You are on page 1of 3

1

Checked the work permit is available for subject Tag


number of equipments (Verify Tag No carefully before
energi!es the electrical equipments"
#
$nsulation %esistance tested and recorded in approved
format
&i'(ot test done for medium and high voltage
equipments
)
Confirmed *witchgear +us Contact resistance test record
available
)
,quipment foundation released from Civil and grouting
completed (if required
-
Confirmed that there is no loose connection in Control
wiring termination and control power supply is available
as per requirement for respective equipments"
.
Checked all inter tripping functions are as per logic and
all indications are function well
/
Checked all alarm and annunciations available in
0nnunciator (anel
1 Confirmed grounding cable connected well and tested
2 Checked the switchgear 0T* function are as per scheme
3 Checked the %elay setting as per relay coordination table
14
Verified all CT 5 VT and %elay test records and its
setting"
11
Confirmed 0mmeter and Volt 6eter test record available
and no physical damages appear in those meters
1#
Checked *elector switches and lockout %elay are
function well and identified as schematic drawing
1-
0ll cables restored and connected after
insulation test and enclosure covers
closed properly
7p *tream
8own *tream
11
Confirmed all +us bar connection along the +us 8uct is
checked" ((hase *equence 5 Torque
12
Confirmed Contact resistance test records available and
accepted by owner representative
13
Checked +us duct enclosure9s covers are fi:ed properly
along the +us 8uct" 0nd both end of bus duct are
grounded"
#4
Checked +us 8uct entry is sealed by fire retardant
material ( $f +us 8uct (assing thru ;all
;itnessed Name *ignature 8ate
Construction
<C $nspector (,(C
<C (6T
=thers



#1
Confirmed *witchgear control function test annunciation
are activated in 0nnuncitor panel
##
Checked all logic interlocks and tripping schemes from
up stream and down stream and all indication are
acceptable
#)
Checked all mechanical interlocks of +reaker in the up
stream feeder and it is ready for %ack $n"
#-
Checked all mechanical interlocks of +reaker in the
down stream $ncomer and it is %ack =ut"
#. Checked ,arth switch operation"
7p *tream
8own *tream
#/
Confirm that the earth switch is open before rack in the
breaker> contactor
#1
Confirmed that VT mechanical operation (%ack $n 5
%ack =ut and fuses are ok in 8own *tream $ncomer
#2
Checked the 8own *tream incomer grounding connected
well and tested"
#3
Checked all gauges (winding and oil temperature?
(ressure and level are good condition working well
)4 Confirmed the *pace heater is working
)1 Checked all test result 5 <V8s for
@eeder
,quipment
)# ,quipment 8ata sheet available"
))
Checked the Tap changer position is as per requirement
and locked on power transformer
)- Checked all radiator Valves are opened
).
Checked the *witchgear oil level and pressure are
sufficient"
)/ Checked the ,quipment and *urrounding area clean well
)1 Checked @ire e:tinguisher available nearby equipments
)2
Checked %ubber *hoes and &and Alows are suitable for
use of the nominal voltage"
)3
Checked calibration certificate is valid for measuring
instruments as %equired ( (hase *equence 6eter? Clamp
on meter? 6ulti meter? Thermometer? Noise level meter
-4
+arricaded surrounding equipment and confirmed that
there is no other activity is under progress
-1 Checked communication radio available
;itnessed Name *ignature 8ate
Construction
<C $nspector (,(C
<C (6T
=thers



-#
@ire 0larm system should be activated prior to energi!e
the substation (NoteB (ermission to be obtain from (6T
to energi!e substation? $f the @ire 0larm system was not
activated at the time of energi!ation
%emarks 5 %ecommendationB
;itnessed Name *ignature 8ate
Construction
<C $nspector (,(C
<C (6T
=thers

You might also like