You are on page 1of 48

May 2005

2005

The AACE International Journal of


Cost Estimation, Cost/Schedule Control, and Project Management

Promoting the Planning and


Management of
Cost and Schedules

IN
IN THIS
THIS ISSUE
ISSUE
• Technical Article -
Design/Build Selection
Process — Art or
Science?
• Technical Article -
Using Earned Value
Management Indexes
as Team Development
Factor and a
Compensation Tool
• Technical Article -
The Goalposts for
Project Success Have
Moved — A Marketing
View
• Executive Article -
The Art of
Compromise

• Education Board News -


AACE
AACE International’s
International’s 2005
2005 2005 Update on
ANNUAL Globalization of
ANNUAL MEETING
MEETING ISSUE
ISSUE Educational Materials
• Certification Corner -
Study Groups

• Special Feature -
Earned Value
Professional
Certification on Track
for New Orleans
Premier

The Association for the Advancement of


Cost Engineering International
Visit our website at www.aacei.org
The AACE International Journal of
AACE International
Cost Estimation, Cost/Schedule Control, and Project Management
Board of Directors

President
Clive D. Francis, CCC ESTABLISHED 1958
Black & Veatch, MI
734-622-8543/fax: 734-622-8700
e-mail: president@aacei.org
Depar tments
President-Elect
Philip D. Larson, CCE PSP President’s Message ................................3 Special Feature ....................................26
WinEstimator, WA In Our Estimation ..................................5 Professional Services Directory ..............38
253-395-3631/fax: 253-395-3634
Letters to the Editor................................8 AACE International Bulletin ..............39
e-mail: preselect@aacei.org
Education Board News ........................10 Article Reprints and Permissions ..........43
Past President Calendar of Events ..............................44
Certification Corner ............................11
Ozzie F. Belcher
Belstar, Inc., VA Executive Article ..................................13
703-645-0280/fax: 703-645-0286
e-mail: pastpres@aacei.org Featured Ar ticles
Vice President-Finance
Robert B. Brown, PE Design/Build Selection Process — Art or Science? 14
PMA Consultants of Illinois, LLC, IL
312-920-0404/fax: 312-920-0405
Talal Abi-Karam, PE CCE
e-mail: vpfinance@aacei.org Although Design/Build is one of the most popular integrated alternative delivery methods, it does not have well-
established contractor selection procedures. The selection of a Design/Builder can be based solely on qualifi-
Vice President-Administration cation, solely on price, or a combination of price/qualification. Even with qualification-based selection (QBS),
William E. Kraus, PE CCE the selection process may be subjective, since various state agencies (DOT's) and municipalities have different
B & C Project Services, CO selection criteria for pre-qualifying and evaluating bids of the perceptive Design/Build teams. This article exam-
970-206-0947/fax: 970-226-1818 ines the various selection methods of Design/Build teams in the public works sector. It addresses the legal
e-mail: vpadmin@aacei.org
framework for selecting Design/Build teams, including qualification-based selection (QBS), selection criteria,
Vice President-Regions and weighting of criteria.
Marvin Woods, CCE
Project Controls Group, Inc., MO
314-838-4987/fax: 314-389-8957
Using Earned Value Management Indexes as 20
e-mail: vpregions@aacei.org Team Development Factor and a Compensation Tool
Vice President-TEC Ricardo Viana Vargas
James G. Zack Jr., The objective of this article is to present the main components of the development of a project team and the
Fluor Daniel, CA motivational characteristics inherent to team work. It also looks at an interrelation proposal between the earned
949-349-7905/fax: 949-349-7919 value analysis and team development through the SPI and CPI indexes. These are obtained by tool use and
e-mail: vptec@aacei.org
team development models and the compensation and reward in the project. This reduces the subjectiveness
Director-Region 1 of humans resource in the project evaluation. The article presents a brief report about team development and
Mustansir H. Raj, CCE compensation policies, as well as an introduction to the earned value concept, aiming to align the approached
Bantrel, Calgary, Canada concepts.
403-282-6545/fax: 403-290-5050
e-mail: dirregion1@aacei.org
The Goalposts for Project Success Have Moved — 28
Director-Region 2
Charles E. Bolyard Jr., PSP
A Marketing View
McDonough Bolyard Peck, Inc., VA P.S. Kupakuwana and G.J.H. van der Berg
703-641-9088/fax: 703-641-8965 Traditionally, a successful project was seen as one in which the triad of time, budget, and specification was com-
e-mail: dirregion2@aacei.org plied with at a profit. Current project literature places more emphasis on customer satisfaction as a fourth
Director-Region 3 important success parameter. This article discusses project management services and focuses on what consti-
Robert E. McCoy, CCC tutes project success. This type of project is named the new project in this article and a set of new project rules
BWXT Y-12, LLC, TN is arrived at. The article also takes a services marketing view and examines the customer's motivation in appoint-
865-482-7658 ing a project manager.
e-mail: dirregion3@aacei.org

Director-Region 4
Jeffrey D. Kursave, CCC
In This Issue
SAIC., MO
Board of Directors Contact List ........................1 Index to Advertisers ......................................38
314-770-3006/fax: 314-344-4349
e-mail: dirregion4@aacei.org AACE Certification Exams ..........................11 AACE International HQ Contact List ........42

Director-Region 5
Stephen W. Warhoe, PE CCE On the Cover: New Orleans is ready to welcome AACE International members and guests to our 49th
303-740-2665 Annual Meeting, June 26-29. Register by May 27, and save $100.
e-mail: dirregion5@aacei.org

Director-Region 6 COST ENGINEERING AACE International Headquarters


Mark G. Grotefend, CCC Vol. 47, No.5/May 2005
209 Prairie Avenue, Suite 100
253-835-8081 Managing Editor - Marvin Gelhausen Morgantown, WV 26501
e-mail: dirregion6@aacei.org e-mail: mgelhausen@aacei.org
ph: 800.858.COST
Interim Executive Director Graphic Designer/Editor - Noah Kinderknecht
e-mail: nkinderknecht@aacei.org fax: 304.291.5728
Charla Miller
e-mail: cmiller@aacei.org
Policy concerning published columns, features, and articles -
Viewpoints expressed in columns, features, and articles published in Cost Engineering journal are solely those of the authors and do not represent an official position of AACE
International. AACE International is not endorsing or sponsoring the author’s work. All content is presented solely for informational purposes. Columns, features, and articles not
designated as Technical Articles are not subject to the peer-review process.
Cost Engineering (ISSN: 0274-9696) is
published monthly by AACE International,
Inc, 209 Prairie Ave., Suite 100, Morgantown,
P resident’s
P resident’s Message
WV 26501 USA. Periodicals postage paid at
Morgantown, WV, and at additional mailing
office. POSTMASTER: Send address
Clive D. Francis, CCC
changes to AACE International; 209 Prairie President
Ave., Suite 100, Morgantown, WV 26501
USA. Single copies: US$8 members/ US$12
nonmembers (both +shipping), excluding
special inserts available to AACE members
only. Subscription rates: United States,
Our Association Continues to Change
US$65/year; all other countries, US$82/year.
Overseas airmail delivery is available at
s I sit to write this message, it is hard earned value analysis, and who work on con-

A
US$99. Subscriptions are accepted on an
annual-year basis only. Copyright © 2005 by
AACE International, Inc. All rights reserved. to believe that there have been nine struction and other claims. With the strategic
This publication or any part thereof may not messages which have preceded this plan, we will have a guide to help us define
be reproduced in any form without written
permission from the publisher. AACE one, and I look forward to recognize that who we are and where we need to be in the
assumes no responsibility for statements there are only two more to go. The elections next few years.
and opinions advanced by the contributors
to its publications. Views expressed by them have been completed, and the makeup of the What else is new? We have introduced
or the editor do not necessarily represent next year’s Board of Directors (BOD) is truly and successfully completed two Beta tests of
the official position of Cost Engineering, its
staff, or AACE International, Inc. Printed in exciting. The elections have brought to the new Earned Value Professional (EVP) certifi-
York, PA, USA. Cost Engineering is a BOD three new persons who have never cation. The certification gives AACE
refereed journal. All technical articles are
subject to review by a minimum of three been on the BOD. They will bring new ideas International professionals who perform
experts in the field. To submit a manuscript
for peer review, please e-mail it to
and energy to your association and provide a earned value analysis as part of their daily
editor@aacei.org. Cost Engineering is new outlook and ideas to make us grow. work activities the recognition for the work
indexed regularly in the Engineering Index.,
Cambridge Scientific Abstracts, by EBSCO
The other exciting action to come from they do. The certification was developed by a
Publishing, and in the ABI/Inform database. the elections was the overwhelming vote to dedicated group of professionals who devel-
Cost Engineering is available online, via the
ProQuest information service; on microform; change the method of voting for your associ- oped questions, developed processes, and
electronically on CD-ROM and/or magnetic ation executives. Our votes in this election developed the criteria.
tape from Bell & Howell Information and
Learning, PO Box 1346, Ann Arbor, MI 48106. were decided by only 15 percent of our mem- Also, by the time you read this message
Photocopy permission : Authorization to bership. I recently voted for new directors our Interim Executive Director, Andy Dowd,
photocopy articles herein for internal or
personal use, or the internal or personal use and other issues for another group via elec- will have returned to his life before working
of specific clients, is granted by AACE tronic voting method. This was so easy and at AACE International Headquarters. Andy
International, Inc., provided that the base
fee of US$4.00 is paid directly to Copyright quick and I am sure brought out a much has served the Association well over the last
Clearance Center, 222 Rosewood Drive, higher percentage of those eligible to vote. eight months. As Interim Executive Director,
Danvers, MA 01923 USA. Telephone:
978.750.8400. For those organizations that The Association will implement electronic Andy chose to take the high road and to make
have been granted a photocopy license by
CCC, a separate system of payment has
voting for all members, hopefully by the improvements in operations, to guide the
been arranged. The fee code for users of the 2006 election. staff, helping to mentor them, and to be the
transactional reporting service is ISSN-
0274-9696/02 US$4.00. This permission to
By the time you read this, the April conscience to the Board of Directors. All that
photocopy does not extend to any Cost Board meeting will be history. I am going to Andy did was dedicated to improving the
Engineers’ Notebook, AACE Recommended
Practices supplements, or membership this meeting with a lot of anticipation and Association's operations. Andy also chose to
directories published in this magazine hope for an exciting new process for AACE be our representative with other associations.
and/or special inserts. Payment should be
sent directly to CCC. Copying for other than International. The plan is for us to spend a All of us at AACE International owe Andy a
personal or internal reference use without portion of the Board of Directors meeting special thanks for his contributions. From a
the express permission of AACE is
prohibited. Address requests for permission developing an outline for a new AACE personal point of view, I believe that Andy
on bulk orders to the editor. ADVERTISING International Strategic Plan. The new plan was there when needed and I could depend
COPY: Contact Network Publications Inc.,
Executive Plaza 1, 11350 McCormick Road, Suite will be our guide for the next two to three on him to be there as a guide, mentor, and
900; Hunt Valley, MD 21031. Telephone: 410.584.1966. years. The expectation is that the strategic more importantly, as a friend. ◆
E-mail: aace@networkpub.com for rates.
Advertisers and advertising agencies assume plan will be reviewed each year and used as a
liability for all content (including text, guide for the coming year. At the same time,
representation, and illustrations) of
advertisements printed and also assume we would expect that, after each two year
responsibility for any claims arising
therefrom made against the publisher. The
interval, it would continue to serve as a guide
publisher reserves the right to reject any for further updates and become the blueprint
advertising that is not considered in keeping
with the publication’s mission and
for the following two year interval.
standards. The publisher reserves the right So why do we need a strategic plan? It
to place the word advertisement with copy
which, in the publisher’s opinion, resembles has become very evident over the last couple
editorial matter. All advertising accepted for of years that we need to spend time to deter-
publication in Cost Engineering is limited to
subjects that directly relate to the cost mine who we are and where we want to be in
management profession. Current rate card the future. The whole profession of cost engi-
available on request. COST ENGINEERING
DEADLINES : Submissions for Cost neering has changed over the years. The pro-
Engineering must be received at least 7 fession is no longer a group dealing only with
weeks in advance of the issue date. Send to:
Editor, 209 Prairie Ave., Suite 100, numbers. We are now a group of profession-
Morgantown, WV 26501 USA. Deadlines do als who also deal with schedules, who provide
not apply to technical papers.

Cost Engineering Vol. 47/No. 5 MAY 2005 3


I Inn Our
Our Estimation
Estimation
Jennie Amos
Manager, Marketing and Meetings

AACE International Board Adopts


New Vision and Mission Statements
n my way to work today, I passed the time of the 30

O minute drive by listening, as I do most mornings, to


National Public Radio. I was intrigued with the inter-
view on NPR's Morning Edition with Microsoft Chairman Bill
AACE International's Vision:
To be the recognized technical authority in cost
Gates. That interview jump started my thought process of recent and schedule management for programs, proj-
activities with AACE International and its Board of Directors. ects, and products.
During the interview, Bill Gates was asked his opinion about
the problem with the reduced number of science and engineer- AACE International's Mission:
ing students in the US and whether the problems were with the
educational system or a problem of the US culture. Here is what To provide technical programs, research, recom-
Bill Gates had to say: mended practices, and professional development
and expertise through technical programs, con-
"The Chinese are clearly inculcating the idea that sci- tinuing education, and professional certification.
ence is exciting and important and that's why they, as a
whole, are graduating four times as many engineers as
we [the US] are. That's just happened over the last 20 It was then that I learned that a former AACE International
years. We see drop offs in terms of interest in this at President, Chris Walker, had been a project manager on the
every level of the educational system, particularly for Channel Tunnel—how exciting that must have been! During
women and minorities, but as a whole. So we have got my tenure at AACE International, I have also learned of members
to work on that in every stage." working on projects like the NASA Space Shuttle facilities,
Disney's Epcot Center, and let's not forget AACE International
So you may be reading this and saying to yourself, "Self, what President-Elect, Phil Larson, CCE PSP's, work as lead scheduler
on earth does this have to do with AACE International?" Or you on Bill Gates' residence!
could be thinking that this girl at AACE Headquarters is a little These few examples and the many current projects AACE
wacky…I'll address the question on how Bill Gates' comments International members perform on a daily basis are just scratch-
relate to AACE International, and leave you to judge the level of ing the surface of a typical AACE member’s work. These could
my sanity for yourself. not have been done without some stimulation and notion that the
At the AACE International Board of Directors meeting, April work they were doing was not only difficult and technical, but
21-22, in Toronto, Ontario, Canada, the Board conducted a exciting and important as well.
strategic planning session for the first time in a few years. The With the good work being done by our dedicated members
newly adopted vision and mission statements for AACE on our Board of Directors, TEC Boards, Technical Committees
International, I believe, help to define the Association to the pro- and SIGs, Sections, and our membership as a whole, AACE
fession at large. Although there is still more work to be done in International will be the recognized technical authority in cost
the area of strategic planning, many of the issues and goals that and schedule management for programs, projects, and products.
were discussed in this day-long session touched on those com- I hope by this point, assuming that you haven't already decid-
ments made by Bill Gates. ed that I'm a little too nuts for you and have stopped reading this
I believe that, like in Bill Gates' statement, AACE article, you are asking yourself, "Self, what can I do right now to
International should be instilling the idea that the work being help ensure that AACE International is able to achieve it's vision
done by our members is exciting and important. and mission?"
I am always fascinated to learn of many of the works and pro- With the 49th Annual Meeting just around the corner, I
grams of our members, both historical and current. I recall that hope you will be supporting our efforts for technical programs,
just a few days ago, while touring Toronto's CN Tower with fellow continuing education, and professional certification offered
Headquarters Staffers Christian Heller, Teri Jefferson, and Charla there!
Miller, we saw a display on the Seven Wonders of the Modern AACE International is extremely thankful to one of our
World (according to our friends at the American Society of Civil Sections, Genesee Valley, for their fifth year in sponsoring the
Engineers) which include the Channel Tunnel, CN Tower, Annual Meeting (they are the only section in recent years to have
Empire State Building, Golden Gate Bridge, Itaipu Dam, done so)! This year, the Genesee Valley section is also sponsor-
Netherlands North Sea Protection Works, and the Panama Canal. ing the attendance of one of their members to the Annual
Meeting! I think this is quite a feat for a section of only 40 mem-

Cost Engineering Vol. 47/No. 5 MAY 2005 5


bers! Section Leaders, won't you consider matching support of
AACE International like your friends at Genesee Valley have
done for several years to help support AACE International's vision
MONEY SAVING TIPS
and mission? for
for the
the
As an individual member, there are a number of ways you
can help AACE International demonstrate its vision and mission 2005 ANNUAL MEETING
by making your own contribution: get a friend to join AACE
International, attend the Annual Meeting, brush up on your skills TIP 1 - Stay in the AACE International Host
with the Professional Practice Guides, participate in a Technical Hotel, Sheraton New Orleans, and save $100 off of
Committee or SIG, attend a Continuing Education Seminar,
take a Distance Learning Course, sign up to be an Approved your Technical Program Registration. If you are tak-
Education Provider, or get AACE International certified: CCC ing a Continuing Education Seminar, you can receive
(Certified Cost Consultant), CCE (Certified Cost Engineer), $100 on one or both by staying at the Sheraton New
ICC (Interim Cost Consultant), PSP (Planning and Scheduling Orleans as well!! Just make sure to enter your confir-
Professional), or EVP (Earned Value Professional).
AACE International is helping you to do your exciting and
mation number on your annual Annual Meeting
important work, but your input and involvement is, as it has been for Registration Form.
the last 49 years, vital to these overall efforts of the Association! ◆
TIP 2 - Register before the Early Registration Cut-
Off Date, May 27th, and save an additional $100!

