Professional Documents
Culture Documents
Draft
Budget
20142015
Administration and Clerical
Principal Office of the Authority $0 $0 $0 $0 $5,000
Clerk of the Board $35,000 $35,000 $35,000 $0 $24,000
Financial Services $0 $0 $0 $0 $6,000
Executive Director $94,680 $90,680 $90,044 $636 $94,680
Misc Admin Expenses $0 $0 $0 $500
Legal Services
Board Counsel $63,000 $59,000 $27,000 $32,000 $63,000
Special Counsel $100,000 $186,000 $186,000 $0 $152,000
Contract Services
Public Outreach $35,000 $15,000 $15,000 $0 $35,000
Audit Services $5,000 $6,700 $6,700 $0 $6,000
Televised Meetings $14,000 $10,000 $4,663 $5,338 $10,000
Contract Services & Studies $25,000 $3,000 $0 $3,000 $30,000
Contract SPI $20,000 $35,000 $34,610 $390 $0
Contract VE $0 $200,000 $200,000 $0 $0
Insurance $7,000 $7,000 $6,702 $298 $7,500
Travel Expenses $5,000 $1,000 $0 $1,000 $5,000
Contingency $20,000 $2,000 $1,657 $343 $20,000
TOTALOPERATINGEXPENSES $423,680 $650,380 $607,376 $43,005 $458,680
Table 3
Member City
Approved %
Distribution
Total
Contributions
FY 2014-15
Total
Contributions
FY 2013-14
Carmel By the Sea 9.30% $42,657 $31,771
Sand City 1.30% $5,963 $4,441
City of Pacific Grove 18.80% $86,232 $64,225
City of Seaside 22.00% $100,910 $75,157
City of Monterey 46.50% $213,286 $158,855
City of Del Rey Oaks 2.10% $9,632 $7,174
Total Income 100.00% $458,680 $341,263
* Contributions were lower in FY 13-14 due to carry over balance of $82,417
Member City Contributions
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 5.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and provide direction with regards to expected
changes to the California Public Utilities Commission(CPUC) schedule for
the Monterey Peninsula Water Supply Project (MPWSP).
RECOMMENDATION:
It is recommended that the Water Authority Board receive a report on expected changes
in the CPUC schedule resulting from delays in the completion of the draft EIR (DEIR),
determine if any action is required at this time, and provide direction to staff.
DISCUSSION:
The latest CPUC schedule as revised July 3, 2014 is attached. That schedule indicated
that a number of legal filings and DEIR comments were to be completed between the
DEIR circulation in 3rd quarter 2014 (not later than Sept 30) and the Administrative Law
Judge (ALJ) hearings in December 2014.
However, on August 8, we received a telephonic notification from the CPUC consultant
preparing the EIR that the DEIR has been delayed several months and the ALJ hearing
in December is likely to be delayed as well, possibly as long a 3 months.
As of August 11, we have not received official notice of a hearing delay. None-the-less,
staff recommends the Authority Board accept the likelihood of a delay, consider its
implications, and provide staff direction accordingly.
EXHIBIT:
A-CPUC schedule as revised on July 3, 2014
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 6.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and provide direction with regards to the current
status of the source water negotiations for the Monterey Regional Water
Pollution Control Agency (MRWPCA) Ground Water Replenishment
(GWR) Project.
RECOMMENDATION:
It is recommended that the Water Authority Board receive a report on the current status
of negotiations on source water for the MRWPCA Pure Water Monterey (PWM) /
Ground Water Replenishment (GWR )project, determine if any action is required at this
time, and provide direction to staff.
DISCUSSION:
The latest GWR schedule as revised June 12, 2014 by the Monterey Regional Water
Pollution Control Agency (MRWPCA) is attached. A MOU for GWR source water was to
have been completed by June 30, 2014. On July 10th, the Water Authority Board
extended the deadline to July 31 to allow more time for negotiations between the
MRWPCA and Salinas Valley agricultural representatives. Unfortunately, as of August
8th, an MOU on source water has not been reached.
