You are on page 1of 30

SUMMARY TRANSFORMER ROOM

AS PER B.O.Q PAGE NO. DIVISION NO.


TOTAL AMOUNT TOTAL AMOUNT 100.00%

AS PER EXECUTED

2 3 4 5 7 8 9 15 16

Site Work Concrete Masonry Metal Thermal and Moisture Protection Doors and Windows Finishes Mechanical Electrical

1,675.250 4,012.500 414.000 140.000 #REF! 0.000 1,431.250 3,284.250 17,681.000

1,675.250 4,012.500 414.000 140.000 890.350 1,200.000 1,431.250 3,284.250 17,681.000

100.00%

100.00%

100.00%

#REF!

#DIV/0!

100.00%

100.00%

100.00%

Grand Total

#REF!

#REF!

30,728.600

Amount in words:

Thirty Thousand Seven Hundred Twenty Eight & Sixty Fills& Only

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 2 SITE WORK The Contractor is referred to the specifications & drawings for all details related to division of the works and he is to include for complying with all the requirements contained there in whether or Section 02110 Demolition & Site preparations 2.1 Site cleaning including demolition of any existing structure until the foundations with removing the foundations and all debris within the working space as per requirement and engineer's approval including cleaning and grading of soil and excavated material to distance approved by municipality and Filling with lean concrete if reach more than the approved level. Section 02222 Excavation for Building 2.2 Excavation mechanically/manually in any type of soil up to the required height including removing any obstruction during excavation and removal of surplus excavation material from site. Excavation starting from N.G.L. to the foundation bed. Section 02223 Filling & Back Filling 2.3 Filling and back filling with approved clear sand/soil for excavated area of building. All complete as per drawings and specifications. Filling shall be compacted in layers ( not more than 25 cm thick each) and compaction shall not be less than 98% dry density. Section 02280 Termite Control Termite Control/Soil treatment for the whole building all as described. 62 M3 1.5 93.000
100.00% 100.00% 93.000

L.S

L.S

1000

1000.000

100.00% 100.00%

1,000.000

2.2.1

47

M3

1.75

82.250

100.00% 100.00%

82.250

2.4

L.S

L.S

500

500.000

100.00% 100.00%

500.000

CARRIED TO COLLECTION

1,675.250

1,675.250

DOC(III-4)

SITE WORK

(2-2)

....../ TRANSFORMER ROOM- UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

Note: a The excavation, filling and back filling, substructure, including water proofing systems. These quantities are based on bearing capacity 1.5kg/cm2 exact quantity for each site will depend on the recommendations of soil investigation report for each site and contractor must provides engineers with soil investigations reports for site. During execution of Site Work and excavation if any external services require protection, diversions / re-routing including any modification there to. The Contractor shall implement such works as per statutory authorities and Engineer's approval and the cost of such work is deemed to be included in the Contractor's Price.

CARRIED TO COLLECTION

DOC(III-4)

SITE WORK

(2-3)

....../ TRANSFORMER ROOM- UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 2 SITE WORK COLLECTION 1 TOTAL OF PAGE (2-1) 1675.250 1675.250

CARRIED TO SUMMARY

1,675.250

1,675.250

DOC(III-4)

SITE WORK

(2-4)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 3 CONCRETE The Contractor is referred to the specifications & drawings for all details related to division of the works and he is to include for complying with all the requirements contained there in whether or Section 03300 Cast-in-Place Concrete Plain Concrete - Grade K-150 Plain concrete using sulphate resisting cement including form work and all other materials. 10 cm thick under Footing 5 cm thick under G.B.

3.1 3.1.1 3.1.2 3.1.3

31 12

M2 M2 M2

3.500 2.000 2.000

108.500 24.000 62.000

0.00% 0.00% 0.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

108.500 24.000 62.000

5 cm thick Sand Cement Screed under Footings 31 Reinforced Concrete Reinforced concrete Grade K-300 using sulphate resisting cement filled into formwork and tamped around reinforcement including all watertight formwork, tie bolts and reinforcement, all complete as per drawing. R.C. Footings R.C. slab-on-grade R.C. Ground Beam R.C. Trance wall R.C. Neck Columns Reinforced concrete Grade K-300 using ordinary Portland cement filled into formwork and tamped around reinforcement including all formwork and reinforcement (fair finished on all exposed faced) Or Preferred Column, Beams & Slabs to be precast concrete complete skeleton With R.C. Columns R.C. beams, parapet etc. R.C. Suspended solid slabs 16 8 5 4 1