6 Cost Engineering Vol. 47/No. 5 MAY 2005


LLetters to the Editor
etters to the Editor
Marvin Gelhausen, Editor

All, results of this research with you in the coming 9 months or


I was on the telephone recently with a gentlemen who has so…….
the Planning & Scheduling Professional (PSP) Certification And for those of you thinking about getting your Ph.D., I can-
through AACE International. This individual is also a testifying not think of any better distance learning program than the Ph.D.
expert in the area of construction scheduling. He just completed in Project/Program Management offered by Professor Bredillet at
testifying in a jury trial in Northern California. Since he had ESC-Lille. www.esc-lille.com . And rumor has it that a distance
recently achieved his PSP Certification, he had briefed the attor- learning Masters degree from ESC-Lille in Program/Project
ney he was working with on the implications of having a PSP Management may be in the works as well.
Certification, as well as the requirements to attain such certifica-
tion. His attorney asked all the "right questions" during voir dire BR,
(the qualifying process for an expert witness in Court) and the PDG, Jakarta
judge readily admitted him as an expert.
Opposing counsel was unable to keep him off the stand as an Dear ICEC Members and Delegates:
expert. Additionally, it was noted during the trial that the oppos- Many of you have submitted payments for your 2005 ICEC
ing expert did not have this certification. Subscriptions and we trust that those who have not yet done so
The outcome of the trial was a settlement very much in favor will arrange payment soon.
of this individual's client. Now, it cannot be said that the PSP As indicated in the instructions previously sent to you for
Certification was the only reason this happened or even the pri- handling payments, if bank transfers are used, it is preferred that
mary reason. I'm pretty confident that facts, law, contract lan- they be sent to the ICEC office in Australia, not to our United
guage, analysis and presentation skills had something to do with States bank account.
the outcome also. But, the point is, having the PSP Certification Unfortunately, the United States Federal reserve system has
made it much easier to be admitted as a testifying expert in the changed the manner in which bank transfers are handled. When
area of construction scheduling, at least in this case. transfers are sent to the United States they are simply credited to
You may want to pass this information along to those you accounts and no identification of who sent the funds is provided.
know who are schedulers and who either are, or want to become, Everything is done electronically. We have received several wire
testifying experts in this area. This certification is starting to pay transfers and do not know who sent them. We must know when
off -- at least for this individual. you send payments so that we can identify them. Even if you
inform us of the amount transferred, because of fees charged on
James G. Zack, Jr. transactions, the amount credited to our account will not match
Executive Director the amount sent. This makes it very difficult for ICEC to identify
Corporate Claims Management who sent the payment and to properly credit the sender. This
Fluor Corporation problem does not occur with transfers to the Australian bank.
One Enterprise Drive, S3-148 If you have sent a transfer to the United States, or if you send
Aliso Viejo, CA 92656-2606 one in the future, always send an e-mail to kenh@icoste.org pro-
viding us with the details of your transmittal including the name
Hello AACE Colleagues, of your bank and the name of the US correspondent bank which
As many of you know, I am in the process of researching my they used to handle the transfer so that we may properly identify
Ph.D. thesis: “Is Project Management a Profession? And If Not, your payment. Otherwise we may not know that you have made
What is it?” under the supervision of Dr. Christophe N. Bredillet, payment.
Lille Graduate School of Management, Lille, France. We have received several payments this month which we
Accordingly, I would be very appreciative if my AACE col- cannot identify. If one of them is yours, please provide the
leagues were to register your opinions on how you perceive and requested information so that we can properly identify your pay-
define what we do for a living. I am especially keen to make cer- ment.
tain I get the input from as many PE’s as possible. I think the per-
spective of how PE’s perceive project management is going to be Thank you.
very interesting.
Please take about 1.5 hours of your time to fill in my cus- Kenneth K. Humphreys
tomer survey, and earn 2 PDU’s in the process. (You will receive Secretary-Treasurer
a personal copy of the results and the analysis as soon as I com- International Cost Engineering Council
plete it) OR you can earn one of our famous “Project 1168 Hidden Lake Drive
Management- Art?, Science? Or Bull…..?” T-shirts as a reward for Granite Falls, NC 28630, USA
your efforts. Just visit, http://FreeOnlineSurveys.com/rendersur- http://www.icoste.org
vey.asp?id=76670 Reply to: kenh@icoste.org
Many thanks in advance and look forward to sharing the

8 Cost Engineering Vol. 47/No. 5 MAY 2005


Consulting “101” International; ASPE; PMI; SAVE) and agencies (among them:
Two years ago, when I was, “selected to participate in a force AGC; ASA;NFIB; et.al.) where further networking could be
reduction,” many emotions were felt. Since several lay-offs had achieved. There are numerous societies where one can share in
occurred in previous quarters, one emotion was relief—removing knowledge and potential contracts.
the uncertainty of the effects of market conditions on one’s daily Be prepared to spend many hours in the up-front efforts of
employment. networking, marketing, planning, and research. And, yes, there
The most prominent emotion, however, was that of optimism are up-front costs associated with licenses, equipment, supplies,
and opportunity. I had always had the notion planted in the far advertising, and much more that require the need to be planned
reaches of my mind that “one day,” after retirement, I would like for—and addressed in your business plan.
to become an independent consultant. Above all, dream your dream. Contact others in the consult-
I consider it extremely fortunate that, as one of the out-place- ing field to be appraised of pitfalls to avoid, hurdles to overcome,
ment benefits provided by my former employer, I was able to par- and rewards to be gained.
ticipate in the “Fast Trac New Venture” program of the Ewing If you choose this route, best wishes in your endeavors!
Marion Kauffman Foundation. The materials provided me with
the information and tools needed to research and develop busi- Bruce A. Martin ◆
ness plans, marketing plans, and to establish realistic goals for a
successful entrepreneurial adventure.
Hoping to springboard off my years of experience in the Cost
Engineering profession, I filed the necessary forms to license with
my state, acquire my FEIN, and register with the business associ-
ations.
As many will tell you, networking is essential in “getting the
word out” that your shingle is now flapping in the breeze. Letters
of introduction were mailed to colleagues, former coworkers, pro-
fessional association affiliations, potential clients, and (yes) fami-
ly members.
With a background in estimation, budget management,
value engineering, and process improvement, I subscribed to var-
ious publications and journals dealing in entrepreneurship, new
partnerships, and new projects where these skills could be
applied. I sought out associations (among them AACE

Cost Engineering Vol. 47/No. 5 MAY 2005 9


EEducation
ducation Board News
Dr. Sean T. Regan, CCE

2005 Update on Globalization of Educational Materials


n 2004, I shared my thoughts with you on the benefits of involved in international projects, thus increasing membership

I globalizing our educational materials. In a world that is con-


tinually changing, and constantly blending, it is my belief
that our success in the international arena is dependent on shared
and participation in our vision.
Now that there is a core group of volunteers to support our
vision of "globalization," we invite other members who would like
knowledge that is mutually understood among all nations. to contribute their time and talents, as well as start a charter. The
The goal: to create translations that truly transcend our his- committee's mission will be the continual translation of papers,
toric language barriers. books, manuals, and presentations in languages that help outside
Having children from two culturally diverse marriages, I have firms to develop their own dual (or multi) language programs.
witnessed first hand how language barriers can introduce conflict As the Association comes to its golden anniversary, the intro-
and misunderstanding. However, the beauty of translation also duction and use of multiple languages and exams within our
means that it is possible to transcend those barriers and commu- organization, will keep the association in the forefront for anoth-
nicate freely and effectively. While my three sons from my first er 50 years.
marriage are of US descent, they are eagerly learning Russian If you would like to provide a paper, recommend a text, be a
words and phrases and are now communicating with their two presenter, or donate your time to translate a chapter from the
younger brothers who are of Russian lineage. They may not be Skills & Knowledge of Cost Engineering, please feel free to send
fluent, but they have learned the importance of embracing their an e-mail to stregan@revolutionst.com and I will be happy to add
dual cultures. This same consideration must be adopted in our you to our pioneer committee on globalization education. ◆
international arena if we are to be an effective Association both
educationally and professionally.
The Education Board is proud to acknowledge that we will
be embracing this process by offering multi-language translations
of a chapter on scheduling; specifically Chapter 13 of Skills and
Knowledge of Cost Engineering - 5th Edition. The document
has already been successfully translated into Russian, and we are
working diligently to complete the Spanish, Japanese, and
Mandarin translations as well. The goal is to have at least three of
the languages available for sale at our Annual Meeting in New
Orleans in June 2005.
In order to fully understand and appreciate the time and sup-
port that it takes for these translations to take place, I share the fol-
lowing insights with you. From one culture to another, words and
phrases have different meanings. Therefore, we take the following
approach when translating our documents.

• A single individual translates the document.


• The translated document is reviewed by a second group of
peers for content and subject matter.
• After the group comes to an agreement that the translation
meets the context of the original document, we then "reverse
translate" to verify that the meanings have not changed.

The initial chapter, "Scheduling", was translated by volun-


teers who are practicing professionals, not a paid firm. These vol-
unteers translated while working a full time job, managing their
own educational pursuits, and family commitments. And, while
the primary goal of translating this document was done under the
premise of supporting a globally cohesive community, we offer
them "for sale" so that the monies earned may support further
translation of other vital materials. In addition, the income gen-
erated from these sales can also be used to train more individuals

10 Cost Engineering Vol. 47/No. 5 MAY 2005


C
Cer tification
ertification Corner
Valerie Venters, CCC, Certification Board Member

Study Groups
ou want to become certified, but don't know how to get cepts and material.

Y started. I know what you are thinking. . .its has been a


long, long, time since you poured over exam material and
really studied for a test. Then the burning question is, “What if I
Our group agreed to meet once a week immediately after
work for two hours. We divided the chapters of Skills and
Knowledge into blocks of material: scheduling, cost engineering,
don't pass?” estimating, earned value, and other related material. The pre-
Let me offer a suggestion for how to get started—join a study senter for that block of material would prepare his/her presenta-
group. The study group approach may not work for you, but your tion, assemble work problems on the subject, and lead an open
ultimate goal is to improve your skills and get certified. One of question/answer discussion at the end of the evening. The open
the best places to get questions answered about confusing or diffi- discussion at the end is very important. This is where real life
cult concepts or problems is in a study group. examples from the workplace are tied to the presentation materi-
Oftentimes, individual group members have more expertise al.
in the material covered in one of the exam sections than another, The results have been extremely successful. Six project con-
and can teach the material to the other members in the group. . . trols professionals applied and sat for the exam. All six were suc-
all learn together. Taking turns teaching and explaining helps cessful. As word spread through our local section that a project
build confidence for each of the members. The study group also controls study group was happening, many other members began
provides a support group. All of us feel discouraged and over- to attend the classes. The concepts and material presented not
whelmed at times, but a study group can refuel your motivation only benefited the people interested in taking the exam, but also
and make studying more productive. was a great benefit to less experienced project controls profes-
Let me give you an example. At one of our local section sionals who were new to our profession.
meetings, several members indicated an interest in becoming cer- We can sum it up this way by quoting one of our study group
tified. The idea of forming a study group began to take shape. members: "Procrastination has always been a problem for me,
We needed presenters who were experienced project controls pro- but studying with others kept me motivated and excited about
fessionals. We recruited an experienced scheduler to present the learning. Telling a co-worker that I would meet them at the study
scheduling material, an experienced cost engineer to present the group meeting tonight ensured that I would actually be there. If
cost material, and an experienced estimator to present cost esti- I had studied alone, I would have procrastinated and started
mating material. Other volunteers helped present contracts, tomorrow. I would never have become certified at that rate. I
earned value, and behavioral science. An eight week program just received my letter—I passed!!!"
was mapped out. At the beginning of each class, the first few There is no time like the present to get started. Gain confi-
minutes are spent reviewing the paper requirements and answer- dence in your abilities, improve your skills, and set yourself apart
ing any questions. The rest of the class is focused upon exam con- from the crowd—Become Certified!! ◆

AACE International Certification Exams


The Second Quarter (2Q) 2005 Saturday, July 16, 2005 Kansas City
CCC/CCE, PSP, and ICC Final Registration for Exam -May Moscow
Certification Exams will be 20, 2005 Nevada
given at the following AACE New Mexico
Atlanta Niagara Frontier
International sites -
Caribbean Oklahoma
Catawba Valley Rattlesnake Mountain Section
Saturday, June 25, 2005 Central Savannah River Rocky Mountain
New Orleans, LA only - Right Chinook-Calgary St. Louis
before AACE International’s Dubai, United Arab Emirates South Africa
Annual Meeting. The new Earned Delaware Valley Southwest Ohio
Value Professional (EVP) East Tennessee Tennessee Valley
Certification Exam will also be Genesee Valley
offered on this exam date. Great Lakes
Register online at www.aacei.org Hawaii

The Final Deadline for submitting an examination application is May 20, 2005

Cost Engineering Vol. 47/No. 5 MAY 2005 11


EExecutive Ar
xecutive Article
ticle
Dr. Barton Goldsmith

The Art of Compromise


ompromise may be the most important and most under- About the Author

C used word in modern business. Webster defines com-


promise as a settlement of differences by consent,
reached by mutual concessions. Put in simple terms, you've got
Barton Goldsmith, Ph.D., is a highly sought after speaker
and business consultant, US syndicated author, and radio talk
show host. He presents to numerous companies, associations and
to give a little to get a little, with the understanding that just leaders worldwide. His articles have appeared in more than 500
because you don't get what you want, doesn't mean you won't get publications and he has given over 2,000 professional presenta-
all you need. tions. He can be contacted through his web site at:
For a business to be successful, leaders and team members www.BartonGoldsmith.com or at (818) 879-9996. ◆
need to learn how to engage in this beneficial behavior. And it's
not as hard as you might think.
The first thing to remember is that in a business deal, you
won't be comfortable unless the other company (or person) is
comfortable as well. For some reason, compromising can be HAVE YOU MOVED?
looked at as a loss, caving in or even being a doormat. The real Be sure to let AACE International Headquarters know your
truth is that if you have any of these sensations you are not really new address. You can update your information by contacting
compromising. For there to be a real meeting of the minds, both AACE International Headquarters at 800-858-COST,
people have to feel good about the end result. e-mailing info@aacei.org, or sending your information to:
Getting everything you want every time you want it is not
realistic. Those are the desires of a spoiled child, not an adult who AACE International, 209 Prairie Avenue, Suite 100,
wants to be in a successful business environment. Ask yourself Morgantown, WV, 26501.
something, if you get everything you want, and your client is feel-
ing like they got the fuzzy end of the lollipop (and not at all happy
about it), can you really see this deal being successful? Do you
think this client will be back for more?
To become willing to compromise you have to understand
that it benefits everyone involved. If you are truly business part-
ners then what is good for one should be good for the other. Try
looking at the big picture and do what you can to make it bal-
anced. The closer you come to equality, the more successful both
of you will be. If either one of you feel that the deal is unbal-
anced, then something isn't working properly.
Once you've agreed to a set of ground rules for your business
relationship, if one of you decides to make drastic changes, for
example you or your client want to change the financial terms, it
can make future negotiations difficult. Before you do anything
that changes the foundation of your agreements, you need to talk
with your client or team mate and closely examine how this deci-
sion will change things.
Most compromise issues are far less drastic than this, but the
process for achieving a balanced situation is the same. Talk,
examine and take some time to see how the changes will effect
everyone involved. Getting the best terms possible is an appropri-
ate business decision. However, if this is a new direction, you
need your client to be willing to compromise and make the
changes necessary so that both of you can feel comfortable and
safe.
Compromise is an art form that successful leaders have mas-
tered. The key is understanding that you're not giving up or giv-
ing in—you're just seeking balance.