As shown on the attached schedule, the completion date of the draft water purchase
agreement (WPA) is critical, and is dependent on the MOU. The Monterey Peninsula
Water Management District (MPWMD) will need enough time to complete follow-on
studies required by the settlement agreements prior to the CPUC hearings that had
been scheduled for December 2014.
Although the deadline for the draft WPA is currently August 2014, as discussed in an
earlier agenda item the CPUC hearing scheduled for December 2014 is likely to be
delayed as a result of problems by the CPUC consultant in completing the EIR.
Dave Stoldt, General Manager of the MPWMD, will present the latest information on
that subject at today's meeting. Depending on information provided, some of the options
available to the Water Authority include:
1. Determine that GWR will not be available in time for inclusion in the Peninsula
supply portfolio and decide in favor of the 9.6 mgd desal facility.
2. Agendize a decision on removal or retention of GWR for the September 11
meeting, or at a special meeting to be announced.
3. Authorize an extension of the deadlines for the GWR MOU and WPA on the
assumption that the December 2014 CPUC hearing will be delayed.
4. Request the source water issue go to arbitration immediately as is permitted by
current agreements.
5. Take no action.
EXHIBIT:
A-GWR schedule as revised on June12, 2014
October 7, 2013
015621\0002\11340073.1
8/11/14
Revised Schedule and Task List for MPWSP Post Settlement (REV 12 JUNE 2014)
Italics are changes. Red are actions past due. Yellow are near term.
CPUC Calendar Dates
Task Due Date Responsible Party Notes
Comments on
Settlement Agreements
Due
August 30, 2013 Complete
Reply Comments on
Settlement Agreements
Due
September 13, 2013 Complete
Prehearing
Conference: Status of
Settlement Motion (if
any), of CEQA work
& other matters
September 16, 2013 Complete
Quarterly Check-in Call
with Settling Parties
October 2013 MPRWA In Progress
Informational Hearing
on Settlement
Agreements
December 2-3, 2013
Quarterly Check-in Call
with Settling Parties
January 2014 MPRWA
DEIR circulated for
Comment
3
rd
Qtr 2014 DEIR out in June 2014
Quarterly Check-in Call
with Settling Parties
April 2014 MPRWA
Cal-Am to file and serve
a common outline for
legal and policy briefs,
after consulting with
parties
15 days after issuance
of DEIR
Comments on DEIR
Due
45 days after issuance
of DEIR
DEIR to be published 1
st
Qtr 2015
Common Outline
Opening Briefs filed and
served on legal and
policy issues
60 Days after Issuance
of DEIR
15 days after Issuance
DEIR- Cal Am to
file/serve common
outline for legal & policy
briefs
Reply Briefs filed and
served on legal and
policy issues
75 days after issuance
of DEIR
FEIR published 1
st
Qtr 2015
Proposed
Decision addressing
certification of FEIR and
issuance of CPCN
1
st
Qtr 2015
Quarterly Check-in Call
with Settling Parties
July 2014 MPRWA
Target for Commission
Action on Phase I
1
st
Qtr 2015
Quarterly Check-in Call October 2014 MPRWA
October 7, 2013
015621\0002\11340073.1
8/11/14
Task Due Date Responsible Party Notes
with Settling Parties
Quarterly Check-in Call
with Settling Parties
January 2015 MPRWA
October 7, 2013
015621\0002\11340073.1
8/11/14
GWR
Task Due Date Responsible Party Notes
File Motion for
Bifurcation of the
GWR Decision
August 2013 MRWPCA Complete and Granted
Board Actions to
Approve Revised
Governance Committee
Agreement
October 2013
August/Sept 2013
MPWMD, MPRWA,
County, & Cal-Am
To be Completed in
October
Executed Agreements
for GWR Source Water
and/or Declaratory
Relief
June 23, 2014
MRWPCA Meet & Confer in
Progress
Draft WPA
Mar 2014
MPWMD & MRWPCA
Obtain Representations
from DPH re Use of
Extracted GWR Water
Oct 2014
MRWPCA
Obtain Representations
from RWQCB re Use of
Extracted GWR Water
Oct 2014
MRWPCA
Storage Agreement
with Seaside Basin
Watermaster
Jul 2014
MRWPCA & MPWMD
GWR Basis of Design
Complete with At Least
10% Design
Jul 2014
MRWPCA
GWR Financing Plan
Sufficient for SRF
Funding
Aug 2014
MRWPCA & MPWMD
Agreement on Terms of
WPA
May 2014
Cal-Am, MRWPCA,
&MPWMD
Perform Revenue
Requirement Analysis
Including Any Debt
Equivalency Effect
Jul 2014
MRWPCA & MPWMD
Perform Assessment of
GWR Positive and
Negative Externalities
for Any Premium
Showing
June 2014
MRWPCA & MPWMD
DEIR Circulated July 2014 MRWPCA
Dilution Water
Requirements
July-October 2014 MRWPCA
Project Approved and
FEIR
October 2014 MRWPCA
All Permits for GWR
Construction Obtained
???
