Project Schedule for

ID

Task Name

Total schedule
Substation-1

1
2

Duration

Start

Finish

433 days

Sat 6/7/14

428 days

Sat 6/7/14

Sat 8/8/15

12 days

Sat 6/7/14

Wed 6/18/14
Wed 7/16/14

Topographical Survey and Report Preparation

Soil Investigation and Report Preparation

40 days

Sat 6/7/14

Drawing and Design Finalization

72 days

Thu 7/17/14

Fri 9/26/14

72 days

Thu 7/17/14

Fri 9/26/14

18 days

Thu 7/17/14

Sun 8/3/14

Civl Design

Substation General & Switchyard Layout

Cable Trench/Tray

9 days

Thu 7/17/14

Fri 7/25/14

Quarter Buildings

30 days

Fri 7/18/14

Sat 8/16/14
Sun 8/10/14

10

Boundary wall

10 days

Fri 8/1/14

11

Access Road/Switchyard Road

15 days

Fri 8/1/14

Fri 8/15/14

12

Control Building

30 days

Thu 8/14/14

Fri 9/12/14

13

Guard House

14 days

Sat 8/30/14

Fri 9/12/14

14

Supporting Structures

29 days

Thu 8/21/14

Thu 9/18/14

15
16

Switchyard Foundation
Electrical Design

18 days

Tue 9/9/14

Fri 9/26/14

47 days

Mon 8/4/14

Fri 9/19/14

17

Substation Earthing

12 days

Mon 8/4/14

Fri 8/15/14

18

Substation Shielding

10 days

Wed 8/20/14

Fri 8/29/14

19

Illumination System Design

8 days

Fri 9/12/14

Fri 9/19/14

20

Outdoor Lighting

3 days

Fri 8/22/14

Sun 8/24/14

21
22
23
24

Cable Schedule
Civil Works
Quarter Building (Single Storied)
Upto Plinth Level

25

Excavation of Foundation

26

Solling, PCC for footing

27

Reinforcement and form work for Mat and


Column
Concreting of Pad

28
29
30
31
32
33
34

Reinforcement and form work for Tie


Beam-1
Concreting of Tie Beam -1
Reinforcement and Form work for Tie
Beam -2
Concreting of Tie Beam-2
Above Plinth Level
Reinforcement and Formwork of Columns

43 days

Mon 8/4/14

Mon 9/15/14

212 days

Sun 8/17/14

Mon 3/16/15

158 days

Sun 8/17/14

Wed 1/21/15

50 days

Sun 8/17/14

Sun 10/5/14

5 days

Sun 8/17/14

Thu 8/21/14

12 days

Fri 8/22/14

Tue 9/2/14

8 days

Wed 9/3/14

Wed 9/10/14

3 days

Thu 9/11/14

Sat 9/13/14

8 days

Sun 9/14/14

Sun 9/21/14

3 days

Mon 9/22/14

Wed 9/24/14

8 days

Thu 9/25/14

Thu 10/2/14

3 days

Fri 10/3/14

Sun 10/5/14

18 days

Mon 10/6/14

Thu 10/23/14

8 days

Mon 10/6/14

Mon 10/13/14

35

Concreting of Columns

5 days

Tue 10/14/14

Sat 10/18/14

36

Flooring of Control Building

5 days

Sun 10/19/14

Thu 10/23/14
Wed 11/12/14

37

13 days

Fri 10/31/14

38

Formwork of Slab

5 days

Fri 10/31/14

Tue 11/4/14

39

Reinforcement of Beam and Slab

6 days

Wed 11/5/14

Mon 11/10/14

40
41

Slab

Concreting of Slab
Others

2 days

Tue 11/11/14

Wed 11/12/14

70 days

Thu 11/13/14

Wed 1/21/15

10 days

Thu 11/13/14

Sat 11/22/14

9 days

Sun 11/23/14

Mon 12/1/14

Fri 12/5/14

Thu 12/18/14
Sun 12/28/14

42

Brick Masonary Works

43

Illumination Work

44

Heating and Ventilation

14 days

45

Fire Fighting System

15 days

Sun 12/14/14

46

Plaster works

8 days

Mon 12/29/14

Mon 1/5/15

47

Air conditioning works

6 days

Sat 12/20/14

Thu 12/25/14

48

Door and Windows work

49

Painting and Glazing works

7 days

Wed 1/7/15

Tue 1/13/15

19 days

Sat 1/3/15

Wed 1/21/15

50

Water supply and sanitation

10 days

Mon 12/29/14

Wed 1/7/15

51

Quarter Building (Double Storied)