Cost Engineering Vol. 47/No. 5 MAY 2005 13


T ECHNICAL A RTICLE
The perceived disadvantages of
Design/Build include the following.
Design/Build Selection Process — • the owner needs to hire a third party to
Art or Science? •
watch for his/her interests;
substitution of lower quality material
and equipment;
• the owner must give up control over
Talal Abi-Karam, PE CCE
the process; and
ABSTRACT: The Design/Build method is an innovative project delivery system that is revolu- • the owner must have a clear design
tionizing the delivery of private and public works projects. Advantages include a reduced proj- criteria package (DCP).
ect delivery time, costs, and reduced claims. The selection of a Design/Builder in the public
works sector is a complex process that has required a number of US states to modify their pro- Design/Build is not a new project
curement laws, state statutes, and licensing laws. Although Design/Build is one of the most pop- delivery method. The Design/Build
ular integrated alternative delivery methods, it does not have well-established contractor selec- method (i.e., turnkey, performance
tion procedures. The selection of a Design/Builder can be based solely on qualification, solely
contracts, etc.) has been used for delivering
on price, or a combination of price/qualification. Even with qualification-based selection
(QBS), the selection process may be subjective, since various state agencies (DOT's) and domestic (pulp and paper, industrial,
municipalities have different selection criteria for pre-qualifying and evaluating bids of the per- hydroelectric) and international projects
ceptive Design/Build teams. This article examines the various selection methods of around the world for the last 50 years [2].
Design/Build teams in the public works sector. It addresses the legal framework for selecting Design/Build allows the owner to
Design/Build teams, including qualification-based selection (QBS), selection criteria, and acquire goods and services with a single-
weighting of criteria. source of responsibility and a single-source
of accountability. Despite popular
KEY WORDS: Bidding, cost, Design/Build, fixed budget, and project delivery systems misconceptions, Design/Build does not
eliminate risk and claims. In fact, one
he delivery method of the majority New delivery methods will require could still advance the same types of

T of public works projects has been


the traditional hard bid method.
While this method results in the lowest
new procurement processes to properly
allocate risks and to provide public owners
with value and quality of goods and
claims, whether using the AIA, EJCDC,
FAR, or DBIA model contract documents.
Owners switching to the Design/Build
price for the construction of a project, it services. The transition to a new method must examine their procurement
also carries a high degree of risk. procurement process will require a laws, state statutes, and licensing laws to
In the hard bid process, the owner is fundamental change and modifications to ensure that they can legally engage in
faced with the risk that the low bid is not current legislation, procurements laws, US Design/Build.
within the budget allocated, and may hire state statutes, and licensing laws at the US
an unknown contractor whose goals and federal, state, and local levels. DESIGN/BUILD
interests are in direct conflict with the LEGAL ENVIRONMENT
owner’s interests. THE DESIGN/BUILD METHOD
Trends in the 1990s showed a sharp The Design/Build method is an The rapid increase in the use of
increase in the volume of litigation in integrated, project delivery technique Design/Build is fueled by the passage of
public works construction. This increase whereby an owner contracts directly with a key legislation at the US federal and state
was primarily because of an increase in the single entity (Design/Builder) to deliver the levels that allow public owners to legally
volume of construction put in place, while project (see figure 1). engage in Design/Build.
using the competitive bidding method [1]. Advantages of Design/Build, as listed
Stiff competition caused contractors to by W. Friedman, include the following
cut their margins to gets jobs, and forced [6].
them to seek claims to make up profits.
The increase in claims led all parties to • the selection is based on qualification,
seek alternative delivery methods. and definitive performance criteria;
Public works owners were searching • the contractor is involved early in the
for alternative project delivery methods to design phase;
reduce the risk of project overruns and • allows for reduction in the design, and
prolonged litigation. The Design/Build construction phases;
project delivery method has emerged as the • allows for a single source of
most attractive alternative. responsibility; and
Moving into the new millennium, the • eliminates the adversarial relationship
engineering and construction community between contractors, owners, and
recognized the limitations of the engineers.
procurement process that supports the
traditional design-bid-build method.
Figure 1— Design Builder

14 Cost Engineering Vol. 47/No. 5 MAY 2005


The successful passage of this sector, and changed past practices, giving While the private sector has the option
legislation is primarily because of an municipality's legal authority to award jobs to negotiate directly with a single
aggressive lobbying, marketing, and based on qualification criteria rather than participant, the public sector typically
educational campaign by the Design Build low price. requires a competitive selection process.
Institute of America (DBIA). The selection of a Design/Builder can
The Institute was founded in 1993, Transportation Equity Act (TEA-21) - be solely based on qualifications, solely on
with the purpose of influencing US federal 1998, 2003 price, or on a combination of price and
and state licensing laws to facilitate the use A final rule, published Dec. 10, 2003, qualifications [7]. Many public works
of Design/Build. allows but does not require, Design/Build agencies are using forms of competitive
The following are key milestones and to be used on projects valued at $50 selection that fall between qualification-
events that helped the use of Design/Build millions or more (23CFR, Part 636). based and a low-bid selection. This is
in the public works sector. The new rule permits state and local accomplished through the use of
agencies to take full advantages of the prequalification and complex bid
Brooks Act - 1972 Design/Build method. This final rule was evaluation system.
In 1972 the Brooks Act required the effective Jan. 9, 2003. The rule was Although bid evaluation systems are
segregation of design and construction for required under the provision of the fairly standardized, objective scoring of the
public works projects (40 U.C.S. Section Transportation Equity Act for the 21st proposals varies from agency to agency.
541). This act essentially limited the Century (TEA-21), which allowed states to Since scoring involves human effort,
delivery options of publicly funded projects use Design/Build on an experimental objectivity may not be fully achieved.
to the competitive bidding method (lowest basis. Section 1307(c) of the TEA-21 Act, Most selection processes for a public-sector
price). One consequence of this is that US enacted June 9, 1998, allowed Design/Builder involves prequalification.
federal and state agencies alike were forced Design/Build on an experimental basis. Prequalification serves to shorten the list of
to assume direct responsibility for the prospective bidders, and to increase
planning, designing, maintaining and SELECTION OF A competition among the providers.
operating of infrastructure projects. DESIGN-BUILDER Prequalification also streamlines the
selection process, helps agencies manage
Federal Acquisition Reform Act (FARA) - Public works owners and municipal the selection process, and helps to reduce
1996 managers are entrusted with public funds. the amount of stipends paid to prospective
The Federal Acquisition Reform Act They are consistently challenged to put bidders. The following are the three
was promugulated in 1996, giving US public dollars to their maximum use. At primary methods of Design/Build
federal agencies the legal authority to the same time, public owners are looking procurement [7].
engage in Design/Build. for more quality and value in the goods and
In 1997, the Civilian Agency services they acquire. • the one-step method;
Acquisition Council and the Defense Value is created by finding the best • the two-step method; and
Regulation Council agreed on a final rule combination of cost, quality and schedule. • qualification-based Design/Build.
to amend the US federal acquisition It is believed that alternative project
regulation (FAR) to implement two-step delivery methods, including Design/Build, The one-step and the two-step
procedures for Design/Build contracting. are the frontier where value is created and methods are procedures that fit into the
With the implementation of the maximized. larger category of best value selection. Best
amendment to (FAR) and the FARA of Competition affords public value procurement is one that is structured
1996, Design/Build has become a accountability and protects the public from to consider price and other relevant factors
prevalent method for US federal exuberance. Public owners who elect to in making the bid selection to provide the
contracting. use alternative project delivery methods owner the greatest value for the money.
must ensure that the method chosen is The one-step and the two-step
Florida Law: Qualification-Based properly and fairly used to serve the public methods are also considered to be
Selection (QSB) - 1997 interest with quality, cost effectiveness, and competitive selection methods.
A Florida law that took effect in Oct., timely delivery of goods and services. Qualification-based selection is purely
1997, (FS 287.055 sec 10 (c)) provides an Whatever methods used, the selection based on the qualification of the
alternative to the competitive bidding process for Design/Build services must be respondents. It is typically used when
process and could greatly reduce the time consistent, open, competitive, and most there are limited numbers of qualified
needed to select a Design/Build team. importantly legal. bidders, or when a government agency is
Under this law, most public agencies not regulated by the FARA (US Postal
in the state of Florida can use qualification- Selection Methods Services, some state agencies).
based selection (QBS) when awarding The traditional design-bid-build Since price is not part of the
Design/Build projects. method uses the fixed-price, sealed-bid evaluation, most public procurement laws
The FARA of 1996, reinforced by system, as required by the Brooks Act. prohibit this form of selection, and it is
(QBS) in Florida, has opened the door for Price is the only consideration, and mostly used in the private sector.
the formal and legal acceptance of the projects are awarded to the lowest bidder. Qualification-based method fits into the
Design/Build method in the public works category of negotiated selection [4].

Cost Engineering Vol. 47/No. 5 MAY 2005 15


Figure 1— The One Step Method

Regardless of the method used, the • the technical proposal is then scored; In scoring the technical proposals, the
cost of preparing proposals by a • scores below a pre-determined selection committee may assign a weight
Design/Builder can be very significant. threshold are deemed non-responsive; factor for each of the criteria. The
Some proposals are comprehensive and • scores above the threshold are deemed following table is an example of a
include detailed designs, construction responsive; selection/evaluation scenario with weight
sequences, baseline schedules (CPM), cost • price envelops for the responsive factors.
estimates, material selection, process bidders only are opened; and Scores for criteria 1-5 are compiled
equipment, and prices. • the committee selects the lowest (including the weight factor). Compiled
The cost of preparing proposals could bidder. scores above the threshold (responsive
amount to 2-5 percent of the overall project bidders) are only considered. Then, the
costs, and will require resources, technical The selection committee may include price envelops for the responsive bidders
expertise, and commitment from vendors members from across the owner's only are opened, and the cost envelop of
and subcontractors. Some transportation organization such as, engineering, those bidders who do not score a
agencies, such as the Florida Department purchasing, legal, operation and predetermined number will not be opened.
of Transportation (FDOT), have maintenance (O&M). The committee At this stage, the agency can simply
recognized this burden, and allow for a may include voting members and non- select the lowest price proposal of the
stipend to be paid to perspective bidders. voting members. responsive bidders and award the project.
However, this stipend is fixed and often Non-voting members may be Some agencies compile a composite price
limited to the direct labor hours spent on technology advisors or average citizens score that takes into account the score from
the proposal, and does not include any from the district, whose presence is to the technical evaluation and the score from
allowance for overhead, expenses and ensure that the process is competitive and the price evaluation and awards the project
profits. working as required. The selection to the bidder with the lowest composite
committee evaluates and scores the price.
THE ONE-STEP METHOD technical proposal on a wide range of Other agencies have used an index
The one-step procedure (single stage criteria, including the following. value which is equal to the ratio of the
contractor selection) involves the
evaluation of the technical proposal in • innovations of designs and
addition to price at the same time (one construction;
package, see figure 2). • meet owner's needs;
This procedure will provide for • prior experience in this specific type of
competitive evolution of the technical projects; price score divided by the technical score
proposal with the contract award decision • management criteria such as, quality (see equation 1), and the project is awarded
based on best value to the agency for the control, supervision, and management to the Design/Builder with the lowest
combination of evaluated technical merit approach; and index.
and associated price, but not necessary to • project schedule (deliverables, CPM).
the lowest cost. The one-step method is
mainly used for simple Design/Build
projects. The evaluation process is
primarily a low-bid selection. This process Evaluation Criteria: Weight Factor (percent)
is recommended where the following 1. Understanding of the project 20 %
procedure is required. 2. Design and construction approach 10 %
3. Delivery of the work 10 %
Procedure
• owner issues an invitation for bids 4. Management of the services 10 %
(IFB); 5. Qualifications and experience of the team 10 %
• D/B teams submit a proposal Total 60 %
containing separate technical proposal
Compile Technical Score
and a price proposal at the same time
(separate envelopes); 6. Cost of the project 40 %
• the technical proposal is evaluated by Compile Price Score
the selection committee;
Table 1— Sample Selection/Evaluation Scenario

16 Cost Engineering Vol. 47/No. 5 MAY 2005


Figure 3 — The Two-Step Method

THE TWO-STEP METHOD Prequalification SELECTED EVALUATION


(COMPETITIVE SELECTION) The purpose of prequalification is to METHODS
The two-step method is the most evaluate the capabilities of interested firms, There are numerous bid evaluation
commonly used in the pubic sector. It in terms of financial assets, track records, methods. Some state agencies such as the
separates the price from the qualification equipment resources, and human FDOT have modified standard evaluation
process. The two-step method involves resources. methods to fits their specific needs. For
prequalification of firms through a request Since the efforts and cost involved in example, the value-of-time factor (VTF)
for qualification (RFQ), and then bid preparation are enormous, the number adjustment is based on the proposed
evaluation of the price and proposal [3]. of qualified, short-listed bidders is limited numbers of days to complete the project
First, technical proposals are received to three to five teams. This number of pre- (schedule) multiplied by a value per day
and qualified D/B teams are pre-qualified qualified bidders allows the agency to established by FDOT [8]. The value per
(short listed), next the qualified teams conduct comprehensive and detailed day is derived from the benefits that users
submit bids, and the award is based either analyses of the bidders to avoid any get by using a bridge or by having a bridge
on price or best value. subsequent failures and other risks. open that day. The following is a list of
The two-step method is used for large, Pre-qualifying more than five bidders selective evaluation methods [4].
highly complex projects, requiring only undermines the credibility of the • Weighted criteria, (assign a weight
firms with financial strength, experience, prequalification process, and discourages factor for each criteria);
and technical expertise to deliver the high quality proposals. • Adjusted low bid, (adjusted score
project. It limits the final competitors to Design/Build ASDB);
the most pre-qualified firms by examining Bid Evaluation • Equivalent design, low-bid, (design
their financial strength and organizational Normally, pre-qualified and short- changes and price amendment);
resources (see figure 3). listed bidders are asked to submit two • Fixed budget best design, (owner states
proposals, namely a technical proposal and the price in the RFP);
Procedure a price proposal. These two proposals are • Meeting criteria low bid, (low bid
• owner analyzes current and future evaluated separately. Design/Build, FDOT); and
facility requirements; Members of the technical evaluation • Emergency, (safety, national emergency).
• owner establishes the project, needs, team evaluate the technical proposal based
facility size, requirements and on approved criteria. Similarly, the Weighted Criteria
performances; financial evaluation team evaluates the After Design/Build teams are
• owner requests letter of interest (LOI); price proposal and allocates scores for the shortlisted, the owner issues a request for
• interested D/B teams submit letter of price bids. proposal (RFP). D/B teams submit their
interest (LOI); The technical and price scores are proposal which usually encompass a
• owner issues request for qualification then combined based on an approved qualification part and a price proposal.
(RFQ); proportion or by using a formula/equation Typically, qualification proposal
• D/B teams submit statement of to decide the best bids considering the best includes a management plan, firm
qualification (SOQ); value for the money. experience, and design solutions. A price
• owner pre-qualifies and short-lists 3-5 These formulas and equations are proposal includes the price for performing
finalists; often devised based on owner's specific the contract.
• owner conducts interviews and experience, or based on the opinions of Proposals are evaluated and scored.
presentations; and advisory teams. While these equations and Price may account for 40 percent, and
• owner selects a team and negotiates a formulas are standardized, they may not be qualification accounts for 60 percent, for a
contract. applicable to every situation, and may not total of 100 percent (refer to table 1). In
fit an agency's specific needs. evaluating a team's qualification, each

