Sl No 1 2 3

Description

Unit Day Day Day

Quantity 1.00 4.00 5.00

Maistry Mason Class I Heavy mazdoor

Rate in Rs. 141.50 159.00 132.00 Contd

Amount in Rs. 141.50 636.00 660.00

C. LABOUR ( Contd ) : Sl No Description

Unit

Quantity

4 5

Cartman with Bullock cart for water Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

Day Day

1.00 1.00

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. Contd 178.50 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 178.50 130.50 1746.50 17.47 174.65 261.98 87.33 2287.92

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: YEAR: 2010-11

517.12 0.00 2287.92 2805.03 0.00 2805.03 28.00 28.00 ITEM No: 19

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and resetting disturbed dry rubble / size stone pitching 250 to 450 mm thick including packing, wedging, finishing etc., complete with all leads and lifts. DATA: Consider removing and resetting of 100 sqm pitching for rate analysis. 1. Requirement of materials: Available materials from removal of disturbed pitching. 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Heavy mazdoor for removing and handling stones and chips Mason cl- II for re-laying and packing stones Maistry RATE ANALYSIS UNIT :

: 6 Nos : 6 Nos. : 1 No. 100.00 sqm

49

DATA RATES- P AND M WORKS

A. MATERIALS: Sl No 1

Perticulars NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

1% 10% 5% Total cost of Materials :

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day Day

Quantity 1.00 6.00 6.00

Maistry Mason Class II Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 148.50 132.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 891.00 792.00 1824.50 18.25 182.45 273.68 91.23 2390.10

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: YEAR: 2010-11

0.00 0.00 2390.10 2390.10 0.00 2390.10 24.00 24.00 ITEM No: 20

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and refixing disturbed chainage / demarcation / hectometre / guard stones including excavation, back filling etc., complete with all leads and lifts. DATA: 1 heavy mazdoor can remove and refix 9 stones / day @ 45 minutes per stone. Consider removing and refixing 18 stones for rate analysis.

50

DATA RATES- P AND M WORKS

1. Requirement of materials: Available materials from removal of disturbed stones. 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Maistry Heavy mazdoor

: 1 No. : 2 Nos.

RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity

UNIT :

18.00 Nos. Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 1% 10% 5% Total cost of Materials :

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day

Quantity 1.00 2.00

Maistry Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 132.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 264.00 405.50 4.06 40.55 60.83 20.28 531.21

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour TOTAL Add for enabling works @ Total cost for 0.00% 18.00 Nos.

Rs: Rs: Rs: Rs: Rs: Rs:

0.00 0.00 531.21 531.21 0.00 531.21

51

DATA RATES- P AND M WORKS

Rate per Each Rate approved per Each SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11

Rs: Rs:

30.00 30.00 ITEM No: 21

ITEM: Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including excavation, back filling with available stuff after refixing, forming base platform of size 900 x 900 x 75 mm including watering, ramming etc complete with all leads and lifts.

DATA: 1 heavy mazdoor can remove and refix 4 stones / day @ 2 hours per stone. Consider removing and refixing 8 stones for rate analysis. 1. Requirement of materials: Available materials from removal of disturbed stones. 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Maistry Heavy mazdoor RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity 0.00 0.00 1% 10% 5% Total cost of Materials : UNIT :

: 1 No. : 2 Nos. 8.00 Nos.

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day

Quantity 1.00 2.00 1% 10% 15% 5%

Maistry Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

Rate in Rs. 141.50 132.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 141.50 264.00 405.50 4.06 40.55 60.83 20.28

52

DATA RATES- P AND M WORKS

Total cost of Labour : ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour TOTAL

Rs:

531.21

Rs: Rs: Rs: Rs:

0.00 0.00 531.21 531.21

Add for enabling works @ Total cost for

0.00% 8.00 Nos. Rate per Each Rate approved per Each YEAR: 2010-11

Rs: Rs: Rs: Rs:

