Florida Department of

Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well #& Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 9.16 North & 11.43 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in11-12 beforepad built) DF 25.5 above G.L. TD 1,980 DF TVD 1,979.85
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark J ones (drilling consultants) (713) 395-7571
Well Status Repairing top drive after drilling 12 hole to 1,980 DF.


I certify that the above well and premise was inspected on 12-26-12, 1-2-13, 1-7-13, 1-8-13, 1-9-13, 1-11-13, 1-14-13, 1-16-13, 1-17-13, 1-21-13,
1-24-13, 1-25-13, 1-27-13, 1-28-13, 1-29-13, 1-30-13, 1-31-13, 2-1-13, & 2-2-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J . Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 3
rd
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/03/13
Permit #
1349
Date
02 03 2013


First Report (#1349-pilot): Drilled 1,861 of 17 hole from 47 DF to 1,908 DF;
Cemented 13.375 O.D. x 54.5#/ft. casing at 1,714 DF with 863.38 bbls.
(composed of 2,138 sacks of cement + 660 sacks of pea gravel);
Drilled 201 of cement from 1,707 DF to 1,908 DF;
Drilled 72 of 12 hole from 1,908 DF to 1,980 DF.



Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)

Pre-spud activities:
12-20-12: Contractors started building 300 x 300 limerock pad & augmenting 2.7 miles of access road leading to location.
(Bruno arrived 12-26-12 at 1 PM, left 12-26-12 at 2 PM.)
(Bruno arrived 1-2-13 at 9 AM, left 1-2-13 at 10 AM.)
(Attwood arrived 1-2-13 at 3:29 PM, left 1-2-13 at 3:40 PM.)
01-07-13: Six (6) joints of 24 O.D. x 23 I.D. steel conductor on location. Pile driver en route to location to start driving conductor.
(Attwood arrived 1-7-13 at 12:55 PM, left 1-7-13 at 1:04 PM.)
01-08-13: 24 O.D. x 23 I.D. steel conductor driven to point of refusal at 196.5 BGL.
Note: Point of refusal reached when 60 blows were required to drive conductor the final one inch (1) per 1-9-13 communication
with Chad Mudge-contractor.
01-08-13: 16 O.D. steel mouse hole driven inside cellar to 90 BGL.
(Bruno arrived 1-8-13 at 11:30 AM, left 1-8-13 at 4:30 PM.)
01-09-13: 10-diameter x 10-tall (NOT 8 tall) x 0.109-thick corrugated metal cellar installed around #1349 well.
(Attwood arrived 1-9-13 at 9:11 AM, left 1-9-13 at 9:25 AM.)
01-10-13: Finished laying down 145 x 110 x 40 mil liner on top of compacted limerock pad.
01-11-13: Contractors began installing interlocking, polyethylene drilling mats on top of liner.
Note: Drilling mats hauled from#1345-H well site at N. Bear Island Field & re-assembled on top of liner for #1349 (pilot) well.
(Bruno arrived 1-11-13 at 9 AM, left 1-11-13 at 9:30 AM.)
(Attwood arrived 1-11-13 at 9:15 AM, left 1-11-13 at 9:54 AM.)
01-14-13: Began moving Precision #314 drilling rig components from#1345-H well at N. Bear Island Field to #1349.
(Attwood arrived 1-14-13 at 8:04 AM, left 1-14-13 at 8:12 AM.)
01-16-13: LaBelle Well Drilling completed northwest water supply well.
10 PVC casing cemented with 26 sacks of cement fromsurface to 59 BGL. Well drilled to a total depth of 80 BGL (in sand.)
(Attwood arrived 1-16-13 at 10:52 AM, left 1-16-13 at 11:08 AM.)
01-17-13: LaBelle Well Drilling completed southeast water supply well.
10 PVC casing cemented fromsurface to 59 BGL. Well drilled to a total depth of 90 BGL.
Note: Limerock pad complete. All perimeter dikes finished except for northern dike.
(Attwood arrived 1-17-13 at 12:16 PM, left 1-17-13 at 12:25 PM.)

Day 1 Summary: 1-21-13 TD = 1,029 DF. Drilled 1,015 of 17 O.D. hole from 47 DF to 1,029 DF in 14 hrs.
(2 PM 1-20-13 to 6 AM 1-21-13) Spud #1349 well on 1-20-13 at 2 PM.

Day 2 Summary: 1-22-13 TD = 1,440 DF. Drilled 411 of 17 O.D. hole from 1,029 DF to 1,440 DF in 4.5 hrs.
(6 AM 1-21-13 to 6 AM 1-22-13) 189 of fish left in well from 1,251 DF to 1,440 DF.
Twisted off 6 drill collar (pin broken). Left 189 of fish in well from1,251 DF to 1,440 DF.
189-long fish composed of 17 drill bit +bit sub +prodrift tool +three (3) drill collars +two (2) stabilizers
+crossover +two (2) 6 drill collars.
(Attwood arrived 1-21-13 at 8:17 AM, left 1-21-13 at 8:49 AM.)


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well #& Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 9.16 North & 11.43 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in11-12 beforepad built) DF 25.5 above G.L. TD 1,980 DF TVD 1,979.85
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark J ones (drilling consultants) (713) 395-7571
Well Status Repairing top drive after drilling 12 hole to 1,980 DF.


I certify that the above well and premise was inspected on 12-26-12, 1-2-13, 1-7-13, 1-8-13, 1-9-13, 1-11-13, 1-14-13, 1-16-13, 1-17-13, 1-21-13,
1-24-13, 1-25-13, 1-27-13, 1-28-13, 1-29-13, 1-30-13, 1-31-13, 2-1-13, & 2-2-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J . Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 3
rd
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/03/13
Permit #
1349
Date
02 03 2013


Day 3 Summary: 1-23-13 TD = 1,440 DF. Unable to latch onto fish with overshot + fishing jars. Ordered overshot with larger skirt.
(6 AM 1-22-13 to 6 AM 1-23-13)

Day 4 Summary: 1-24-13 TD = 1,638 DF. Recovered 189 of fish with bent joint of drill pipe attached to larger cut lip guide on overshot.
(6 AM 1-23-13 to 6 AM 1-24-13) Washed 99 of 17 O.D. hole from 1,341 DF to 1,440 DF.
Drilled 198 of 17 O.D. hole from 1,440 DF to 1,638 DF in 3 hrs.
Lost circulation (0% returns) at 1,638 DF.

Day 5 Summary: 1-25-13 TD = 1,908 DF. Drilled 270 of 17 O.D. hole from 1,638 DF to 1,908 DF.
(6 AM 1-24-13 to 6 AM 1-25-13)
(Bruno arrived 1-24-13 at 4:30 PM, left 1-24-13 at 5:42 PM.)

Day 6 Summary: 1-26-13 TD = 1,908 DF. Back reamed 1,514 of 17 O.D. hole from 1,791 DF to 277 DF.
(6 AM 1-25-13 to 6 AM 1-26-13) B.H.A. stuck in bottom of 24 conductor.
(Attwood arrived 1-25-13 at 7:47 AM, left 1-25-13 at 9:14 AM.)

Day 7 Summary: 1-27-13 TD = 1,908 DF. P.O.O.H. 24 conductor shoe damaged. Milled conductor shoe with modified stabilizer assembly.
(6 AM 1-26-13 to 6 AM 1-27-13)
17 drill bit damaged (see Photo 8) (2-wide x 3-long section of metal above three cones worn away.)
17 stabilizer damaged (see Photo 9) (9 of the 24-long x 1.55-thick stabilizer fin worn away.)

Day 8 Summary: 1-28-13 TD = 1,908 DF. Finished milling 24 conductor shoe. Back reamed out of hole.
(6 AM 1-27-13 to 6 AM 1-28-13) Junk in hole. 24 conductor shoe damaged.
Ran in hole with 14 drill bit. Bit plugged at 526 DF. P.O.O.H. to clear & inspect drill bit.
(Attwood arrived 1-27-13 at 4:49 PM, left 1-27-13 at 5:47 PM;
Attwood returned 1-27-13 at 6:55 PM, left 1-27-13 at 8:14 PM.)

Day 9 Summary: 1-29-13 TD = 1,908 DF. Cleared LCM material from 14 drill bit & jets.
(6 AM 1-28-13 to 6 AM 1-29-13) Tripped in hole to base of 24 conductor. No obstructions encountered at base of conductor.
Tagged junk in wellbore at 385 DF.
Washed & reamed from 385 DF to 1,898 DF. Pushed junk to bottom at 1,898 DF.
Circulated well at 1,896 DF. Attempted to wash metal debris out of bottom of well.
Tripped in hole from 1,896 DF to 1,898 DF.
Tagged obstruction at 1,898 DF (= 10 off bottom) with 30,000# of drill string weight.
P.O.O.H. slowly.
Tripped in hole with 13 3/8 surface casing to 1,644 DF. (started running casing on 1-28-13 at 11:30 PM.)
Tagged obstruction at 1,644 DF on 1-29-13 at 2:15 AM.
Made up circulating swedge. Washed 13 3/8 casing down from 1,644 DF to 1,664 DF.
(Attwood arrived 1-28-13 at 7:35 AM, left 1-28-13 at 7:57 AM.)
(Bruno arrived 1-28-13 at 9 AM, on location 1-29-13 at 6 AM.)

Day 10 Summary: 1-30-13 TD = 1,908 DF. Washed 13 3/8 casing down from 1,664 DF to 1,714 DF, then top drive broke down.
(6 AM 1-29-13 to 6 AM 1-30-13) Unable to rotate 13 3/8 casing. Pumped through casing with no returns.
(Bruno on location 1-29-13 at 6 AM, left 1-29-13 at 12:50 PM.)
(Attwood arrived 1-29-13 at 11:30 AM, left 1-29-13 at 12:55 PM;
Attwood returned 1-29-13 at 1:40 PM, left 1-29-13 at 3:55 PM;
Attwood returned 1-30-13 at 3:36 AM, left 1-30-13 at 3:43 AM.)





Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well #& Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 9.16 North & 11.43 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in11-12 beforepad built) DF 25.5 above G.L. TD 1,980 DF TVD 1,979.85
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark J ones (drilling consultants) (713) 395-7571
Well Status Repairing top drive after drilling 12 hole to 1,980 DF.


I certify that the above well and premise was inspected on 12-26-12, 1-2-13, 1-7-13, 1-8-13, 1-9-13, 1-11-13, 1-14-13, 1-16-13, 1-17-13, 1-21-13,
1-24-13, 1-25-13, 1-27-13, 1-28-13, 1-29-13, 1-30-13, 1-31-13, 2-1-13, & 2-2-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J . Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 3
rd
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/03/13
Permit #
1349
Date
02 03 2013


Day 11 Summary: 1-31-13 TD = 1,908 DF. Unable to rotate 13 3/8 casing. Pumped through casing at 1,714 DF with no returns.
(6 AM 1-30-13 to 6 AM 1-31-13) 13.375 O.D. x 54.5#/ft. surface casing manufactured in Korea by SeAH Steel Co.
(Bruno arrived 1-30-13 at 8:30 AM, left 1-30-13 at 2:30 PM.)

Day 12 Summary: 2-01-13 PBTD = 1,707 DF. Cemented 13.375 surface casing with 651.79 barrels (1,698 sacks) of cement at 1,714 DF.
(6 AM 1-31-13 to 6 AM 2-1-13) Waiting for cement to settle in annulus before pumping three (3) stages of top off cement.
(tagged cement inside 13 3/8 surface casing at 1,707 DF on 2-2-13.)
Rigged up Youngquist Bros. Logging. Ran Cement Bond Log from1,711 DF to 50 DF on 2-1-13 at 12:30 AM.
(Bruno arrived 1-31-13 at 7:50 AM, left 1-31-13 at 11:24 PM.)
(Attwood arrived 2-1-13 at 3:31 AM, left 2-1-13 at 4:25 AM.)

Surface Casing Cement Jobs on 1-31-13 (by Baker Hughes) & 2-1-13 (by Eagle Ready Mix):
13.375" O.D. x 54.5#/ft. J-55 BT&C casing set at 1,714' DF in #1349 (pilot well).
1-31-13 @ 1:55 PM Tested cementing lines to 3,000 PSI. Tested OK.
1-31-13 @ 2:00 PM
Spacer Ahead: Pumped 20 bbls. 8.34 ppg fresh water at 5.4 bpminto 5 O.D. x 4.276 I.D. x 19.5#/ft. Grade G-105 drill pipe
& tag-in cementing adapter stung into 13.375 casing shoe at 500 PSI.
Note: Unplugged line on Baker Hughes pumping unit after pumping spacer.
1-31-13 @ 4:30 PM
1st Lead (Scavenger) cement:
Pumped 118.33 bbls. (210 sacks/11.0 PPG) of 35:65:6 Poz (fly ash) Class H scavenger cement
composed of 136.5 sacks (= 12,831#) of Class H cement +73.5 sacks (= 5,439#) of Poz/fly ash
+6% b.w.o.c. (= 1,096.2#) of gel/bentonite +3% b.w.o.c. (= 384.93#) of calciumchloride
+3% b.w.o.c. (= 384.93#) of sodiummetasilicate +0.001 gal. per second (= 1.06 gal.) of FP-6L yielding 3.16 cu. ft. of slurry
per sack of cement at 6.7 bpmthrough 5" O.D. drill pipe & stab-in sub into annulus at 633 PSI.
1-31-13 @ 4:55 PM
2nd Lead cement:
Pumped 333.06 bbls. (703 sacks/11.5 PPG) of 35:65:6 Poz (fly ash) Class H cement
composed of 456.95 sacks (= 42,953.3#) of Class H cement +246.5 sacks (= 18,241#) of Poz/fly ash
+6% b.w.o.c. (= 3,669.7#) of gel/bentonite +3% b.w.o.c. (= 1,288.60#) of calciumchloride
+3% b.w.o.c. (= 1,288.60#) of sodiummetasilicate +0.001 gal. per second (= 3.33 gal.) of FP-6L yielding 2.66 cu. ft. of slurry
per sack of cement at 6.0 bpmthrough 5" O.D. drill pipe & stab-in sub into annulus at 525 PSI.
1-31-13 @ 6:05 PM
Tail cement:
Pumped 112.40 bbls. (450 sacks/14.5 PPG) of Type I (Class A) cement
mixed with +1% b.w.o.c. (= 423#) of calciumchloride +0.2% b.w.o.c. (= 84.6#) of ASA-301
+0.001 gal. per second (= 1.43 gal.) of FP-6L yielding 1.40 cu. ft. of slurry per sack of cement at 4.7 bpm
through 5" O.D. drill pipe & stab-in sub into annulus at 338 PSI.
450 sacks of Type 1 (Class A) cement weighed 42,300#.
No returns.
1-31-13 @ 6:54 PM
Displacement: Pumped 28 bbls. of 9.0 ppg drilling mud at 5 bpm(for 6 minutes)
into 5" O.D. drill pipe & stab-in sub into annulus at 641 PSI to push tail cement into annulus.
1-31-13 @ 7:00 PM Shut down.
1-31-13 @ 7:30 PM
P.O.O.H. with 9 joints of 5" O.D. drill pipe. Pumped sponge wiper ball through drill pipe to displace 5 bbls. of cement
into 13.375 casing. P.O.O.H. with 45 joints of 5 drill pipe +stab-in sub +centralizer +stinger.
1-31-13 @ 8:45 PM
Fromthe drill floor, tripped in annular space between 23 I.D. conductor and 13.375 O.D. surface casing
with 1 O.D. steel tremmie pipe.

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 4 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well #& Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 9.16 North & 11.43 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in11-12 beforepad built) DF 25.5 above G.L. TD 1,980 DF TVD 1,979.85
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark J ones (drilling consultants) (713) 395-7571
Well Status Repairing top drive after drilling 12 hole to 1,980 DF.


I certify that the above well and premise was inspected on 12-26-12, 1-2-13, 1-7-13, 1-8-13, 1-9-13, 1-11-13, 1-14-13, 1-16-13, 1-17-13, 1-21-13,
1-24-13, 1-25-13, 1-27-13, 1-28-13, 1-29-13, 1-30-13, 1-31-13, 2-1-13, & 2-2-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J . Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 3
rd
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/03/13
Permit #
1349
Date
02 03 2013

1-31-13 @ 9:06 PM
Top Out #1 cement (portion supplied by Baker Hughes):
Pumped 40 bbls. (150 sacks/12.7 PPG) of Type I (Class A) cement
mixed with 2% b.w.o.c. (= 282#) of calciumchloride +0.001 gal. per second (= 2.82 gal.) of FP-6L
at 0.85 bpm into the annulus of the 13.375" surface casing at 72 PSI.
150 sacks of Type 1 (Class A) cement weighed 14,100#.
1-31-13 @ 9:53 PM
Top Out #2 cement (portion supplied by Youngquist Bros.):
Pumped 48 bbls. (185 sacks/12.7 PPG) of Type I (Class A) cement
mixed with 2% b.w.o.c. (= 347.8#) of calciumchloride +0.001 gal. per second (= 3.36 gal.) of FP-6L
at 0.85 bpm into the annulus of the 13.375" surface casing at 72 PSI.
185 sacks of Type 1 (Class A) cement weighed 17,390#.
1-31-13 @ 10:49 PM Shut down. Stopped pumping cement. P.O.O.H. with 1 O.D. tremmie pipe & rigged down Baker Hughes cementers.
2-01-13 @ 1:35 PM
Final Top Out #3 cement (supplied by Eagle Ready Mix-Estero, FL):
Began pumping 44 cubic yards (per delivery ticket) which equals 211.59 bbls. (1,100 sacks) of Ready Mix cement.
Concrete aggregate consisted of 60% -diameter rock/pea gravel +40% cement.
Note: 25 sacks of the 60:40 slurry were mixed with water
to yield 1 cubic yard of 60:40 slurry(per 2-19-13 conversation with Craig Davis-Youngquist Brothers.)
Hence, 660 sacks of aggregate +440 sacks of cement were mixed with water to yield 44 cu. yards of ready mix cement.
Strength of aggregate pumped: 3,000 PSI.
Started pumping final 10 cubic yards of Ready Mix cement mixed with pea gravel on 2-1-13 at 5:10 PM.
2-01-13 @ 6:00 PM Top of cement observed in 23 I.D. x 13.375 O.D. annulus at surface.

Day 13 Summary: 2-02-13 PBTD = 1,707 DF. Lifted diverter stack & made rough cut of 13 3/8 surface casing & 24 conductor.
(6 AM 2-1-13 to 6 AM 2-2-13) Pumped 211.59 bbls. (1,100 sacks) of Ready Mix cement for final top off.
Total volume of cement/aggregate used for surface casing cement job: 863.38 barrels (which = 2,138 sacks of cement + 660 sacks of pea gravel.)
Made final cut of 13 3/8 surface casing, then installed & welded wellhead.
(tagged cement inside 13 3/8 surface casing at 1,707 DF on 2-2-13.)
(Bruno arrived 2-1-13 at noon, left 2-1-13 at 1 PM.)
(Attwood arrived 2-1-13 at 12:20 PM, left 2-1-13 at 2:23 PM.)