Cost Engineering Vol. 47/No. 5 MAY 2005 17


criterion is provided with a weight factor, lowest price proposal. The role of the meet with neighborhood associations,
based on its relevance or importance to the selected team is to complete the design listen to what they are looking for in the
owner. This weighting system ensures that established earlier in the DCP rather than project, and bring all stakeholders on
each criterion get its proper rating (score) to propose and provide innovation. board with the proposed solution.
based on its utility to the overall project. A Fixed Budget, Best Design This will ensure their support, and will
maximum price score is assigned to the As the title indicates, the owner help buy-in of the solution by the agency.
lowest price. Selection and award are then establishes a fixed budget for the project. This can be critical on a large bridge
made to the team with the highest Selection and initial prequalification steps crossing where adjacent property owners
combined score. are used in same manner as other methods. and homeowners associations are affected
Shortlisted teams submit their qualitative at both bridge approaches and by the
Adjusted Low Bid proposals which contain their design overall appearance and aesthetics of the
This method follows the process of concepts. The owner conducts oral bridge.
prequalification, short listing, RFP, and the presentations, evaluates qualitative There have been numerous studies
proposal. The qualitative proposals are (weighted) items, and scores the proposals. about the effect of the chosen method on
scored on a scale of 1 to 100 expressed in Award is based on the best qualitative project performances and potential costs
decimals (example a score of 80 is 0.80). score, and price is not a factor in the growth and cost overrun. K.R. Moolenaar,
Price envelops are opened and listed. selection. in 1999, studied the following performance
The adjusted price for a team is variables under the one and two-step
calculated by dividing the price score by Emergency method [7].
the qualitative score for an adjusted price This method is used in case of
(refer to equation 1). Award is made to the emergencies when public safety and • cost and time growth;
team with the lowest adjusted price. Please welfare are paramount. Examples of these • project quality;
note that lowest adjusted price is not the emergencies include floods, hurricanes, • conformity to expectation;
contract price for the project. acts of terrorism, and national security • administrative burden; and
matters. Under these circumstances, • owner satisfaction,
Equivalent Design, Low-Bid contracting agencies negotiate and award
This method is similar to the weighted Design/Build contracts with the best In general, the two-step method
criteria and adjusted low bid methods. All qualified team available at that time. resulted in better cost and time
the steps involved in prequalification, performance. Projects under this method
short-listing, RFP, and proposal are EFFECT of the were closer to the schedule and budget
followed. SELECTION METHOD better than under the one-step method and
Design proposals submitted by various under the purely qualification procedures.
teams are evaluated and critiqued by the There are many factors that that must The study also concluded that
owner. The owner returns the design be considered when choosing the qualification-based selection has a
comments and provides a deadline for all appropriate selection method. Owners substantially lower administrative burden
participants to respond with specific design must be aware of their capabilities and cost than both the one-step and the two-
changes and any applicable limitations during the request for proposal steps method. Obviously, the two-step
changes/amendment to the price proposal (RFP) stage, and how much information is method requires more time and resources
submitted earlier. provided in the design criteria packages to analyze and rank the proposals.
The owner evaluates the revised (DCP). The question of value is always
designs and revised price proposals. The Under the one-step method, simple present. Will the owner get more value for
award is then made based on both the new projects may be developed up to 50 the money under the one-step, two-step, or
price and original price. This method percent design completion. On the other the qualification-based method? The
allows the owner to customize design hand, under the two-step method, a design answer to this question is not simple since
concepts, to create equivalent designs, and criteria package may be developed up to there are many measured benefits, as well
make the award based on the lowest price. the 20 percent or 30 percent level. The as non-tangible negatives in the process.
higher the design level in the DCP, the How do you measure value? Will the
Meeting Criteria, Low-Bid lower are the innovations in the proposed measure be objective?
The essence of this method is to list solutions. Regardless of the method chosen to
stringent, definitive criteria in the design Another factor to consider is the time select a Design/Builder, public owners will
criteria package (DCP). The RFP and and resources required for evaluating all of be involved in negotiations. This represent
design criteria will outline very specific the proposals (technical and financial). An a dramatic shift since public owners tends
performances and designs concepts that element of public-sector Design/Build to avoid negotiations because of the
must be followed. There is little or no selection is the public (stakeholders). following.
creativity allowed in the process. While the process is mostly controlled
D/B teams submit their proposal based by the agency, the proposed selection • it appears to contradict the philosophy
on the criteria listed. Since the playing method and solution will daily affect many of open competition;
fields are made equal among participants stakeholders and users. A Design/Build
the selection and award is made to the team should take the time to visit the site,

18 Cost Engineering Vol. 47/No. 5 MAY 2005


• it is very difficult to maintain seeking to use the Design/Build must (Qualification Based Selection, QBS),
confidentiality during negotiations evaluate their procurement laws, state (Oct. 1997).
and most importantly; and statutes, and licensing laws to ensure that 6. Friedman, W. Construction
• public owners and utility managers are they can legally engage in design/ build. ◆ Marketing and Strategic Planning,
answerable to the public and their McGraw-Hill, Inc., New York, NY.
governing bodies to justify the REFERENCES (1984): 172-173.
selection and evaluation methods used 1. Abi-Karam, T. Project Delivery Trends 7. Molernaar, K.R., A.D. Songer, and M.
in the process. in the Water and Wastewater Market, Barash, Public Sector Design/Build
Proceedings of the Water Evolution and Performance, ASCE
esign/Build procurement Environment Federation, WEFTEC Journal of Management in

D provides opportunities
integration, innovation, and
efficient delivery of projects. While the
for 2003, 76th Technical Exhibition and
Conference, Los Angeles Calif.
Published by WEF, 601 Wythe Street, 8.
Engineering,
(March/April 1999).
Palaneeswarn,
ASCE

E., M.
15(2),

M.
Design/Build process is becoming more Va., 22314. (Oct. 11-15, 2003). Kumaraswamy, and P.W.M. Tam,
popular, the selection of a Design/Builder 2. Abi-Karam, T., (1999). Design/Build- Comparing Approaches to Contractor
remains a mysterious process. Is it an art? The Professional Services Race," Selection for Design/Build Projects,
Is it a science? Or is it a combination of Proceedings of 43rd Annual Meeting Proceeding, Joint Triennial
both? of AACE International, Denver, Co., Symposium on Customer Satisfaction:
There are many standard models for editor: Marvin Gelhausen, AACE A Focus for Research and Practice, P.
selecting a successful Design/Builder in International, Morgantown, WV, Bowen and R. Hindle, Eds, Vol 3,
the public works sector. The one-step (June 1999). (1999): 936-945.
method, the two-step method, and the 3. Design/Build Institute of America,
qualification-based method are all The Design/Build Process— ABOUT THE AUTHOR
established procedures in the marketplace. Utilizing Competitive Selection. A Talal Abi-Karam,PE CCE, is an
These methods focus on pre-qualifying of publication by the Design/Build associate with Hazen & Sawyer, PC, 4000
bidders and evaluating bids that provide Institute of America (DBIA), Hollywood, Blvd., Suite 750 North,
the best combination of costs and value for Washington, D,C. (DBIA 2003, a). Hollywood, Fla., 33021. He can be
the owner. 4. Design/Build Institute of America, contacted by sending e-mail to: tabi-
There are several standardized The Design/Build Process— karam@hazenandsawyer.com,
published evaluation techniques in the Utilizing Negotiated Selection. A
market. These statistical techniques publication by the Design/Build Technical Articles - Each month, Cost
involve formulae and equations that strive Institute of America (DBIA), Engineering journal publishes one or more peer-
to systematically search for best value. Washington, D.C. (DBIA 2003, b). reviewed technical articles. These articles go
through a blind peer review evaluation prior to
Also, the composition of the selection 5. Florida State Statutes, (1997). FS
publication. Experts in the subject area judge the
committee, the hidden agenda of its 287.055 Sec. 10 (c). Applicability to technical accuracy of the articles. They advise the
members, and the subjectivity of Design/Build Contract. authors on the strengths and weaknesses of their
participants, may taint the results. Owners submissions and what changes can be made to
improve the article.

AACE International’s Chicago Midwest Section’s


ANNUAL SEMINAR
Friday May 20, 2005
Birmingham, Alabama
“CHAMPIONS of PROJECT CONTROLS — 2nd Edition”

INFORMATION:
Don Giegerich
E-mail: don_giegerich@URSCorp.com

Cost Engineering Vol. 47/No. 5 MAY 2005 19


T ECHNICAL A RTICLE
• Organizational planning—identify,
document and assign project roles,
Using Earned Value Management responsibilities, and the reporting
relationships.
Indexes as Team Development • Staff acquisition—make the required
human resources be designed and

Factor and a Compensation Tool •


work in the project.
Team development—develop
individual and group skills to increase
Ricardo Viana Vargas project performance.
ABSTRACT: The objective of this article is to present the main components of the development
of a project team and the motivational characteristics inherent to team work. It also looks at an Figure 1 provides an overview of the
interrelation proposal between the earned value analysis and team development through the processes according to each project phase.
SPI and CPI indexes. These are obtained by tool use and team development models and the These processes interact with each other
compensation and reward in the project. This reduces the subjectiveness of humans resource in and with the process in the other
the project evaluation. The article presents a brief report about team development and com- knowledge areas. Each process may involve
pensation policies, as well as an introduction to the earned value concept, aiming to align the effort from one or more individuals, or
approached concepts. groups, depending on the needs of the
project.
KEY WORDS: Analysis, earned value management, human resources, and projects
Team development, as outlined in this
article, involves an increase of the
he project human resources area is the processes required to make the most

T
capability of the involved parties to
one of the PMBOK Guide 2000 effective use of the human resources contribute individually, as well as an
knowledge areas that managers and involved with the project. It includes all increase of people capable of working as a
project teams have requested be given project stakeholders: sponsors, customers, team. Individual growth (managerial and
more attention [6]. individual contributors and others. The technical) is the basis required to develop
As reported in the Guide, human main processes include the following. the team. This becomes crucial to the
resources project management includes

Figure 1— Human Resources Management Processes Distributed Throughout the Project Phases.

Figure 2— Performance Change Factors

20 Cost Engineering Vol. 47/No. 5 MAY 2005


Figure 3— Reward Policies and Bonuses (G. Parker, J. McAdams and D. Zielinski, [5])

success of projects and becomes a key for Equity Theory, people get motivated when
the organization to accomplish its goals. they are treated in an equitable, impartial,
According to J. Fitz-Enz, each and fair way [8].
organization and each project is led by a
combination of strengths and internal and Professional Compensation (Reward)
external factors. These factors are the ones Some of the main tools available to
that make the organization unique, increase performance are compensation
describing collectively how and why the and reward policies. These, according to
organizational processes PMI, are the formal actions that promote
influence
performance improvement. The internal or reinforce desired behavior [6]. To be
factors are the ones determined by an effective, such a system should make the
link between performance and reward
organization and its project goals, while the
clear, explicit, and achievable.
external objectives are those determined by
the external business environment in According to G. Parker, J. McAdams
which the company and projects are and D. Zielinski, the reward models are
inserted (See figure 2). designed to create a focus on specific goals Figure 4— Team and Individual Performance
According to S.W. Flanes and Ginger or to celebrate and reward individuals or Extent (Based on Shuster, [7])
Levin, performance problems that impede teams with diversified performance. To
be earned initially by an activity is the value
the team members to perform their them, the reward models should meet
budgeted for it. As each activity or task of a
individual, team and organization needs
activities successfully can be divided into
project is performed, the initial budgeted
the following. [5]. See the model shown in figure 3.
value for the activity starts to constitute the
H.D. Shuster, said the bonuses always
earned value of the project.
• problems related to technical need to satisfy the individual and the team.
These concepts are based upon a 1997
competency; If team satisfaction is neglected to satisfy an
Earned Value Implementation Guide
• problems related to relationship and isolated individual, this process naturally
from the US Department of Defense
communication; and generates dissatisfaction and demotivation.
(DOD )[1] and on norm ANSI/EIA 748 of
• problems related to time management A higher reward can only be achieved
the American National Standards Institute.
and work habits [3]. when high team and individual
To formalize the concepts, a specific
performances are achieved, (see figure 4).
terminology was created. It is based on
Because of these problems, it is
forecasted and actual costs, as well as
fundamental to have an impartial and Earned Value Analysis
earned value. The basic three elements of
objective performance evaluation process Earned value is focused on the
the earned value analysis include the
that besides addressing the mentioned relationship between incurred actual cots
following.
problems, allows improvements in and the work performed on the project in a
individual skills, team behavior, and given time period. The focus is on
• BCWS (Budget cost of work
individual and team competencies. performance obtained in comparison to
scheduled)—is the value that indicates
This impartial model directly reduces what was spent to get it. [4]
the budget portion that should be
the subjectiveness of performance Earned value is the evaluation
spent, taking into account the activity
evaluation and increases the team between what was actually spent and what
budget base line cost, allocation, or
motivation. According to the Adam's was budgeted, proposing that the value to
resource. BCWS is calculated as the

Cost Engineering Vol. 47/No. 5 MAY 2005 21


budget base line cost divided into
phases and cumulative up to the status
date, or current date. It is the budgeted
cost.
• BCWP (Budget cost of work
performed)—is the value that
indicates the budget portion that
should be spent, taking into account
the work performed up to the moment
and the budget base line cost for the
activity, allocation, or resource.
BCWP is also called earned value.
• ACWP (Actual cost of work
performed)—is the value that shows
actual costs incurred from the work
already performed by a resource or
task up to the status date or project
current date from financial inputs.