0.00 531.21 66.00 66.00 ITEM No: 22

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Providing impervious hearting for breached / damaged portion of embankment with soil from approved borrow areas in layers of 250 to 300 mm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated by using combination of road roller and dozer etc., complete with initial lead upto 1 km and all lifts. DATA: Capacity of shovel bucket Capacity of shovel bucket under heaped condition Capacity of tipper Lead for conveyance of soil Speed for loaded tipper under haul road condition Speed for empty tipper under haul road condition Turning and unloading time Shovel digging and loading cycle per bucket In-situ qty / bucket for 15 % bulkage of soil In-situ quantity per load for 20 % bulkage of soil Number of buckets per load Cycle time for loading 8 buckets Round trip cycle time for tipper: Ideal cycle time of shovel for digging and loading Time for 1km haulage under load Time for turning and un-loading Time for 1 km return trip Time for turning and spotting : : : : : : : : : : say : say : 0.50 cum 0.58 cum 5.00 cum Upto 1 km 15 km / hr 20 km / hr 2.00 min 20 sec 0.50 cum 4.00 cum 8 buckets 2.67 min

( 0.58 / 1.15 ) ( 5.0 / 1.2 ) ( 4.00 / 0.50 ) ( 8 x 20 / 60 )

: 2.67 min : 4.00 min : 2.00 min ( 60 / 20 ) : 3.00 min : 0.50 min Total : 12.17 min As the movement of tippers will be slow in breached portion due limited area 1 minute extra time may be considered for the round trip cycle time of tippers. Corrected round trip cycle time for tipper ( 12.17 + 1.00 ) : 13.17 min No.of tippers to match corrected cycle time of tipper ( 13.17 / 2.67) say : 5 Nos Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 13.17 ) say : 15.20 cum Output for 5 tippers per day ( 5 x 15.2 x 8 ) say : 608 cum ( 60 / 15 ) The in-situ dry density of soil in borrow area will be generally less than dry density of compacted embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction. For 95 % density control of embankment a shrinkage factor of 5 % may be assumed.

53

DATA RATES- P AND M WORKS

Quantity of embankment considering 5 %shrinkage ( 608 x 0.95 ) Qty of soil for computing royalty charges @ 1.6 t /cum ( 578 x 1.6 ) 1. Stripping of borrow area / Formation of rampways in breached portion : Area to be stripped assuming 2.0 m depth of cut ( 608 / 2.0 ) Depth of stripping

say : 578 cum : 925 tonnes

: 304 sqm : 0.25 m

Qty of stripping with 5 % extra area ( 304 x 1.05 x 0.25 ) : 80 cum Output of dozer per hr with 50 min / hr working for stripping : 100 cum Time required for stripping 80 cum say : 0.80 hour Consider 1 hour including time for shifting dozer etc., for stripping borrow for one day work. Further, use of dozer is necessary for forming rampways and for trimming the old embankment on either side in breached portion to required slope for abutting the fresh embankment layers. Assume use of dozer for 0.5 hour daily for this purpose. Deploy dozer for stripping / forming ramps / slopes etc., for 1 day work : 1.5 hour 2. Collection of soil for embankment: Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil. Deploy 5 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area. 3. Spreading soil in 250 to 300 mm layer: Quantity of loose soil to be spread Output of dozer for levelling per hour Time required for levelling 730 cum

( 608 x 1.20 )

: 730 cum : 200 cum say : 3.50 hours

4. Watering; Generally soil in the borrow area will be in moist condition. In the beginning of the season no watering may be necessary and in summer months about 8 to 10 percent watering may be needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 578 cum of embankment will be about 5 tanker loads of 8000 ltrs each. Deploy 8000 ltr capacity water tanker for 5 hours for watering before rolling. Deploy 5 hp pump for 2.5 hours. 5. Compaction: Soil collected for embankment layer gets compacted to some extent during levelling by dozer. Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining adjacent to breached portion a combination of 8 to 10 passes of road roller followed by 2 to 4 passes of dozer is considered for compaction and roughening top surface for laying next layer. Effective length of roller drum : 1.50 m Speed of roller per hour : 3.0 km Thickness of layer : 0.3 m Number of roller passes : 9 Nos Output of road roller / hr with 50 min / hr working and 70 % effinciancy: ( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 say : 88 cum Time for rolling 730 cum soil in embankment layer say : 8.5 hours Effective width of dozer track : 1.00 m Speed of dozer per hour : 4.0 km Thickness of layer : 0.3 m Number of dozer passes : 3 Nos Output of dozer / hr with 50 min / hr working and 70 % effinciancy: ( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 say : 230 cum

54

DATA RATES- P AND M WORKS

Time for compacting 730 cum soil in embankment layer Deploy road roller for 8.5 hours and dozer for 3 hours for compaction. 6. Sorting out / sectioning / labour for testing etc : Assume 2 heavy and 2 light mazdoors.