Day 14 Summary: 2-03-13 TD = 1,980 DF Tagged firm cement inside 13 3/8 surface casing at 1,707 DF (= 7 above casing shoe) with 20,000#.
(6 AM 2-2-13 to 6 AM 2-3-13) Performed successful M.I.T. of 13 3/8 surface casing at 1,000 PSI (witnessed by drilling consultant.)
Drilled 7 of cement inside 13 3/8 surface casing with 12 bit from 1,707 DF to 1,714 DF.
Drilled 194 of cement with 12 bit from 1,714 DF to 1,908 DF(interval previously drilled on 1-25-13.)
Drilled 72 of formation with 12 bit from 1,908 DF to 1,980 DF.
Youngquist Bros. ran GR/Caliper log from 1,912 DF to 1,652 DF.
Youngquist Bros. ran SP/Dual Induction log from 1,912 DF to 1,728 DF.
13 3/8 surface casing shoe logged at 1,714 DF (per X-Y caliper log.)
U.S.D.W. ABOVE 13 3/8 casing shoe (resistivity= 2.5 ohms to 3.5 ohms BELOW 1,728 DF per induction log.)
U.S.D.W. protected.
Observation: Saltwater fromthe Boulder Zone may have migrated up to the severe lost circulation zone
at 1,638 DF, then contaminated the porous zones below 1,638 DF.
TDS of water below 1,728 DF greater than 10,000 PPM per induction log.
(Attwood arrived 2-2-13 at 10:22 PM, left 2-3-13 at 3:03 AM)

---No Violations---

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 6.96 North & 16.50 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 4,608 DF TVD 4,607.55
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole at 4,608 DF.


I certify that the above well and premise was inspected on 2-4-13, 2-6-13, 2-8-13, 2-9-13, 2-10-13, 2-11-13, & 2-12-13 by Paul Attwood
& Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 13
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/13/13
Permit #
1349
Date
02 13 2013


Second Report (#1349-pilot): Drilled 1,985 of 12 hole from 1,980 DF to 3,965 DF;
Cemented 9.625 O.D. x 47#/ft. casing at 3,964 DF
with 212.10 bbls./630 sacks of cement;
Drilled 162 of cement inside 9.625 O.D. casing from 3,802 DF to 3,964 DF;
Drilled 1 of cement in (former) 12 bore hole from 3,964 DF to 3,965 DF;
Drilled 643 of 8 hole from 3,965 DF to 4,608 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.

Day 15 Summary: 2-04-13 TD = 1,980 DF Repairing top drive. No hole drilled.
(6 AM 2-3-13 to 6 AM 2-4-13)

Day 16 Summary: 2-05-13 TD = 2,182 DF Drilled 202 of 12 hole from 1,980 DF to 2,182 DF in 6.5 hrs.
(6 AM 2-4-13 to 6 AM 2-5-13)
Lost all returns at 2,031 DF.
(Bruno arrived 2-4-13 at 8:40 AM, left 2-4-13 at 9:30 AM.)
(Attwood arrived 2-4-13 at 1:40 PM, left 2-4-13 at 1:50 PM.)

Day 17 Summary: 2-06-13 TD = 2,277 DF. Drilled 95 of 12 hole from 2,182 DF to 2,277 DF in 10 hrs. with no returns.
(6 AM 2-5-13 to 6 AM 2-6-13)

Day 18 Summary: 2-07-13 TD = 2,849 DF. Drilled 572 of 12 hole from 2,277 DF to 2,849 DF in 23 hrs. with no returns.
(6 AM 2-6-13 to 6 AM 2-7-13)
(Attwood arrived 2-6-13 at 9:15 AM, left 2-6-13 at 9:50 AM.)

Day 19 Summary: 2-08-13 TD = 3,196 DF. Drilled 347 of 12 hole from 2,849 DF to 3,196 DF in 19.5 hrs. with no returns.
(6 AM 2-7-13 to 6 AM 2-8-13)

Day 20 Summary: 2-09-13 TD = 3,775 DF. Drilled 579 of 12 hole from 3,196 DF to 3,775 DF in hrs. with no returns.
(6 AM 2-8-13 to 6 AM 2-9-13)
(Bruno arrived 2-8-13 at 3:08 PM, left 2-8-13 at 4:39 PM.)

Day 21 Summary: 2-10-13 TD = 3,965 DF. Drilled 190 of hole from 3,775 DF to 3,965 DF in 6 hrs. with no returns.
(6 AM 2-9-13 to 6 AM 2-10-13) Rigged up Offshore Energy casing crew.
Tripped in hole with pump-in sub, then washed & reamed 9 5/8 intermediate casing to 3,618 DF.
9 5/8 O.D. x 47#/ft. intermediate casing manufactured in the United States.
While washing and reaming 9 5/8 casing, obstructions hit at: 2,026 DF, 2,075 DF, 2,085 DF,
2,200 DF, & 2,300 DF (per Precisions driller.)
Note: 1 hours was needed to get the 9 5/8 casing by obstruction at 2,200 DF.
(Attwood arrived 2-9-13 at 5:16 PM, left 2-9-13 at 5:47 PM.)









Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 6.96 North & 16.50 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 4,608 DF TVD 4,607.55
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole at 4,608 DF.


I certify that the above well and premise was inspected on 2-4-13, 2-6-13, 2-8-13, 2-9-13, 2-10-13, 2-11-13, & 2-12-13 by Paul Attwood
& Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 13
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/13/13
Permit #
1349
Date
02 13 2013




Day 22 Summary: 2-11-13 PBTD = 3,802 DF. Finished washing & reaming 9 5/8 int. casing from 3,618 DF to 3,964 DF (=1 off bottom.)
(6 AM 2-10-13 to 6 AM 2-11-13) Cemented 9 5/8 x 47#/ft. intermediate casing with 212.10 bbls. (630 sacks) of cement.
Nippled down diverter system & set 9 5/8 casing slips with 105,000#of tension.
Made final cut on 9 5/8 casing.
I nstalled & tested wellhead to 1,500 PSI . Tested OK.
Nippled up BOP stack and choke manifold.
(tagged cement inside 9 5/8 casing at 3,802.4 DF on 2-12-13.)
Last (final) joint of 9 5/8 casing inserted in well on 2-10-13 at 6:30 AM.
Tagged fill in 12 wellbore with 30,000# of casing string weight.
(Attwood arrived 2-10-13 at 6:02 AM, left 2-10-13 at 10:26 AM;
Attwood returned 2-10-13 at 11:14 PM, on location 2-11-13 at 6:00 AM.)

Intermediate Casing Cement Job on 2-10-13:
9.625" O.D. x 47#/ft. P-110 GB Buttress casing set at 3,964' DF in #1349 (pilot well).
2-10-13 @ 7:25 AM Tested cementing lines to 3,500 PSI. Tested OK.
2-10-13 @ 7:35 AM Spacer Ahead: Pumped 20 bbls. 8.4 ppg MudClean II at 5 bpm into 9 5/8 casing at 179 PSI.
2-10-13 @ 7:45 AM
Lead cement:
Pumped 150 bbls. (310 sacks/11.5 PPG) of 35:65:6 Poz (fly ash) Class H cement
composed of 108.7 sacks (= 8,043.8#) of Poz/fly ash + 201.5 sacks (=18,941#) of Class H cement
+ 6% b.w.o.c. (= 1,618.2#) of gel/bentonite + 3% b.w.o.c. (= 568.2#) of calcium chloride
+ 3% b.w.o.c. (= 568.2#) of sodium metasilicate + 0.001 gal. per second (= 2.15 gal.) of FP-6L yielding 2.66 cu. ft. of slurry
per sack of cement at 4.19 bpm into 9 5/8 intermediate casing at 280 PSI.
2-10-13 @ 8:20 AM
Tail cement:
Pumped 62.10 bbls. (320 sacks/16.2 PPG) of Class H cement
mixed with 0.001 gal. per second (= 0.91 gal.) of FP-6L yielding 1.09 cu. ft. of slurry per sack of cement at 4.11 bpm
into 9 5/8 intermediate casing at 273 PSI.
320 sacks of Class H cement weighed 30,080#.
2-10-13 @ 8:42 AM
Displacement: Dropped top plug, then displaced lead cement & tail cement in 9 5/8 casing into annulus with 284 bbls.
of 9.0 ppg drilling mud at 7.5 bpm & 328 PSI.
2-10-13 @ 9:15 AM Bumped plug to 1,300 PSI. Plug held.
2-10-13 @ 9:20 AM Bled pressure on cement plug to 0 PSI, then began rigging down Baker Hughes cementers.


Day 23 Summary: 2-12-13 PBTD = 3,871 DF. F.D.E.P. personnel witnessed tests #1a. thru 9b. of BOP Test #66.
(6 AM 2-11-13 to 6 AM 2-12-13) Drilling engr. witnessed rest of BOP test.
Tagged hard cement inside 9 5/8 casing with 19,700#of weight at 3,802.4 DF.
Drilled 69 of hard cement inside 9 5/8 casing from 3,802 DF to 3,871 DF.
Driller tagged hard cement inside 9 5/8 casing with 19,700# of drill string weight at 3,802.4 DF on 2-12-13 at 4:33 AM.
(Attwood on location 2-11-13 at 6:00 AM, left 2-11-13 at 9:30 AM.)
(Bruno arrived 2-11-13 at 8:30 AM, left 2-11-13 at 12:15 PM.)
(Attwood arrived 2-11-13 at 5:09 PM, left 2-11-13 at 5:39 PM.)
(Attwood arrived 2-12-13 at 2:19 AM, on location 2-12-13 at 6:00 AM.)



Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 6.96 North & 16.50 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 4,608 DF TVD 4,607.55
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole at 4,608 DF.


I certify that the above well and premise was inspected on 2-4-13, 2-6-13, 2-8-13, 2-9-13, 2-10-13, 2-11-13, & 2-12-13 by Paul Attwood
& Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 13
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/13/13
Permit #
1349
Date
02 13 2013

BOP Test #66 on 2-11-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
2-11-13 @ 7:13 AM 2-11-13 @ 7:18 AM
1a. Tested Lower pipe rams at 270 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 7:19 AM 2-11-13 @ 7:24 AM
1b. Tested Lower pipe rams at 3,510 PSI.
Lost 40 PSI (1.1%) in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 7:28 AM 2-11-13 @ 7:28:30 AM
2a(1). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 240 PSI.
Lost 240 PSI (100%) in minute. FAILED 1
st
low pressure test.
Re-pressurized system to 400 PSI & re-started test.
2-11-13 @ 7:29:15 AM 2-11-13 @ 7:33:15 AM
2a(2). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 400 PSI.
Lost 40 PSI (10.0%) in 4 minutes. FAILED 2
nd
low pressure test.
Opened line. Pumped one stroke. Closed line & started 3
rd
low pressure test.
2-11-13 @ 7:33:45 AM 2-11-13 @ 7:38:45 AM
2a(3). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 365 PSI.
No pressure lost in 5 minutes. PASSED on 3
rd
attempt.
2-11-13 @ 7:40:30 AM 2-11-13 @ 7:45:30 AM
2b(1). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,490 PSI.
Lost 140 PSI (4.0%) in 5 minutes. FAILED 1
st
high pressure test.
Opened line. Pumped one stroke. Closed line & started 2
nd
high pressure test.
2-11-13 @ 7:46 AM 2-11-13 @ 7:51 AM
2b(2). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,480 PSI.
Lost 100 PSI (2.9%) in 5 minutes. PASSED on 2
nd
attempt.
2-11-13 @ 7:54:45 AM 2-11-13 @ 7:59:45 AM
3a. Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 290 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 8:00:30 AM 2-11-13 @ 8:05:30 AM
3b. Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 3,525 PSI.
Lost 95 PSI (2.7%) in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 8:09:30 AM 2-11-13 @ 8:14 AM
4a(1). Tested Hydril at 270 PSI.
Lost 40 PSI (14.8%) in 4 minutes. FAILED on 1
st
low pressure test.
Opened line. Pumped one stroke. Closed line & started 2
nd
low pressure test.
2-11-13 @ 8:14:15 AM 2-11-13 @ 8:19:15 AM
4a(2). Tested Hydril at 250 PSI.
No pressure lost in 5 minutes. PASSED on 2
nd
attempt.
2-11-13 @ 8:20 AM 2-11-13 @ 8:25 AM
4b(1). Tested Hydril at 2,005 PSI.
Lost 75 PSI (3.7%) in 5 minutes. FAILED 1
st
high pressure test.
Pressured-up Hydril bladder to 1,550 PSI, then started 2
nd
high pressure test.
2-11-13 @ 8:31:30 AM 2-11-13 @ 8:36:30 AM
4b(2). Tested Hydril at 2,010 PSI.
Lost 40 PSI (2.0%) in 5 minutes. PASSED on 2
nd
attempt.
2-11-13 @ 10:14 AM 2-11-13 @ 10:19 AM
5a. Tested Manual T.I.W. (Full Open Safety Ball) valve at 400 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 10:20 AM 2-11-13 @ 10:25 AM
5b. Tested Manual T.I.W. (Full Open Safety Ball) valve at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 10:33 AM 2-11-13 @ 10:38 AM
6a. Tested Inside Gray (manual dart) valve at 400 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 10:39 AM 2-11-13 @ 10:44 AM
6b. Tested Inside Gray (manual dart) valve at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 10:58 AM 2-11-13 @ 10:59:30 AM
7a(1). Tested Lower manual I.B.O.P. on top drive at 300 PSI.
Lost 180 PSI (40.0%) in 1 minutes. FAILED on 1
st
low pressure test.

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 4 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 6.96 North & 16.50 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 4,608 DF TVD 4,607.55
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole at 4,608 DF.


I certify that the above well and premise was inspected on 2-4-13, 2-6-13, 2-8-13, 2-9-13, 2-10-13, 2-11-13, & 2-12-13 by Paul Attwood
& Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 13
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/13/13
Permit #
1349
Date
02 13 2013

BOP Test #66 on 2-11-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
2-11-13 @ 11:02 AM 2-11-13 @ 11:08 AM
7a(2). Tested Lower manual I.B.O.P. on top drive at 400 PSI.
No pressure lost in 6 minutes. PASSED on 2
nd
attempt.
2-11-13 @ 11:09 AM 2-11-13 @ 11:14 AM
7b. Tested Lower manual I.B.O.P. on top drive at 3,500 PSI.
Lost 100 PSI (2.9%) in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 11:21 AM 2-11-13 @ 11:22 AM
8a(1). Tested Upper hydraulic I.B.O.P. on top drive at 300 PSI.
Lost 100 PSI (33.3%) in 1 minute. FAILED 1
st
low pressure test.
2-11-13 @ 11:26 AM 2-11-13 @ 11:31 AM
8a(2). Tested Upper hydraulic I.B.O.P. on top drive at 390 PSI.
No pressure lost in 5 minutes. PASSED on 2
nd
attempt.
2-11-13 @ 11:32 AM 2-11-13 @ 11:37 AM
8b. Tested Upper hydraulic I.B.O.P. on top drive at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 11:53 AM 2-11-13 @ 11:58 AM
9a. Tested 4 Standpipe valve at 310 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 11:59 AM 2-11-13 @ 12:04 PM
9b. Tested 4 Standpipe valve at 3,600 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
FDEP witness (Mr. Pierre Bruno) had to leave location after Test #9b. Tests #10a .thru #14b. witnessed by Mr. Ricky Baughman (PPI drilling consultant).
2-11-13 @ 2:31 PM 2-11-13 @ 2:36 PM
10a. Tested HCR + Inside manual valve +choke manifold valves to gas buster and shale shaker at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 2:37 PM 2-11-13 @ 2:42 PM
10b. Tested HCR + Inside manual valve + choke manifold valves to gas buster and shale shaker at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
A 150 PSI (4.3%) pressure decline was recorded on the chart record for Test #10b.
2-11-13 @ 2:51 PM 2-11-13 @ 2:56 PM
11a. Tested HCR + Inside manual valve + three (3) MIDDLE choke manifold valves at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 2:57 PM 2-11-13 @ 3:02 PM
11b. Tested HCR + Inside manual valve + three (3) MIDDLE choke manifold valves at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
A 150 PSI (4.3%) pressure decline was recorded on the chart record for Test #11b.
2-11-13 @ 3:08 PM 2-11-13 @ 3:13 PM
12a. Tested HCR + Inside manual valve + three (3) INSIDE choke manifold valves at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 3:14 PM 2-11-13 @ 3:19 PM
12b. Tested HCR + Inside manual valve + three (3) INSIDE choke manifold valves at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
A 100 PSI (2.9%) pressure decline was recorded on the chart record for Test #12b.
2-11-13 @ 4:27 PM 2-11-13 @ 4:32 PM
13a. Tested 4 mud pump valves at 400 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 4:33 PM 2-11-13 @ 4:38 PM
13b. Tested 4 mud pump valves at 3,600 PSI.
Lost 100 PSI (2.8%) in 5 minutes. PASSED on 1
st
attempt.
A 120 PSI (3.3%) pressure decline was recorded on the chart record for Test #13b.
2-11-13 @ 5:02 PM 2-11-13 @ 5:07 PM
14a. Tested Blind rams at 350 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-11-13 @ 5:08 PM 2-11-13 @ 5:13 PM
14b. Tested Blind rams at 3,600 PSI.
Lost 60 PSI (1.7%) in 5 minutes. PASSED on 1
st
attempt.
An 80 PSI (2.2%) pressure decline was recorded on the chart record for Test #14b.


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 5 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 6.96 North & 16.50 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 4,608 DF TVD 4,607.55
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole at 4,608 DF.


I certify that the above well and premise was inspected on 2-4-13, 2-6-13, 2-8-13, 2-9-13, 2-10-13, 2-11-13, & 2-12-13 by Paul Attwood
& Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 13
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/13/13
Permit #
1349
Date
02 13 2013


Day 24 Summary: 2-13-13 TD = 4,608 DF. F.D.E.P. witnessed successful M.I .T. of 9 5/8 intermediate casing.
(6 AM 2-12-13 to 6 AM 2-13-13) Drilled 69 of hard cement inside 9 5/8 casing from 3,871 DF to 3,964 DF.
Drilled 1 of hard cement in (former) 12 hole from 3964 DF to 3,965 DF.
Drilled 643 of 8 hole from 3,965 DF to 4,608 DF in 20 hrs.
(Attwood on location 2-12-13 at 6:00 AM, left 2-12-13 at 7:14 AM.)

Performed MIT of 9 5/8 intermediate casing. MIT witnessed by P. Attwood (FDEP-Oil & Gas Section.)