MRWPCA
October 7, 2013
015621\0002\11340073.1
8/11/14
January 2015
October 7, 2013
015621\0002\11340073.1
8/11/14
Source Wells
Task Due Date Responsible Party Notes
Drill Exploratory
Boreholes
Sept. 2013 February
2014
Cal-Am PENDING
Commence
Hydrogeologic Study
and Technical Report
August 2013 Cal-Am / SVWC Draft completed. ?
Permits for CEMEX
Site Test Well
January 2014
Aug 2014
Cal-Am MND circulated in May
2014
Drill CEMEX Site Test
Well
February 2014
Nov 2014
Cal-Am DELAYED
Results of Test Well
Operation Obtained
February 2014
February 2016
Cal-Am DELAYED
Hydrogeologic Study
and Technical Report
Complete and Results
Filed with CPUC
June 2015
Cal-Am DELAYED
Necessary Agreements
from CEMEX for
Source Wells
Nov. 2015, or sooner Cal-Am ?
All Necessary Permits
for Construction of
Source Wells Obtained
Nov. 2015, or sooner Cal-Am ?
October 7, 2013
015621\0002\11340073.1
8/11/14
Securitization
Initial Revision and
Redline of Legislation
Early September 2013 MPWMD Complete
October 7, 2013
015621\0002\11340073.1
8/11/14
Obtain Cal-Am Input on
Draft Legislation
Late September 2013 MPWMD, MPRWA, &
Cal-Am
Complete
Retain Necessary
Additional
Financial/Legal
Consultants (Charles
Atkins)
October 2013
MPWMD In Progress
Revise Financial
Comparison of
Securitization v. Cal-Am
Financing
October 2013 MPWMD & Cal-Am In Progress
Meeting with
Community/Interest
Groups and Cities
October-December
2013
MPWMD & MPRWA In Progress
Further Revise
Legislation as
Necessary
October-November
2013
In Progress
Draft Summary of
Legislation
December 2013 MPWMD Complete
Introduce Legislation January 2014 Complete
Lobbying Effort February-April 2014 MPWMD, MPRWA, &
Cal-Am
In Progress
Legislation Adopted April-May 2014
?
Passed Senate
Unanimously; Referred
to Assembly
Initial Draft of Motion for
Financing Order
April 2014
?
MPWMD
Perform Analysis to
Demonstrate Annual
Customer Benefits
Exceed 1.0% of Total
Annual Revenue
Requirement
April 2014
?
MPWMD & Cal-Am
Motion for Financing
Order
May 2014
?
MPWMD
Obtain CPUC Financing Order on securitization
October 7, 2013
015621\0002\11340073.1
8/11/14
Order ? financing on satisfaction
of remaining criteria
from Settlement K
Preliminary Discussions
with Bond Underwriters
September-December
2014
MPWMD
Drafting of
documentation for bond
requests
September 2014-April
2015
MPWMD & Cal-Am
Preliminary Discussions
with Rating Agencies
February-April 2015 MPWMD
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 7.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and vote on staff proposal to add the General
Manager, or District Engineer, of the Marina Coast Water District
(MCWD) as a member of the Authority Technical Advisory Committee
(TAC) and to add a MCWD hydrologist to the Monterey Peninsula Water
Supply Project (MPWSP) Hydrogeologic Working Group.