say : 3.00 hours

RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity

UNIT :

578.00 cum Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 9250.00 9250.00

0.00 0.00 1% 10% 5% Rs: 10.00 / tonne Total cost of Materials :

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on 925 t soil @

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 8.00 8.00 8.00 8.00 40.00 40.00 2.50 2.50 5.00 5.00 8.50 8.50 2.00

Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 5 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Road roller 10 tonne ( diesel ) Fuel / Energy charges Sundries

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Rate in Rs. 1154.00 423.00 725.00 330.00 271.00 208.00 7.00 55.00 268.00 208.00 228.00 495.00 30.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 9232.00 3384.00 5800.00 2640.00 10840.00 8320.00 17.50 137.50 1340.00 1040.00 1938.00 4207.50 60.00 48956.50 489.57 1978.90 2447.83 53872.79

Description

Unit Hour Hour Hour Hour Hour Hour Day Day

Quantity 8.00 8.00 40.00 2.50 5.00 8.50 2.00 2.00

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller Maistry Heavy mazdoor

Rate in Rs. 77.50 77.50 56.70 35.80 56.70 72.00 141.50 132.00

Amount in Rs. 620.00 620.00 2268.00 89.50 283.50 612.00 283.00 264.00

55

DATA RATES- P AND M WORKS

Light mazdoor Add for small Tools and Plants @

Day

2.00 1%

130.50 Total Rs: Rs: Contd

261.00 5301.00 53.01

C. LABOUR ( Contd ) : Sl No Description

Unit

Quantity

Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

10% 15% 5% Total cost of Labour :

Rate in Rs. Contd Rs: Rs: Rs: Rs:

Amount in Rs. 530.10 795.15 265.05 6944.31

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 1.00% Rs: 578.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

9250.00 53872.79 6944.31 70067.10 700.67 70767.77 122.00 122.00 ITEM No: 23

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Providing pervious/semi-pervious casing for breached / damaged portion of embankment with soil from approved borrow areas in layers of 250 to 300 mm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated using combination of road roller and dozer etc., complete with initial lead upto 1 km and all lifts. DATA: Capacity of shovel bucket Capacity of shovel bucket under heaped condition Capacity of tipper Lead for conveyance of soil Speed for loaded tipper under haul road condition Speed for empty tipper under haul road condition Turning and unloading time Shovel digging and loading cycle per bucket In-situ qty per bucket for 15 % bulkage of soil In-situ quantity per load for 20 % bulkage of soil Number of buckets per load Cycle time for loading 8 buckets Round trip cycle time for tipper: Ideal cycle time of shovel for digging & loading Time for 1km haulage under load Time for turning and un-loading Time for 1 km return trip Time for turning and spotting : : : : : : : : : say : say : say : : : : : : : 0.50 cum 0.58 cum 5.00 cum Upto 1 km 15 km / hr 20 km / hr 2.00 min 25 sec 0.50 cum 4.00 cum 8 buckets 3.50 min 3.50 min 4.00 min 2.00 min 3.00 min 0.50 min 13.00 min

( 0.58 / 1.15 ) ( 5.0 / 1.2 ) ( 4.00 / 0.50 ) ( 8 x 25 / 60 )

( 60 / 15 ) ( 60 / 20 ) Total

56

DATA RATES- P AND M WORKS

As the movement of tippers will be slow in breached portion due limited area 1 minute extra time may be considered for the round trip cycle time of tippers. Corrected round trip cycle time for tipper ( 13.00 + 1.00 ) : 14.00 min