184 days

Sun 8/17/14

Mon 2/16/15

50 days

Sun 8/17/14

Sun 10/5/14

5 days

Sun 8/17/14

Thu 8/21/14

12 days

Fri 8/22/14

Tue 9/2/14

8 days

Wed 9/3/14

Wed 9/10/14

52

Upto Plinth Level

53

Excavation of Foundation

54

Solling, PCC for footing

55

Reinforcement and form work for Mat and


Column
Concreting of Pad

56
57
58
59
60
61
62

Reinforcement and form work for Tie


Beam-1
Concreting of Tie Beam -1
Reinforcement and Form work for Tie
Beam -2
Concreting of Tie Beam-2
Above Plinth Level
Reinforcement and Formwork of Columns

3 days

Thu 9/11/14

Sat 9/13/14

8 days

Sun 9/14/14

Sun 9/21/14

3 days

Mon 9/22/14

Wed 9/24/14

8 days

Thu 9/25/14

Thu 10/2/14

3 days

Fri 10/3/14

Sun 10/5/14

18 days

Mon 10/6/14

Thu 10/23/14

8 days

Mon 10/6/14

Mon 10/13/14

63

Concreting of Columns

5 days

Tue 10/14/14

Sat 10/18/14

64

Flooring of Control Building

5 days

Sun 10/19/14

Thu 10/23/14
Wed 11/12/14

65

13 days

Fri 10/31/14

66

Formwork of Slab

5 days

Fri 10/31/14

Tue 11/4/14

67

Reinforcement of Beam and Slab

6 days

Wed 11/5/14

Mon 11/10/14
Wed 11/12/14

68
69
70
71
72

Slab1

Concreting of Slab
Above Ground Floor
Reinforcement and Formwork of Columns
Concreting of Columns
Slab2

2 days

Tue 11/11/14

13 days

Wed 11/19/14

Mon 12/1/14

8 days

Wed 11/19/14

Wed 11/26/14

5 days

Thu 11/27/14

Mon 12/1/14

13 days

Tue 12/2/14

Sun 12/14/14

73

Formwork of Slab

5 days

Tue 12/2/14

Sat 12/6/14

74

Reinforcement of Beam and Slab

6 days

Sun 12/7/14

Fri 12/12/14
Sun 12/14/14

75
76

Concreting of Slab
Others

2 days

Sat 12/13/14

69 days

Wed 12/10/14

Mon 2/16/15

77

Brick Masonary Works

15 days

Wed 12/10/14

Thu 12/25/14

78

Illumination Work

13 days

Fri 12/26/14

Thu 1/8/15

Project:
Date: Thu 3/20/14

Task

Split

2015
June
July
August
September
October
November
December
January
February
March
April
May
June
July
Au
6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9