3.2

3.2.1 3.2.2 3.2.3 3.2.3 3.2.4 3.3

M3 M3 M3 M3 M3

67.000 72.000 87.000 90.000 93.000

1072.000 576.000 435.000 360.000 93.000

0.00% 0.00% 0.00% 0.00% 0.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

1,072.000 576.000 435.000 360.000 93.000

3.3.1 3.3.2 3.3.3

4 4 7

M3 M3 M3

90.000 87.000 82.000

360.000 348.000 574.000

0.00% 0.00% 0.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

360.000 348.000 574.000

CARRIED TO COLLECTION

4,012.500

4,012.500

DOC(III-4)

SITE WORK

(2-5)

....../ TRANSFORMER ROOM-

DIVISION - 3 CONCRETE COLLECTION 1 TOTAL OF PAGE (3-1) 4012.500 4012.500

CARRIED TO SUMMARY

4,012.500

4,012.500

DOC(III-4)

SITE WORK

(2-6)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 4 MASONRY Section 04200 Masonry 4.1. Non load bearing solid concrete block work, duly bedded in cement and sand mortar including R.C. lintel, head fixing, curing, scaffolding to any height galvanized steel ties etc. and all works complete as per drawings. 200 mm thick block wall 92 M2 4.500 414.000
0.00% 100.00% 100.00% 414.000

4.1.1

CARRIED TO COLLECTION

414.000

414.000

DOC(III-4)

SITE WORK

(2-7)

....../ TRANSFORMER ROOM-

DIVISION - 4 MASONRY COLLECTION 1 TOTAL OF PAGE (4-1) 414.000 414.000

CARRIED TO SUMMARY

414.000

414.000

DOC(III-4)

SITE WORK

(2-8)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 5 METAL Section 05500 Metal Fabrication Chequered Plate 5.1 Galvanized steel chequer plate over Substation trance, 4 mm thickness, fitting, fixing with angle iron frame in position, all complete as per Manufacturer's / Engineer's instruction.

M2

20.000

140.000

0.00%

100.00% 100.00%

140.000

CARRIED TO COLLECTION

140.000

140.000

DOC(III-4)

SITE WORK

(2-9)

....../ TRANSFORMER ROOM-

DIVISION - 5 METAL COLLECTION 1 TOTAL OF PAGE (5-1) 140.000 140.000

CARRIED TO SUMMARY

140.000

140.000

DOC(III-4)

SITE WORK

(2-10)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 7 THERMAL AND MOISTURE PROTECTION Section 07100 Waterproofing System Protective membrane laid under footings. Footing surface and neck columns Water proofing for G.B See the note in page (2-1) Supply and use polyethylene sheets (1000 gauge) under slab-on-grade, all complete as per drawings. Section 07500 Membrane Roofing composite Roofing System 7.3 Roof treatment with roofing layers laid over R.C. roof as per drawings, specifications and manufacturer's instructions. 2 coats of waterproofing paint 49 5:15 cm thick foam concrete laid in slope 2 cm thick sand-cemnt screed smoothing layer 4 mm thick waterproofing membrane 2 layers 2 cm thick sand-cemnt screed 7.5 cm thick extruded rigid insulation (joints shall be covered with tape) Filter fabric 40x40x4 cm Precast concrete (loosely laid) tiles with 5 cm thick sand bed including 10 cm width mix aggregates around tiles laid recessed with parapet and including expansion joint filled with celotex/rubber/mastic/ sealant / aluminum flashing etc. all as per drawings, specifications (Jointsmastic/sealant shall be installed All required flashing between parapet and skirting all as per detail drawings. M2 13.000 637.000
0.00% 100.00% 100.00% 637.000

7.1 7.1.1 7.1.2 7.1.3

32 81 30

M2 M2 M2

2.250 0.350 2.500

72.000 28.350 75.000

0.00% 0.00% 0.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

72.000 28.350 75.000

7.2

39

M2

2.000

78.000

0.00%

100.00% 100.00%

78.000

7.3.1

CARRIED TO COLLECTION

890.350

890.350

DOC(III-4)

SITE WORK

(2-11)