M.I.T #1 of 9 5/8 intermediate casing on 2-12-13 in #1349 well
8 drill bit at 3,870.4 DF during MIT
Duration Time (per Pason) Actual/True Time PSIG (per Pason)
Start 6:44:30 AM 6:32:48 AM 1002
5 min. 6:49:30 AM 6:37:48 AM 991
10 min. 6:54:30 AM 6:42:48 AM 990
15 min. 6:59:30 AM 6:47:48 AM 989
20 min. 7:04:30 AM 6:52:48 AM 990
Note: Pressure registered on the digital Pason screen (=990 PSI) was 50 PSI lower
than the pressure registered on the mechanical Totco gauge (=1,040 PSI)
after 20 minutes of the test had elapsed.
25 min. 7:09:30 AM 6:57:48 AM 991
30 min. 7:14:30 AM 7:02:48 AM 992
Summary of MIT #1: Lost 10 PSI (1.00%) in 30 minutes. Passed MIT.
PASSED MIT #1 on 2-12-13 at 7:02:48 AM.

---No Violations---


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 14.64 South & 134.65 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 11,704 DF TVD 11,701.74
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status P.O.O.H. to rig up Halliburton & cut conventional core #1.


I certify that the above well and premise was inspected on 2-15-13, 2-18-13, 2-21-13, 2-24-13, & 2-25-13 by Paul Attwood.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 26
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/26/13
Permit #
1349
Date
02 26 2013


Third Report (#1349-pilot): Drilled 7,096 of 8 hole from 4,608 DF to 11,704 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF

Day 25 Summary: 2-14-13 TD = 5,695 DF Drilled 1,087 of 8 hole from 4,608 DF to 5,695 DF in 22 hrs.
(6 AM 2-13-13 to 6 AM 2-14-13)

Day 26 Summary: 2-15-13 TD = 6,554 DF Drilled 859 of 8 hole from 5,695 DF to 6,554 DF in 22 hrs.
(6 AM 2-14-13 to 6 AM 2-15-13)

Day 27 Summary: 2-16-13 TD = 6,792 DF Drilled 238 of 8 hole from 6,554 DF to 6,792 DF in 7.5 hrs.
(6 AM 2-15-13 to 6 AM 2-16-13)
(Attwood arrived 2-15-13 at 9:51 AM, left 2-15-13 at 10:04 AM.)

Day 28 Summary: 2-17-13 TD = 7,302 DF Drilled 510 of 8 hole from 6,792 DF to 7,302 DF in 20.5 hrs.
(6 AM 2-16-13 to 6 AM 2-17-13) 276.89 of fish left in hole from 7,025 DF to 7,301.89 DF.
Well flowing. Raised mud weight from 8.7 PPG to 8.8 PPG.

Day 29 Summary: 2-18-13 TD = 7,302 DF Attempting to recover 276.89 of fish in well from 7,025 DF to 7,301.89 DF.
(6 AM 2-17-13 to 6 AM 2-18-13)
Well flowing.
Crossover below jars broke off .
276.89-long fish in well: 8 drill bit + mud motor + crossover + prodrift tool + seven 6 drill collars
+ two stabilizers + 1.19-long crossover.
Tripped in hole with fishing tools. Made seven unsuccessful attempts to recover fish. No success.

Day 30 Summary: 2-19-13 TD = 7,302 DF Recovered 276.89 of fish in well from 7,025 DF to 7,301.89 DF.
(6 AM 2-18-13 to 6 AM 2-19-13)
Tripped in hole with overshot + bent joint of drill pipe. Latched onto & recovered 276.89 of fish.
(Attwood arrived 2-18-13 at 7:20 AM, left 2-18-13 at 7:48 AM.)

Day 31 Summary: 2-20-13 TD = 7,983 DF Drilled 681 of 8 hole from 7,302 DF to 7,983 DF in 18 hrs.
(6 AM 2-19-13 to 6 AM 2-20-13)

Day 32 Summary: 2-21-13 TD = 8,823 DF Drilled 840 of 8 hole from 7,983 DF to 8,823 DF in 21.5 hrs.
(6 AM 2-20-13 to 6 AM 2-21-13)

Day 33 Summary: 2-22-13 TD = 9,900 DF Drilled 1,077 of 8 hole from 8,823 DF to 9,900 DF in 19 hrs.
(6 AM 2-21-13 to 6 AM 2-22-13)
(Attwood arrived 2-21-13 at 1:18 PM, left 2-21-13 at 2:09 PM.)

Day 34 Summary: 2-23-13 TD = 10,835 DF Drilled 935 of 8 hole from 9,900 DF to 10,835 DF in 19 hrs.
(6 AM 2-22-13 to 6 AM 2-23-13)

Day 35 Summary: 2-24-13 TD = 11,535 DF Drilled 700 of 8 hole from 10,835 DF to 11,535 DF in 21 hrs.
(6 AM 2-23-13 to 6 AM 2-24-13)

Day 36 Summary: 2-25-13 TD = 11,600 DF Drilled 65 of 8 hole from 11,535 DF to 11,600 DF in 3 hrs.
(6 AM 2-24-13 to 6 AM 2-25-13) Performed B.O.P. Test #67.
Ran Gamma Ray/Sonic/Dual induction correlation logs from 8,500 DF to 11,600 DF.
Performed B.O.P. Test #67. Entire test witnessed by P. Attwood (FDEP-Oil & Gas Section.)
Rigged up Youngquist Bros. logging truck & ran wireline logs for correlation (to pick core points) on 2-25-13:
Run #1: Gamma Ray/Sonic from 8,500 DF to 11,600 DF.
Run #2: Dual induction from 8,500 DF to 11,600 DF.

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 14.64 South & 134.65 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 11,704 DF TVD 11,701.74
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status P.O.O.H. to rig up Halliburton & cut conventional core #1.


I certify that the above well and premise was inspected on 2-15-13, 2-18-13, 2-21-13, 2-24-13, & 2-25-13 by Paul Attwood.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 26
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/26/13
Permit #
1349
Date
02 26 2013


BOP Test #67 on 2-24-13 & 2-25-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
2-24-13 @ 9:22:15 PM 2-24-13 @ 9:27:15 PM
1a. Tested Lower pipe rams at 300 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-24-13 @ 9:28 PM 2-24-13 @ 9:29:15 PM
1b(1). Tested Lower pipe rams at 3,500 PSI.
Lost 800 PSI (22.9%) in 1 minutes. FAILED 1
st
high pressure test.
Repaired loose O ring connection where pressurized line connects to pressure gauge.
2-24-13 @ 9:32:15 PM 2-24-13 @ 9:37:15 PM
1b(2). Tested Lower pipe rams at 3,370 PSI.
Lost 60 PSI (1.8%) in 5 minutes. PASSED on 2
nd
attempt.
2-24-13 @ 9:41:30 PM 2-24-13 @ 9:44 PM
2a(1). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 320 PSI.
Lost 40 PSI (12.5%) in 2 minutes. FAILED 1
st
low pressure test.
Increased pressure in system from 280 PSI to 420 PSI, then started 2
nd
low pressure test.
2-24-13 @ 9:44:30 PM 2-24-13 @ 9:49:30 PM
2a(2). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 420 PSI.
Lost 10 PSI (2.4%) in 5 minutes. PASSED on 2
nd
attempt.
2-24-13 @ 9:50:15 PM 2-24-13 @ 9:51:45 PM
2b(1). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,390 PSI.
Lost 220 PSI (6.5%) in 1 minutes. FAILED 1
st
high pressure test.
Opened line. Pumped one stroke. Closed line & started 2
nd
high pressure test.
2-24-13 @ 9:52:30 PM 2-24-13 @ 9:55:30 PM
2b(2). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,475 PSI.
Lost 245 PSI (7.0%) in 3 minutes. FAILED 2
nd
high pressure test.
Opened & closed INSIDE manual valve + INSIDE kill line valve, then re-pressurized line & started 3
rd
high PSI test.
2-24-13 @ 9:58:30 PM 2-24-13 @ 10:03:30 PM
2b(3). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,500 PSI.
Lost 60 PSI (1.7%) in 5 minutes. PASSED on 3
rd
attempt.
2-24-13 @ 10:06:45 PM 2-24-13 @ 10:08:45 PM
3a(1). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 270 PSI.
Lost 50 PSI (18.5%) in 2 minutes. FAILED 1
st
low pressure test.
Opened line. Pumped one stroke. Closed line & started 2
nd
low pressure test.
2-24-13 @ 10:09:15 PM 2-24-13 @ 10:12:15 PM
3a(2). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 355 PSI.
Lost 25 PSI (7.0%) in 3 minutes. FAILED 2
nd
low pressure test.
At this point, operator decided to run high pressure test.
2-24-13 @ 10:13:30 PM 2-24-13 @ 10:14:30 PM
3b(1). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 3,380 PSI.
Lost 220 PSI (6.5%) in 1 minute. FAILED 1
st
high pressure test.
Opened & closed upper pipe rams, then started 3
rd
low pressure test.
2-24-13 @ 10:30:30 PM 2-24-13 @ 10:32:30 PM
3a(3). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 300 PSI.
Lost 40 PSI (13.3%) in 2 minutes. FAILED 3
rd
low pressure test.
Opened line. Pumped one stroke. Closed line & started 4
th
low pressure test.
2-24-13 @ 10:33 PM 2-24-13 @ 10:35:30 PM
3a(4). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 295 PSI.
Lost 30 PSI (10.2%) in 2 minutes. FAILED 4
th
low pressure test.
Operator decided to try a 2
nd
high pressure test.
2-24-13 @ 10:36:15 PM 2-24-13 @ 10:41:15 PM
3b(2). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 3,430 PSI.
Lost 45 PSI (1.3%) in 5 minutes. PASSED on 2
nd
attempt.
Bled pressure from 3,385 PSI to 320 PSI, then started 5
th
low pressure test.
2-24-13 @ 10:42:30 PM 2-24-13 @ 10:47:30 PM
3a(5). Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve at 320 PSI.
Lost 5 PSI (1.6%) in 5 minutes. PASSED on 5
th
attempt.
2-24-13 @ 10:52 PM 2-24-13 @ 10:54:30 PM
4a(1). Tested Hydril at 300 PSI.
Lost 50 PSI (16.7%) in 2 minutes. FAILED 1
st
low pressure test.
Increased pressure from 250 PSI to 300 PSI & continued testing.

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 14.64 South & 134.65 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 11,704 DF TVD 11,701.74
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status P.O.O.H. to rig up Halliburton & cut conventional core #1.


I certify that the above well and premise was inspected on 2-15-13, 2-18-13, 2-21-13, 2-24-13, & 2-25-13 by Paul Attwood.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 26
th
day of February 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 02/26/13
Permit #
1349
Date
02 26 2013

BOP Test #67 on 2-24-13 & 2-25-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
2-24-13 @ 10:55 PM 2-24-13 @ 11:01 PM
4a(2). Tested Hydril at 300 PSI.
Lost 10 PSI (3.3%) in 6 minutes. No drips or leaks observed from & around Hydril. PASSED on 2
nd
attempt.
2-24-13 @ 11:01:45 PM 2-24-13 @ 11:06 PM
4b(1). Tested Hydril at 1,880 PSI.
Lost 60 PSI (3.7%) in 4 minutes. FAILED 1
st
high pressure test.
Increased pressure from 1,820 PSI to 2,000 PSI & continued testing.
2-24-13 @ 11:06:45 PM 2-24-13 @ 11:11:45 PM
4b(2). Tested Hydril at 2,000 PSI.
Lost 40 PSI (2.0%) in 5 minutes. PASSED on 2
nd
attempt.
2-24-13 @ 11:27 PM 2-24-13 @ 11:28 PM
5a(1). Blind rams + three (3) INSIDE choke manifold valves at 290 PSI.
Lost 115 PSI (39.7%) in 1 minute. FAILED 1
st
low pressure test.
Pressured up line to 1,000 PSI, then bled pressure back to 350 PSI & started 2
nd
low pressure test.
2-24-13 @ 11:31:45 PM 2-24-13 @ 11:36:45 PM
5a(2). Blind rams + three (3) INSIDE choke manifold valves at 350 PSI.
No pressure lost in 5 minutes. PASSED on 2
nd
attempt.
2-24-13 @ 11:37:30 PM 2-24-13 @ 11:40 PM
5b(1). Blind rams + three (3) INSIDE choke manifold valves at 3,490 PSI.
Lost 150 PSI (4.3%) in 2 minutes. FAILED 1
st
high pressure test.
Increased pressure from 3,340 PSI to 3,520 PSI & continued testing.
2-24-13 @ 11:40:30 PM 2-24-13 @ 11:45:30 PM
5b(2). Blind rams + three (3) INSIDE choke manifold valves at 3,520 PSI.
Lost 30 PSI (0.9%) in 5 minutes. PASSED on 2
nd
attempt.
2-24-13 @ 11:54:30 PM 2-24-13 @ 11:59:30 PM
6a. Blind rams + three (3) MIDDLE choke manifold valves at 310 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
2-25-13 @ 12:00:45 AM 2-25-13 @ 12:04:45 AM
6b(1). Blind rams + three (3) MIDDLE choke manifold valves at 3,490 PSI.
Lost 85 PSI (2.4%) in 4 minutes. Technically, would have probably PASSED 1
st
high pressure test if duration = 5 min.
I wanted a better test result based on previous questionable test of these three valves on 2-11-13.
2-25-13 @ 12:05:15 AM 2-25-13 @ 12:10:15 AM
6b(2). Blind rams + three (3) MIDDLE choke manifold valves at 3,600 PSI.
Lost 15 PSI (0.4%) in 5 minutes. Definitely PASSED on 2
nd
attempt.
2-25-13 @ 12:15:45 AM 2-25-13 @ 12:20:45 AM
7a. Blind rams + choke manifold valves to shale shakers, panic line, & gas buster at 300 PSI.
Lost 5 PSI (1.7%) in 5 minutes. PASSED on 1
st
attempt.
2-25-13 @ 12:21:30 AM 2-25-13 @ 12:24:30 AM
7b(1). Blind rams + choke manifold valves to shale shakers, panic line, & gas buster at 3,500 PSI.
Lost 50 PSI (1.4%) in 3 minutes. Technically, would have probably PASSED 1
st
high pressure test if duration = 5 min.
I wanted a better test result based on previous questionable test of these three valves on 2-11-13.
Increased pressure from 3,450 PSI to 3,670 PSI & continued testing.
2-25-13 @ 12:25 AM 2-25-13 @ 12:30 AM
7b(2). Blind rams + choke manifold valves to shale shakers, panic line, & gas buster at 3,670 PSI.
Lost 40 PSI (1.1%) in 5 minutes. PASSED on 2
nd
attempt.

(Attwood arrived 2-24-13 at 6:55 PM, left 2-25-13 at 12:46 AM.)

Day 37 Summary: 2-26-13 TD = 11,704 DF Drilled 104 of 8 hole from 11,600 DF to 11,704 DF in 3.5 hrs.
(6 AM 2-25-13 to 6 AM 2-26-13) P.O.O.H. to take conventional core #1.

---No Violations---


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 74.96 South & 193.18 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,908 DF TVD 12,904.27
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Ricky Baughman (drilling consultants) (713) 395-7571
Well Status Waiting on fishing tools. 236.20 of fish in hole from 12,672.40 DF to 12,908.6 DF.


I certify that the above well and premise was inspected on 2-26-13, 3-4-13, 3-6-13, 3-7-13, & 3-8-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 9
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/09/13
Permit #
1349
Date
03 09 2013


Fourth Report (#1349-pilot): Cored 32 from 11,704 DF to 11,736 DF. Recovered 32 of 32 cored;
Drilled 134 of 8 hole from 11,736 DF to 11,870 DF;
Cored 83 from 11,870 DF to 11,953 DF. Recovered 50 of 83 cored;
Cored 33 from 11,953 DF to 11,986 DF. Recovered 19 of 33 cored;
Drilled 922 of 8 hole from 11,986 DF to 12,908 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.


Day 38 Summary: 2-27-13 TD = 11,736 DF. Conventionally cored 32 from 11,704 DF to 11,736 DF (Halliburton Core #1).
(6 AM 2-26-13 to 6 AM 2-27-13)
(10:30 AM 2-26-13 to 5:30 PM 2-26-13) Tripped in hole with Halliburton Core Barrel #1 to 11,700 DF. Washed 4 from 11,700 DF to 11,704 DF.
(5:30 PM 2-26-13 to 9 PM 2-26-13) Cored 32 from 11,704 DF to 11,736 DF.
Note A: Top of Sunniland = 11,771 DF.
(9 PM 2-26-13 to 6 AM 2-27-13) P.O.O.H. very slowly with Halliburton Core Barrel #1 from 11,736 DF to 1,550 DF.
(Attwood arrived 2-26-13 at 8:36 AM, left 2-26-13 at 9:08 AM.)


Day 39 Summary: 2-28-13 TD = 11,818 DF. Recovered 32 of 32 cored from 11,704 DF to 11,736 DF (Halliburton Core #1).
(6 AM 2-27-13 to 6 AM 2-28-13) Lost 0 of core.
Drilled 82 of 8 hole from 11,736 DF to 11,818 DF in 2.5 hrs.
(6 AM 2-27-13 to 9:30 AM 2-27-13) P.O.O.H. very slowly with Halliburton Core Barrel #1 from 1,550 DF to surface.


Day 40 Summary: 3-01-13 TD = 11,870 DF. Drilled 52 of 8 hole from 11,818 DF to 11,870 DF in 1.5 hrs.
(6 AM 2-28-13 to 6 AM 3-1-13) Youngquist Bros. logging ran Sonic/Gamma Ray correlation log from 11,870 DF to 8,500 DF.

Day 41 Summary: 3-02-13 TD = 11,937 DF. Conventionally cored 67 from 11,870 DF to 11,937 DF (Halliburton Core #2).
(6 AM 3-1-13 to 6 AM 3-2-13)
(1:30 PM 3-1-13 to 7:30 PM 3-1-13) Tripped in hole with Halliburton Core Barrel #2 to 11,850 DF. Washed 20 from 11,850 DF to 11,870 DF.
(7:30 PM 3-1-13 to 6 AM 3-2-13) Cored 67 from 11,870 DF to 11,937 DF.
Note B: Bottom of Sunniland B = 11,834 DF.
Note C: Top of Sunniland C = 11,845 DF.
Note D: Top of Rubble Zone = 11,924 DF.