Thu 8/13/15

Substation/Switching Station

2014

Progress

Milestone

Summary

Project Summary
Page 1

External Tasks

External Milestone

Deadline

Project Schedule for LAOS Substation/Switching Station


ID

Task Name

Duration

Start

Finish

79

Heating and Ventilation

18 days

Sat 12/20/14

80

Fire Fighting System

19 days

Mon 12/29/14

Sat 1/17/15

81

Plaster works

13 days

Tue 1/6/15

Sun 1/18/15

82

Air conditioning works

83

Door and Windows work

Wed 1/7/15

8 days

Fri 12/26/14

Fri 1/2/15

10 days

Wed 1/14/15

Fri 1/23/15
Mon 2/16/15

84

Painting and Glazing works

26 days

Thu 1/22/15

85

Water supply and sanitation

13 days

Thu 1/8/15

Tue 1/20/15

185 days

Sat 9/13/14

Mon 3/16/15

56 days

Sat 9/13/14

Fri 11/7/14

5 days

Sat 9/13/14

Wed 9/17/14

86
87
88

Control Building
Upto Plinth Level
Excavation of Foundation

89

Solling, PCC for footing

90

Reinforcement and form work for Mat and


Column
Concreting of Pad

91
92
93
94
95
96

Reinforcement and form work for Tie


Beam-1
Concreting of Tie Beam -1
Reinforcement and Form work for Tie
Beam -2
Concreting of Tie Beam-2
Above Plinth Level