....../ TRANSFORMER ROOM-

DIVISION - 7 THERMAL AND MOISTURE PROTECTION

COLLECTION 1 TOTAL OF PAGE (7-1) 890.350 890.350

CARRIED TO SUMMARY

890.350

890.350

DOC(III-4)

SITE WORK

(2-12)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 8 DOORS AND WINDOWS Section 08110 Steel Doors and Frames 8.1 Steel frame with 3mm thick steel panel both side claded hollow steel door fixing to concrete or block wall complete with glazing, painting, all hardware (hinges, tower bolt, door lock, door closer etc.). The Contractor should refer Hardware Schedule Section 08711 and Finish Hardware Section 08710 in Specifications and drawings, showing Hardware set for each type of door. All Steel door double leaf, size 2750x2750mm Type D1 2 Nos. 600.000 1200.000
0.00% 100.00% 100.00% 1,200.000

8.1.1

CARRIED TO COLLECTION

1,200.000

1,200.000

DOC(III-4)

SITE WORK

(2-13)

....../ TRANSFORMER ROOM-

DIVISION - 8 DOORS AND WINDOWS COLLECTION 1 TOTAL OF PAGE (8-1) 1200.000 1200.000

CARRIED TO SUMMARY

1,200.000

1,200.000

DOC(III-4)

SITE WORK

(2-14)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

DIVISION - 9 FINISHES Secton 09200 Lath and Plaster 9.1 Render and set in cement plaster, 2 cm thick to internal / external wall and ceiling (concrete or block wall), including under coat, metal lathe, corner beads, stop beads etc. complete as per drawings and specification.

280

M2

2.150

602.000

0.00%

100.00% 100.00%

602.000

Section 09400 Terrazzo Tile 9.2 Precast Terrazzo floor tile 30x30x3 cm Grade-1 on and including cement and sand setting bed and backing sand cushion, joints grouted in white cement including grinding, polishing etc. complete as described.

35

M2

5.250

183.750

0.00%

100.00% 100.00%

183.750

9.3

2 cm thick x 10 cm high Terrazzo skirting on and including cement and sand setting bed and backing, joints grouted in white cement ditto.

32

MR

2.500

80.000

0.00%

100.00% 100.00%

80.000

Section 09900 Painting 9.4 Prepare and apply 2 coats of paint including preparation of surfaces, under coat, seal coat etc. complete as per specifications and Manufacture's instructions.

9.4.1

Textured paint over plaster and fair face concrete surfaces. Emulsion paint

113 170

M2 M2

3.500 1.000

395.500 170.000

0.00% 0.00%

100.00% 100.00% 100.00% 100.00%

395.500 170.000

9.4.2

CARRIED TO COLLECTION

1,431.250

1,431.250

DOC(III-4)

SITE WORK

(2-15)

....../ TRANSFORMER ROOM-

DIVISION - 9 FINISHES COLLECTION 1 TOTAL OF PAGE (9-1) 1431.250 1431.250

CARRIED TO SUMMARY

1,431.250

1,431.250

DOC(III-4)

SITE WORK

(2-16)

....../ TRANSFORMER ROOM-


UNIT RATE ITEM DESCRIPTION QTY UNIT KD. FILS KD. FILS AMOUNT
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

AMOUNT COMPLETED KD. FILS

INTERNAL WORKS MECHANICAL WORKS FIRE FIGHTING SYSTEM


Supply and installation the following items as per specifications and drawings complete in all respect, including testing, commissioning and any related work to complete the job in perfect condition for the satisfaction of the Engineer.

15.1

2 Nos. 25 Kgs. Powder fire extinguisher with trolley in low tension room and transformer room SUNDRIES

Nos.

350.000

700.000

0.00%

100.00% 100.00%

700.000

15.2 15.3

Documents including drawings , operating instructions and maintenance manuals. Tools and spares including loose keys and consumable stores as per engineer recommendations. Work incidental to the fire fighting installation

L.S. L.S.

L.S. L.S.

included included

included included

15.4

Allow for co-ordination with other engineering installations. Allow for cutting or forming holes,mortise, chases or the like and making good finishing

L.S.

L.S. included included 500.000


0.00% 100.00% 100.00% 500.000

15.5

L.S.

L.S.

500.000

15.6

Supply and install all missing items, refer to specifications and works needed.

L.S.