Day 42 Summary: 3-03-13 TD = 11,953 DF. Conventionally cored 16 from 11,937 DF to 11,953 DF (bottomportion of Halliburton Core #2).
(6 AM 3-2-13 to 6 AM 3-3-13) Recovered 50 of 83 cored from 11,870 DF to 11,920 DF (upper part of Halliburton Core #2).
Lost 33 of core from 11,920 DF to 11,953 DF down well (bottomportion of Halliburton Core #2).
(6 AM 3-2-13 to 10:30 AM 3-2-13) Cored 16 from 11,937 DF to 11,953 DF after which core barrel appeared to be jammed.
Unable to core entire 90.
Note D: Top of Rubble Zone = 11,924 DF.
Note E: Top of Punta Gorda Anhydrite = 11,951 DF.
(11 AM 3-2-13 to 12:30 AM 3-3-13) P.O.O.H. very slowly with Halliburton Core Barrel #2 from 11,953 DF to surface.
(5 AM 3-3-13 to 6 AM 3-3-13) Tripped in hole with Halliburton Core Barrel #3 to 471 DF.



Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 74.96 South & 193.18 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,908 DF TVD 12,904.27
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Ricky Baughman (drilling consultants) (713) 395-7571
Well Status Waiting on fishing tools. 236.20 of fish in hole from 12,672.40 DF to 12,908.6 DF.


I certify that the above well and premise was inspected on 2-26-13, 3-4-13, 3-6-13, 3-7-13, & 3-8-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 9
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/09/13
Permit #
1349
Date
03 09 2013




Day 43 Summary: 3-04-13 TD = 11,986 DF. Tagged top of lost core at 11,924 DF. Washed over & attempted to capture 29 of lost core
(6 AM 3-3-13 to 6 AM 3-4-13) from 11,924 DF to 11,953 DF (bottomportion of Halliburton Core #2).
Conventionally cored 33 from 11,953 DF to 11,986 DF (Halliburton Core #3).
(6 AM 3-3-13 to 11:30 AM 3-3-13) Continued tripping in hole with Halliburton Core Barrel #3 from 471 DF to 11,924 DF.
Tagged top of lost bottom portion of core from conventional core #2 at 11,924 DF.
(11:30 AM 3-3-13 to 1 PM 3-3-13) Attempted to wash & capture lost core from 11,924 DF to 11,953 DF.
(1 PM 3-3-13 to 4 PM 3-3-13) Cored 33 from 11,953 DF to 11,986 DF.
Note E: Top of Punta Gorda Anhydrite = 11,951 DF.
(4 PM 3-3-13 to 6 AM 3-4-13) P.O.O.H. very slowly with Halliburton Core Barrel #3 from 11,986 DF to 172 DF.


Day 44 Summary: 3-05-13 TD = 11,986 DF. Recovered 0 of lost core from 11,924 DF to 11,953 DF (Bottomportion of Halliburton Core #2).
(6 AM 3-4-13 to 6 AM 3-5-13) Recovered 19 of core from 11,953 DF to 11,972 DF (Halliburton Core #3).
Lost 14 of core from 11,973 DF to 11,986 down well (Halliburton Core #3).
(6 AM 3-4-13 to 7 AM 3-4-13) P.O.O.H. very slowly with Halliburton Core Barrel #3 from 172 DF to surface.
(1 PM 3-4-13 to 2 PM 3-4-13) Tripped in hole with Halliburton Core Barrel #4 to 3,360 DF, then cut & slipped drill line (3 hrs.)
(5 PM 3-4-13 to 5:30 PM 3-4-13) Tripped in hole with Halliburton Core Barrel #4 from 3,360 DF to 3,748 DF, then shut down for rig repairs.
(Attwood arrived 3-4-13 at 7:05 AM, left 3-4-13 at 7:25 AM.)



Day 45 Summary: 3-06-13 TD = 11,986 DF. Rig repairs. Began rebuilding drawworks low drum clutch assembly.
(6 AM 3-5-13 to 6 AM 3-6-13)



Day 46 Summary: 3-07-13 TD = 12,299 DF. Rig repairs. Finished rebuilding drawworks low drum clutch assembly.
(6 AM 3-6-13 to 6 AM 3-7-13) Drilled 313 of 8 hole from 11,986 DF to 12,299 DF in 7.5 hrs.
(1 PM 3-6-13 to 4 PM 3-6-13) P.O.O.H. with Halliburton Core Barrel #4 from 3,748 DF to surface.
Operator decided to abandon efforts to recover 14 of lost core from 11,973 DF to 11,986 DF.
(Attwood arrived 3-6-13 at 6:16 AM, left 3-6-13 at 6:34 AM.)



Day 47 Summary: 3-08-13 TD = 12,908 DF. Drilled 609 of 8 hole from 12,299 DF to 12,908 DF in 22 hrs.
(6 AM 3-7-13 to 6 AM 3-8-13)
(Bruno arrived 3-7-13 at 3:36 PM, left 3-7-13 at 5 PM.)


Day 48 Summary: 3-09-13 TD = 12,908 DF. J ars broke off. 236.20 of fish left in hole from 12,672.40 DF to 12,908.6 DF.
(6 AM 3-8-13 to 6 AM 3-9-13) Performed B.O.P. Test #68. Waited on fishing tools.
236.20-long fish in well:
8 drill bit + mud motor + float sub + crossover + pro drift tool + six 6 drill collars + 3.59 of jars
(Attwood arrived 3-8-13 at 8:45 AM, left 3-8-13 at 9:23 AM.)








Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 74.96 South & 193.18 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,908 DF TVD 12,904.27
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Ricky Baughman (drilling consultants) (713) 395-7571
Well Status Waiting on fishing tools. 236.20 of fish in hole from 12,672.40 DF to 12,908.6 DF.


I certify that the above well and premise was inspected on 2-26-13, 3-4-13, 3-6-13, 3-7-13, & 3-8-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 9
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/09/13
Permit #
1349
Date
03 09 2013

Day 48: 3-09-13 TD = 12,908 DF (continued)

BOP Test #68 on 3-8-13 & 3-9-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
3-8-13 @ 10:07 PM 3-8-13 @ 10:13 PM
1a. Tested Lower pipe rams at 250 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
3-8-13 @ 10:14 PM 3-8-13 @ 10:20 PM
1b. Tested Lower pipe rams at 3,500 PSI.
Lost 40 PSI (1.1%) in 6 minutes per chart record. PASSED on 1
st
attempt.
3-8-13 @ 10:25 PM 3-8-13 @ 10:31 PM
2a. Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 250 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
3-8-13 @ 10:32 PM 3-8-13 @ 10:33 PM
2b(1). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,500 PSI.
Lost 200 PSI (5.7%) in 1 minute. FAILED 1
st
high pressure test.
3-8-13 @ 10:56 PM 3-8-13 @ 11:02 PM
2b(2). Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve at 3,500 PSI.
Lost 50 PSI (1.4%) in 6 minutes. PASSED on 2
nd
attempt.
3-8-13 @ 11:19 PM 3-8-13 @ 11:26 PM
3a. Tested Hydril at 250 PSI.
No pressure lost in 7 minutes. PASSED on 1
st
attempt.
3-8-13 @ 11:28 PM 3-8-13 @ 11:35 PM
3b. Tested Hydril at 2,000 PSI.
Lost 50 PSI (2.5%) in 7 minutes per chart record. PASSED on 1
st
attempt.
3-8-13 @ 11:48 PM 3-8-13 @ 11:55 PM
4a. Tested Blind rams + Inside manual valve + three (3) INSIDE choke manifold valves at 250 PSI.
No pressure lost in 7 minutes. PASSED on 1
st
attempt.
3-8-13 @ 11:56 PM 3-9-13 @ 12:01 AM
4b. Tested Blind rams + Inside manual valve + three (3) INSIDE choke manifold valves at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
3-9-13 @ 12:28 AM 3-9-13 @ 12:34 AM
5a. Tested Blind rams + three (3) MIDDLE choke manifold valves at 250 PSI.
Lost 30 PSI (12.0%) in 6 minutes per chart record. No pressure loss detected on test pressure gauge.
3-9-13 @ 12:36 AM 3-9-13 @ 12:37 AM
5b(1). Tested Blind rams + three (3) MIDDLE choke manifold valves at 3,500 PSI.
Lost 150 PSI (4.3%) in 1 minute. FAILED 1
st
high pressure test.
3-9-13 @ 12:52 AM 3-9-13 @ 12:55 AM
5b(2). Tested Blind rams + three (3) MIDDLE choke manifold valves at 3,500 PSI.
Lost 100 PSI (2.9%) in only 3 minutes. FAILED 2
nd
high pressure test.
3-9-13 @ 1:01 AM 3-9-13 @ 1:06 AM
5b(3). Tested Blind rams + three (3) MIDDLE choke manifold valves at 3,500 PSI.
Lost 50 PSI (1.4%) in 5 minutes per chart record. PASSED on 3
rd
attempt.
3-9-13 @ 1:15 AM 3-9-13 @ 1:20 AM
6a. Tested Blind rams + right manual & left manual choke manifold valves at 250 PSI.
No pressure lost in 5 minutes per chart record. PASSED on 1
st
attempt.
3-9-13 @ 1:21 AM 3-9-13 @ 1:26 AM
6b. Tested Blind rams + right manual & left manual choke manifold valves at 3,500 PSI.
No pressure lost in 5 minutes per chart record. PASSED on 1
st
attempt
3-9-13 @ 1:34 AM 3-9-13 @ 1:39 AM
7a. Tested HCR (High Closing Ratio) valve + choke manifold valves to shale shaker, panic line, & gas buster
at 250 PSI.
No pressure lost in 5 minutes per chart record. PASSED on 1
st
attempt.
3-9-13 @ 1:40 AM 3-9-13 @ 1:44 AM
7b. Tested HCR (High Closing Ratio) valve + choke manifold valves to shale shaker, panic line, & gas buster
at 3,500 PSI.
No pressure lost in only 4 minutes per chart record. PASSED on 1
st
attempt.

---No Violations---


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Cemented 5 O.D. x 19.5#/ft. drill pipe in well at 11,382 DF. Waiting on freepoint tool to arrive from Louisiana.


I certify that the above well and premise was inspected on 3-11-13, 3-12-13, 3-13-13, 3-14-13, 3-15-13, 3-17-13, 3-18-13, & 3-19-13
by Paul Attwood. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 19
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/19/13
Permit #
1349
Date
03 19 2013


Fifth Report (#1349-pilot): Recovered entire 236.20-long fish in well from 12,672.40 DF to 12,908.6 DF;
Drilled 265 of 8 hole from 12,908 DF to 13,173 DF;
Conventionally cored 92 from 13,173 DF to 13,265 DF (recovered 90);
Drilled 537 of 8 hole from 13,265 DF to 13,802 DF;
Logged well & recovered 30 rotary sidewall cores;
Pumped Kickoff Plug #1 at 11,382 DF consisting of 164.98 barrels
(= 865 sacks) of Class H cement;
Stuck open-ended 5 drill pipe cementing string in cement at 11,365 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.


Day 49 Summary: 3-10-13 TD = 12,908 DF Began recovering 236.20 of fish left in hole from 12,672.40 DF to 12,908.6 DF.
(6 AM 3-9-13 to 6 AM 3-10-13)
Tripped in hole with 6 grapple on overshot. Tagged fish at 12,665 DF. Began P.O.O.H. with fish.

Day 50 Summary: 3-11-13 TD = 13,000 DF Finished recovering 236.20 of fish left in hole from 12,672.40 DF to 12,908.6 DF.
(6 AM 3-10-13 to 6 AM 3-11-13) Ran Youngquist Bros. GR/CCL log from 12,146 DF to 11,554 DF (Run #5.)
(Could not get down past 12,146 DF.) P.O.O.H. with log. Added weight bars.
Ran Youngquist Bros. GR/CCL log again. (Could not get down past 12,146 DF.) P.O.O.H.
Drilled 92 of 8 hole from 12,908 DF to 13,000 DF in 1 hr.

Day 51 Summary: 3-12-13 TD = 13,000 DF Ran Youngquist Bros. GR/CCL log (Run #6.) (Could not get down past 12,146 DF.) P.O.O.H.
(6 AM 3-11-13 to 6 AM 3-12-13) Tripped in hole with 5 O.D. x 19.5#/ft. drill pipe to 12,989 DF.
Ran Youngquist Bros. GR/CCL log thru drill pipe from 12,989 DF to 10,900 DF (Run #7.)
P.O.O.H. with log.
(Attwood arrived 3-11-13 at 7:46 AM, left 3-11-13 at 8:12 AM.)

Day 52 Summary: 3-13-13 TD = 13,170 DF (corrected) Drilled 118 of 8 hole from 13,000 DF to 13,118 DF in 7.5 hrs.
(6 AM 3-12-13 to 6 AM 3-13-13) Ran Youngquist Bros. GR/CCL log thru drill pipe from 13,115 DF to 10,900 DF (Run #8.)
Drilled 52 of 8 hole from 13,118 DF to 13,170 DF in 3.5 hrs.
NO hydrogen sulfide gas encountered so far during the drilling of this well thru 13,059 DF.
(Attwood arrived 3-12-13 at 8:11 AM, left 3-12-13 at 8:58 AM.)

Day 53 Summary: 3-14-13 TD = 13,223 DF Drilled 3 of 8 hole from 13,170 DF to 13,173 DF.
(6 AM 3-13-13 to 6 AM 3-14-13) Conventionally cored 50 of the Pumpkin Bay Formation from 13,173 DF to 13,223 DF
(top portion of Halliburton Core #4).
NO hydrogen sulfide gas encountered so far during the drilling of this well thru 13,173 DF.
(Attwood arrived 3-13-13 at 7:52 AM, left 3-13-13 at 8:49 AM.)

Day 54 Summary: 3-15-13 TD = 13,265 DF Conventionally cored 42 of the Pumpkin Bay Formation from 13,223 DF to 13,265 DF
(6 AM 3-14-13 to 6 AM 3-15-13) (bottomportion of Halliburton Core #4).
Recovered 90 of 92 cored from 13,173 DF to 13,265 DF (Halliburton Core #4).
(Attwood arrived 3-14-13 at 8:44 AM, left 3-14-13 at 9:02 AM;
Attwood returned 3-14-13 at 10:24 PM, left 3-15-13 at 12:06 AM.)



Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Cemented 5 O.D. x 19.5#/ft. drill pipe in well at 11,382 DF. Waiting on freepoint tool to arrive from Louisiana.


I certify that the above well and premise was inspected on 3-11-13, 3-12-13, 3-13-13, 3-14-13, 3-15-13, 3-17-13, 3-18-13, & 3-19-13
by Paul Attwood. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 19
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/19/13
Permit #
1349
Date
03 19 2013


Day 55 Summary: 3-16-13 TD = 13,802 DF Drilled 537 of 8 hole from 13,265 DF to 13,802 DF in 14.5 hrs.
(6 AM 3-15-13 to 6 AM 3-16-13) Scientific Drilling ran gyroscopic (directional) survey from 13,753 DF to surface.

Day 56 Summary: 3-17-13 TD = 13,802 DF Ran Halliburtons Triple Gem HFDT log (Run #1) and Wave XRMI log (Run #2).
(6 AM 3-16-13 to 6 AM 3-17-13)
Triple Gem HFDT = High Frequency Dielectric Tool. This tool has a fancy Gamma Ray (which measures
different radioactive elements) + measures resistivity, formation density, & neutron emissions.
Full Wave XRMI = eXtended Range MicroImaging Tool. The wave component of this tool measures
the sonic velocity, and the microimaging component of this tool paints a 3-D picture of the fractures.

Day 57 Summary: 3-18-13 TD = 13,802 DF Tried to run Halliburtons Electric Magnetic Resonance Imaging Log (tool failed downhole twice.)
(6 AM 3-17-13 to 6 AM 3-18-13)


(Attwood arrived 3-17-13 at 12:44 PM, left 3-17-13 at 2:40 PM.)





















Formation tops (#1349-pilot well)
(per Emily Shane -geologist for Dan A. Hughes)
Top of Sunniland 11,693 DF
Top of Sunniland A 11,771 DF
Top of Sunniland B 11,816 DF
Top of OIL in Sunniland B 11,820 DF
Bottom of Sunniland B 11,834 DF
Top of Sunniland C 11,845 DF
Top of Rubble Zone 11,924 DF
Top of Punta Gorda Anhydrite 11,951 DF
Top of Lehigh Acres Fm. 12,614 DF
Top of West Felda Shale Member 13,178 DF
Top of Pumpkin Bay Fm. 13,222 DF

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Cemented 5 O.D. x 19.5#/ft. drill pipe in well at 11,382 DF. Waiting on freepoint tool to arrive from Louisiana.


I certify that the above well and premise was inspected on 3-11-13, 3-12-13, 3-13-13, 3-14-13, 3-15-13, 3-17-13, 3-18-13, & 3-19-13
by Paul Attwood. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 19
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/19/13
Permit #
1349
Date
03 19 2013


Day 58 Summary: 3-19-13 TD = 13,802 DF Recovered 30 of 31 rotary sidewall cores from 8,345 DF to 11,950 DF using Halliburtons
(6 AM 3-18-13 to 6 AM 3-19-13) Hostile Rotary coring tool (see results below.)
Tripped in hole to 12,100 DF. Pumped sweep. Circulated hole clean. Spotted high viscosity LCM pill.
Pulled up to 10,512 DF & circulated well while waiting for cementers to arrive.



(Attwood arrived 3-18-13 at 8:07 AM, left 3-18-13 at 8:26 AM.)






Rotary Sidewall cores taken in #1349 (pilot) well
Depth Stratigraphic location core recovered
8,345 DF above Sunniland Marker solid core
8,365 DF above Sunniland Marker solid core
8,383 DF above Sunniland Marker solid core
9,838 DF above Sunniland Marker solid core
11,609 DF above Sunniland Marker solid core
11,793 DF between Sun. A & Sun. B fractured core
11,844 DF 1 above top of Sunniland C solid core
11,865 DF 20 below top of Sunniland C no core recovered
11,871 DF 26 below top of Sunniland C solid core
11,918 DF 6 above top of Rubble Zone solid core
11,919 DF 5 above top of Rubble Zone solid core
11,920.5 DF 3.5 above top of Rubble Zone solid core
11,921 DF 3 above top of Rubble Zone solid core
11,923 DF 1 above top of Rubble Zone solid core
11,926 DF 2 below top of Rubble Zone solid core
11,928 DF 4 below top of Rubble Zone solid core
11,929 DF 5 below top of Rubble Zone solid core
11,931.5 DF 7.5 below top of Rubble Zone solid core
11,932.5 DF 8.5 below top of Rubble Zone fractured core
11,934.5 DF 10.5 below top of Rubble Zone solid core
11,935.5 DF 11.5 below top of Rubble Zone fractured core
11,936 DF 12 below top of Rubble Zone solid core
11,938.5 DF 14.5 below top of Rubble Zone solid core
11,940.5 DF 16.5 below top of Rubble Zone solid core
11,942 DF 18 below top of Rubble Zone solid core
11,943 DF 19 below top of Rubble Zone solid core
11,944 DF 20 below top of Rubble Zone solid core
11,945 DF 21 below top of Rubble Zone fractured core
11,946.5 DF 4.5 above top of Punta Gorda Anhydrite solid core
11,949 DF 2 above top of Punta Gorda Anhydrite solid core
11,950 DF 1 above top of Punta Gorda Anhydrite solid core

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 4 of 4

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Cemented 5 O.D. x 19.5#/ft. drill pipe in well at 11,382 DF. Waiting on freepoint tool to arrive from Louisiana.