18 days

Thu 9/18/14

Sun 10/5/14

8 days

Mon 10/6/14

Mon 10/13/14

3 days

Tue 10/14/14

Thu 10/16/14

8 days

Fri 10/17/14

Fri 10/24/14

3 days

Sat 10/25/14

Mon 10/27/14

8 days

Tue 10/28/14

Tue 11/4/14

3 days

Wed 11/5/14

Fri 11/7/14

20 days

Sat 11/8/14

Thu 11/27/14

97

Reinforcement and Formwork of Columns

8 days

Sat 11/8/14

Sat 11/15/14

98

Concreting of Columns

5 days

Sun 11/16/14

Thu 11/20/14

99
100

Flooring of Control Building


Slab

7 days

Fri 11/21/14

Thu 11/27/14

22 days

Fri 11/28/14

Fri 12/19/14

101

Formwork of Slab

10 days

Fri 11/28/14

Sun 12/7/14

102

Reinforcement of Beam and Slab

10 days

Mon 12/8/14

Wed 12/17/14

103
104

Concreting of Slab
Indoor Cable Trench

2 days

Thu 12/18/14

Fri 12/19/14

7 days

Wed 12/31/14

Tue 1/6/15

105

Reinforcement for Trench

3 days

Wed 12/31/14

Fri 1/2/15

106

Formwork for Trench

2 days

Sat 1/3/15

Sun 1/4/15

107
108

Concreting of Trench
Others

2 days

Mon 1/5/15

Tue 1/6/15

76 days

Wed 12/31/14

Mon 3/16/15
Thu 1/15/15

109

Brick Masonary Works

14 days

Wed 12/31/14

110

Illumination Work

20 days

Fri 1/16/15

Wed 2/4/15

111

Heating and Ventilation

25 days

Mon 1/5/15

Thu 1/29/15

112

Fire Fighting System

22 days

Tue 1/6/15

Tue 1/27/15

113

Plaster works

15 days

Thu 2/5/15

Thu 2/19/15

114

Tile Works

30 days

Wed 12/31/14

Thu 1/29/15

115

Door and Windows work

15 days

Wed 1/14/15

Wed 1/28/15

116

False ceiling and Air conditioning works

20 days

Fri 2/20/15

Wed 3/11/15

117

Painting and Glazing works

25 days

Fri 2/20/15

Mon 3/16/15

118

Water supply and sanitation

15 days

Wed 2/25/15

Wed 3/11/15

118 days

Sat 9/13/14

Thu 1/8/15

23 days

Sat 9/13/14

Sun 10/5/14

119
120

Guard House
Upto Plinth Level

121

Excavation of Foundation

2 days

Sat 9/13/14

Sun 9/14/14

122

Solling, PCC for footing

4 days

Mon 9/15/14

Thu 9/18/14

123

Reinforcement and form work for Mat and


Column
Concreting of Pad

5 days

Fri 9/19/14

Tue 9/23/14

124
125
126
127
128
129

2 days

Wed 9/24/14

Thu 9/25/14

Reinforcement and form work for Tie


Beam-1
Concreting of Tie Beam -1

4 days

Fri 9/26/14

Mon 9/29/14

1 day

Tue 9/30/14

Tue 9/30/14

Reinforcement and Form work for Tie


Beam -2
Concreting of Tie Beam-2

4 days

Wed 10/1/14

Sat 10/4/14

Above Plinth Level

1 day

Sun 10/5/14

Sun 10/5/14

18 days

Mon 10/6/14

Thu 10/23/14

Mon 10/6/14

Wed 10/8/14

130

Reinforcement and Formwork of Columns

3 days

131

Concreting of Columns

3 days

Thu 10/9/14

Sat 10/11/14

132

Flooring

2 days

Wed 10/22/14

Thu 10/23/14
Fri 11/14/14

133

10 days

Wed 11/5/14

134

Formwork of Slab

4 days

Wed 11/5/14

Sat 11/8/14

135

Reinforcement of Beam and Slab

5 days

Sun 11/9/14

Thu 11/13/14
Fri 11/14/14

136
137

Slab

Concreting of Slab
Others

1 day

Fri 11/14/14

50 days

Thu 11/20/14

Thu 1/8/15

Thu 11/20/14

Mon 11/24/14

138

Brick Masonary Works

5 days

139

Illumination Work

3 days

Tue 11/25/14

Thu 11/27/14

140

Fire Fighting System

5 days

Sun 12/14/14

Thu 12/18/14

141

Heating and Ventilation

4 days

Thu 12/18/14

Sun 12/21/14

142

Plaster works

3 days

Fri 12/19/14

Sun 12/21/14

143

Tile Works

6 days

Mon 12/22/14

Sat 12/27/14

144

Door and Windows work

3 days

Tue 11/25/14

Thu 11/27/14

145

Air conditioning works

4 days

Fri 12/26/14

Mon 12/29/14

146

Painting and Glazing works

6 days

Tue 12/30/14

Sun 1/4/15

147

Water supply and sanitation

4 days

Mon 1/5/15

Thu 1/8/15

88 days

Sat 9/27/14

Tue 12/23/14
Wed 10/29/14

148
149

Switchyard Foundation Works

33 days

Sat 9/27/14

150

Line Bay
Excavation

3 days

Sat 9/27/14

Mon 10/13/14

151

Soling PCC for the footing

4 days

Sun 9/28/14

Wed 10/15/14

152

Reinforcement work for mat

8 days

Mon 9/29/14

Sat 10/18/14

153

Concreting of pad

3 days

Thu 10/2/14

Tue 10/21/14

154

Reinforcement work for Column

8 days

Fri 10/3/14

Sat 10/25/14

155

Formwork for column

5 days

Mon 10/6/14

Sun 10/26/14

156

Fixing of anchor bolts

5 days

Wed 10/8/14

Tue 10/28/14

Project:
Date: Thu 3/20/14

Task

Split

2014

2015
June
July
August
September
October
November
December
January
February
March
April
May
June
July
Au
6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9