L.S.

included

included

DOC(III-4)

SITE WORK

(2-17)

....../ TRANSFORMER ROOM-

CARRIED TO COLLECTION INTERNAL WORKS MECHANICAL WORKS


Supply and installation the following items as per specifications and drawings complete in all respect, including testing, commissioning and any related work to complete the job in perfect condition for the satisfaction of the Engineer.

1,200.000

1,200.000

STORM WATER 15.7 Rain water suspended ( U.P.V.C. ) pipes fittings as per Specifications and Drawings, fixing with and including all requisite and fixing devices including joints. L.S. 1 L.S. Nos. 500.000 100.000 500.000 100.000
0.00% 100.00% 100.00% 500.000

15.7.1 3 inch diameter pipe 15.7.2 3 inch dia. Parapet roof drain 15.8 RAIN WATER PIPE WORK

0.00%

100.00% 100.00%

100.000

15.8.1 3 inch diameter cast iron shoe 15.9 Supply and install all missing items, refer to specifications and works needed.

1 L.S.

Nos. L.S.

200.000 included

200.000 included

0.00%

100.00% 100.00%

200.000

CARRIED TO COLLECTION

800.000

800.000

DOC(III-4)

SITE WORK

(2-18)

....../ TRANSFORMER ROOM-

DIVISION - 15 - MECHANICAL HVAC GENERAL NOTES A. B. Contractor is responsible to get approval local authorities. The HVAC system is a scheme contractor check all drawings and do all adjustments including complete with all discipline in order get good performance of HVAC system Include in quotation all catalogues for materials and other in which price based HVAC System 15.10 15.11 15.12 Any other item(s) not mentioned above and necessary for the optimum operation of the Allow for builders works required for all works Allow for two years maintenance all HVAC equipments and system including providing all required spare parts. Allow for submitting as-built drawings, operation, instruction and maintenance etc. Exhaust Fans 15.14 Exhaust roof extractor (centrifugal type), with fan, electric motor, casing housing the flanges back draft damper, vibration isolatros (spring type), inlet cones, wire guards, panels and all accessorie as per drawings. 1 No. 548.650 548.650
0.00% 100.00% 100.00% 548.650

C.

L.S. L.S. L.S.

L.S. L.S. L.S.

included included included

included included included

15.13

L.S.

L.S.

included

included

15.14.1 E.F - 01 (3600 cfm)

CARRIED TO COLLECTION

548.650

548.650

DOC(III-4)

SITE WORK

(2-19)

....../ TRANSFORMER ROOM-

Duct Work 15.15 Galvanized sheet, rectangular/round duct for supply, return, fresh air, toilet exhaust etc. complete with supply, fabrication, installation, hanger, support, equipment connection, duct accessories, sealant, air leakage tests etc. SMACNA, specification and A/C drawings. 130 70 Kg Kg 0.700 0.680 91.000 47.600
0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 91.000 47.600

15.15.1 USG (20) 15.15.2 USG (22)

Duct Work Accessories 15.16 Motorized and manual volume control damper, fire damper, turning vens etc. as and specified. Air Outlets and Inlets Air outlets and inlets, include an exhaust grill, exhaust louver, door grill etc, complete as specified and shown. 15.17 Exhaust air grill (EAG) 1 1 1 No. No. No. 57.000 40.000 included 57.000 40.000 included
0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 57.000 40.000

L.S.

L.S.

500.000

500.000

0.00%

100.00% 100.00%

500.000

15.17.1 EAG 60 x 18 15.17.2 EAG 24 x 14 15.18 Elect. Type wall mounted thermostat for room fan c.w. sensor and all required Supply and install all missing items, refer to specifications and works needed.

15.19

L.S.

L.S.

included

included

CARRIED TO COLLECTION

735.600

735.600

DOC(III-4)

SITE WORK

(2-20)

....../ TRANSFORMER ROOM-

DIVISION - 15 - MECHANICAL COLLECTION 1 TOTAL OF PAGE (15-1) 1200.000 1200.000

TOTAL OF PAGE(15-2)

800.000

800.000

TOTAL OF PAGE(15-3)

548.650

548.650

TOTAL OF PAGE(15-4)

735.600

735.600

CARRIED TO SUMMARY

3,284.250

3,284.250

DOC(III-4)

SITE WORK

(2-21)

....../ TRANSFORMER ROOM-


UNIT RATE AMOUNT
ITEM DESCRIPTION
PREVIOUS MONTH % COMP. THIS MONTH % COMP. UP TO DATE % COMP.