Once these three parameters are Figure 5— BCWS, BCWP, and ACWP Graphic Example Throughout the Time for a Given
Project
determined, the outcome analysis is
obtained based on the correlation between earned values in the same period, (See index, while at the end of project occurs an
values found for each one in a given status equation 2). inversion in the participation of indexes,
date, (See figure 5). once the SPI tends to 1 (BCWP ? BCWS)
The correlation among BCWS, with the termination of the project.
BCWP, and ACWP values allows one to The resulting formula is shown in
rate project outcomes and to proceed with equation 3.
evaluations and future final cost forecasts.
To treat the ratio among BCWP and A CPI that equals 1, indicates that the HPI =%c x CPI + (1-%c) x SPI
BCWS and ACWP parameters, there are value spent by the project was completely (equation 3)
the following indexes. earned to the project (project in the
budget). A CPI lower than 1, indicates that Where CPI = Cost performance index
• SPI (Schedule Performance Index)— the project is spending more than SPI = Schedule performance index
Division between the earned value scheduled up to the moment. If the CPI is %C = Project complete physical percentage
(BCWP) and the budgeted base line cost higher than 1, this indicates that the
(BCWS). SPI shows the conversion rate of project is costing less than scheduled up to Figure 6 shows the participation of the
the budgeted value in the earned value, that moment. indexes in the HPI composition along the
(See equation 1). project.
Human Performance Index and From the creation of this index, it is
Professional Evaluation Models required to evaluate the HPI´s. This is for
In order to allow the team to do not only the individual work outcome, but
evaluation and for project professionalism, also the team work. It’s in the team work in
a new index, called human performance which the resource is an integral part of the
An SPI equal to 1, indicates that the index (HPI), was developed. This index project as a whole. Creating a final HPI
budgeted value was completely earned to consists of the relationship between the
the project. An SPI lower than 1, indicates CPI and SPI, allowing the creation of an
that the project is being performed at a index that evaluates the accomplishment of
conversion rate lower than scheduled. In the schedule and budget of the activities
other words, the financial amount executed by the resources simultaneously.
scheduled to be earned in the period was In developing this article, the author
not achieved and the project is late. An SPI studied several types of relationships
higher than 1, indicates that the project is between indexes (sum, average, product,
earning outcomes in a speed higher than etc.). However, because the nature of the
scheduled, i.e., it is advanced. two indexes differs from the complete
• CPI (Cost Performance Index)— percentage of the project, the composition
Division between the earned value of the indexes with complete percentages
(BCWP) and the actual cost and (ACWP). was chosen. The participation of schedule
CPI shows the conversion between the performance index in the beginning of the
actual values spent by the project and the project is higher than the cost performance Figure 6— Participation of the Indexes
According to Project Complete Percentage

22 Cost Engineering Vol. 47/No. 5 MAY 2005


that is the weighed average of these three
indexes as shown in equation 4.
HPIFinal can be obtained from
different strategies, starting from a strong
focus on individual outcomes up to a
balanced focus among the individual, team
and project. A model of weight Figure 7— Example of a Proposal of Weight Distribution for the HPI Resource Composition
composition for different focuses is shown
in figure 7.
It is important to emphasize that the
resource, team and project HPI´s are not
obtained from CPI and SPI´s work
packages, but from the sum of the BCWS,
BCWP and ACWP's resource activities
and later from the formula application,
CPI=BCWP/ACWP and SPI = BCWP (equation 4)
/BCWS.
Where: CPIIndividual = Cost performance index of the work packages where the
Example evaluated resource was involved
To illustrate index development, SPIIndividual = Scheduled performance index of the work packages where
consider a project composed of 20 different the evaluated resource was involved
work packages to be performed by five
resources in two teams. Resources 1, 2, and CPITeam = Cost performance index of the team work packages of which the
3 belong to Team A and the resources 4 evaluated resource is participant
and 5 to Team B, respectively. In figure 8, SPITeam = Schedule performance index of the team work packages of
a distribution of the resources in the work which the evaluated resource is participant
packages is shown. CPIProject = Cost performance index of the project
At a given time period, the project the
package performance inputs were SPIProject = Schedule performance index of the project
evaluated. The results are shown in figure WeightIndividual = Contribution of resource HPI in the HPIFinal
9, with BCWS, BCWP and ACWP inputs
for each work package. WeightTeam = Contribution of team HPI in the HPIFinal
From the crossing of each package WeightProject = Contribution of project HPI in the HPIFinal
with resources used in them, the HPI of
each one of the resources was obtained, as %C = Project complete physical percentage
well as the HPI of each one of the teams,

Figure 8— Resource Distribution to be Used in the Work Packages

Cost Engineering Vol. 47/No. 5 MAY 2005 23


and the total HPI of the project. This is the final HPI of each resource from the team outcome. An example of this is shown
shown in figure 10. individual, team, project focus, and the in figure 13.
Each resource belongs to a given team. balance focus among the three parameters. In this example, resources 1 and 3
However, the following individual results These results are shown in figure 12. showed a performance lower than their
are shown in figure 11. From these values, one can determine team and project; resource 2 showed a
If you combine the results of figure 11 the outcomes of each one of the resources higher individual performance. However,
with the ones of figure 7, you can obtain and its contribution for the project and in analyzing its team, its performance was

Figure 9— Example of Data Collected for a Project With Determined BCWS, BCWP, and ACWP

Figure 10— Project and Resource HPI Outcomes

Figure 11— HPI Results of Each Resource

Figure 12— Resource HPI Final for Each One of the Profiles of the Analysis Focus

24 Cost Engineering Vol. 47/No. 5 MAY 2005


Figure 13— Comparative Graphic of the Focuses Among the Individual, Team, and Project for the Five Evaluated Resources

damaged by a weak performance of subjective human aspects inside the team 8. Verma, V. K. Human Resource Skills
resources 1 and 3. Resources 4 and 5 had work. ◆ for the Project Manager, Vol. 2.
high performance, increasing the Upper Darby: Project Management
performance of Team B. The project REFERENCES Institute, (1995).
performance was lower than the 4 and 5 1. DOD Earned Value Management
resources performance and Team B. This Implementation Guide. Washington: ABOUT THE AUTHOR
was because the members of Team A United States of America Department Ricardo Viana Vargas is a professor at
lowered the global performance by their of Defense, (1997). the Getulio Vargas Foundation in Brazil.
weak individual performances. 2. Fitz-Enz, J. The ROI of Human He is chair of the Grupo A&C in Brazil.
Capital: Measuring the Economic He can be contacted by sending e-mail to:
he main objective of this article was Value of Employee Performance. ricardo.vargas@uol.com.br or to: rvar-

T to present an evaluation of the


human resources and teams
through a more direct mathematical model
New York; AMACOM, (2000).
3. Flanes, S. W. and G. Levin, People
Skills for Project Managers. Vienna:
gas@aec.com.br.

Technical Articles - Each month, Cost


Engineering journal publishes one or more peer-
than the subjective evaluation by the Management Concepts, (2001). reviewed technical articles. These articles go
project manager. Besides, bonuses and 4. Fleming, Q. W. and J. M. Koppelman, through a blind peer review evaluation prior to
reward policies may be directly connected Earned Value Project Management, publication. Experts in the subject area judge the
to the indexes causing a more transparent 2nd Ed. Newton Square: Project technical accuracy of the articles. They advise the
authors on the strengths and weaknesses of their
mechanism of the distribution of project Management Institute, (1999). submissions and what changes can be made to
outcomes 5. Parker, G., J. McAdams, and D. improve the article.
However, some cautions have to be Zielinski, Rewarding Teams: Lesson
taken in using this kind of evaluation. First, from the Trenches. San Francisco:
when the executer is not responsible for Jossey-Bass, (2000). Did You Know?
overseeing the budget, he/she can have 6. PMI. A Guide to the Project All AACE International members who
his/her performance compromised by, as Management Body of Knowledge. attend the 49th Annual Meeting or
an example, weak performance of the Newton Square: Project Management Continuing Education Seminars will
procurement team. Secondly, this Institute, (2000). receive Continuing Education
mathematical model may not be 7. Shuster, H. D. Teaming for Quality: Credits/Professional Development Hours
deterministic, i.e., the only one to represent The Right Way for the Right Reason. for their attendance. Continuing
the truth of the work outcome of the Newton Square: Project Management Education Seminar credits slightly vary for
project resource. Once they are completely Institute, (2000). each course and are listed on AACE’s web-
mathematical, they may not evidence site. Attendees of the 3-day technical pro-
gram will receive 20 PDHs / 2.0 CEUs.

Cost Engineering Vol. 47/No. 5 MAY 2005 25


SSpecial Feature
pecial Feature
Jennie Amos, Manager Marketing and Meetings

Earned Value Professional Certification on Track


for New Orleans Premier
ACE International's certification programs have been operat-

A ing since 1976, and offer applicants who meet the eligibility
requirements the ability to successfully take a text and attain
certification through the Association. The Certified Cost Consultant
(CCC)/Certified Cost Engineer (CCE) programs are accredited by
the Council of Engineering Specialty Board (CESB) and the
International Cost Engineering Council (ICEC). In 2000, AACE
developed an interim certification program, Interim Cost
Consultants (ICC). The ICC certification program is accredited by
ICEC. In 2004, AACE began offering its first specialty certification,
Planning & Scheduling Professional (PSP) which has been met with
great interest.
With the first official examination scheduled for the Annual
Meeting in New Orleans, AACE International is gearing up to offer
its second specialty certification, Earned Value Professional (EVP).
Jennie Amos, Manager, Marketing and Meetings, repre-
senting the Cost Engineering journal, recently talked with Nick L.
Kellar, CCC, and Jonathan P. (Jon) Mihalic, CCC, Chair and Co- Earned Value Professional (EVP) Task Force Committee Members
Chair, respectively, of the Earned Value Professional task force to dis- (pictured from left to right, top to bottom)
cuss the process in which the task force has undergone to create the • Nicholas L. Kellar, CCC (Chair); Alyeska Pipeline Service Co.;
newest certification program. • Jonathan P. Mihalic, CCC (Co-Chair); Booz Allen Hamilton;
• Donald J. Cass, CCE, The Cass Group;
CE journal: This is a major undertaking—creating a valid certifica- • Ann Marie Cox, ARES Corporation;
tion program from the ground up. Tell us about the overall process • Dan J. Demangos, PSP; Booz Allen Hamilton;
for creating the EVP certification. • Michael B. Fisher, CCC; Parametrix, Inc.;
• Tia Okwesa; Booz Allen Hamilton;
Kellar: Our process followed a time line of creating a competency • Ruthanne Schulte, Welcom; and
model, writing and documenting each component of the competen- • Cheryl Johnson (not pictured); Booz Allen Hamilton.
cy model, and then writing a complete outline for each component
that described—a definition, how it is applied, what a professional
should know about the topic, what areas of competency that a candi- ment, large and small companies in most every type of business sec-
date must demonstrate specific knowledge, and finally, a matrix to tors [IT, consulting, research, oil and gas, construction, manufactur-
which questions in the database are tied to the topic. ing, etc.] we often found that we had different views on most topics.
This diversity, though, really became our strength and the key to a
CE journal: Can you expand on the actual creation of the exam? well developed exam that was not industry specific.
Probably the most challenging issue that the task force had
Kellar: Sure. After the competency model, we started question to over come was the structure of the competency model itself. In its
development. Then we compared questions to the competency early stages, the model followed AACE international's earlier out-
model to identify areas where more questions were needed. After the lines of project management components. The task force really strug-
initial questions were developed, we finalized the format of the exam gled with the first model and approach because we all knew that the
to coincide with AACE International's other certification exam struc- model would have to be one that was universally accepted. After
tures (a 4-part exam, each part lasting 1 hour, 45 minutes for a total much debate, a decision was made to follow the ANSI standard (748)
of a 7 hour exam.) for earned value. Once this decision was made, we knew we were on
the right track for this certification.
CE journal: So everything went smoothly with the task force in the
creation of the exam? CE journal: You held a beta exam, right? Can you explain how this
Kellar: When ever you bring together a group with this much talent helped the overall process in creating the EVP exam?
and experience, your going have a few exciting times. But I think that
the thing that impressed me the most was the professionalism and a Kellar: We didn't hold a beta exam—we held beta one in four dif-
commitment that this task force maintained toward the earned value ferent locations on the weekend of March 5, with a total of 20 par-
project and the goals that AACE International has for this certifica- ticipants. Beta one used a lot of open ended questions to have the
tion. Because the backgrounds of the task force ranged from govern- beta testers write their answers and rational. After Beta one, we

26 Cost Engineering Vol. 47/No. 5 MAY 2005


revised the exam with information supplied during that test to create
Beta two. Beta two was scheduled for the weekend of April 9, in CE: Aside from the difference in ages and work-related back-
eight different locations with a total of 84 participants. We wanted a grounds, what helped make the Task Force member's diversity so
large number of beta testers to really see how the exam applied to dif- vital to the overall experience?
ferent levels of experiences, industries, backgrounds, and education.
Mihalic: Each individual approached the task with their own idea on
CE journal: The EVP Task Force was comprised of nine profes- what it should look like and what it should be used for. Some want-
sionals in the field, how did you get everyone together on the same ed a certification that can help them find skilled earned value pro-
page to undergo this very considerable task of creating a specialty cer- fessional for hiring; others just want earned value to have a great
tification program? meaning in the project management world. These varying
approaches provide the opportunity to mode a professional certifica-
Kellar: Our meeting approach was to conduct weekly Thursday tion that met most, if not all needs.
meetings where we followed an agenda review of our schedule and
priority tasks. We only had one meeting face to face in Las Vegas in CE journal: And you'll be ready for June 25th in New Orleans?
January, but what happened in Vegas did not stay in Vegas. We
pushed on hard and had the first beta exam only five weeks after our Kellar: We'll be ready. We are on schedule to turn over this exam a
Vegas meeting and conducted our second beta four weeks later. We full three months ahead of schedule.
used technology effectively and had everyone on the task force using
the same software, and passed electronic data back and forth weekly. CE journal: Then what?

CE journal: So aside from the great distance and time zone issues Kellar: We'll finalize the exam after it is given in New Orleans, and
faced by the Task Force (Nick lives and works in Alaska, Jon in then turn it over to the Certification Board. ◆
McLean, Virginia, just outside of Washington, D.C.—other Task
Force members in California, Texas, and Washington) what were the
other differences in the make up of the Task Force.

Kellar: The composition of task force—Ages ranged from the 20's to


the 60's, and areas of expertise was also varied with government, com-
mercial, software developers, and many industries including IT,
manufacturing, operations, consulting, construction, and education.

Mihalic: The team members also include skill sets and experience
ranging for true implementer of EV systems to experts in analysis.

Cost Engineering Vol. 47/No. 5 MAY 2005 27


T ECHNICAL A RTICLE

The Goalposts for Project Success


Have Moved — A Marketing View
P.S. Kupakuwana and G.J.H. van der Berg

ABSTRACT: Traditionally, a successful project was seen as one in which the triad of time, budg-
et, and specification was complied with at a profit. Current project literature places more
emphasis on customer satisfaction as a fourth important success parameter. This article discuss- Figure 2— Contractual Relationships [3]
es project management services and focuses on what constitutes project success. This type of However, as far as project success is
project is named the new project in this article and a set of new project rules is arrived at. The
concerned, it is traditionally accepted that
article also takes a services marketing view and examines the customer's motivation in appoint-
ing a project manager. a project that is completed on time, on
budget, and to specifications is a success.
KEY WORDS: Customers, deliverables, financial, profit, project management, scope, and value Although true in the majority of instances,
if a more market-oriented view is taken, the
converse can, and should be, true as is
rofessional project management has

P become an industry of its own.


Many organizations buy the services
of project managers, especially where the
illustrated by:

• Project 1—Completed on time, on


budget and to specification, but the
needed technical expertise does not exist in
customer is not entirely happy.
the buyer's company or where temporary
• Project 2—Overspent the budget,
peaks exist in activities. Even professional Figure 1— Typical Management Structure [14]
exceeded the time frame, but the
engineers, architects, surveyors, and other Project management services are fairly customer is happy.
professionals really render project common in the South African market and
management services. typically are rendered by various This idea was summarized by Ruskin
companies to other companies. This has and Estes [12] who stated, "The single
R. Nobbs [1] argues that architects caused competition to increase and project
most important responsibility of the project
have, "always had to be schizophrenic" in managers have to differentiate themselves
manager is to ensure customer satisfaction.
that they have to act both as their in the market—currently mostly on an area
If the project is successful in every respect
employer's agent in supervising the works of specialization basis.
in terms of meeting its stated objectives,
and as an independent certifier. The increased competition in turn schedule, and budget, but the customer is
The Arbitration Act of 1950 ensured forces project managers to take a closer
somehow not satisfied, then the job was not
that the architect, "could not act as final look at their services for increased
done well enough . . ."
arbiter," because of doubts about his effectiveness and ways in which business
This statement, however, is not an
impartiality and relationship with the growth and profitability can be improved.
absolute rule. It applies in specific
employer. The concept of what constitutes a circumstances where the customer
However, Nobbs [10] adds, "Although successful project must also be closely
requires a result that is not well specified,
the 1950 act changed the law as far as an examined.
or it may be a function of the project
architect also acting as a final arbiter was The unique characteristics of project objectives being not well defined.
concerned, it did not affect the position in management services must be investigated
It is believed that the current
relation to an architect's independent and service characteristics must be kept in
overemphasis on project success as
certifying function." mind. For instance, when supplying the achieving time, budget, and quality targets,
A. Howarth [6] quotes another author service, the sale is concluded before the
is equivalent to the overemphasis on
as stating that the origins of project service is provided and in a sense the
production rather than market focus in a
managers date back to the decline of service provider works with a captive
manufacturing company.
architect's as leaders of building projects customer. It also is an ideal opportunity for
This article aims to arrive at a better
and the advent of the Labor government's relationship marketing as the contract
definition of project success, and to explain
private financing Initiatives (PFI), which normally is of a relatively long term and
the circumstances where the conventional
has seen increasingly complex joint performance during the contract will
success goal posts do not apply. It also aims
venture groups bidding for the design and determine whether work will be expanded
to provide a theoretical viewpoint to justify
build of a development. With so many and/or continued. The project team, who
the deviations from the more established
different companies involved on one job, all relate with the customer's personnel,
values, and it describes the new rules that
demand has risen for project managers should be targeted for internal marketing,
combine to form the project manager's
who can coordinate the work of everyone. as they in turn will influence the
new project environment.
(See figure 1). customer's perceptions of the project
organization.