Progress

Milestone

Summary

Project Summary
Page 2

External Tasks

External Milestone

Deadline

Project Schedule for LAOS Substation/Switching Station


ID

Task Name

Duration

157

Concreting of Column

158

Transformer Bay

Start

Finish

4 days

Fri 10/10/14

36 days

Thu 10/30/14

Wed 10/29/14
Thu 12/4/14

5 days

Thu 10/30/14

Mon 11/17/14
Mon 11/17/14

159

Excavation

160

Soling PCC for the footing

161

Reinforcement work for mat

162

Concreting of pad

163

Reinforcement work for Column

11 days

Fri 11/7/14

Tue 12/2/14

164

Formwork for column

8 days

Mon 11/10/14

Wed 12/3/14

165

Fixing of anchor bolts and Transformer


Leaque
Concreting of Column

7 days

Tue 11/11/14

Wed 12/3/14

166

6 days

Thu 11/13/14

Thu 12/4/14

167

Structures for overhead strung Busbars

19 days

Fri 12/5/14

Tue 12/23/14

4 days

Fri 10/31/14

11 days

Sat 11/1/14

Tue 11/25/14

4 days

Wed 11/5/14

Tue 11/25/14

168

Excavation

1 day

Fri 12/5/14

Fri 12/5/14

169

Soling PCC for the footing

2 days

Sat 12/6/14

Sun 12/7/14

170

Reinforcement work for mat

3 days

Mon 12/8/14

Wed 12/10/14

171

Concreting of pad

2 days

Thu 12/11/14

Fri 12/12/14

172

Reinforcement work for Column

3 days

Sat 12/13/14

Mon 12/15/14

173

Formwork for column

2 days

Tue 12/16/14

Wed 12/17/14

174

Fixing of anchor bolts

3 days

Thu 12/18/14

Sat 12/20/14

175

Concreting of Column

3 days

Sun 12/21/14

Tue 12/23/14

176

27 days

Sun 12/21/14

Fri 1/16/15

177

Excavation

3 days

Sun 12/21/14

Tue 12/23/14

178

Reinforcement work

5 days

Wed 12/24/14

Sun 12/28/14

179

Formwork

4 days

Mon 12/29/14

Thu 1/1/15

180

Concreting

2 days

Fri 1/2/15

Sat 1/3/15

181

Installation of Cable Tray

13 days

Sun 1/4/15

Fri 1/16/15

182
183

Cable Trench and Tray

Acess Road and Switchyard Road


Earthing

15 days

Sat 1/17/15

Sat 1/31/15

19 days

Sat 9/27/14

Wed 10/15/14
Thu 10/2/14

184

Excavation if required

6 days

Sat 9/27/14

185

Chemical Treatment

2 days

Fri 10/3/14

Sat 10/4/14

186

Laying of Copper Strip

5 days

Sun 10/5/14

Thu 10/9/14

Installation of Copper Electrode

2 days

187

Fri 10/10/14

Sat 10/11/14

4 days

Sun 10/12/14

Wed 10/15/14

189

Backfilling/filling with red clay and Bentonite


powder
Steel Structural works

42 days

Thu 1/1/15

Wed 2/11/15

190

Erection of Equipment Supporting Structure

42 days

Thu 1/1/15

Wed 2/11/15

191

Erection of Gantries

17 days

Sun 1/18/15

Tue 2/3/15

61 days

Tue 1/20/15

Sat 3/21/15

188

192

Installation

193

Outdoor Equipment

60 days

Tue 1/20/15

Fri 3/20/15

194

Transformer

12 days

Tue 1/20/15

Sat 1/31/15

195

Circuit Breaker

196

Disconnecting Switches

7 days

Thu 2/12/15

Wed 2/18/15

12 days

Thu 2/19/15

197

Mon 3/2/15