QTY

UNIT KD. FILS KD. FILS

AMOUNT COMPLETED KD. FILS

16

GENERAL NOTES The price for all the following items shall include the supply of all materials and equipment unless otherwise specified, delivery to site, installations, connections, testing, commissioning and making ready for work complete with all necessary cables wiring, earthing, conduits, draw and outlet boxes, switches, push-buttons, KWHM, cable trays, trenches, supply steel frames, angles, beams, rods fixation etc. and all necessary accessories and components for complete and perfect installation ready for All works shall be carried out according to drawings, particular and general specifications, contract conditions, and to the latest rules and regulations of M.E.W, M.O.C., Kuwait Fire Brigade, and any other concerned authorities, and as approved by these authorities and approved by the Engineering.

The contractor has the responsibility to finalize work as per MEW approval on the shop drawings and as built drawings without extra cost implication on the owner side Contractor must coordinate with other services (architect, civil and mechanical works) to finalize his work in a coordinated manner the contractor has the responsibility to fire alarm equipments in the substation to the main fire alarm control panel located in the building including all ducts, conduites, cables, handholes, manholes and all requirements accessories. The contractor has the responsibility to complete voltage drop calculations the site conditions and exact locations and to change the sizes of cables according to the voltage drop calculation results without cost implication on the owner side.

CARRIED TO COLLECTION DIVISION 16 ELECTRICAL

DOC(III-4)

SITE WORK

(2-22)

....../ TRANSFORMER ROOM-

16.1
Supply, install, connect, test and commission the following Main Low Tension Pannel, including all feeding cables, cable trays, ducts, hand holes, man holes, and all accessories, foundation, earthing, trenching, contract drawings, MEW requirement and as per the approval of the Engineer.

16.1.1 M.L.T.B.
Supply , install, connect, test and commission the following Main feeding cables including all its cable trays, trenches, ducts, conduites,hand holes, man holes, handholes,covers and all requirements, accessories, foundation, earthing, trenching, contract drawings, MEW requirement and as per the approval of the Engineer.

1.00

No.

4700.00

4700.00

0.00%

100.00% 100.00%

4,700.000

16.2

16.2.1 4c/95mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-01 16.2.2 4c/95mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-02 16.2.3 4c/95mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-03 16.2.4 4c/95mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-04 16.2.5 4c/95mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-AHU 16.2.6 3(4c/300mm2) cu/xlpe/swa/pvc feeding cable from MLTP to MSB-CH/P 16.2.7 4c/25mm2 cu/xlpe/swa/pvc feeding cable from MLTP to MSB-PUMP 16.2.8 (4c/16mm2) cu/xlpe/swa/pvc feeding cable from MLTP to S/F-FFP-01 16.2.9 (4c/16mm2) cu/xlpe/swa/pvc feeding cable from MLTP to S/F-FFP-02 16.2.10 (4c/16mm2) cu/xlpe/swa/pvc feeding cable from MLTP to S/F-JFP 16.2.11 (4c/35mm2) cu/xlpe/swa/pvc feeding cable from MLTP to feeder pillar
Supply , install, connect, test and commission the following distribution boards,switch fuses including all feeding cables, cable trays, ducts, handholes, wiring, accessories, foundation, earthing, contract drawings, MEW requirement , general specifications and as per the approval of DB-SS feeder pillar FP-01

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

20.00

mt

30.00

600.00

0.00%

100.00% 100.00%

600.000

16.3

16.3.1 16.3.2

1.00 1.00

NO. NO.

500.00 2500.00

500.00 2500.00

0.00% 0.00%

100.00% 100.00% 100.00% 100.00%

500.000 2,500.000

CARRIED TO COLLECTION DIVISION 16 ELECTRICAL

14,300.000

14,300.000

DOC(III-4)

SITE WORK

(2-23)

....../ TRANSFORMER ROOM-

16.4

supply, install, connect, fix, test and make ready for work of all lighting fittings. , the price for the following items shall be included the lighting points to the respective DBS c/w Wiring ,Conduits , Earthing,Switches, Push Button, Ceiling Rose , Silicon Wire, and all accessories required as per drawings, specifications and MEW regulations for light fittings types shown on drawings the Contractor should submit a sample of light fittings for approval with all internal wiring, control gear and components. The Contractor should submit the fixation way of light fittings for approval, as arch. Requirements and according to the type of ceiling.and as per approval of Engineer.