28 Cost Engineering Vol. 47/No. 5 MAY 2005


LITERATURE REVIEW • constant and effective communication; environment and view their project as part
• a controlled project scope; and of the customer company's struggle for
Project Success Parameters • management support. competitive advantage, revenues, and
profit.
Project Success Jack R. Meredith and Samuel J. To complicate matters further, A.J.
There is a general trend in project Mantel recognizes the same three Shenhar, O. Levy and D. Dvir suggested
management literature toward greater traditional items for project success, but that the relative importance of project
customer focus and customer satisfaction. they state that the triple constraints of time, success dimensions change with time 13].
It is also believed that there is too much budget, and specification are rapidly being As in a relationship, different periods bring
emphasis on the traditional measures of replaced by a new model that invokes a different expectations. In the early stages,
project success i.e., the triad of on time, on fourth hurdle for project success: client internal dimensions (meeting schedule,
budget, and to specification (see figure 3). satisfaction [9]. budget, and specifications) are most
Rigorously sticking to these yardsticks can D. Baccarini distinguishes between important. Later in the project cycle,
in certain circumstances actively detract the components of project success as being external dimensions (customer needs and
from project success. the following. satisfaction) become more important. To
Eric Verzuh [15] defines a successful the project manager it has special
project as one in which the project • project management success; and significance as it is in the later stages of the
objectives were reached on time, on • product success. project that the customer decides on re-
budget, and with a product of high quality. appointment or an increase in the scope of
Quality in turn would be measured by Project management success focuses work.
functionality and performance. At the on the project process and the successful A.J. Shenhar, O. Levy and D. Dvir
same time, however, he stresses that a accomplishment of cost, time, and quality deal specifically with those projects that are
successful project must meet stakeholders' objectives. Product success in turn focuses perceived as successful by persons involved
expectations (see figure 4). on the effect of the project's final product in their implementation, yet are poorly
Verzuh [15] lists the five project [1]. It was noted that project managers received by their customers [13]. They
success factors as the following. largely interpreted successful projects as draw attention to the importance of
meeting the project management criteria viewpoints in defining project success and
• agreement among the project team, such as budget and schedule, whereas report that success can only be meaningful
the customer and management on customers interpret successful projects as if considered from the following two
project goals; those meeting product success criteria such vantage points.
• a project plan that shows the overall as response time and reliability. Project
path and clear responsibilities; managers therefore tend to focus more on • the degree to which the project's
short-term criteria relating to the project technical performance objective was
process, but customers focus more on the attained on time and within budget;
longer-term criteria relating to the project's and
product. • the contribution that the project made
If the project manager bears the to the strategic mission of the
customer's interest at heart, as he or she enterprise.
should, the manager must place traditional
project success indicators lower on the It was suggested to push the definition
importance scale than the customer's of project success even further by including
overall interest. The project must also the level of satisfaction of the following
appear successful from the customer's four different groups of stakeholders.
point of view.
Belout stated that a synonym for • the customer organization;
success is effectiveness, i.e., the degree of • the developing organization;
Figure 3— The Triangle of Project Objectives
achievement of objectives [2]. The • the project team; and
(adapted from Barnes and Wearne, 1993)
customer typically employs the project • the end-user.
manager as a tool to improve or optimize
his or her own profitability. That is the This viewpoint turns all of the project
customer's overriding objective and to be stakeholders into customers that must be
successful, the project manager should be satisfied.
effective in helping the customer achieve
his or her objectives. The Customer—Procurer of Project
The PMBOK Guide, by PMI, confirms Management Services
that all projects should be supportive of the The trend in project literature toward
performing organization's strategic goals. It greater customer satisfaction is clear. The
is therefore imperative for project project manager should therefore turn his
Figure 4— Primary and Secondary managers to understand the business or her focus toward the customer and their
Stakeholder Map [14]

Cost Engineering Vol. 47/No. 5 MAY 2005 29


needs. A project is not only about providing problems and may even involve an absent • profit from increased purchases;
an end product, but is also a service customer. • profit from reduced operating cost;
product in and of itself. The processes of In the case of an absent customer, the and
service delivery should be taken note of intermediary/consultant may become the • profit from price premium.
and service delivery best practices project manager's real customer. This of
integrated into project management. course changes all the rules as the We are therefore in a paradoxical area
In terms of the customer organization, intermediary may have his or her own set of —a project is short term by its very nature,
it was found that business managers see the goals (e.g., a long term appointment from but for real success a long-term view has to
success of their units as comprising the the customer), which may not necessarily be taken by both the project manager and
following four separate dimensions. include the end customer's best interest. In the customer.
this case, the incentive chain is deformed For the seller of the (project
• profitability level; and adapting solutions to real customer management) service, Lovelock states that
• level of sales and new orders; needs becomes difficult. creating a competitive position is vital for
• generating new opportunities for new success and identifies the following four
products and markets; and The Project as a Service Product principles to achieve this:
• preparing the scientific and The project management organization
technological infrastructure for the sells its services to the customer and only • the company (or project manager)
development and production of future after completing the sale is the service must establish a position in the minds
products. rendered. of its targeted customer;
Theodore Levitt relates the service • the position should be singular,
In order to be supportive of the provider/customer relationship to a providing one consistent message;
customer organization's objectives, project marriage, the sale consummates the • the position must set the company
managers must be aware of these four courtship and the marriage begins [7]. apart from its competitors; and
dimensions. The quality of the marriage is then • the company cannot be all things to all
In Transaction Cost Economics, based upon continued and expanded people; it must focus its efforts [8].
authors C. Berggren, J. Soderlund and C. business or there will be trouble and
Anderson investigates the boundaries of a divorce. In a project management
firm, for instance when an activity should In a marriage, what is good for one environment, the problem of demand and
be performed in-house or contracted out partner will also benefit the other and by capacity is a very real one and virtually the
[3]. working in his or her customer's interest, only certainty is that there will be periods
If a project is associated with a low the project manager will benefit himself in in which demand will exceed capacity and
frequency of purchase, if uncertainty and the long run. The customer procured the vice versa. Lovelock states that strategies for
degree of uniqueness is high, the preferred services of the project management managing demand must be developed and
way should be to obtain the service in the organization as a tool with which to he says that one of the most direct ways to
market, rather than the organization produce items to yield a profit. reduce excess costs is to charge customers
performing the work itself. The customer C. Berggren, J. Soderlund and C. more money during peak periods. An
therefore avoids risk by transferring project Anderson state, "the maxim about alternative also would be to change
execution to a professional project customers as kings assumes the customer product elements.
management organization, but typically has a long term interest in the service On the importance of technology,
pays a premium for this experience. delivery and that he or she is approachable Lovelock states that the real power of
During project execution the and negotiable" [3]. They warn that the technology is not in making old processes
customer may notice the price premium, same rules do not always apply. If it is work better, but rather in enabling
(he or she could do it less expensively on known that a once off transaction is entered organizations to break old rules and create
their own) but may forget the risk that they into, then the customer is king rule is not new ways of working.
are avoiding, especially if the project is necessarily true. To become an effective service
executed smoothly. This aspect must be Christopher H. Lovelock defines a provider, project management
accommodated and benefits achieved by valued relationship as one in which the organizations have to make full use of
the customer must be brought to his or her customer finds value because the benefits technology to inform and astound their
attention to ensure that a negative feeling received from the service significantly customers and apply new ways of
toward the project manager does not exceed the associated cost of obtaining it communicating and supplying information
develop. [8]. as it is developed.
C. Berggren, J. Soderlund and C. To a firm, a valued relationship is one The project environment provides an
Anderson discuss the problem found in that is financially profitable over time. ideal situation for relationship marketing
large engineering contracts where the Lovelock also states that in a healthy and with valuable relationships forming and
customer appoints various consultants, e.g., mutually profitable relationship, both internal marketing playing an important
for design, for project management, and parties have an incentive to ensure that it role to all the project team members.
even as financial controllers/advisors [3]. extends for many years.
Such instances create unique management For the seller, the profit potential lies
mainly in the following three items.

30 Cost Engineering Vol. 47/No. 5 MAY 2005


Proposed Project Success Yardsticks THE NEW PROJECT AND execute the customer's wishes to the letter
There is no getting around it—for the SUCCESSFUL PROJECTS and thus become exactly the tool he or she
new project, the customer will play a most requested, or is it better to follow his or her
important role. Project Success—A Services and intent and deviate from the letter of the
The traditional three project success Relationship Marketing View instruction?
parameters of on time, in budget, and to From a services and marketing Traditionally, it was seen that intent or
specification will not disappear, but they viewpoint the project can only be a success strategic factors fell outside the scope of the
will be relegated to a secondary position if the customer is happy. By executing the project team—the team should function
behind customer satisfaction. Faultless project correctly with aspects such as on purely in an executing mode and leave
project execution will always remain time, on budget, to specification, etc., interpretation or strategy to a more senior
important but long-term customer chances are greatly increased for customer level of management. So the question is—
satisfaction will be the main target. satisfaction although it is not guaranteed. should the project management team act
Long-term customer satisfaction, Other non-product related factors that will as a dumb tool and purely execute, or
however, cannot be measured in the short ensure customer satisfaction include, but should a more intelligent route be followed
term and a degree of faith in the project are not limited to, the following. where the customer's intention is
outcome will have to be involved. interpreted and anticipated?
In the mean time, the project may run • good relations between the customer The "intelligent tool" option is
behind schedule and over budget and be and project management personnel; definitely more risky, but also is the one
unsuccessful by all the old yardsticks. This • providing a service that meets or with the most potential benefits. It is most
will have to be compensated for by exceeds the customer's expectations likely the only way in which the customer
introducing all possible excellent service even in areas not falling within the can get more than asked for, which is the
delivery tools available to the project project's objectives; way to provide a successful service—by
group. It will require greater leadership • professional appearance of the project astounding the customer and giving him
from the project manager to form a vision managers staff—prompt response to more than expected.
of the project outcome and marketing skills crises, good presentations, factual
as he or she will have to sell the idea of, information supply; The Tables are Turned—When the
"what can be" to the customer rather than, • the project organization's image of Conventional Rules Do Not Apply
"what is." Communication at all levels will success; In smaller projects with an easily
have to be excellent with internal • taking the customer with or through definable scope, e.g., install 20 lampposts
marketing required to get the project team the process (i.e., keeping him or her for the local municipality, the traditional
to believe in the vision. informed, and making the customer success parameters of on time, on-budget,
Financial factors also play an understand the logic behind and to specification certainly still apply.
important role. In general it can be said decisions); Unnecessary time and effort should not be
from a financial perspective that the project • making the customer’s life easy (for expended in trying to second-guess the
is a success if; instance if motivations have to be done customer (whose project control
for additional funds—provide the representative may in any case not hold a
• the customer gets a profitable result customer with all the required backup strategic view).
from the project (if not in the short information); and However, for instance if the project
term, at least measurable in some • professional reports and presentations concerns a multi-million de-bottlenecking
financial terms e.g., internal rate of (a good professional report leaves a of a large chemical plant, the new project
return method (IRR) or some capital positive image even if the project is not rules should apply. If the customer's scope
expenditure valuation technique); and that well executed—the customer specifically requires f a 50 percent increase
• to the project manager the project forms an impression from the report in throughput (in a minimum time and at
must have been profitable to execute. that is in front of him or her). a minimum cost) opportunities abound for
new project rules. The customer will
Note that in many of the above, certainly give friendly consideration to any
communication plays an important role project extensions that can decrease his or
whether verbal or written—the importance her maintenance cost, increase plant yield,
of good communication cannot be over decrease operating costs (utilities) or labor
emphasized. cost if the economic viability can be
proven. It is therefore vital that the project
The Role of the Project Manager as a manager understands the customer's
Tool to the Customer business—not only the technical or
As mentioned earlier, the end operational aspects, but also the financial
customer uses the project manager as a tool and business aspects.
to achieve his or her own objectives. This is The money value of time must be
a position where the distinction becomes taken into consideration. Depending on
blurry, especially where project objectives the project profitability it may be
are not clearly specified. Is it better to worthwhile to more than double the cost of
Figure 5— Components of Activity Cost [4]

Cost Engineering Vol. 47/No. 5 MAY 2005 31


the project if it can halve the execution customer and expect an immediate positive has shown that only a relatively small
time. In order to take this type of decision result. In the ideal situation, the customer percentage of customers complain even if
the business aspects must be clearly must believe it is his or her own idea that they are unhappy. If the project manager is
understood and a financial model rather will now be implemented. It is likely that perceived as an expert, the likelihood of
than the project manager's gut feel should the customer will have a deep-lying complaints diminishes even further,
determine the outcome. knowledge of his or her business and may Lovelock states [8]. Effective problem
On the negative side—beware of have the best ideas of how to solve any resolution techniques should then be
misbehaving customers. New project rules problems. The method of achieving good followed—e.g., act fast, admit mistakes,
assume a logical/rational customer who is results is not as important as the results and do not be defensive, show you
willing to participate in a win-win itself. understand the problem, clarify steps
transaction. The likelihood exists that a The customer wants value for his or needed to solve the problem, and keep the
powerful win-loose type customer is her money and net value equals perceived customer informed of progress.
encountered at which time it may be better benefits—perceived outlays. If the Negative critical incidents that are
to switch back to old project rules and to do customer is on the winning side, it would satisfactorily resolved have great potential
exactly as the customer asks. Such a be irrational not to proceed with the plan. for enhancing loyalty, as it demonstrates to
relationship may in any case not be worth But, the customer must have proof (even in the customer that the project manager
pursuing in the longer term. the form of projected figures) and he or she really cares about him or her.
must not spend too much effort in The receipt of complaints and
gathering the proof —it must be provided. corrections to the source, allows the
opportunity to make changes that can
The progress Meeting as a Critical really improve service delivery. Customer
Service Encounter complaints traditionally are invited at the
On most projects there are standard project close-out meeting. This meeting is
periodic progress meetings attended by the too late in the process for problems to be
customer and other professionals. The brought to light, as at this stage very little
customer’s perceptions of project success remedial action can be taken.
Figure 6— Time/Cost Approximation [3] will most likely be equally formed by what
is happening in practice and by Back to Project Management Principles
Achieving Customer Buy-in in the impressions formed in the meeting. The Does this mean that old project
Changed Rules hardware, or actual project performance, management principles can be discarded
The customer starts the project with a therefore only makes up approximately half and we must just do an excellent sales job?
pre-conceived idea of what it is he wants to of the service experience. The answer is a definite no. Indeed, the
achieve. This concept should ideally be By all service definitions, the project better the project is executed, the easier the
defined in the project objectives. In an meetings are critical service encounters, as sales job should be. The project manager
ideal world, the project team should the customer's perception of the service must make use of all the tools and
exactly execute these objectives. However, received will most likely largely be formed technology within his or her reach to
we do not live in an ideal world. there. Project performance is not always execute an excellent project by all project
To deviate from these objectives, the within the project manager's control (it success standards.
new plan will have to be sold to the may be dependent on the performance of The seed of project success is planted
customer. For such a sale to take place the subcontractors, weather, deliveries by in the planning phase. The old maxim of
customer will have to have a high degree of suppliers, etc.), but the execution of project an ounce of prevention is worth a pound of
trust in the project manager. Any change in meetings are definitely in his or her cure still applies and the following project
plans will have to be very well documented control. rules remain as valid as ever.
and technically and financially motivated.
The customer's project representative Care should however be taken not to • work is to be planned as thoroughly as
will have to sell the idea to his own senior do such a good sales job that the customer possible;
management. If he can start with a well is happy until he leaves the meeting, • think of every possible eventuality;
documented case, it will make his internal connects with the real world, and then feels • break the work down into as small
sales job that much easier. It would also be duped. The project manager's integrity tasks as possible;
better to have the transaction sold on a should not be doubted and he or she • schedule realistically;
number of different levels (each person in should not be selling leases to castles in the • plan not only for the work, but also the
the project organization to his customer sky. A professional presentation backed up staffing;
counterparts) as we know that in by hard facts and good motivations should • ensure that the right people are used
organizational buying, decisions are convince even difficult customers, and in the right positions;
influenced from many different levels. unrealistic expectations will not be • ensure that responsibilities are clearly
The more the customer's involvement encouraged. spelled out;
in the process, the better the chances are It is also at this type of meeting that • empower project personnel to go out
that he or she will buy into the idea. It is customer complaints would surface. and get the job done; and
not a good idea to spring the idea on the Complaints should be invited, as research