I certify that the above well and premise was inspected on 3-11-13, 3-12-13, 3-13-13, 3-14-13, 3-15-13, 3-17-13, 3-18-13, & 3-19-13
by Paul Attwood. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 19
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/19/13
Permit #
1349
Date
03 19 2013


Day 59 Summary: 3-20-13 TD = 13,802 DF Pumped 164.98 bbl./865 sack cement Kickoff Plug #1 at 11,382 DF.
(6 AM 3-19-13 to 6 AM 3-20-13) Moved drill pipe up hole 17 from 11,382 DF to 11,365 DF after pulling up to 400,000#.
Entire 5 O.D. x 19.5#/ft. cementing string (drill pipe) stuck at 11,365 DF.
Kickoff Plug #1 in #1349 (Pilot well) on 3-19-13:
Pump Depth through 5 O.D. x 4.276 I.D. drill pipe = 11,382 DF (=2,420 above T.D.)
3-19-13 @ 1:10 PM Tested cementing lines to 3,100 PSI. Tested OK.
3-19-13 @ 1:15 PM Fresh water spacer: Pumped 30 bbls. of 8.34 PPG fresh water at 5.8 bpm into 5 drill pipe at 410 PSI.
3-19-13 @ 1:18 PM
S,A.P.P. Spacer: Pumped 20 bbls. of 8.34 PPG Mud Clean II at 6 bpm into 5 drill pipe at 423 PSI.
note: Mud Clean II is also known as S.A.P.P. (= Sodium Acid Pyrophosphate.)
3-19-13 @ 1:24 PM
Kickoff Plug #1: Pumped 164.98 bbls. (865 sacks/16.2 PPG) of Class H cement mixed with
0.15% b.w.o.c. (=121.96#) of R-3 + 3.0% b.w.o.w. (=843.99#) of potassium chloride + 0.25% b.w.o.c. (=203.27#)
of CD-32 + 10# of 100 mesh silica sand (sacked) per sack of cement (=8,650#) + 0.001 gal. per sec. FP-6L (=2.19 gal.)
yielding 1.21 cu. ft. of slurry per sack of cement at 4.52 bpm into 5 drill pipe & 8 open hole at 600 PSI.
note: 865 sacks of Class H cement weighed 81,310#.
3-19-13 @ 2:00 PM Fresh water spacer: Pumped 10 bbls. of 8.34 PPG at 5 bpm into 5 drill pipe at 148 PSI.
3-19-13 @ 2:05 PM
Displacement: Pumped 172 bbls. of 8.6 PPG drilling mud (per drilling report & not cement job report) drilling mud
at 9.5 bpm into 5 drill pipe at 300 PSI to displace cement from inside 5 x 19.5#/ft. drill pipe into 8 open hole.
Note: Water flowed out of 5 drill pipe immediately after cementing lines were disconnected.
3-19-13 @ 2:22 PM Cement in place 3-19-13 at 2:22 PM. Unable to P.O.O.H. with 5 drill pipe. Drill pipe stuck at 11,365 DF.

(Attwood arrived 3-19-13 at 11:56 AM, left 3-19-13 at 3:27 PM.)



---No Violations---












Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25 PBTD 9,241 DF
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole for #1349-H (horizontal well) at 9,241 DF.


I certify that the above well and premise was inspected on 3-20-13, 3-21-13, 3-22-13, 3-24-13, & 3-25-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 30
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/30/13
Permit #
1349
Date
03 30 2013


Sixth Report (#1349-pilot): 2,055-long fish consisting of 65 joints of 5 O.D. x 19.5#/ft. drill pipe
left in 8-diameter hole from 9,310 DF to 11,365 DF;
Pumped 64.65 bbl. (300 sack) Kickoff Plug #2 at 9,223 DF;
Tagged top of cement in 8-diameter hole at 9,110 DF;
Drilled 131 of cement from 9,110 DF to 9,241 DF (Kickoff point for #1349-H.)


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.

Day 60 Summary: 3-21-13 TD = 13,802 DF Unsuccessfully attempted to back off 5 drill pipe at 10,092 DF.
(6 AM 3-20-13 to 6 AM 3-21-13)
Tripped in hole with Weatherfords freepoint tool using Youngquist Bros. wireline truck.
Results of freepoint survey:
Tagged top of cement inside 5 drill pipe with freepoint tool at 10,375 DF.
5 drill pipe intermittently stuck between 10,375 DF & 10,100 DF.
Determined that 5 drill pipe was 100% free at 10,100 DF. Nearest drill pipe collar up hole at 10,092 DF.
First attempt to backoff drill pipe: Tripped in hole with collar locator log + nine (9) 4-long strands of 80 grain primacord to 10,092 DF.
Primacord string shot misfired. P.O.O.H. with live charge.
(Attwood arrived 3-20-13 at 7:20 AM, left 3-20-13 at 8:12 AM;
Attwood returned 3-20-13 at 2:04 PM, left 3-20-23 at 2:35 PM.)

Day 61 Summary: 3-22-13 TD = 13,802 DF Unsuccessfully attempted to back off 5 drill pipe at 10,092 DF & 10,060.5 DF.
(6 AM 3-21-13 to 6 AM 3-22-13)
Second attempt to backoff drill pipe: Tripped in hole with CCL (log) + eleven (11) 4-long strands of 80 grain primacord to 10,092 DF.
Fired primacord string shot. Unable to back off drill pipe. P.O.O.H. with detonated charge.
Third attempt to backoff drill pipe: Tripped in hole with CCL (log) + twenty five (25) 4-long strands of 80 grain primacord to 10,092 DF.
Fired primacord string shot. Unable to back off drill pipe. P.O.O.H. with detonated charge.
Fourth attempt to backoff drill pipe: Tripped in hole with CCL (log) + forty (40) 4-long strands of 80 grain primacord to 10,060.5 DF.
Fired primacord string shot. Unable to back off drill pipe. P.O.O.H. with detonated charge.
Tripped inside 5 drill pipe with Youngquist Bros. Temperature logging tool & logged well from 10,378 DF to 8,496 DF.
Results of temperature survey:
Tagged top of cement inside 5 drill pipe with logging tool at 10,378 DF.
Found slight variations in temperature at 10,063 DF.
Unable to detect top of cement between exterior of drill pipe & 8-diameter hole possibly due to the fact that 50.3 hours had elapsed
since the cement kickoff plug was pumped.
Cement volume calculations for Kickoff Plug #1. 5 O.D. x 19.5#/ft. drill pipe stuck in cement at 11,365 DF:
164.98 barrels of cement pumped.
-6.44 barrels of cement occupied by 987 of 5 O.D. x 4.276 I.D. drill pipe from 10,378 DF to 11,365 DF.
Therefore, 70.46 barrels of cement in 1,004 of 8 open hole from 10,378 DF (tagged top of cement) to 11,382 DF (pump depth.)
and 88.08 barrels of cement in 1,255 of 8 open hole from 11,382 DF (pump depth) to 12,637 DF (est. bottomof plug.)
2,259 of cement in 8 hole from 10,378 DF to 12,637 DF (assuming 0% of cement lost.)
(Attwood arrived 3-21-13 at 10;19 AM, left 3-21-13 at 12:51 PM;
Attwood returned 3-21-13 at 1:55 PM, left 3-21-23 at 2:46 PM.)







Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25 PBTD 9,241 DF
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole for #1349-H (horizontal well) at 9,241 DF.


I certify that the above well and premise was inspected on 3-20-13, 3-21-13, 3-22-13, 3-24-13, & 3-25-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 30
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/30/13
Permit #
1349
Date
03 30 2013



Day 62 Summary: 3-23-13 TD = 13,802 DF Unsuccessfully attempted to sever 5 drill pipe at 10,028 DF.
(6 AM 3-22-13 to 6 AM 3-23-13) Perforated 5 drill pipe at 9,800 DF with 5 shots. Unable to circulate through perforations.
Fifth attempt to backoff drill pipe: Tripped in hole with collar locator log + 2 O.D. severing tool to 10,028 DF.
Pipe severing charge did not fire. Drill pipe not cut. P.O.O.H. with live charge.
Sixth attempt to backoff drill pipe: Tripped in hole with collar locator log + 2 O.D. severing tool to 10,028 DF.
Well started flowing after pipe severing charge was fired.
Youngquist Bros. was not able to go below 10,028 DF with CCL logging tool after severing tool was fired.
Tried to physically part the drill pipe by reciprocating & rotating it. Drill pipe not fully cut.
P.O.O.H. with detonated charge. Screwed into drill pipe fish with top drive.
Attempted to free pipe with 2500# of trapped drill pipe pressure & 20,000# of torque. No success.
Tripped inside 5 drill pipe with collar locator log + 5 shot perforating gun to 9,800 DF. Successfully fired perforating gun.
Unable to circulate well through probable holes in drill pipe. Bullets may not have penetrated drill pipe. P.O.O.H. with perforating gun.
(Attwood arrived 3-22-13 at 8:48 AM, left 3-22-13 at 9:16 AM;
Attwood returned 3-22-13 at 5:14 PM, left 3-22-23 at 5:55 PM.)


Day 63 Summary: 3-24-13 TD = 13,802 DF Rigged up Halliburton truck to run a second freepoint on wireline.
(6 AM 3-23-13 to 6 AM 3-24-13)


Day 64 Summary: 3-25-13 TD = 13,802 DF Determined 5 drill pipe 100% free above 9,983 DF.
(6 AM 3-24-13 to 6 AM 3-25-13) Unsuccessfully attempted to back off 5 drill pipe at 9,966 DF.
Perforated 5 drill pipe at 9,956 DF with 10 shots.
Tripped in hole with Halliburtons 1.6875 O.D. freepoint tool using Halliburtons wireline truck.
Results of second freepoint survey:
Determined that cemented 5 drill pipe was 100% free from 9,983 DF to surface. Nearest drill pipe collar up hole at 9,966 DF.
Seventh attempt to backoff drill pipe:Tripped in hole with collar locator log + ten (10) 6-long strands of 100 grain primacord to 9,966 DF.
Primacord string shot malfunctioned (did not fire). P.O.O.H. with live charge.
Eighth attempt to backoff drill pipe: Tripped in hole with CCL (log) + fifteen (15) 6-long strands of 100 grain primacord to 9,966 DF.
Primacord string shot fired successfully. Drill pipe did not back off. P.O.O.H. with detonated charge.
Tripped inside 5 drill pipe with collar locator log + a ten (10) shot perforating gun to 9,956 DF. Tried to perforate 5 drill pipe.
Perforating gun did not fire. P.O.O.H. with live perforating gun.
Tripped inside 5 drill pipe with collar locator log + a second (new) ten (10) shot perforating gun to 9,956 DF. Tried to perforate 5 drill pipe.
Perforating gun did not fire. P.O.O.H. with live perforating gun.
Tripped inside 5 drill pipe with collar locator log + a third (new) ten (10) shot perforating gun to 9,956 DF.
Successfully fired perforating gun. P.O.O.H. with detonated perforating gun.
Note: Drill pipe being perforated at 9,956 DF in order to vent exhaust from possible future wireline radial cut.
(Attwood arrived 3-24-13 at 8:55 AM, left 3-24-13 at 10:14 AM.)















Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25 PBTD 9,241 DF
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole for #1349-H (horizontal well) at 9,241 DF.


I certify that the above well and premise was inspected on 3-20-13, 3-21-13, 3-22-13, 3-24-13, & 3-25-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 30
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/30/13
Permit #
1349
Date
03 30 2013



Day 65 Summary: 3-26-13 TD = 13,802 DF Successfully backed off 5 drill pipe at 9,310 DF.
(6 AM 3-25-13 to 6 AM 3-26-13) 2,055 of 5 O.D. x 19.5#/ft. drill pipe fish cemented in hole from 9,310 DF to 11,365 DF.
Drilling consultant for Dan A. Hughes witnessed B.O.P. Test #69.
Results of perforating 5 drill pipe with ten (10) shots at 9,956 DF:
Unable to circulate through perforations in drill pipe after pressuring up stuck pipe to 2,500 PSI.
No circulation & no loss of trapped pressure after repeating procedure a second time. Bullets may not have penetrated drill pipe.
Tripped inside 5 drill pipe with collar locator log + a fifteen (15) shot perforating gun to 9,956 DF.
Successfully fired perforating gun. P.O.O.H. with detonated perforating gun.
Results of perforating 5 drill pipe with fifteen (15) shots at 9,956 DF:
Unable to circulate through perforations after pressuring up drill pipe to 2,400 PSI. No loss of trapped pressure.
Bullets may not have penetrated drill pipe.
Ninth attempt to backoff drill pipe: Tripped in hole with CCL (log) + fifteen (15) 6-long strands of 100 grain primacord to 9,310 DF.
Primacord string shot fired successfully. Drill string not free. Unable to circulate well.
P.O.O.H. with detonated charge. Screwed into drill pipe fish with top drive.
5 drill pipe came free at 9,310 DF after pulling 248,000#. Circulated bottoms up.
A 2,055-long fish consisting of sixty five (65) joints of 5 O.D. x 19.5#/ft. drill pipe will be left
in the 8-diameter #1349 (pilot) wellbore from 9,310 DF to 11,365 DF.
Top of fish = 9,310 DF.
Top of cement INSIDE fish = 10,375 DF to 10,378 DF.
Bottom of fish = 11,365 DF. (990 of cement I NSI DE fish.)
(Attwood arrived 3-25-13 at 10:55 AM, left 3-25-13 at 11:46 AM.)
(Bruno inspected well & location on 3-25-13.)





























Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 4 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25 PBTD 9,241 DF
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole for #1349-H (horizontal well) at 9,241 DF.


I certify that the above well and premise was inspected on 3-20-13, 3-21-13, 3-22-13, 3-24-13, & 3-25-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 30
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/30/13
Permit #
1349
Date
03 30 2013

BOP Test #69 on 3-26-13:
Test of Blowout Preventers, Kill Valves, Hydril, Chokes & Floor Valves (#1349-pilot well)
No beginning & starting times or starting & ending test gauge pressures recorded for the various tests.
BOP Test #69 witnessed by Mr. Robert Mark Jones (drilling consultant for Dan A. Hughes, L.P.)
1
st
low pressure test 1a. Tested Lower pipe rams at 250 PSI (per chart record.) No pressure lost.
1
st
high pressure test 1b(1). Tested Lower pipe rams at 3,475 PSI (per chart record.) Lost 750 PSI (21.6%)
2
nd
high pressure test 1b(2). Tested Lower pipe rams at 3,460 PSI (per chart record.) Lost 925 PSI (26.7%)
3
rd
high pressure test 1b(3). Tested Lower pipe rams at 3,450 PSI (per chart record.) Lost 70 PSI (2.0%)
1
st
low pressure test
2a. Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve
at 360 PSI (per chart record.) No pressure lost
1
st
high pressure test
2b. Tested Upper pipe rams + INSIDE manual valve + INSIDE kill line valve
at 3,450 PSI (per chart record.) Lost 100 PSI (2.9%)
1
st
low pressure test
3a. Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve
at 400 PSI (per chart record.) Lost 25 PSI (6.2%)
1
st
high pressure test
3b. Tested Upper pipe rams + HCR (High Closing Ratio) valve + OUTSIDE kill line valve
at 3,460 PSI (per chart record.) Lost 120 PSI (3.5%)
1
st
low pressure test
4a. Tested Blind rams + three (3) INSIDE choke manifold valves
at 350 PSI (per chart record.) Lost 10 PSI (2.9%)
1
st
high pressure test
4b. Tested Blind rams + three (3) INSIDE choke manifold valves
at 3,500 PSI (per chart record.) Lost 100 PSI (2.9%)
1
st
low pressure test
5a. Tested Blind rams + three (3) MIDDLE choke manifold valves
at 425 PSI (per chart record.) Lost 25 PSI (5.9%)
1
st
high pressure test
5b. Tested Blind rams + three (3) MIDDLE choke manifold valves
at 3,505 PSI (per chart record.) Lost 90 PSI (2.5%)
1
st
low pressure test
6a. Tested Blind rams + choke manifold valves to gas buster and shale shaker & panic line
at 300 PSI (per chart record.) No pressure lost
1
st
high pressure test
6b. Tested Blind rams + choke manifold valves to gas buster and shale shaker & panic line
at 3,275 PSI (per chart record.) Lost 35 PSI (1.1%)
1
st
low pressure test 7a. Tested Hydril at 375 PSI (per chart record.) No pressure lost
1
st
high pressure test 7b. Tested Hydril at 2,000 PSI (per chart record.) No pressure lost
1
st
low pressure test 8a. Tested Inside Gray (manual dart) valve at 290 PSI (per chart record.) Lost 35 PSI (12.1%)
1
st
high pressure test 8b. Tested Inside Gray (manual dart) valve at 3,585 PSI (per chart record.) Lost 85 PSI (2.4%)
1
st
low pressure test
9a. Tested Manual T.I.W. (Full Open Safety Ball) valve
at 375 PSI (per chart record.) Lost 15 PSI (4.0%)
1
st
high pressure test
9b. Tested Manual T.I.W. (Full Open Safety Ball) valve
at 3,540 PSI (per chart record.) Lost 40 PSI (1.1%)
1
st
low pressure test 10a. Tested Upper hydraulic I.B.O.P. on top drive at 350 PSI (per chart record.) No pressure lost
1
st
high pressure test 10b. Tested Upper hydraulic I.B.O.P. on top drive at 3,550 PSI (per chart record.) Lost 50 PSI (1.4%)

(Attwood arrived 3-25-13 at 10:55 AM, left 3-25-13 at 11:46 AM.)



Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 5 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211 Permit # 1349 (pilot)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3 Collier-Hogan (pilot)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 20 T 47S R 28E , 69.96 South & 194.15 East of S.H.L.
Spud 1-20-13 at 2 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 13,802 DF TVD 13,798.25 PBTD 9,241 DF
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Drilling 8 hole for #1349-H (horizontal well) at 9,241 DF.