16.4.1

TYPE

4.00

No.

50.00

200.00

0.00%

100.00% 100.00%

200.000

16.4.2

TYPE

E'

3.00

No.

20.00

60.00

0.00%

100.00% 100.00%

60.000

16.4.3

TYPE

2.00

No.

35.00

70.00

0.00%

100.00% 100.00%

70.000

16.5

Supply, install and connect to the respective DBs , the following points including conduit wiring, draw boxes, outlet boxes, face plates, trenching, earthing, switches, accessories, cable, silicon wire, switches, double pole switches and all requirements as specified and as shown in drawing and as per the approval of Engineer.

16.5.1 13 A 3 Pin Sw. Socket 16.5.2 20 A T.P.N. S/F -EF-01/DB-SS 16.5.3 20 A T.P.N. S/F -FOR MSU EARTHING SYSTEM 16.6
Supply, install and connect complete earthing system as per drawing, specification and MEW regulation any addition earth electrodes needed shall be included without extra cost.

6.00 1.00 1.00

No. No. No.

30.00 35.00 36.00

180.00 35.00 36.00

0.00% 0.00% 0.00%

100.00% 100.00% 100.00% 100.00% 100.00% 100.00%

180.000 35.000 36.000

1.00

L.S.

250.00

250.00

0.00%

100.00% 100.00%

250.000

SITE INFRA STRUCTURES&BUILDER WORK


All necessary Builders Works, civil work, foundations, trenching required for electrical installation for transfromer room, LT room and site layout. Including all under ground upvc conduits, manholes, handholes , covers ,warning tape, excavation , backfilling and all accessories required for completion work as per mew regulations ,approvals and engineer

16.7

1.00

L.S.

included

included

CARRIED TO COLLECTION DIVISION 16 ELECTRICAL

831.000

831.000

DOC(III-4)

SITE WORK

(2-24)

....../ TRANSFORMER ROOM-

FIRE ALARM SYSTEMS 16.8


Supply, install, connect, test and make ready for complete addressable analogue fire alarm system including conduits, wiring, boxes draw boxes, terminal box and all components and accessories to make the system ready for work as per the drawing, specifications, KFBD approval and as per approval of Engineer. The contractor is responsible to finalize the work according to any

changes of KFBD without any extra cost on the owner side the system shall contain as a minimum. 16.8.1 Optical Detector 16.8.2 Interfaces with AHU's 16.8.3 Interfaces with fire fighting system Arranging to connect to main system and 16.8.4 getting approval of KFB for F.A installation after completion 16.8.5 General Fire Alarm Bell suitable for outdoor W/P
2.00 1.00 1.00 No. L.S. L.S. 150.00 100.00 350.00 300.00 100.00 350.00 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 300.000 100.000 350.000

1.00

L.S.

300.00

300.00

0.00%

100.00% 100.00%

300.000

1.00

No.

1500.00

1500.00

0.00%

100.00% 100.00%

1,500.000

CARRIED TO COLLECTION

2,550.000

2,550.000

DOC(III-4)

SITE WORK

(2-25)

....../ TRANSFORMER ROOM-

Collection - Electrical TOTAL OF PAGE (16-1) TOTAL OF PAGE (16-2) TOTAL OF PAGE (16-3) TOTAL OF PAGE (16-4)
0.00 14300.00 831.00 2550.00 0.00 14300.00 831.00 2550.00

CARRIED TO SUMMARY

17,681.000

17,681.000

DOC(III-4)

SITE WORK

(2-26)

Bill No. 3 INDEX OF BOQ


DIVISION NO. Index of B.O.Q. 2 3 4 5 7 8 9 15 16 Site Work Concrete Masonry Metal Thermal and Moisture Protection Doors and Windows Finishes Mechanical Electrical TITLE

Summary

PAGE NO. III-4/Index-1 2-1 to 2-2 3-1 to 3-2 4-1 to 4-2 5-1 to 5-2 7-1 to 7-2 8-1 to 8-2 9-1 to 9-2 15-1 to 15-5 16-1 to 16- 5

Sum-1

You might also like