32 Cost Engineering Vol. 47/No. 5 MAY 2005


• do not forget about infrastructure Back to Marketing Principles pay for. This will negatively affect the
requirements for the project team— The marketing concept means that an project manager's profits;
make sure that their physical, organization aims all its efforts at satisfying • long-term smaller profits are normally
communication, and administrative its customers—at a profit, says E.D. better than short-term higher profits.
backup requirements are met. Perrault [11]. To have a market orientation • keeping an existing customer is much
means the organization is trying to carry more cost-effective than winning a
out the marketing concept. This entails the new customer;
following three basic ideas. • a satisfied customer increases the
chances for long-term profits.
• customer satisfaction; • invoicing the customer what is due
• a total company effort; and may dissatisfy the customer and reduce
• profit—not just sales as the objective. long-term prospects;
• a satisfied customer may accept over-
In the competitive service invoicing;
environment it is necessary for the project • over invoicing is not in the customer's
management organization to differentiate best interest—and as stated before, to
Figure 7— Planning and Control Cycle [14] its services from that of the competition, be really effective the project manager
and it must do so in ways that are must work in the customer's best
Communication is a vital requirement meaningful to customers. When defining interest;
for project success and communication via the service, two main components must be • salaries are likely the project
cellular phones and e-mail. Having a considered—i.e., the core product and the organization's biggest single expense
project information Internet or intranet core delivery process. The core product and therefore the main destroyer of
website can largely help to alleviate this should be to provide the customer with an profit;
problem. To update the old maxim item or tool, which he in turn can use to • good salaries attract good staff and are
somewhat—a digital photograph can be generate his own profits. The core delivery seen as incentives to perform; and
worth a thousand words and such process should be a project managed as a • conversely—paying peanuts attracts
photographs can be easily and widely service delivery product by all the monkeys and is a sure road to project
dispersed electronically. standards of service excellence. failure
The principle should be followed of— A project management service can be
when in doubt, supply too much seen as a business product, which is treated All in all, rocky waters to navigate for a
information too widely. Communication differently than a consumer product. project manager, and a golden middle way
should not only flow between the project Organizations buy things to satisfy has to be, and is typically found on the
manager and the customer, but also within their own customers and typically focus on majority of projects.
the project management group. Without economic factors when they make However, new project rules that can
effective internal information not only will purchase decisions. Many different people change the above scenario can luckily be
the work execution be more difficult, but influence purchase decisions. Again it is added, including the following.
the sales job will be limited to the project quite clear that the real people that must be
manager where the whole project team can satisfied are the customer's customers. • innovative extras to the end product
and must act as new salesmen. For the project manager to sell his own can add more value than what is
Verbal communication should not be service effectively, it must be sold on many consumed by the extra effort;
underestimated and will probably remain levels to many different people—from the • if convinced of higher value received,
the most important communication media key decision makers to the influencers of the customer may be prepared to pay
of all. the key decision makers. In this, the value for it;
of a good customer relationship should not • smaller profits per item (or project)
be underestimated. with higher throughput (more
projects) can generate a higher total
Back to Financial Principles profit;
For the project manager the basic • most, if not all, project decisions have
equation is simple—i.e., work = income. a financial implication, a scheduling
The specifics, however, are not that simple implication, or both. However,
and in practice most project managers live commonly available financial and
by the following, often paradoxical rules. schedule/implementation modeling
tools are available to determine the
• work or income does not equal profit; effect of decisions;
• the project management organization • even apparently "schedule only"
demands profit as a non-negotiable; changes have financial applications for
• giving the customer more than what both the customer and the project
Figure 8— The Main Information Channels [4] he asked for has cost implications that manager. For the customer the longer
the customer may not be prepared to time-to-market of a highly profitable

Cost Engineering Vol. 47/No. 5 MAY 2005 33


product may be the most expensive whether a natural or a taught leader contracts (QS), Paper 3722, Level 3,
item of all; does not matter; Block A, (2000).
• appropriate use of technology can • maintain excellent relations with the 5. College of Estate Management,
reduce costs; and customer and keep him fully informed (CEM)(2), Diploma In Surveying,
• pricing can be based on value of all aspects of the project, and Lecture notes on management
delivered and therefore does not maintain integrity to ensure a trusting information and quality systems,
always need to be market related. relationship; Papers 0965, Level 3, Block A, 2000.
• on all project decisions take note of 6. Howarth A, Arbitration (UK)—
The services marketing sphere—the financial implications of decisions— Contradiction in the Role of
service-profit chain, according to Lovelock make extensive use of schedule and Architects, (Nov. 4, 2002).
offers the following [8]. financial modeling to determine the 7. Levitt, Theodore. After the Sale is
full impact of the decision, because Over, Harvard Business Review
• profit and growth are stimulated information empowers the project paperback No 90056, (1995): 64.
primarily by customer loyalty; team; 8. Lovelock, Christopher H. Services
• satisfaction is influenced by the value • communicate extensively— make full Marketing—People, Technology,
of services provided to the customer; use of technology, e-mail, intranet and Strategy, (Fourth Edition). Prentice
• value is created by satisfied, loyal, and internet, to keep all project Hall, 2001.
productive employees; and participants informed, and do not 9. Meredith, Jack R. and Samuel J.
• employee satisfaction in turn results neglect verbal communication; Mantel Jr. Project Management—A
primarily from high-quality support • make utmost use of service delivery Managerial Approach, New York:
services and policies that allow them to techniques, treat periodic project John Wiley & Sons Inc., 2000.
perform. meetings as critical service encounters, 10. Nobbs, R. Architectural Schizophrenia,
invite complaints, and pay special Building, (Oct. 25, 2002): 56
As noted above, all but the smallest attention to the fast and effective 11. Perrault, E.D, E.J. McCarthy, Basic
projects should however be executed in resolution of these complaints; Marketing—A Global and
terms of a financial model. This would take • make the customer's life easy—it will Managerial Approach, 12th Ed,
the guesswork out of many project add to his perception of receiving Richard D Irwin, (1996).
decisions value; 12. Ruskin and Estes, Anonymous, 1995.
• the project team mainly delivers the 13. Shenhar, A.J., O Levy, D. Dvir,
The Ideal Project project service, so look well after these Mapping the Dimensions of Project
To summarize, for a new project to be persons and ensure they are properly Success, Project Management
successful it must result in the following. supported and operate within an Journal, (1997): 5-13.
empowering environment. 14. Smith N.J, Engineering Project
• a satisfied end customer; Management, Second Edition,
• a profitable product for the customer Project management can be likened to Blackwell Science, (2002).
(or at least the customer must be in a an orchestra (project) where a conductor 15. Verzuh, Eric, The Fast Forward MBA
position to develop profitable products (project manager) directs every participant in Project, Management. New York:
as a result of the project); and (player/professional) to play his/her tune John Wiley & Sons Inc., publishers,
• the execution of the project must have (deliverable) as expected of him/her, to the 1999.
been profitable for the project satisfaction and delight of the audience
management organization. (external customers) and all involved Technical Articles - Each month, Cost
(internal customers). ◆ Engineering journal publishes one or more peer-
For a new project the following is reviewed technical articles. These articles go
through a blind peer review evaluation prior to
recommended. REFERENCES publication. Experts in the subject area judge the
1. Baccarini D, The Logical Framework technical accuracy of the articles. They advise the
• as far as possible, always work in the Method for Defining Project Success, authors on the strengths and weaknesses of their
customer's interest; Project Management Journal; 30, 4 submissions and what changes can be made to
improve the article.
• turn customer orientation into the 25-32.
project management organization's 2. Bergren, C., J. Soderlund, C.
competitive advantage; Anderson. Clients, Contractors and ARTICLES AVAILABLE - Articles from
• always maintain a long-term Consultants: The Consequences of previous editions of the Cost Engineering
journal may be purchased through the
outlook—this project is important, but Organizational Fragmentation in
AACE International Online Bookstore,
the aim is to get many future projects. Contemporary Project Environments,
www.aacei.org. The cost per article is
• know the technical aspects of the Project Management Journal, 32, 3 US$7.50 for nonmembers and US$5.00
project, and, just as importantly, know (2001): 39-48. for members of AACE International. If you
the business background to the 3. Belout, Anonymous, (1998). are interested in purchasing additional
project; 4. College of Estate Management copies of articles appearing in this issue
• the project manager must be a strong (CEM) (1), Diploma In Surveying, please refer to the Article Reprint and
leader to convey the mission— Lecture Notes on construction Permissions information on page 43.

34 Cost Engineering Vol. 47/No. 5 MAY 2005


Cost Engineering Vol. 47/No. 5 MAY 2005 35
The 2005 Annual Meeting




Registraistopen
ion
Photo courtesy of the New Orleans CVB & Richard Nowitz

Keynote Speaker
Joel M. Koppelman, CEO,
Primavera Systems, Inc.

Register online at:


www.aacei.org
Save by staying at the host hotel - Sheraton New Orleans!
Call 800 325-3535 for reservations!

JUNE 26-29, 2005





The Big Easy Way to Project Effectiveness


Earn 20 PDHs/2.0 CEUs during our many technical programs and seminars!
For Your
Information:
AACE International
Membership
now has a single e-mail
address for all of your
Membership assistance
needs.
Please contact us at:
membership@aacei.org

Cost Engineering Vol. 47/No. 5 MAY 2005 37


P rofessional S er vices D irector y

Index to Adver tisers Missing


Administrative Controls, this page Primavera Systems, Inc., inside cover
out?
ARES Corporation, back cover Rider Hunt, page 9
Call 410.584.1966 today
Calpine Planning Solutions, this page
to reserve exhibit space at
Ron Winter Consulting, page 42 the next annual meeting, to place your
Computer Guidance Corp., page 2 Skire, Inc., page 13 ad in Cost Engineering, or to be a part
eBid Systems, page 35 U.S. Cost, inside back cover of the AACE International website!
EOS Group Inc, page 37 University of Texas at Dallas, page 37
Hanscomb Faithful & Gould, page 7 Vertigraph, Inc., page 9
George Washington University, page 10 Warner Construction Consultants, page 35 Professional Services
KAS - Estimating, page 41 Win Estimator, page 6
Join the Directory
McDonough Bolyard Peck, page 27 Placing your business card in the hands of
For information about the listed advertisers or about thousands of corporate leaders every month is
Meridian Systems, page 4 advertising with us, please phone Chris Martin at
PMA Consultants, page 35 Network Publications, (410) 584-1966, or e-mail an opportunity you shouldn’t pass up!
PMO Link, page 12 him at cmartin@networkpub.com phone: 410.584.1966

AACE International Provides Internet Learning


Opportunities through www.aacei.org
Check out the new courses in AACE International’s
on-line distance learning catalog.
There's something for every skill level.

These courses are available to start any time – These 10-week courses start on June 27, 2005:
An Applied Framework for Project Management • Construction Blueprint Reading (CEI)
Fundamental Skills and Knowledge of Cost Engineering • Oral and Written Communications for Construction
Writing for Results Supervisors (CEI)
Handling Personal Interactions • Contract Documents and Construction Law (CEI)
Working in Teams • Planning and Scheduling (CEI)
Communicating on the Job
• Estimating and Bidding 2 (CEI)
Presenting Ideas
Being an Effective Leader Learn more about these courses at:
Finding the First Job www.aacei.org/education/distancelearning
Finding the Next Job
Entrepreneurial Cost Engineer
Introduction to Construction Estimating Complete information on all courses can be accessed
at: w w w.aacei.org/education/distancelearning

38 Cost Engineering Vol. 47/No. 5 MAY 2005


TThe Bulletin
he AACE International Bulletin

Atlanta Section Central Savannah River Area Section


Anthony Dixon of IAC was the speaker at the Atlanta The Central Savannah River Area (CSRA) Section had a
Section’s March meeting. He provided an update on the MH joint April meeting with the American Society of Mechanical
Jackson International Terminal project. At the April 13 meeting, Engineers - CSRA Chapter. The meeting included an excellent
Dr. Khalid M. Siddiqi, chairman of the Southern Polytechnic presentation, by Donald McDonald, PE PSP, on senior manage-
State University, spoke on, “Opportunities in Construction ment review of project CPM schedules. Mr. McDonald's presen-
Management Education.” He worked on development of a strate- tation also covered various aspects of design engineering and con-
gic technology policy for the US Army’s global readiness, worked struction management that contribute to cost efficiency and over-
with the US Army Environmental Policy Institute, has experi- all project success. Included in the discussion were various valu-
ence with project planning and monitoring, served as a consult- able tools that are available to ensure efficient project manage-
ant on World Bank projects and was the director of a master plan ment and effective multi-disciplinary communication. The goal
for Karachi, Pakistan, a city of over 10 million people. of the presentation focused on what level of detail is necessary to
communicate; analysis of trends and control recommendations;
Cascade Section communication details to prove analysis and recommendations;
The Cascade Section was treated to an excellent presenta- and understanding internal and external elements of scheduling.
tion on the water infrastructure rebuilding program in Iraq and The CSRA Section hosted an EVP/PSP Workshop in
the extreme conditions facing this effort in a war zone. Les Augusta, Georgia on Saturday, May 5. This proved an excellent
Brown, Human Resource Director, IDC - previously assigned as opportunity for participants to prepare for the certification exam
HR Director for the CH2M HILL/Parsons, Joint Venture in for the AACE International Earned Value Professional (EVP)
Baghdad, was the speaker. It was truly a most informative and and/or Planning & Scheduling Professional (PSP) certification.
enlightening presentation. The Cascade Section holds it's regu- Professionals who obtain certification achieve industry recogni-
larly scheduled dinner meetings on the second Thursday of the tion and increase the value of their work to their clients and their
month through June at the University Place in downtown employers.
Portland. In April, the topic wase a panel discussion on, The Cost
of Building Green, Does It really Cost Less? This was a joint meet- Chicago Midwest Section
ing with ASPE. For further information, refer to the Section’s The Chicago Midwest Section met April 18 in a joint meet-
website at www.aacei-cascade.org or contact our President, Rob ing with ASPE, the American Society of Professional Estimators.
Edgerton at 503-423-3998 x22119. The meeting program looked at the estimating process that W.E.
O’Neil Construction used in bidding on such projects as a foun-
tain at Millennium Park and the relocation of a submarine at a
museum. The Chicago Midwest Section will hot its annual sem-
inar program on Friday, May 20. The theme will be, “Champions
of Project Controls, 2nd edition. Contact Don Giegerich at
don_giegerich@urscorp.com.

Chinook-Calgary Section
About 150 Chinook-Calgary and PMI members and guests
heard Jamie Cool of Kildrummy do a presentation at the Telus
Convention Centre in March on using standardization to assist in
training new participants in cost estimating, scheduling and proj-
ect management reporting. Such new participants will be better
able to continue in cost engineering as the current 48- 50 year old
experienced workers reach retirement age.

Submitted photo
Two Chinook-Calgary
Submitted photo scholarship winners
Guest speaker, Les Brown, above left, HR Director for CH2M HILL IDC, were recently honored.
is shown with Cascade Section Vice-President, Greg Baker at the March Shown at left are
dinner meeting of the Cascade Section. The program featured a presenta- Yashie Sukhu (recipi-
tion on the water infrastructure rebuilding program in Iraq. ent), Cindy Striekland
(Scholarship Director),
and Sushil Peres-da-
Silva (recipient.)