I certify that the above well and premise was inspected on 3-20-13, 3-21-13, 3-22-13, 3-24-13, & 3-25-13 by Paul Attwood & Pierre Bruno.
No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 30
th
day of March 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 03/30/13
Permit #
1349
Date
03 30 2013


Day 66 Summary: 3-27-13 PBTD = 9,110 DF (top of cement tagged in 8 open hole on 3-27-13.)
(6 AM 3-26-13 to 6 AM 3-27-13) Pumped 64.65 bbl. (300 sack) Kickoff Plug #2 at 9,223 DF.
(6 AM 3-26-13 to 6:30 AM 3-26-13) Rigged down B.O.P. testing unit.
(8 AM 3-26-13 to 12:30 PM 3-26-13) Tripped in hole open-ended with 295 joints of 5 O.D. x 4.276 I.D. drill pipe to 9,290 DF.
(12:30 PM 3-26-13 to 2 PM 3-26-13) Mixed & spotted 40 bbl. 8.6 PPG high viscosity pill lost circulation pill at 9,290 DF.
(2 PM 3-26-13 to 2:30 PM 3-26-13) P.O.O.H. 5 stands (= 15 joints) to 8,832 DF.
(2:30 PM 3-26-13 to 4 PM 3-26-13) Circulated well at 8,832 DF at 150 spm & 524 gpm. Had initial partial returns & ended with full returns.
(4 PM 3-26-13 to 4:15 PM 3-26-13) Tripped in hole with 4 stands (= 12 joints) from 8,832 DF to 9,223 DF.
Pump Depth for Kickoff Plug #2 at 9,223 DF (=87 above top of 5 drill pipe fish.)
(4:15 PM 3-26-13 to 4:25 PM 3-26-13) Tied into Baker Hughes cementing lines. Tested lines to 3,200 PSI.
(4:26 PM 3-26-13 to 5:15 PM 3-26-13) Pumped & displaced Kickoff Plug #2.
Kickoff Plug #2 in place on 3-26-13 at 5:15 PM.
(5:30 PM 3-26-13 to 7 PM 3-26-13) P.O.O.H. to 8,471 DF & circulated well for 1 hr. with full returns.
(7 PM 3-26-13 to 9 PM 3-26-13) P.O.O.H. from 8,471 DF to 3,707 DF.
(9 PM 3-26-13 to 11:30 PM 3-26-13) Cut & slipped drill line.
(11:30 PM 3-26-13 to 6 AM 3-27-13) P.O.O.H. from 3,707 DF to surface & waited on cement.

Kickoff Plug #2 in #1349 (Pilot well) on 3-26-13:
Pump Depth through 5 O.D. x 4.276 I.D. drill pipe = 9,223 DF (=4,579 above T.D.)
3-26-13 @ 4:25 PM Tested cementing lines to 3,200 PSI. Tested OK.
3-26-13 @ 4:26 PM Fresh water spacer: Pumped 30 bbls. of 8.34 PPG fresh water at 7 bpm into 5 drill pipe at 536 PSI.
3-26-13 @ 4:31 PM
S,A.P.P. Spacer: Pumped 20 bbls. of 8.34 PPG Mud Clean II at 7 bpm into 5 drill pipe at 539 PSI.
note: Mud Clean II is also known as S.A.P.P. (= Sodium Acid Pyrophosphate.)
3-26-13 @ 4:35 PM
Kickoff Plug #2: Pumped 64.65 bbls. (300 sacks/15.8 PPG) of Class H cement mixed with
0.15% b.w.o.c. (=42.3#) of R-3 + 3.0% b.w.o.w. (=291.96#) of potassium chloride + 0.25% b.w.o.c. (=70.5#)
of CD-32 + 10# of 100 mesh silica sand (sacked) per sack of cement (=3,000#) + 0.001 gal. per sec. FP-6L (=1.04 gal.)
yielding 1.21 cu. ft. of slurry per sack of cement at 4.5 bpm into 5 drill pipe & 8 open hole at 243 PSI.
note: 300 sacks of Class H cement weighed 28,200#.
3-26-13 @ 4:54 PM Fresh water spacer: Pumped 10 bbls. of 8.34 PPG at 4.5 bpm into 5 drill pipe at 191 PSI.
3-26-13 @ 4:56 PM
Displacement: Pumped 140 bbls. of 8.4 PPG drilling mud drilling mud
at 7.4 bpm into 5 drill pipe at 218 PSI to displace cement from inside 5 x 19.5#/ft. drill pipe into 8 open hole.
3-26-13 @ 5:15 PM Shut down & began rigging down Baker Hughes. Cement in place 3-26-13 at 5:15 PM.

Day 67 Summary: 3-28-13 TD = 9,180 DF Tagged cement Kickoff Plug #2 at 9,110 DF with 20,000#.
(6 AM 3-27-13 to 6 AM 3-28-13) Drilled 70 of 8 hole (70% cement & 30% formation) from 9,110 DF to 9,180 DF.

Day 68 Summary: 3-29-13 TD = 9,194 DF Drilled 14 of 8 hole (60% cement & 40% formation) from 9,180 DF to 9,194 DF.
(6 AM 3-28-13 to 6 AM 3-29-13)

Day 69 Summary: 3-30-13 TD = 9,241 DF Drilled 47 of 8 hole from 9,194 DF to 9,241 DF (0% cement & 100% formation at 9,241 DF.)
(6 AM 3-29-13 to 11 PM 3-29-13) END report for 20-3 Collier-Hogan (#1349 pilot well) at 9,241 DF.
BEGIN report for 20-3-H Collier-Hogan (#1349-H horizontal well) at 9,241 DF.
99-thick remnant Kickoff Plug #2 in #1349 (pilot) wellbore from 9,241 DF to 9,340 DF
(.assuming 0% of the 64.65 bbl./230.3-thick cement plug was lost into the formation.)
---No Violations---

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1st pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 216.58 South & 900.47 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,445 DF TVD 11,942.62
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Preparing to run 7 production casing to 12,440 DF in 8-diameter to 9 7/8-diameter hole.


I certify that the above well and premise was inspected on 4-1-13, 4-2-13, 4-4-13, 4-8-13, 4-9-13, 4-10-13, 4-12-13, & 4-15-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/17/13
Permit #
1349-H
Date
04 17 2013


First Report (#1349-H (horizontal): Drilled 3,204 of 8 hole from 9,241 DF (Kickoff point for #1349-H)
to production casing point of 12,445 DF;
Tripped in hole with 7.625 O.D. production casing;
Stuck 7.625 O.D. casing at 5,352 DF, then P.O.O.H. & laid down
130 joints. Casing to large for borehole.
Reamed selected intervals & enlarged 8-dia. hole to 9 7/8-dia.
with 8 O.D. under reamer from 4,004 DF to 10,410 DF;
Reamed 1,166-thick interval with 8 mill tooth bit
from 11,271 DF to 12,437 DF. Junk in hole.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.

Day 69 Summary: 3-30-13 TD = 9,316 DF Drilled 75 of 8 hole from 9,241 DF to 9,316 DF in 13.5 hrs.
(11 PM 3-29-13 to 6 AM 3-30-13) BEGIN report for 20-3-H Collier-Hogan (#1349-H horizontal well) on 3-29-13 at 9,241 DF.

Day 70 Summary: 3-31-13 TD = 9,522 DF Drilled 206 of 8 hole from 9,316 DF to 9,522 DF in 13.5 hrs.
(6 AM 3-30-13 to 6 AM 3-31-13)

Day 71 Summary: 4-01-13 TD = 10,373 DF Drilled 851 of 8 hole from 9,522 DF to 10,373 DF in 17 hrs.
(6 AM 3-31-13 to 6 AM 4-1-13)

Day 72 Summary: 4-02-13 TD = 11,153 DF Drilled 780 of 8 hole from 10,373 DF to 11,153 DF in 22 hrs.
(6 AM 4-1-13 to 6 AM 4-2-13) (Bruno arrived 4-1-13 at 9:45 AM, left 4-1-13 at 11 AM.)

Day 73 Summary: 4-03-13 TD = 11,352 DF Drilled 199 of 8 hole from 11,153 DF to 11,352 DF in 10.5 hrs.
(6 AM 4-2-13 to 6 AM 4-3-13) Drilling at 11,289 DF on 4-2-13 at 11:55 AM.
(Attwood arrived 4-2-13 at 11:52 AM, left 4-2-13 at 12:16 PM.)

Day 74 Summary: 4-04-13 TD = 11,919 DF Drilled 567 of 8 hole from 11,352 DF to 11,919 DF in 23.5 hrs.
(6 AM 4-3-13 to 6 AM 4-4-13)

Day 75 Summary: 4-05-13 TD = 12,009 DF Drilled 90 of 8 hole from 11,919 DF to 12,009 DF in 6 hrs.
(6 AM 4-4-13 to 6 AM 4-5-13) (Bruno arrived 4-4-13 at 9 AM, left 4-4-13 at 9:20 AM.)

Day 76 Summary: 4-06-13 TD = 12,009 DF Rig repairs. Changed brake bands. Repaired air leaks.
(6 AM 4-5-13 to 6 AM 4-6-13) Began repairing high clutch on draw works.

Day 77 Summary: 4-07-13 TD = 12,009 DF Finished repairing high clutch on draw works.
(6 AM 4-6-13 to 6 AM 4-7-13) Tripped in hole with B.H.A. #13 & 5 O.D. x 19.5#/ft. drill pipe to 10,788 DF.

Day 78 Summary: 4-08-13 TD = 12,445 DF Drilled 436 of 8 hole from 12,009 DF to 12,445 DF in 18 hrs.
(6 AM 4-7-13 to 6 AM 4-8-13) Reached production casing point for #1349-H (horizontal well) of 12,445 DF on 4-8-13 at 3:30 AM.

Day 79 Summary: 4-09-13 TD = 12,445 DF Ran 130 joints of 7.625 O.D. x 33.7#/ft/ L-80 LT&C production casing to 5,352 DF.
(6 AM 4-8-13 to 6 AM 4-9-13) Stuck 7.625 O.D. casing at 5,352 DF in 8-diameter hole. Could not go any deeper.
(Bruno arrived 4-8-13 at 1:30 PM, left 4-8-13 at 2:15 PM.)

Day 80 Summary: 4-10-13 TD = 12,445 DF Laid down 130 joints of 7.625 O.D. x 33.7#/ft/ L-80 LT&C production casing.
(6 AM 4-9-13 to 6 AM 4-10-13) B.O.P. Test #70 performed & witnessed by P. Attwood (FDEP-O&G Section.)
P. Attwood witnessed BOP Test #70 beginning 10:06 PM 4-30-13 & ending 12:44 AM 4-10-13.


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1st pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 216.58 South & 900.47 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,445 DF TVD 11,942.62
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Preparing to run 7 production casing to 12,440 DF in 8-diameter to 9 7/8-diameter hole.


I certify that the above well and premise was inspected on 4-1-13, 4-2-13, 4-4-13, 4-8-13, 4-9-13, 4-10-13, 4-12-13, & 4-15-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/17/13
Permit #
1349-H
Date
04 17 2013

BOP Test #70 on 4-9-13 & 4-10-13:
Test of Blowout Preventers, Kill Valves, Hydril, & Choke Manifold Valves (#1349-H horizontal well)
4-9-13 @ 10:06:30 PM 4-9-13 @ 10:11:30 PM
1a. Tested Lower pipe rams + INSIDE 4.0625 manual valve + INSIDE 2.0625 kill line valve at 370 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 10:13 PM 4-9-13 @ 10:20 PM
1b. Tested Lower pipe rams + INSIDE 4.0625 manual valve + INSIDE 2.0625 kill line valve at 3,600 PSI.
Lost 70 PSI (1.9%) in 7 minutes. PASSED on 1
st
attempt.
4-9-13 @ 10:30 PM 4-9-13 @ 10:35 PM
2a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + choke manifold valves to panic line
gas buster & shale shakers at 295 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 10:36:15 PM 4-9-13 @ 10:41:15 PM
2b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + choke manifold valves to panic line
gas buster & shale shakers at 3,450 PSI.
Lost 80 PSI (2.3%) in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 10:48:15 PM 4-9-13 @ 10:53:30 PM
3a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) MIDDLE choke manifold valves
at 300 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 10:54:30 PM 4-9-13 @ 10:59:30 PM
3b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) MIDDLE choke manifold valves
at 3,500 PSI.
Lost 70 PSI (2.0%) in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 11:02:30 PM 4-9-13 @ 11:07:30 PM
4a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + middle MIDDLE choke manifold valve
+ (2) INSIDE choke manifold valves at 320 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 11:08:30 PM 4-9-13 @ 11:13:30 PM
4b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + middle MIDDLE choke manifold valve
+ (2) INSIDE choke manifold valves at 3,485 PSI.
Lost 65 PSI (1.9%) in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 11:18:30 PM 4-9-13 @ 11:23:30 PM
5a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 370 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 11:24:30 PM 4-9-13 @ 11:29:30 PM
5b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 3,480 PSI.
Lost 30 PSI (0.9%) in 5 minutes. PASSED on 1
st
attempt.
4-9-13 @ 11:33:15 PM 4-9-13 @ 11:36:15 PM
6a(1). Tested Hydril + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 260 PSI.
Lost 30 PSI (11.5%) in 3 minutes. FAILED 1
st
low pressure test.
Hydril bladder was pressured up to 1,150 PSI for 1
st
low pressure test.
4-9-13 @ 11:36:30 PM 4-9-13 @ 11:39:30 PM
6a(2). Tested Hydril + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 300 PSI.
Lost 20 PSI (6.7%) in 3 minutes. FAILED 2
nd
low pressure test.
Hydril bladder was pressured up to 1,150 PSI for 2
nd
low pressure test.
4-9-13 @ 11:47:45 PM 4-9-13 @ 11:52:45 PM
6a(3). Tested Hydril + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 260 PSI.
No pressure lost in 5 minutes. PASSED on 3
rd
attempt.
Opened & closed Hydril, then pressured-up bladder to 1,450 PSI for 3
rd
low pressure test.
4-9-13 @ 11:53:30 PM 4-9-13 @ 11:58:30 PM
6b. Tested Hydril + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 2,000 PSI.
Lost 50 PSI (2.5%) in 5 minutes. PASSED on 1
st
attempt.
4-10-13 @ 12:33 AM 4-10-13 @ 12:38 AM
7a. Tested Blind rams + three (3) INSIDE choke manifold valves + OUTSIDE 2.0625 kill line valve at 355 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-10-13 @ 12:39 AM 4-10-13 @ 12:44 AM
7b. Tested Blind rams + three (3) INSIDE choke manifold valves + OUTSIDE 2.0625 kill line valve at 3,440 PSI.
Lost 80 PSI (2.3%) in 5 minutes. PASSED on 1
st
attempt.
(Attwood arrived 4-9-13 at 7:58 PM, left 4-10-13 at 12:53 AM.)
(Bruno arrived 4-9-13 at 8 AM, left 4-9-13 at 10:30 AM;
Bruno returned 4-9-13 at 12:05 PM, left 4-9-13 at 1 PM.)

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1st pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 216.58 South & 900.47 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,445 DF TVD 11,942.62
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Preparing to run 7 production casing to 12,440 DF in 8-diameter to 9 7/8-diameter hole.


I certify that the above well and premise was inspected on 4-1-13, 4-2-13, 4-4-13, 4-8-13, 4-9-13, 4-10-13, 4-12-13, & 4-15-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: FDEP (Oil & Gas Section): Tallahassee, FL
FDEP (Oil & Gas Section): Fort Myers, FL
Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/17/13
Permit #
1349-H
Date
04 17 2013








Day 81 Summary: 4-11-13 TD = 12,445 DF Enlarged 176 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
(6 AM 4-10-13 to 6 AM 4-11-13) from 4,004 DF to 4,180 DF to accommodate future 7 production casing string.


Day 82 Summary: 4-12-13 TD = 12,445 DF Enlarged 1,520 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
(6 AM 4-11-13 to 6 AM 4-12-13) from 4,180 DF to 5,700 DF to accommodate future 7 production casing string.


Day 83 Summary: 4-13-13 TD = 12,445 DF Enlarged 1,607 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
(6 AM 4-12-13 to 6 AM 4-13-13) from 5,700 DF to 7,307 DF to accommodate future 7 production casing string.
Reaming at 6,078 DF on 4-12-13 at 10:40 AM.
(Attwood arrived 4-12-13 at 10:18 AM, left 4-12-13 at 10:42 AM.)


Day 84 Summary: 4-14-13 TD = 12,445 DF Enlarged 208 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
(6 AM 4-13-13 to 6 AM 4-14-13) from 7,307 DF to 7,515 DF, then tripped in hole to 8,300 DF.
Enlarged 163 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
from 8,300 DF to 8,463 DF, then tripped in hole to 9,190 DF.
Enlarged 50 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
from 9,190 DF to 9,240 DF, then tripped in hole to 9,938 DF.
Enlarged 472 of 8-diameter hole to 9 7/8-diameter with 8 O.D. under reamer
from 9,938 DF to 10,410 DF, after which system started stalling & torquing out..


Day 85 Summary: 4-15-13 TD = 12,445 DF Tripped in hole from 10,410 DF to 11,750 DF, then attempted to ream at 11,750 DF
(6 AM 4-14-13 to 6 AM 4-15-13) with 8 O.D. under reamer. Unable to rotate. Pipe stuck. J arred on pipe. Pipe came free.
Pulled up to 11,699 DF. Unable to ream. System stalled & torque out.
Pulled up to 11,668 DF. Circulated sweep. P.O.O.H. to 9,400 DF, then tripped in hole to 11,322 DF.
Unable to ream at 11,322 DF.
P.O.O.H. One (1) metal fin missing & one fin barely attached to 8 O.D. under reamer.

Day 86 Summary: 4-16-13 TD = 12,445 DF Tripped in hole & reamed 1,046 of 8-diameter hole with 8 mill tooth bit
(6 AM 4-15-13 to 6 AM 4-16-13) from 11,271 DF to 12,317 DF to accommodate future 7 production casing string.
(Bruno arrived 4-15-13 at 9 AM, left 4-15-13 at 9:20 AM.)

Day 87 Summary: 4-17-13 TD = 12,445 DF Reamed 1,166 of 8-diameter hole with 8 mill tooth bit
(6 AM 4-16-13 to 6 AM 4-17-13) from 12,317 DF to 12,437 DF to accommodate future 7 production casing string,
Drilled 1 to 12,438 DF, then spotted 70 bbl. graphite pill on bottom.
P.O.O.H. and laid down 5 O.D. drill pipe. Preparing to run 7 casing.

---No Violations---


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 274.22 South & 1,326.18 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,874 DF TVD 11,951.21
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Tripping out of 6.125-diameter hole after drilling to 12,874 DF.


I certify that the above well and premise was inspected on 4-17-13, 4-18-13, 4-19-13, 4-20-13, 4-22-13, 4-24-13, & 4-25-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 28
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/28/13
Permit #
1349-H
Date
04 28 2013


Second Report (#1349-H (horizontal): Cemented 7 O.D. x 26.0#/ft. L-80 & P-110 production casing at 12,440 DF
with 222.06 bbls./1,010 sacks of cement;
Drilled 1,552 of cement inside 7 O.D. casing from 10,888 DF to 12,440 DF;
Drilled 5 of cement in (former) 8 hole from 12,440 DF to 12,445 DF;
Drilled 429 of formation & tungsten metal JUNK with 6.125 bit
from 12,445 DF to 12,874 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.
4-17-13: 7 O.D. x 6.276 I.D. x 26.0#/ft. P-110 LT&C casing (45 joints) ran from surface to 2,043.05 DF and
7 O.D. x 6.276 I.D. x 26.0#/ft. L-80 LT&C casing (236 joints) ran from 2,043.05 DF to 12,440 DF.