Capacitor Voltage Transformer

6 days

Tue 3/3/15

Sun 3/8/15

198

Current Transformer

4 days

Mon 3/9/15

Thu 3/12/15

199

Surge Arrester

1 day

Fri 3/13/15

Fri 3/13/15

200

Stringing of Conductor for Bus-Bar

1 day

Sat 3/14/15

Sat 3/14/15

201

Stringing of Conductors between Gantries

1 day

Sun 3/15/15

Sun 3/15/15

202

1 day

Mon 3/16/15

Mon 3/16/15

203

Tapping and connection of individual


equipment
Stringing of Earth wire for Shielding Protection

2 days

Tue 3/17/15

Wed 3/18/15

204

Auxillary Transformer

2 days

Thu 3/19/15

Fri 3/20/15

4 days

Wed 3/18/15

Sat 3/21/15
Sat 4/25/15

205
210

Indoor Equipment

35 days

Sun 3/22/15

211

Control and LV Power Cables

20 days

Sun 3/22/15

Fri 4/10/15

212

XLPE MV Power Cables

15 days

Sat 4/11/15

Sat 4/25/15

92 days

Sun 4/26/15

Sun 7/26/15

15 days

Sun 4/26/15

Sun 5/10/15

213

Cable Laying

Wiring

214

Transformer

215

Tap changer Panel

5 days

Mon 5/11/15

Fri 5/15/15

216

Current Transformer

4 days

Sat 5/16/15

Tue 5/19/15

217

Capacitive Voltage Transformer

7 days

Wed 5/20/15

Tue 5/26/15

218

Disconnecting Swithches

12 days

Wed 5/27/15

Sun 6/7/15

219

AC/DC Distribution/Marshalling Boxes

10 days

Mon 6/8/15

Wed 6/17/15

220

Control and Relay Panels

18 days

Thu 6/18/15

Sun 7/5/15

221

22kV Switchgear

21 days

Mon 7/6/15

Sun 7/26/15

222

13 days

Mon 7/27/15

Sat 8/8/15

223

Testing and Commissioning


Pretesting

4 days

Mon 7/27/15

Thu 7/30/15

224

Testing in presence of employer authorities

6 days

Fri 7/31/15

Wed 8/5/15

225

Commissioning

3 days

Thu 8/6/15

Sat 8/8/15

420 days

Fri 6/20/14

Thu 8/13/15

substation 2

226
227

Topographical Survey and Report Preparation

12 days

Fri 6/20/14

Tue 7/1/14

228

Soil Investigation and Report Preparation

40 days

Fri 6/20/14

Tue 7/29/14

229

Drawing and Design Finalization

230

Civl Design

97 days

Sun 7/27/14

Fri 10/31/14

97 days

Sun 7/27/14

Fri 10/31/14
Wed 7/30/14

231

Cable Trench/Tray

4 days

Sun 7/27/14

232

Supporting Structures

14 days

Sat 10/18/14

Fri 10/31/14

233

Switchyard Foundation

10 days

Sat 9/27/14

Mon 10/6/14
Sun 9/21/14

234

37 days

Sat 8/16/14

235

Substation Earthing

7 days

Sat 8/16/14

Fri 8/22/14

236

Substation Shielding

5 days

Sat 8/30/14

Wed 9/3/14

237

Illumination System Design

3 days

Fri 9/19/14

Sun 9/21/14

238

Outdoor Lighting

1 day

Mon 8/25/14

Mon 8/25/14

18 days

Mon 8/25/14

Thu 9/11/14

91 days

Tue 10/7/14

Mon 1/5/15

239
240

Electrical Design

Cable Schedule
Civil Works

Project: Laos Project Schedule


Date: Thu 3/20/14

Task

Split

2014

2015
June
July
August
September
October
November
December
January
February
March
April
May
June
July
Au
6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9