No.of tippers to match corrected cycle time of tipper (14.00 / 3.5.00) : 4 Nos Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 14.00 ) : 14.30 cum Output for 3 tippers per day ( 4 x 14.30 x 8 ) say : 458 cum The in-situ dry density of soil in borrow area will be generally less than dry density of compacted embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction of embankment. For 95 % density control of embankment in breached portion a shrinkage factor of 5 % may be assumed. Quantity of embankment considering 5 %shrinkage ( 458 x 0.95 ) say : 435 cum Qty of soil for computing royalty charges @ 1.6 t /cum ( 435 x 1.6 ) : 696 tonnes 1. Stripping of borrow area : Area to be stripped assuming 2.0 m depth of cut ( 458 / 2.0 ) : 229 sqm Depth of stripping : 0.20 m Qty of stripping considering 5 % extra area ( 229 x 1.05 x 0.20 ) : 48 cum Output of dozer per hr with 50 min / hr working for stripping : 70 cum Time required for stripping 48 cum : 0.70 hours Consider 1 hour including time for shifting. Further, use of dozer is necessary for forming rampways and for trimming the old embankment on either side of breached portion to required slope for abutting the fresh embankment layers. Assume use of dozer for 0.5 hour daily for this purpose. Deploy dozer for stripping / forming ramps / slopes for 1 day work : 1.5 hour 2. Collection of soil for embankment: Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil. Deploy 4 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area. 3. Spreading soil in 250 to 300 mm layer: Quantity of loose soil to be spread ( 458 x 1.20 ) : 550 cum Output of dozer for levelling per hour : 200 cum Time required for levelling 550 cum say : 2.75 hours Deploy dozer for 3 hours for spreading soil. 4. Watering; Generally soil in the borrow area will be in moist condition. In the beginning of the season no watering be may necessary and in summer months about 8 to 10 percent watering may be needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 4 to 5 percent watering by weight, daily requirement of water for 435 cum of embankment will be about 4 tanker loads of 8000 ltrs each. Deploy 8000 ltr capacity water tanker for 4 hours for watering before rolling. Deploy 5 hp pump for 2 hours. 5. Compaction: Soil collected for embankment layer gets compacted to some extent during levelling by dozer. Generally 8 to 10 passes of vibratory pad foot roller is adequate for achieving specified density control of 95 percent. However, as rolling by vibratory padfoot roller may disturb the canal lining adjacent to the breached portion a combination of 8 to 10 passes of road roller followed by 2 to 4 passes of dozer is considered for compaction and roughening the top surface for laying next layer. Effective length of roller drum : 1.50 m Speed of roller per hour : 3.0 km

57

DATA RATES- P AND M WORKS

Thickness of layer Number of roller passes

: 0.3 m : 9 Nos

Output of road roller / hr with 50 min / hr working and 70 % effinciancy: ( 1.5 x 3000 x 0.3 x 0.70 / 9 ) x 50 / 60 Time for rolling 550 cum soil in embankment layer Effective width of dozer track Speed of dozer per hour Thickness of layer Number of dozer passes Output of dozer / hr with 50 min / hr working and 70 % effinciancy: ( 1.0 x 4000 x 0.3 x 0.70 / 3 ) x 50 / 60 Time for rolling 550 cum soil in embankment layer Deploy road roller for 6.5 hours and dozer for 2.5 hours for compaction. 6. Sorting out / sectioning / labour for testing etc : Assume 2 heavy and 2 light mazdoors. RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity 0.00 0.00 1% 10% 5% Rs: 10.00 / tonne Total cost of Materials : UNIT :

say : say : : : : :

88 cum 6.5 hours 1.00 m 4.0 km 0.3 m 3 Nos

say : 230 cum say : 2.5 hours

435.00 cum Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 6960.00 6960.00

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add Royalty charges on 696 t soil @

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS

Quantity 7.00 7.00 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 6.50 6.50 2.00 1% 10% 5%

Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Road roller 10 tonne ( diesel ) Fuel / Energy charges Sundries

Add for small Tools and Plants @ Add for Contractor's Profit on DPOL / Energy @ Add for Contractor's Overheads @

Rate in Rs. 1154.00 423.00 725.00 330.00 271.00 208.00 7.00 55.00 268.00 208.00 228.00 495.00 30.00 Total Rs: Rs: Rs: Rs:

Amount in Rs. 8078.00 2961.00 5800.00 2640.00 8672.00 6656.00 14.00 110.00 1072.00 832.00 1482.00 3217.50 60.00 41594.50 415.95 1647.65 2079.73

58

DATA RATES- P AND M WORKS

Total hire charges of Machinery :

Rs:

45737.82

C. LABOUR: Sl No 1 2 3 4 5 6 7 8 9

Description

Unit Hour Hour Hour Hour Hour Hour Day Day Day

Quantity 7.00 8.00 32.00 2.00 4.00 6.50 2.00 2.00 2.00

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller Maistry Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 77.50 77.50 56.70 35.80 56.70 72.00 141.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 542.50 620.00 1814.40 71.60 226.80 468.00 283.00 264.00 261.00 4551.30 45.51 455.13 682.70 227.57 5962.20