Day 88 Summary: 4-18-13 PBTD = 10,888 DF (tagged top of hard cement inside 7 casing on 4-20-13.)
(6 AM 4-17-13 to 6:33 AM 4-18-13) 7 O.D. x 26.0#/ft. P-110 and L-80 LT&C production casing ran to 12,440 DF(=5 off bottom.)
Cemented 7 O.D. production casing with 222.06 barrels (1,010 sacks) of cement at 12,440 DF.

Production Casing Cement Job on 4-18-13 in #1349-H (Horizontal) Wellbore:
7 O.D. x 26.0 pound per foot P-110 & L-80 LT&C casing set at 12,440' DF.
4-18-13 @ 3:50 AM
Dropped plug. Pumped 5 bbls. of 8.34 PPG S.A.P.P. (sodium acid pyrophosphate) at 6.4 bpm
into 7 casing at 351 PSI. note: S.A.P.P. is also called MudClean II by Baker Hughes.
4-18-13 @ 4:00 AM
Tested cementing lines to 5,000 PSI (per pg. 2 of cement job report.) Tested OK.
note: Lines actually pressure tested to 4,250 PSI (per Baker Hughes pressure chart on pg. 3 of cement job report.)
4-18-13 @ 4:05 AM Spacer Ahead: Pumped 35 bbls. of 8.34 PPG S.A.P.P. (sodium acid pyrophosphate) at 6.4 bpm into 7 casing at 85 PSI.
4-18-13 @ 4:14 AM
Lead cement: Pumped 53.08 bbls. (150 sacks/12.4 PPG) of 35:65:6 Poz (fly ash) Class H cement mixed as follows:
98 sacks (=9,212#) of Class H cement + 53 sacks (= 3,885#) of Poz (fly ash) + 6% b.w.o.c. (=783#) of bentonite
+ 0.225% b.w.o.c. (=29.4#) of R-3 + 0.15% b.w.o.c. (=19.57#) of CD-32 + 0.001 gal. per second (=0.78gal.) of FP-6L
yielding 1.99 cu. ft. of slurry per sack of cement at 4.7 bpm into 7 casing at 154 PSI.
4-18-13 @ 4:27 AM
Tail cement: Pumped 168.98 bbls. (860 sacks/16.2 PPG) of Class H cement + 0.10% b.w.o.c. (=80.84#) of R-3
+ 3% b.w.o.w. (=987.28#) of potassium chloride + 0.15% b.w.o.c. (=121.26#) of FL-25 yielding 1.10 cu. ft. of slurry
per sack of cement at 5.2 bpm into 7 casing at 106 PSI.
note: 860 sacks of Class H cement weighed 80,840#.
4-18-13 @ 5:09 AM
Displacement Spacer: Dropped plug, then pumped 20 bbls. of 8.34 PPG fresh water at 5.2 bpm
into 7 production casing at 153 PSI with the Baker Hughes cementer to begin displacing lead cement into annulus.
4-18-13 @ 5:15 AM Shut down.
4-18-13 @ 5:20 AM
Displacement: Changed over to drilling rigs pump system and pumped an additional 453 bbls. of 8.8 PPG drilling
mud at 7.56 bpm into 7 production casing to displace lead & tail cements into annulus.
4-18-13 @ 6:25 AM
Bumped plug with 1,200 PSI (which = 500 PSI over final circulating pressure of 700 PSI.) Held 1,200 PSI OK for 5 minutes.
Cement in place 4-18-13 at 6:33 AM.
(Attwood arrived 4-17-13 at 11:24 AM, left 4-17-13 at 11:58 AM;
Attwood returned 4-18-13 at 4:17 AM, left 4-18-13 at 6:21 AM.)


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 274.22 South & 1,326.18 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,874 DF TVD 11,951.21
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Tripping out of 6.125-diameter hole after drilling to 12,874 DF.


I certify that the above well and premise was inspected on 4-17-13, 4-18-13, 4-19-13, 4-20-13, 4-22-13, 4-24-13, & 4-25-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 28
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/28/13
Permit #
1349-H
Date
04 28 2013




Day 89 Summary: 4-19-13 PBTD = 10,888 DF (tagged top of hard cement inside 7 casing on 4-20-13.)
(6:33 AM 4-18-13 to 8:15 AM 4-19-13) Set 7 casing slips at 150,000#, then made rough & final cuts of 7 casing.
Changed upper & lower pipe rams to accommodate 3 O.D. drill pipe.
B.O.P. Test #71 performed & witnessed by Pierre Bruno (F.D.E.P.) (results presented below:)


BOP Test #71 on 4-19-13:
Test of Blowout Preventers, Kill Valves, Hydril, Choke Manifold Valves & Floor Valves (#1349-H horizontal well)
4-19-13 @ 2:50 AM 4-19-13 @ 2:58 AM
1a. Tested Lower pipe rams at 200 PSI.
No pressure lost in 8 minutes. PASSED on 1
st
attempt.
4-19-13 @ 3:00 AM 4-19-13 @ 3:08 AM
1b. Tested Lower pipe rams at 3,500 PSI.
Lost 100 PSI (2.9%) in 8 minutes. PASSED on 1
st
attempt.
4-19-13 @ 3:17 AM 4-19-13 @ 3:22 AM
2a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) OUTSIDE choke manifold valves
at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 3:25 AM 4-19-13 @ 3:30 AM
2b(1). Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) OUTSIDE choke manifold valves
at 3,500 PSI.
Lost 200 PSI (5.7%) in 5 minutes. Failed 1
st
high pressure test.
Re-pressurized system from 3,300 PSI to 3,500 PSI & started 2
nd
high pressure test.
4-19-13 @ 3:31 AM 4-19-13 @ 3:37 AM
2b(2). Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) OUTSIDE choke manifold valves
at 3,500 PSI.
No pressure lost in 6 minutes. PASSED on 2
nd
attempt.
4-19-13 @ 3:45 AM 4-19-13 @ 3:50 AM
3a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) MIDDLE choke manifold valves
at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 3:51 AM 4-19-13 @ 3:56 AM
3b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) MIDDLE choke manifold valves
at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:04 AM 4-19-13 @ 4:09 AM
4a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) INSIDE choke manifold valves
at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:10 AM 4-19-13 @ 4:15 AM
4b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + three (3) INSIDE choke manifold valves
at 3,500 PSI.
Lost 50 PSI (1.4%) in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:19 AM 4-19-13 @ 4:24 AM
5a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:25 AM 4-19-13 @ 4:31 AM
5b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 3,500 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:35 AM 4-19-13 @ 4:40 AM
6a. Tested Upper pipe rams + INSIDE 2.0625 kill line valve + INSIDE manual valve at 250 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 4:41 AM 4-19-13 @ 4:46 AM
6b. Tested Upper pipe rams + INSIDE 2.0625 kill line valve + INSIDE manual valve at 3,500 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 274.22 South & 1,326.18 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,874 DF TVD 11,951.21
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Tripping out of 6.125-diameter hole after drilling to 12,874 DF.


I certify that the above well and premise was inspected on 4-17-13, 4-18-13, 4-19-13, 4-20-13, 4-22-13, 4-24-13, & 4-25-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 28
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/28/13
Permit #
1349-H
Date
04 28 2013

BOP Test #71 on 4-19-13:
Test of Blowout Preventers, Kill Valves, Hydril, Choke Manifold Valves & Floor Valves (#1349-H horizontal well)
4-19-13 @ 4:55 AM 4-19-13 @ 5:01 AM
7a. Tested Hydril + INSIDE 2.0625 kill line valve + INSIDE manual valve at 250 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
4-19-13 @ 5:02 AM 4-19-13 @ 5:07 AM
7b(1). Tested Hydril + INSIDE 2.0625 kill line valve + INSIDE manual valve at 2,000 PSI.
Lost 50 PSI (2.5%) in 5 minutes. Tried to get better test results.
Re-pressurized system from 1,950 PSI to 2,000 PSI, then started 2
nd
high pressure test.
4-19-13 @ 5:13 AM 4-19-13 @ 5:18 AM
7b(2). Tested Hydril + INSIDE 2.0625 kill line valve + INSIDE manual valve at 2,000 PSI.
Lost 50 PSI (2.5%) in 5 minutes. Same result as Test #7b(1). PASSED on 2
nd
attempt.
4-19-13 @ 5:56 AM 4-19-13 @ 5:59 AM
8a(1). Tested Blind rams at 300 PSI.
Lost 100 PSI (33.3%) in 3 minutes. Failed 1
st
low pressure test
4-19-13 @ 6:03 AM 4-19-13 @ 6:08 AM
8a(2). Tested Blind rams at 300 PSI.
No pressure lost in 5 minutes. PASSED on 2
nd
attempt.
4-19-13 @ 6:22 AM 4-19-13 @ 6:27 AM
8b(1). Tested Blind rams at 3,800 PSI.
Lost 250 PSI (6.6%) in 5 minutes. Failed 1
st
high pressure test
4-19-13 @ 6:29 AM 4-19-13 @ 6:37 AM
8b(2). Tested Blind rams at 3,300 PSI.
No pressure lost in 8 minutes. PASSED on 2
nd
attempt.
4-19-13 @ 6:44 AM 4-19-13 @ 6:49 AM
9a. Tested Inside Gray (manual dart) valve at 300 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 6:54 AM 4-19-13 @ 6:59 AM
9b. Tested Inside Gray (manual dart) valve at 3,450 PSI.
Lost 100 PSI (2.90%) in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:01 AM 4-19-13 @ 7:07 AM
10a. Tested Manual T.I.W. (Full Open Safety Ball) valve at 400 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:08 AM 4-19-13 @ 7:15 AM
10b. Tested Manual T.I.W. (Full Open Safety Ball) valve at 3,400 PSI.
Lost 100 PSI (2.94%) in 7 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:38 AM 4-19-13 @ 7:44 AM
11a. Tested Lower manual I.B.O.P. on top drive at 450 PSI.
No pressure lost in 6 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:45 AM 4-19-13 @ 7:50 AM
11b. Tested Lower manual I.B.O.P. on top drive at 3,500 PSI.
Lost 50 PSI (1.4%) in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:52 AM 4-19-13 @ 7:57 AM
12a. Tested 4 Standpipe valve at 400 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 7:58 AM 4-19-13 @ 8:03 AM
12b. Tested 4 Standpipe valve at 3,550 PSI.
Lost 50 PSI (1.4%) in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 8:04 AM 4-19-13 @ 8:09 AM
13a. Tested 4 mud pump valves at 400 PSI.
No pressure lost in 5 minutes. PASSED on 1
st
attempt.
4-19-13 @ 8:10 AM 4-19-13 @ 8:15 AM
13b. Tested 4 mud pump valves at 3,400 PSI.
Lost 0 PSI (1.5%) in 5 minutes. PASSED on 1
st
attempt.

(Bruno arrived 4-18-13 at 11 AM, left 4-18-13 at noon.)
(Bruno arrived 4-19-13 at 12:01 AM, on location 4-19-13 at 6 AM.)

Day 90 Summary: 4-20-13 PBTD = 10,888 DF (tagged top of hard cement inside 7 casing on 4-20-13.)
(8:15 AM 4-19-13 to 6 AM 4-20-13) Tripped in hole with autotrack directional B.H.A. & 3 drill pipe to 9,737 DF.
(Bruno on location 4-19-13 at 6 AM, left 4-19-13 at 10:30 AM.)


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 4 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 274.22 South & 1,326.18 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,874 DF TVD 11,951.21
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Tripping out of 6.125-diameter hole after drilling to 12,874 DF.


I certify that the above well and premise was inspected on 4-17-13, 4-18-13, 4-19-13, 4-20-13, 4-22-13, 4-24-13, & 4-25-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 28
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/28/13
Permit #
1349-H
Date
04 28 2013





Day 91 Summary: 4-21-13 PBTD = 12,337 DF Tripped in hole with autotrack directional B.H.A. & 3 drill pipe to 10,888 DF.
(6 AM 4-20-13 to 6 AM 4-21-13) Tagged top of hard cement inside 7 casing on 4-20-13 at 10,888 DF.
Drilled 1,449 of hard cement inside 7 casing from 10,888 DF to 12,337 DF.
Cement volume calculations for 7 casing set at 12,440 DF:
222.06 barrels of cement pumped.
-59.38 barrels of cement inside 7 O.D. x 6.276 I.D. casing from 10,888 DF to 12,440 DF.
-0.35 barrels of cement in 8-diameter open hole from 12,440 DF to 12,445 DF (below 7 casing shoe).
45.85 barrels of cement in annular space between 7 O.D. casing & 8-diameter hole
from 12,440 DF to 10,410 DF (assuming 0% of cement lost into formation.)
22.24 barrels of cement in annular space between 7 O.D. casing & 9.875-diameter hole
from 10,410 DF to 9,938 DF (assuming 0% of cement lost into formation.)
15.76 barrels of cement in annular space between 7 O.D. casing & 8-diameter hole
from 9,938 DF to 9,240 DF (assuming 0% of cement lost into formation.)
2.36 barrels of cement in annular space between 7 O.D. casing & 9.875-diameter hole
from 9,240 DF to 9,190 DF (assuming 0% of cement lost into formation.)
16.42 barrels of cement in annular space between 7 O.D. casing & 8-diameter hole
from 9,190 DF to 8,463 DF (assuming 0% of cement lost into formation.)
7.68 barrels of cement in annular space between 7 O.D. casing & 9.875-diameter hole
from 8,463 DF to 8,300 DF (assuming 0% of cement lost into formation.)
17.73 barrels of cement in annular space between 7 O.D. casing & 8-diameter hole
from 8,300 DF to 7,515 DF (assuming 0% of cement lost into formation.)
34.29 barrels of cement in annular space between 7 O.D. casing & 9.875-diameter hole
from 7,515 DF to 6,788 DF (assuming 0% of cement lost into formation.)
Est. top of cement behind 7 casing at 12,440 DF minus 5,652 = 6,788 DF (assuming 0% of cement.)
(Attwood arrived 4-20-13 at 11:45 AM, left 4-20-13 at 12:36 PM.)


Day 92 Summary: 4-22-13 PBTD = 12,441 DF Successful, 30 minute-long M.I .T. of 7 casing performed.
(6 AM 4-21-13 to 6 AM 4-22-13) Drilled 104 of cement from 12,337 DF to 12,441 DF.

MIT of 7 production casing performed. MIT witnessed by Mark Robert Jones (P.P.I. drilling consultant)

M.I.T #1 of 7 production casing on 4-21-13 in #1349-H well
6.125 drill bit at 12,337 DF during MIT
Duration Time (per Pason) PSIG (per Pason)
Start 6:32 AM 1015
5 min. 6:37 AM 1022
10 min. 6:42 AM 1026
15 min. 6:47 AM 1028
20 min. 6:52 AM 1029
25 min. 6:57 AM 1030
30 min. 7:02 AM 1031
Summary of MIT #1: Gained 16 PSI (1.58%) in 30 minutes. Passed MIT.
PASSED MIT #1 on 4-21-13 at 7:02 AM.



Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 5 of 5

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Current Bottom Hole Location is in Sec. 20 T 47S R 28E , 274.22 South & 1,326.18 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 12,874 DF TVD 11,951.21
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Tripping out of 6.125-diameter hole after drilling to 12,874 DF.


I certify that the above well and premise was inspected on 4-17-13, 4-18-13, 4-19-13, 4-20-13, 4-22-13, 4-24-13, & 4-25-13
by Paul Attwood & Pierre Bruno. No violations of rules 62C-25 through 30, FAC were found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 28
th
day of April 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 04/28/13
Permit #
1349-H
Date
04 28 2013



Day 93 Summary: 4-23-13 PBTD = 12,442 DF Drilled 1 of cement & metal J UNK in hole from 12,441 DF to 12,442 DF. P.O.O.H.
(6 AM 4-22-13 to 6 AM 4-23-13) Tripped in hole with 6.125 O.D. cutrite concave mill to 11,060 DF.
(Attwood arrived 4-22-13 at 10:16 AM, left 4-22-13 at 10:52 AM.)

Day 94 Summary: 4-24-13 TD = 12,455 DF Milled J UNK in hole from 12,442 DF to 12,455 DF, then P.O.O.H. with 6.125 O.D. mill.
(6 AM 4-23-13 to 6 AM 4-24-13)

Day 95 Summary: 4-25-13 TD = 12,455 DF Tripped in hole with 6.125 O.D. bit +autotrak directional assembly +3 drill pipe to 11,585 DF.
(6 AM 4-24-13 to 6 AM 4-25-13)
(Bruno arrived 4-24-13 at 3 PM, left 4-24-13 at 5 PM.)

Day 96 Summary: 4-26-13 TD = 12,695 DF Tripped in hole with 6.125 O.D. bit +autotrak directional assembly +3 drill pipe to 12,430 DF.
(6 AM 4-25-13 to 6 AM 4-26-13) Washed 25 of hole from 12,430 DF to 12,455 DF.
Drilled 240 of 6.125 hole from 12,455 DF to 12,695 DF in 16 hrs.
(Attwood arrived 4-25-13 at 8:01 AM, left 4-25-13 at 8:25 AM.)

Day 97 Summary: 4-27-13 TD = 12,874 DF Drilled 179 of 6.125 hole from 12,695 DF to 12,874 DF in 17.5 hrs.
(6 AM 4-26-13 to 6 AM 4-27-13)


---No Violations---


Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 21 T 47S R 28E , 643.86 South & 4,642.98 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 16,215 DF TVD 11,948.34
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Moving drilling equipment to #1352 (pilot) well at BreitBurns North Bear Island Field. Waiting on completion rig.


I certify that the above well and premise was inspected on 4-27-13, 4-29-13, 4-30-13, 5-3-13, 5-6-13, 5-8-13, 5-10-13, 5-14-13, & 5-16-13
by Paul Attwood & Pierre Bruno. One (1) minor violation of rules 62C-25 through 30, FAC was found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of May 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 05/17/13
Permit #
1349-H
Date
05 17 2013


Third Report (#1349-H (horizontal): Drilled 3,341 of 6.125-diameter hole from 12,874 DF to 16,215 DF;
A 4,231-long horizontal wellbore drilled through Rubble Zone
from 11,984 DF to 16,215 DF.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.
4-17-13: 7 O.D. x 6.276 I.D. x 26.0#/ft. P-110 LT&C casing (45 joints) ran from surface to 2,043.05 DF and
7 O.D. x 6.276 I.D. x 26.0#/ft. L-80 LT&C casing (236 joints) ran from 2,043.05 DF to 12,440 DF.