Progress

Milestone

Summary

Project Summary
Page 3

External Tasks

External Milestone

Deadline

Project Schedule for LAOS Substation/Switching Station


ID

Task Name

241

Duration
Switchyard Foundation Works

242

Line Bay

Start

Finish

43 days

Tue 10/7/14

Tue 11/18/14

24 days

Tue 10/7/14

Thu 10/30/14
Tue 10/7/14

243

Excavation

1 day

Tue 10/7/14

244

Soling PCC for the footing

2 days

Wed 10/8/14

Thu 10/9/14

245

Reinforcement work for mat

5 days

Fri 10/10/14

Tue 10/14/14

246

Concreting of pad

2 days

Wed 10/15/14

Thu 10/16/14

247

Reinforcement work for Column

5 days

Fri 10/17/14

Tue 10/21/14

248

Formwork for column

4 days

Wed 10/22/14

Sat 10/25/14

249

Fixing of anchor bolts

3 days

Sun 10/26/14

Tue 10/28/14

250

Concreting of Column

251

Structures for Busbars

2 days

Wed 10/29/14

Thu 10/30/14

19 days

Fri 10/31/14

Tue 11/18/14

252

Excavation

1 day

Fri 10/31/14

Fri 10/31/14

253

Soling PCC for the footing

2 days

Sat 11/1/14

Sun 11/2/14

254

Reinforcement work for mat

3 days

Mon 11/3/14

Wed 11/5/14

255

Concreting of pad

2 days

Thu 11/6/14

Fri 11/7/14

256

Reinforcement work for Column

3 days

Sat 11/8/14

Mon 11/10/14

257

Formwork for column

2 days

Tue 11/11/14

Wed 11/12/14

258

Fixing of anchor bolts

3 days

Thu 11/13/14

Sat 11/15/14

259

Concreting of Column

3 days

Sun 11/16/14

Tue 11/18/14

260

16 days

Sun 12/21/14

Mon 1/5/15

261

Cable Trench and Tray


Excavation

2 days

Sun 12/21/14

Mon 12/22/14

262

Reinforcement work

3 days

Tue 12/23/14

Thu 12/25/14

263

Formwork

3 days

Fri 12/26/14

Sun 12/28/14
Tue 12/30/14

264

Concreting

2 days

Mon 12/29/14

265

Installation of Cable Tray

6 days

Wed 12/31/14

Mon 1/5/15

8 days

Tue 10/28/14

Tue 11/4/14

2 days

Tue 10/28/14

Wed 10/29/14

1 day

Thu 10/30/14

Thu 10/30/14

2 days

Fri 10/31/14

Sat 11/1/14

1 day

Sun 11/2/14

Sun 11/2/14

266

Earthing

267

Excavation if required

268

Chemical Treatment

269

Laying of Copper Strip

270

Installation of Copper Electrode

271

Backfilling/filling with red clay and Bentonite


powder
Steel Structural works

2 days

Mon 11/3/14

Tue 11/4/14

272

25 days

Mon 1/5/15

Thu 1/29/15

273

Erection of Equipment Supporting Structure

25 days

Mon 1/5/15

Thu 1/29/15

274

Erection of Gantries

7 days

Mon 1/12/15

Sun 1/18/15

15 days

Fri 1/30/15

Fri 2/13/15

14 days

Fri 1/30/15

Thu 2/12/15

275
276

Installation
Outdoor Equipment

277

Circuit Breaker

2 days

Fri 1/30/15

Sat 1/31/15

278

Disconnecting Switches

5 days

Sun 2/1/15

Thu 2/5/15

279

Capacitor Voltage Transformer

1 day

Fri 2/6/15

Fri 2/6/15

280

Current Transformer

1 day

Sat 2/7/15

Sat 2/7/15

281

Surge Arrester

1 day

Sun 2/8/15

Sun 2/8/15

282

Bus-Bar

1 day

Mon 2/9/15

Mon 2/9/15

283

Stringing of Conductors between Gantries

1 day

Tue 2/10/15

Tue 2/10/15

284

Tapping and connection of individual


equipment
Stringing of Earth wire for Shielding Protection

1 day

Wed 2/11/15

Wed 2/11/15

285
286

Indoor Equipment

1 day

Thu 2/12/15

Thu 2/12/15

1 day

Fri 2/13/15

Fri 2/13/15

287

Battery and Charger extension

1 day

Fri 2/13/15

Fri 2/13/15

288

Communication Panels

1 day

Fri 2/13/15

Fri 2/13/15

289
290
291
292

Control and Relay Panels


Cable Laying
Control and LV Power Cables
Wiring

1 day

Fri 2/13/15

Fri 2/13/15

5 days

Sun 3/22/15

Thu 3/26/15

5 days

Sun 3/22/15

Thu 3/26/15

12 days

Fri 3/27/15

Tue 4/7/15

293

Current Transformer

1 day

Fri 3/27/15

Fri 3/27/15

294

Capacitive Voltage Transformer

1 day

Sat 3/28/15

Sat 3/28/15

295

Disconnecting Swithches

1 day

Sun 3/29/15

Sun 3/29/15

296

AC/DC Distribution/Marshalling Boxes

3 days

Mon 3/30/15

Wed 4/1/15

297

Control and Relay Panels

6 days

Thu 4/2/15

Tue 4/7/15

298

Testing and Commissioning

5 days

Sun 8/9/15

Thu 8/13/15

299

Pretesting

2 days

Sun 8/9/15

Mon 8/10/15

300

Testing in presence of employer authorities

2 days

Tue 8/11/15

Wed 8/12/15

301

Commissioning

1 day

Thu 8/13/15

Thu 8/13/15

Project:
Date: Thu 3/20/14

Task

Split

2014

2015
June
July
August
September
October
November
December
January
February
March
April
May
June
July
Au
6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9

Progress

Milestone

Summary

Project Summary
Page 4

External Tasks

External Milestone

Deadline

You might also like