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 1.00% Rs: 435.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

6960.00 45737.82 5962.20 58660.02 586.60 59246.62 136.00 136.00 ITEM No: 24

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Providing impervious hearting for breached / damaged portion of embankment with soil from approved dump areas in layers of 250 to 300 mm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil,sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 95 percent or as stipulated by using combination of road roller and dozer etc., complete with initial lead upto 1 km and all lifts. DATA: Capacity of shovel bucket Capacity of shovel bucket under heaped condition Insitu qty / bucket for 10 % bulkage of soil in dump area Capacity of tipper Lead for conveyance of soil Speed for loaded tipper under haul road condition Speed for empty tipper under haul road condition Turning and unloading time : : : : : : : : 0.50 cum 0.58 cum 0.53 cum 5.00 cum Upto 1 km 15 km / hr 20 km / hr 2.00 min

Same digging and loading cycle as considered for borrow area may be assumed for use of soil from spoil bank formed during construction of canal in view of partial settlement of soil. Shovel digging and loading cycle per bucket : 20 sec

59

DATA RATES- P AND M WORKS

In-situ quantity per load for 10 % bulkage of soil Number of buckets per load Cycle time for loading 8 buckets Round trip cycle time for tipper: Ideal cycle time of shovel for digging and loading Time for 1km haulage under load Time for turning and un-loading Time for 1 km return trip Time for turning and spotting

( 5.0 / 1.1 ) ( 4.54 / 0.53 ) ( 8 x 20 / 60 )

say : 4.54 cum say : 8 buckets say : 2.70 min

: 2.70 min : 4.00 min : 2.00 min ( 60 / 20 ) : 3.00 min : 0.50 min Total : 12.20 min As the movement of tippers will be slow in breached portion due limited area 1 minute extra time may be considered for the round trip cycle time of tippers. Corrected round trip cycle time for tipper ( 12.20 + 1.00 ) : 13.20 min No.of tippers to match corrected cycle time of tipper ( 13.20 / 2.70 ) say : 5 Nos Output of tipper / hr with 50 min working / hr ( 50 x 4.54 / 13.2 ) : 17.20 cum Output for 5 tippers per day ( 5 x 17.20 x 8 ) say : 688 cum The in-situ dry density of soil in borrow area will be generally less than dry density of compacted embankment. Therefore, the rolled embankment quantity will be slightly less than the borrow area in-situ quantity. The extent of shrinkage in quantity depends on the degree of compaction of embankment. For 95 % density control of embankment in breached portion a shrinkage factor of 5 % may be assumed for use of borrow area soil. Further, as the insitu density of soil in dump area will be less compared to natural ground due to bulkage of soil during excavation for applying the shrinkage foctor it is necessary to convert the insitu dump area quantity to equivalent borrow area quantity by applying bulkage factor. Equivalent borrow area quantity for 10% bulkage ( 688 / 1.1 ) : 625 cum Qty of compacted embankment for 5 % shrinkage ( 625 x 0.95 ) : 594 cum Qty of soil for computing royalty charges @ 1.6 t /cum ( 594 x 1.6 ) : 950 tonnes ( 60 / 15 ) 1. Stripping of borrow area : Since soil is from dump area no stripping is involved. However, use of dozer is necessary for forming rampways and for trimming the old embankment on either side of breached portion to required slope for abutting the fresh embankment layers. Assume use of dozer for 0.5 hour daily for this purpose. Deploy dozer for forming ramps / slopes for 1 day work : 0.5 hour 2. Collection of soil for embankment: Deploy one 0.50 cum capacity shovel for 8 hours for re-excavation and loading soil. Deploy 5 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area. 3. Spreading soil in 250 to 300 mm layer: Quantity of loose soil to be spread ( 688 / 1.10 ) : 757 cum Output of dozer for levelling per hour : 200 cum Time required for levelling 757 cum say : 4.00 hours 4. Watering; Generally soil in the dump area will be in moist condition. In the beginning of the season no watering may be necessary. However, in summer months as the loose soil looses moisture at faster rate compared to borrow area about 10 to 12 % watering may be needed to maintain the soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal average of 5 to 6 percent watering by weight, requirement of water for 594 cum of embankment will be about 7 tanker loads of 8000 ltrs each. Deploy 8000 ltr capacity water tanker for 7 hours for watering before rolling. Deploy 5 hp pump for 3.5 hours.

60

You might also like