Cost Engineering Vol. 47/No. 5 MAY 2005 39


More than 80 members and guests attended the April received PPG#13 Parametric and Conceptual Estimating as part
Chinook-Calgary Section’s joint meeting with the quantity sur- of their registration. All Section members attending the Annual
veyors. The record attendance at the joint dinner meeting heard Meeting will be serving as presentation room hosts. The Section
various definitions and discussions of contingency from owners, will be represented at the Section Orientation Meeting in New
contractors and quantity surveyors. Although the percent contin- Orleans.
gency is always open to discussion on a project, owners still have
to pay the costs of a project, in order to place a facility into pro- New Jersey Section
duction to generate revenue for a return on capital invested. The February meeting of the New Jersey Section was on Feb.
16, at the KatManDu Restaurant in Trenton, NJ. Scotty Riemer,
Submitted photo NJ section treasurer, was the host of the meeting, representing
Chinook-Calgary Section’s
Joseph Jingoli and Son. Iftikhar Madni, CCE, NJ section presi-
April Dinner Meeting panel
dent, was the speaker for the evening. He presented several cost
discussion was on
“Contingency Management.” engineering problems to the attendees. The goal of this session
Participants, shown right from was to introduce the type of problems that are on the certification
left to right, included: exam, work through solutions to those problems, and encourage
Trevor Smith, director of the people to begin the process of exam preparation. Gaurav (Gary)
local chapter of CIQS; Lamba, PE, CCE, was acknowledged for recently his passing the
John Croft, director project certification exam.
controls for Suncor Energy; Peter Ripley, President of the Chinook Calgary The March meeting of the New Jersey Section was on
Section; and Ross Clark, manager of project controls for Bantrel.
March 16, at the Lone Star Restaurant in Bridgewater, NJ. Brian
Tighe, NJ section corresponding secretary, was the host of the
East Tennessee Section meeting, representing Skanska USA Building Inc. Debbie
The March 28 meeting of the East Tennessee Section was at Dempsey, NJ section vice president, and Mike Bolhofer, NJ sec-
the Outback Steakhouse in west Knoxville. The guest speaker was tion membership director, were the speakers for the evening.
D. Wayne Loveday, Director of Plants and Collection System, They presented several engineering economics problems to the
Knoxville (TN) Utilities Board (KUB). He is responsible for attendees. The goal of this session was to introduce sample prob-
operation and maintenance of KUB's wastewater treatment lems concerning the time value of money, and review the formu-
plants and water treatment plant, as well as the operation, plan- las, tables, and methodologies to solve such problems.
ning and maintenance of the wastewater collection system total-
ing 1,200 miles. Mr. Loveday gave an very informative 30-minute
presentation on KUB's recently begun 10-year project to upgrade
a significant portion of the Knoxville, TN wastewater and
stormwater system. There were 37 section members in atten-
dance at this meeting (maybe our best-attended section meeting
ever—we're checking our records). Three non-members pushed
the total attendance that evening to 40. That's right, 40 !!! For fur-
ther information about the East Tennessee Section, visit our web-
site at http://www.aace-ets.org/.

Genesee Valley Section


The Genesee Valley Section will be providing a matching Submitted photo
scholarship to a student from SUNY Environmental Science and Iftikhar Madni, CCE, New Jersey Section President, receives a certificate
Forestry at Syracuse NY. The presentation will be made at the of appreciation from Debbie Dempsey, New Jersey Section Vice-President.
May Section meeting. The section will be hosting a coffee hour Mr. Madni presented the Section’s February program on cost engineering
problems as preparation for the certification exam.
at the New Orleans' meeting. This is the fifth year in a row the
the section has provided sponsorship for the annual meeting. As
always we challenge all AACE International sections, especially Rocky Mountain Section
our wealthier fellow sections to follow suit and give back to the The speaker for the March meeting of the Rocky Mountain
Association. Section was Ron Rowbottom, manager of health, safety and work-
The Genesee Valley Section made a $1000 donation to the ers compensation at Ball Packaging Corporation. He spoke on
Red Cross for tsunami relief effort. The Genesee Valley section the Costs and Value of Health and Safety in Impacting the
approved of sponsoring a representative to the Annual Meeting "Bottom Line." Mr. Rowbottom looked at the cost potentials and
from our BOD's. Attending the Annual Meeting is seen by the the cost reduction impacts that derive from a proactive, realistic
Section as a great way to bring cost engineering knowledge to our approach to health and safety. In addition, he overviewed the
membership. The Board member will be reporting back, to both current health and safety landscape to look at both traditional and
the Board and to the individual members at a section meeting, newer innovative approaches to providing a safe and healthy work
about what they learned at the Annual Meeting. environment.
Doug Leo conducted a full day seminar on conceptual and
strategic estimating on April 20. All participants at the seminar

40 Cost Engineering Vol. 47/No. 5 MAY 2005


HOW TO SUBMIT SECTION NEWS TO THE
COST ENGINEERING JOURNAL
All submissions should be e-mailed to editor@aacei.org.
Information may be included in the body of the e-mail or as an
attachment. Microsoft Word files are the preferred format.
All photos should be sent as PC tiff or jpg files at 300 dpi. If
submitting at only 72 dpi, please send the photo as large as
possible as conversion will reduce its size. Include the names and
titles of each person shown in any photos.

Note on Section identification in submissions:


In the write ups submitted to AACE International for the
Bulletin section of Cost Engineering journal, as well as in
Submitted photo
Section newsletters and website articles, many times AACE
Ron Rowbottom talks about “The Costs and Value of Health and Safety in International Sections are referred to as chapters. The correct
Impacting the ‘Bottom Line’” at the March meeting of the Rocky
reference should always be to a Section. AACE International
does not have chapters. Please do not refer to Sections as
Mountain Section. chapters.

South Central California Section Note on the listing of dates:


If an event is during the month of publication, it will be
The newly formed South Central California Section con- listed as an upcoming event even if members will not receive
ducted its first formal meeting on April 13. In addition to many their journal in the mail until after the listed event. The journal
of our founding members, a number of new people attended. goes to press about a month in advance of delivery, the issue date
This was quite an exciting event for all of those who worked is always the first of each month, and the electronic version
toward board approval of the new section petition. A social hour should be posted by that date.
AACE International reserves the right to edit all submissions
with much networking and introductions was followed by dinner and to refuse to publish any submissions determined by the
and the technical presentation. The speaker was Zartab Z. editor or executive director to not meet the standards of the
Quraishi, PE CCE, who is a director with C.A. Rasmussen, Inc. journal.
of Simi Valley, CA. He has 24 years of experience in the engi- Anyone with questions on submitting copy or photos may
contact Managing Editor Marvin Gelhausen at
neering and construction field, held responsible positions in
mgelhausen@aacei.org, or Graphic Designer/Editor Noah
planning, scheduling, estimating, claims analysis, litigation sup- Kinderknecht at nkinderknecht@aacei.org.
port, and teaches at UCLA extension. His presentation discussed
the most acceptable method of performing construction project
delay analysis. He also described some of the faulty critical path
delay analysis techniques that have been employed. This pres-
entation addressed both contractor and owner concerns with
respect to delay.

Submitted photo
On April 13, Zartab Z.
Quraishi, PE CCE, shown
left, presented the first pro-
gram at the newly formed
South Central California
Section. Mr. Quraishi is a
director with C.A. Rasmussen,
Inc. of Simi Valley, CA.
Submitted photo
To celebrate the first formal
meeting of the newly formed
South Central California
Section, a drawing was con-
ducted for a copy of the newly
revised ‘Skills and Knowledge
of Cost Engineering.’ Meeting
facilitator Daniela Andrade is
shown presenting the prize to
winner Melvin Earley.

Cost Engineering Vol. 47/No. 5 MAY 2005 41


AACE International
Headquarters Contact List
209 Prairie Avenue, Suite 100
Morgantown, WV 26501
ph: 800.858.COST fax: 304.291.5728
Interim Executive Director
Charla Miller
e-mail: cmiller@aacei.org

Staff Director, Education and


Administration
Charla Miller
e-mail: cmiller@aacei.org

Staff Director, Technical Operations


Christian Heller
e-mail: cheller@aacei.org

Manager, Finance
Carol Sue Rogers
e-mail: crogers@aacei.org

Assistant Manager, Finance


Paola Tomasiak
e-mail: ptomasiak@aacei.org

Manager, Marketing and Meetings


Jennie Cunningham Amos
e-mail: jamos@aacei.org

Meetings Coordinator Discounted Package Price


Teri Jefferson
e-mail: tjefferson@aacei.org Get more than a 25% discount
by purchasing the paper versions
Administrator, Certification and Education
Sandra Jo Willard
of AACE International’s premier
e-mail: swillard@aacei.org publications, Skills &
Knowledge, 5th Edition and the
Administrator, Membership and Section Certification Study Guide, 2nd
Services
Shannon Brode Edition at a package price.
e-mail: sbrode@aacei.org
Bought separately, these books
Customer Service Assistant would cost: $104.00 for mem-
Sharon Hardman bers and $137.00 for non-mem-
e-mail: shardman@aacei.org bers, but during this special
Managing Editor, offering, both publications
Marvin Gelhausen together are available at a 28%
e-mail: mgelhausen@aacei.org savings: Member price - $75
Graphic Designer/Editor
Nonmember price - $100
Noah Kinderknecht These special prices are only available for the
e-mail: nkinderknecht@aacei.org
printed editions of these publications, although
Advertising Representative the CD versions are still available at regular price.
Network Publications, Inc.
phone: 410.584.1998 To order, visit the AACE International Online
e-mail: aace@networkpub.com Bookstore at www.aacei.org

42 Cost Engineering Vol. 47/No. 5 MAY 2005


A r ticle Reprints and Per missions

Cost Engineering Journal, Volume 47/Number 5, May 2005

Pages 14-19 Pages 22-25


Design/Build Selection Using Earned Value
Readers of the Cost Engineering
journal can purchase copies of selected
Process — Art or Science? Management Indexes as Team
articles that are published with an
Talal Abi-Karam, PE CCE Development Factor and a
The Design/Build method is an innova-
AACE International reference number tive project delivery system that is revolutioniz- Compensation Tool
at the end of the article. Articles can be ing the delivery of private and public works Victoria A. Flores, CCE and Gary E. Chase
delivered in print form or in Adobe projects. Advantages include a reduced project The objective of this article is to present
Acrobat (PDF) format. delivery time, costs, and reduced claims. The the main components of the development of a
Please refer to the AACE selection of a Design/Builder in the public project team and the motivational characteris-
works sector is a complex process that has tics inherent to team work. It also looks at an
International reference number when
required a number of US states to modify their interrelation proposal between the earned
contacting our Publications Sales procurement laws, state statutes, and licensing value analysis and team development through
department. laws. Although Design/Build is one of the most the SPI and CPI indexes. These are obtained
popular integrated alternative delivery meth- by tool use and team development models and
To Order ods, it does not have well-established contrac- the compensation and reward in the project.
Contact: AACE International Publications tor selection procedures. The selection of a This reduces the subjectiveness of humans
Sales at pubsales@aacei.org Design/Builder can be based solely on qualifi- resource in the project evaluation. The article
cation, solely on price, or a combination of presents a brief report about team development
price/qualification. Even with qualification- and compensation policies, as well as an intro-
Reprint Prices: based selection (QBS), the selection process duction to the earned value concept, aiming to
Quantity Member/Non-Member may be subjective, since various state agencies align the approached concepts.
1-9 copies $5.00/$7.50 (DOT's) and municipalities have different Reprint 21069
10-49 $4.50/$7.00 selection criteria for pre-qualifying and evaluat-
50-79 $4.00/$6.50 ing bids of the perceptive Design/Build teams.
Pages 28-34
80-99 $3.50/$6.00 This article examines the various selection
methods of Design/Build teams in the public The Goalposts for Project
100-499 $3.00/$5.50
works sector. It addresses the legal framework Success Have Moved —
for selecting Design/Build teams, including
To Contact Us qualification-based selection (QBS), selection A Marketing View
AACE International criteria, and weighting of criteria. P.S. Kupakuwana and G.J.H. van der Berg
209 Prairie Avenue, Suite 100 Reprint 21068 Traditionally, a successful project was
Morgantown, WV 26501 seen as one in which the triad of time, budget,
USA and specification was complied with at a profit.
Phone: 304.296.8444 Current project literature places more
emphasis on customer satisfaction as a fourth
Fax: 304.291.5728
important success parameter. This article
discusses project management services and
For Information On Other Reuse focuses on what constitutes project success.
Requests This type of project is named the new project
If you are seeking permission to in this article and a set of new project rules is
copy, quote, or translate into another arrived at. The article also takes a services
language any material from any issue of marketing view and examines the customer's
motivation in appointing a project manager.
the Cost Engineering journal, please
Reprint 21070
contact our Managing Editor, Marvin
Gelhausen at mgelhausen@aacei.org

Cost Engineering Vol. 47/No. 5 MAY 2005 43


C
Calendar of Events
alendar of Events
May 2005 June 2005 Center, Austin, TX

20-23 Ecobuild America the Contact:www.energy-


9-13 Comprehensive 5-Day Training congress.com
Program for Business Energy Environmental Systems Technology
Professionals, The Association of Energy Conference & Exhibition, Ecobuild
America, Disney’s Coronado Springs 20-23 ISEC-03 - Third International
Engineers (AEE), Hyatt Rosemont,
Resort, Orlando, FL Structural Engineering and Construction
Chicago, IL
Conference, Tokuyama College of
Contact: www.aeecenter.org/seminars Contact: www.ecobuildamerica.com Technology and ISEC, Tokuyama College
of Technology, Shunan, Japan
15-17 PTI’s Fourth Annual Conference 23-26 AACE International Education
Seminars, AACE International, Contact:www.tokuyama.ac.jp/english/ind
& Exhibition, The Post Tensioning ex.html
Institute (PTI), Westin Tabor Center, New Orleans, LA
Denver, CO Contact: info@aacei.org November 2005
Contact: www.post-tensioning.org www.aacei.org
5-11 2005 ASME International
26-29 AACE International’s 49th Mechanical Engineering Congress and
20 Annual Seminar- “Champions of Annual Meeting, AACE International,
Project Controls - 2nd Edition”, AACE Exposition, The American Society of
New Orleans, LA Mechanical Engineers (ASME), Walt
International’s Chicago Midwest Section
Contact: info@aacei.org Disney World Swan & Dolphin Hotel,
Contact: Don Giegerich www.aacei.org Orlando, FL
e-mail: don_giegerich@URSCorp.com
Contact:Kim Punter
30-31 AACE International Education phone (212) 591-8258
23-25 Fundamentals of Indoor Air Seminars, AACE International, e-mail punterk@asme.org
Quality: Core Skills for the Building New Orleans, LA
Professional, The Association of Energy
Engineers (AEE), Crowne Plaza Atlanta Contact: info@aacei.org April 2006
Buckhead, Atlanta, GA www.aacei.org
23-26 Ist ICEC and IPMA Global
Contact: phone (770) 925-9633 Conference on Project Management, The
July 2005
fax (770) 381-9865 International Cost Engineering Council
www.aeecenter.org 16 AACE International’s 2nd Quarter (ICEC) and the International Project
(2Q) Certification Exam Management Association (IPMA) ,
23-27 Short Courses, The American Cankargev dom, Congress Center,
Society of Mechanical Engineers (ASME) Contact: info@aacei.org Lujubljana, Slovenia
and the American Institute of Chemical www.aacei.org
Contact:www.icec-ipma2006.org
Engineers (AIChE), Toronto, Canada and
Houston, TX 25-29 12th ISPE/CE2005 International
Conference on Concurrent
Contact: ASME Information Central Editor’s Note: Please submit items for
Engineering:Research and Application
phone 1-800 843-2763 or future calendar listings at least 60 days
(CE2005), the International Society of
(201) 882-1167 in advance of desired publication.
Productivity Enhancement, Renaissance
fax (201) 882-1717 or
Worthington Hotel, Fort Worth/Dallas, TX
(201) 882-5155
e-mail: infocentral@asme.org Contact: www.ce2005.org

29-31 Kuwait First Annual Value September 2005


Engineering Conference and Exhibition,
Promedia International, Kuwait 14-16 World Energy Engineering
Contact: www.kuwaitve.com Congress (WEEC), Association of Energy
Engineers (AEE), Austin Convention

AACE International, 209 Prairie Avenue, Suite 100, Morgantown, WV 26501 USA phone: 304-296-8444
fax: 304-291-5728 e-mail: mgelhausen@aacei.org or nkinderknecht@aacei.org website: www.aacei.org

44 Cost Engineering Vol. 47/No. 5 MAY 2005

You might also like