Day 98 Summary: 4-28-13 TD = 12,995 DF Precisions driller witnessed B.O.P. Test #72 (see results below:)
(6 AM 4-27-13 to 6 AM 4-28-13) Drilled 121 of 6.125-diameter hole from 12,874 DF to 12,995 DF in 5.5 hrs.
(Attwood arrived 4-27-13 at 8:44 AM, left 4-27-13 at 9:14 AM.)
Operator was P.O.O.H. on 4-27-13 at 8:50 AM to test BOPs after drilling to 12,874 DF.

BOP Test #72 on 4-27-13 (witnessed by Precisions driller):
Test of Blowout Preventers, Kill Valves, Hydril, & Choke Manifold Valves (#1349-H horizontal well)
4-27-13 @ 11:21 AM 4-27-13 @ 11:26 AM
1a. Tested Upper pipe rams + INSIDE 2.0625 kill line valve + INSIDE manual valve at 300 PSI.
No pressure lost in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure loss recorded on chart.
4-27-13 @ 11:27 AM 4-27-13 @ 11:32 AM
1b. Tested Upper pipe rams + INSIDE 2.0625 kill line valve + INSIDE manual valve at 3,500 PSI.
Pressure increase of 100 PSI (2.9%) recorded in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure increase recorded on chart was 50 PSI (1.4 %.)
4-27-13 @ 11:35 AM 4-27-13 @ 11:40 AM
2a. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 300 PSI.
Pressure increase of 25 PSI (8.3%) recorded in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure increase recorded on chart.
4-27-13 @ 11:41 AM 4-27-13 @ 11:46 AM
2b. Tested Upper pipe rams + OUTSIDE 2.0625 kill line valve + HCR (High Closing Ratio) valve at 3,500 PSI.
Pressure increase of 100 PSI (2.9%) recorded in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure increase recorded on chart was 100 PSI (2.9 %.)
4-27-13 @ 11:49 AM 4-27-13 @ 11:55 AM
3a. Tested Lower pipe rams at 300 PSI.
Lost 5 PSI (1.7%) in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure increase recorded on chart.
4-27-13 @ 11:56 AM 4-27-13 @ noon
3b. Tested Lower pipe rams at 3,550 PSI.
Pressure increase of 40 PSI (1.1%) recorded in 4 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure increase recorded on chart was 20 PSI (0.6 %.)
4-27-13 @ 12:05 PM 4-27-13 @ 12:10 PM
4a. Tested Upper pipe rams + three (3) INSIDE choke manifold valves at 250 PSI.
Lost 5 PSI (2.0%) in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure increase recorded on chart.
4-27-13 @ 12:11 PM 4-27-13 @ 12:17 PM
4b. Tested Upper pipe rams + three (3) INSIDE choke manifold valves at 3,600 PSI.
No pressure lost in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure increase recorded on chart was 70 PSI (2.0 %.)
4-27-13 @ 12:21 PM 4-27-13 @ 12:27 PM
5a. Tested Upper pipe rams + three (3) MIDDLE choke manifold valves at 495 PSI.
No pressure lost in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure loss recorded on chart.
4-27-13 @ 12:28 PM 4-27-13 @ 12:35 PM
5b. Tested Upper pipe rams + three (3) MIDDLE choke manifold valves at 3,500 PSI.
Lost 10 PSI (0.3%) in 7 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure loss recorded on chart was 100 PSI (2.9 %.)

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 2 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 21 T 47S R 28E , 643.86 South & 4,642.98 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 16,215 DF TVD 11,948.34
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Moving drilling equipment to #1352 (pilot) well at BreitBurns North Bear Island Field. Waiting on completion rig.


I certify that the above well and premise was inspected on 4-27-13, 4-29-13, 4-30-13, 5-3-13, 5-6-13, 5-8-13, 5-10-13, 5-14-13, & 5-16-13
by Paul Attwood & Pierre Bruno. One (1) minor violation of rules 62C-25 through 30, FAC was found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of May 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 05/17/13
Permit #
1349-H
Date
05 17 2013

BOP Test #72 on 4-27-13 (witnessed by Precisions driller):
Test of Blowout Preventers, Kill Valves, Hydril, & Choke Manifold Valves (#1349-H horizontal well)
4-27-13 @ 12:37 PM 4-27-13 @ 12:43 PM
6a. Tested Upper pipe rams + choke manifold valves to panic line, gas buster & shale shakers at 400 PSI.
No pressure lost in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure loss recorded on chart.
4-27-13 @ 12:44 PM 4-27-13 @ 12:49 PM
6b. Tested Upper pipe rams + choke manifold valves to panic line, gas buster & shale shakers at 3,600 PSI.
Lost 100 PSI (2.8%) in 5 minutes. PASSED on 1
st
attempt.
Note: pressure loss recorded on chart was 100 PSI (2.8 %.)
4-27-13 @ 12:53 PM 4-27-13 @ 12:58 PM
7a. Tested Hydril at 400 PSI.
No pressure lost in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure loss recorded on chart.
4-27-13 @ 1:00 PM 4-27-13 @ 1:06 PM
7b. Tested Hydril at 2,500 PSI.
Pressure increase of 100 PSI (4.0%) recorded in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure increase recorded on chart was 100 PSI (4.0 %.)
4-27-13 @ 1:18 PM 4-27-13 @ 1:24 PM
8a. Tested Blind rams at 400 PSI.
No pressure lost in 6 minutes (per driller.) PASSED on 1
st
attempt.
Note: No (0%) pressure loss recorded on chart.
4-27-13 @ 1:25 PM 4-27-13 @ 1:30 PM
8b. Tested Blind rams at 3,500 PSI.
No pressure lost in 5 minutes (per driller.) PASSED on 1
st
attempt.
Note: pressure loss recorded on chart was 10 PSI (0.3 %.)
Higher ending than starting pressures may be attributed to natural gas (from Rubble Zone) trying to expand in fluid (per Robert Mark J ones-drilling consultant.)
Bottoms up trip gas was 2,500 units prior to pulling out of the hole earlier in the day to test BOPs (per Robert Mark J ones-drilling consultant.)


Day 99 Summary: 4-29-13 TD = 13,363 DF Drilled 368 of 6.125-diameter hole from 12,995 DF to 13,363 DF in 16.5 hrs.
(6 AM 4-28-13 to 6 AM 4-29-13)

Day 100 Summary: 4-30-13 TD = 13,985 DF Drilled 622 of 6.125-diameter hole from 13,363 DF to 13,985 DF in 20.5 hrs.
(6 AM 4-29-13 to 6 AM 4-30-13)
(Attwood arrived 4-29-13 at 6:54 AM, left 4-29-13 at 7:47 AM.)
Operator was drilling at 13,397 DF on 4-29-13 at 6:58 AM.

Day 101 Summary: 5-01-13 TD = 14,483 DF Drilled 498 of 6.125-diameter hole from 13,985 DF to 14,483 DF in 17.5 hrs.
(6 AM 4-30-13 to 6 AM 5-1-13)
(Attwood arrived 4-30-13 at 9:35 AM, left 4-30-13 at 10:04 AM.)
Operator was drilling at 14,060 DF on 4-30-13 at 9:37 AM.

Day 102 Summary: 5-02-13 TD = 14,772 DF Drilled 289 of 6.125-diameter hole from 14,483 DF to 14,772 DF in 16.5 hrs.
(6 AM 5-1-13 to 6 AM 5-2-13)

Day 103 Summary: 5-03-13 TD = 15,255 DF Drilled 483 of 6.125-diameter hole from 14,772 DF to 15,255 DF in 21 hrs.
(6 AM 5-2-13 to 6 AM 5-3-13)

Day104 Summary: 5-04-13 TD = 15,800 DF Drilled 545 of 6.125-diameter hole from 15,255 DF to 15,800 DF in 20.5 hrs.
(6 AM 5-3-13 to 6 AM 5-4-13)
(Attwood arrived 5-3-13 at 9:55 AM, left 5-3-13 at 10:45 AM.)
Operator was drilling at 15,347 DF on 5-3-13 at 10:24 AM.





Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 3 of 3

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 21 T 47S R 28E , 643.86 South & 4,642.98 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 16,215 DF TVD 11,948.34
Rig Name & # Precision Drilling #314 Contact Person & # Dana Martin & Mark Jones (drilling consultants) (713) 395-7571
Well Status Moving drilling equipment to #1352 (pilot) well at BreitBurns North Bear Island Field. Waiting on completion rig.


I certify that the above well and premise was inspected on 4-27-13, 4-29-13, 4-30-13, 5-3-13, 5-6-13, 5-8-13, 5-10-13, 5-14-13, & 5-16-13
by Paul Attwood & Pierre Bruno. One (1) minor violation of rules 62C-25 through 30, FAC was found.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 17
th
day of May 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 05/17/13
Permit #
1349-H
Date
05 17 2013


Day 105 Summary: 5-05-13 TD = 16,215 DF Drilled 415 of 6.125-diameter hole from 15,800 DF to 16,215 DF in 21 hrs.
(6 AM 5-4-13 to 6 AM 5-5-13)
Reached FINAL total depth of 16,215 DF on 5-5-13 at 5:30 AM.
4,231-long lateral wellbore drilled through Rubble Zone from 11,984 DF to 16,215 DF.

Day 106 Summary: 5-06-13 TD = 16,215 DF Reamed tight spot from 14,580 DF to 16,215 DF, then P.O.O.H.
(6 AM 5-5-13 to 6 AM 5-6-13) Began tripping in hole with Bakers Star Trak high-definition resistivity imaging tool.
This Star Trak imaging tool identifies resistivity, fractures, and sedimentary bedding in conductive drill fluid.

Day 107 Summary: 5-07-13 TD = 16,215 DF Logged well with Bakers Star Trak high-definition resistivity imaging tool
(6 AM 5-6-13 to 6 AM 5-7-13) from 12,452 DF to 13,819 DF.
(Attwood arrived 5-6-13 at 7:28 AM, left 5-6-13 at 7:43 AM.)
Operator was going in hole with Baker Star Trak logging tool at 5,799 DF on 5-6-13 at 7:32 AM.

Day 108 Summary: 5-08-13 TD = 16,215 DF Logged well with Bakers Star Trak high-definition resistivity imaging tool
(6 AM 5-7-13 to 6 AM 5-8-13) from 13,819 DF to 15,896 DF.

Day 109 Summary: 5-09-13 TD = 16,215 DF Logged well with Bakers Star Trak high-definition resistivity imaging tool
(6 AM 5-8-13 to 6 AM 5-9-13) from 15,896 DF to 16,215 DF, then P.O.O.H.
Pumped eight (8) 55 gal. drums of bleach in Rubble Zone, then displaced fluid in hole
with potassium chloride.
Began laying down 3 O.D. drill pipe.
(Attwood arrived 5-8-13 at 10:57 AM, left 5-8-13 at 11:15 AM.)
Operator was pumping eight (8) 55 gal. drums of bleach into Rubble Zone on 5-8-13 at 11:10 AM.

Day 110 Summary: 5-10-13 TD = 16,215 DF Finished laying down 3 O.D. drill pipe & directional tools.
(6 AM 5-9-13 to 6 AM 5-10-13) Changed out pipe rams. Removed blind rams. Nippled down BOPs.
I nstalled dry hole cap on well.

Day 111 Summary: 5-11-13 TD = 16,215 DF Finished cleaning mud tanks.
(6 AM 5-10-13 to 6 AM 5-11-13) Released Precision #314 drilling rig on 5-10-13 at 6 PM.
(Bruno arrived 5-10-13 at 12:40 PM, left 5-10-13 at 4:30 PM.)

5-12-13 TD = 16,215 DF Continued rigging down drilling rig. Rigged down mud pumps, SCR house & cables. 30% rigged down at days end.
(6 AM 5-11-13 to 6 AM 5-12-13)

5-13-13 TD = 16,215 DF 65% rigged down. 5% rigged up. 30% rigged down and moved to BreitBurns #1352 (pilot) location at N. Bear I sland.
(6 AM 5-12-13 to 6 AM 5-13-13) Began moving drilling rig equipment to BreitBurn Floridas #1352 (pilot) well at North Bear Island Field (Pad 1) on 5-12-13.

5-15-13 TD = 16,215 DF
(6 AM 5-14-13 to 6 AM 5-15-13) (Attwood arrived 5-14-13 at 9:02 AM, left 5-14-13 at 9:20 AM.)
Contractors for BreitBurn Florida were hauling drilling mats to #1352 (pilot) well at North Bear Island Field on 5-14-13 at 9:15 AM.
Torn & stained liner formerly underlying rig has not yet been removed. Location has not been cleaned up.

5-17-13 TD = 16,215 DF 100% rigged down. 5% (6 loads) left to be moved to BreitBurns #1352 (pilot) location at N. Bear I sland.
(6 AM 5-16-13 to 6 AM 5-17-13) (Attwood arrived 5-16-13 at 10 AM, left 5-16-13 at 10:42 AM.)
Torn & stained liner formerly underlying rig has not yet been removed. Location has not been cleaned up.
40-long x 4-12-wide area on limerock pad (centered 89 E & 38 N of SW corner of perimeter dike) with oil on standing water.
28-long x 5-wide area on limerock pad (centered 139 E & 30 N of SW corner of perimeter dike) stained with oil.

---one (1) minor violation: Two (2) areas near southern perimeter dike are stained with hydrocarbons & need to be excavated & removed.
(see 5-17-13 entry on this report.)

Florida Department of
Environmental Protection
Bureau of Mining & Minerals Regulation
Ft. Myers Oil & Gas Field Office
2295 Victoria Avenue, Suite 179
Fort Myers, FL 33901
Office: (239) 344-5721 & (239) 344-5611
Confidential
Page 1 of 1

OIL WELL INSPECTION REPORT

County Collier API # 09-021-20211-01 Permit # 1349-H (horizontal)
Operator Dan A. Hughes Company, L.P. Well # & Name 20-3-H Collier-Hogan (horizontal)
Field/Pad Wildcat (1
st
pad) Well Type Wildcat-Oil BCS/BCNP B.C.S.
Surface Location (SHL) 2,116 FSL & 3,315 FEL Sec. 20 T 47S R 28E
Final Bottom Hole Location is in Sec. 21 T 47S R 28E , 643.86 South & 4,642.98 East of S.H.L.
Spud 3-29-13 at 11 PM GL 20.6 (in 11-12 before pad built) DF 25.5 above G.L. TD 16,215 DF TVD 11,948.34
Rig Name & # C.S. Forbes #71 Contact Person & # Dana Martin (drilling consultant) (361) 701-8069
Well Status C.S. Forbes completion rig on well on 7-12-13.
Well making 16 bbls. to 27 bbls. of 23 to 24 oil + trace of 1,500 PPM chloride water per day.


I certify that the above well and premise was inspected on 5-14-13, 5-16-13, 5-19-13, 5-24-13, & 7-12-13 by Paul Attwood.
No violations of rules 62C-25 through 30, FAC were found on 7-12-13.

Signed________________________________________________
Paul J. Attwood, Oil and Gas Coordinator

This Oil Well Inspection Report was mailed to recipients marked below on the 15
th
day of July 20 13.
Note: If a violation exists, designate the rule violated and describe the infraction. Specify to the operator what must be done and time frame.
A copy of rule 62C-25.0075 as well as a copy of the rule violated will be mailed upon request.

cc: x FDEP (Oil & Gas Section): Tallahassee, FL
x FDEP (Oil & Gas Section): Fort Myers, FL
x Dan A. Hughes Company: Dana Martin (drilling consultant)

IH-1 Rev. 07/15/13
Permit #
1349-H
Date
07 15 2013


Fourth Report (#1349-H (horizontal): Eight (8) cu. yds. contaminated limerock excavated & placed
on an impermeable, 40 mil liner;
Completion rig on well. Evaluation still in progress as of 7-12-13.


Casing Summary:
1-08-13: 24 O.D. x 23 I.D. x 125#/ft. conductor driven to 196.5 B.G.L. (= 222 DF using Precision #314 DF elevation.)
1-30-13: 13.375 O.D. x 12.615 I.D. x 54.5#/ft. J-55 BT&C surface casing set at 1,714 DF (per Caliper log ran 2-3-13.)
2-10-13: 9 5/8 O.D. 8.681 I.D. x 47#/ft. P-110 GB buttress intermediate casing set at 3,964 DF.
4-17-13: 7 O.D. x 6.276 I.D. x 26.0#/ft. P-110 LT&C casing (45 joints) ran from surface to 2,043.05 DF and
7 O.D. x 6.276 I.D. x 26.0#/ft. L-80 LT&C casing (236 joints) ran from 2,043.05 DF to 12,440 DF.


A minor violation was noted on the inspection report for #1349-H dated 5-17-13. That minor violation is summarized below:

Two (2) areas on the limerock pad were stained with petroleum products released from equipment associated with the
Precision #314 drilling rig:
40-long x 4 to 12-wide area on limerock pad (centered 89 E & 38 N of SW corner of the perimeter dike) stained
with oil from the drilling rigs mud pumps. See Photos 52 & 53.
28-long x 5-wide area on limerock pad (centered 139 E & 30 N of SW corner of the perimeter dike) stained
with oil &/or diesel in the vicinity of the aboveground diesel tank formerly on the location
& used to fuel the drilling rigs generators. See Photos 54 & 55.

Also, one (1) area on the 40 mil liner underlying the drilling rigs equipment was capped with stained limerock:
24-long x 16-wide area containing limerock on the liner (centered 30 WNW of #1349-H wellhead) stained
with crude oil that dripped off drill pipe and associated downhole drilling equipment. See Photo 51.


On 5-20-13, contractors:
1. scraped off crude oil-stained limerock centered 30 WNW of #1349-H wellhead that was ON the liner and placed it
on a 21-long x 18-wide piece of 40 mil liner.
2. removed the remainder of the 40 mil liner underlying the drilling rigs equipment and disposed of it in dumpsters.
3. excavated the 40-long x 4 to 12-wide area on the limerock pad stained with mud pump oil and placed it on the
21-long x 18-wide piece of 40 mil liner.
4. excavated the 28-long x 5-wide area on the limerock pad stained with oil &/or diesel and placed it on the
21-long x 18-wide piece of 40 mil liner.

Summary: No violations.
8 cu. yds. of contaminated limerock present & contained on an impermeable, 40 mil piece of liner.
Center of pile situated on high ground on the limerock pad 88 N & 14 E of the SW corner of the perimeter dike.
This material, along with any additional limerock that might be stained with crude oil during the current workover operations,
will be transported to the Cemex incinerator in Miami for disposal after the completion rig has moved back to Texas.
As of 7-12-13, a completion rig was rigged up on the well, & the operator was still trying to turn this well into a commercial producer.