RECOMMENDATION:
Staff recommends that the Water Authority invite Marina Coast Water District (MCWD)
participation on the Technical Advisory Committee (TAC) and on the test slant well
Hydrogeologic Working Group (HWG).
DISCUSSION:
During January and July 2014, the City of Marina has been heavily involved in the
permitting of the bore hole construction and in consideration of a mitigated negative
declaration (MND) and coastal development permit (DP) for Cal Am's test slant well at
the CEMEX site.
During public hearings, the Marina Coast Water District (MCWD) raised a number of
concerns that suggest a lack of communication between MCWD and Cal Am, and with
the Water Authority as well. This situation has not only delayed progress on the desal
plant approval and construction, but has raised serious concerns on the part of the
MCWD and City of Marina that its water needs may be placed at risk as a result of the
desal plant slant wells.
To initiate a dialog on these issues, several informal MCWD/MPRWA management
level meetings were held during the week of August 4. Amongst other things, it was
concluded that participation by MCWD representatives in the TAC and in the HWG
would provide early MCWD input on technical issues related to the Desal facility and the
slant wells, facilitate MCWD environmental review of the MPWSP EIR, insure the
concerns of Marina residents get timely consideration, and improve communication
between and amongst MCWD, Cal Am, and the Water Authority.
It should be noted that the TAC already has a member from the agricultural community
to articulate ag interests prior to Water Authority decisions and deliberations. Thus, the
Executive Director recommends the Authority extend an invitation to the MCWD District
Engineer (Interim General Manager) to join the TAC for the same purpose.
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 8.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and provide direction on the Value Engineering
(VE) Final Report for the Cal Am Desal facility, authorize forwarding of the
VE report to the Governance Committee for its action, and
authorize payment to the consultant (VMS) from funding provided by Cal
Am, not to-exceed the contract price of $109,035.70
RECOMMENDATION:
It is recommended that the Monterey Peninsula Regional Water Authority receive a
report on the Final Value Engineering ( VE) Study of the Monterey Peninsula Water
Supply Project (MPWSP), make recommendations, forward the report to the
Governance Committee for its action, and authorize contract closure and payment to
the consultant (VMS).
DISCUSSION:
The draft preliminary Value Engineering (VE) Study for 30% design of the desal facility
was briefed to a joint meeting of the Governance Committee and the MPRWA at a
special meeting on July 10 and to the TAC on Aug 4. The Final report is now complete
and the full text is available on the Water Authority web site http://www.mprwa.org/wp-
content/uploads/2012/03/MPWSP-Final-VE-Report.pdf and on the Cal Am MPWSP
project web site www.watersupplyproject.org .
It should be noted that the VE study focuses on value improvements, in particular
potential cost savings. Requirements mandated by the settlement agreements, as well
as directions from the Governance Committee on environmental and aesthetic issues,
should still be incorporated into the design.
Following review and comment by the MPRWA, the Final Report will be forwarded to
the Governance Committee for action in accordance with the Governance Agreement.
BUDGET CONSIDERATIONS:
The Water Authority awarded the VE contract on behalf of the Governance Committee
to VMS on June 12, 2014 at a price not-to-exceed $109,35.70. It also approved a
contingency of not-to-exceed $11,000.00. The contract was fully paid for by Cal Am.
The contract work is now complete and it has not been necessary to utilize the
contingency funds. Thus, the contractor can be paid and the contract closed. Any
unused funds remaining in the deposit account will be returned to Cal Am.
EXHIBITS:
A-Executive Summary of the VE Study
EXECUTIVESUMMARY
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
EXECUTIVESUMMARY FINALREPORT
AValueEngineering(VE)study,sponsoredbytheMontereyPeninsulaRegionalWaterAuthorityand
facilitatedbyValueManagementStrategies,Inc.,wasconductedfortheDesalinationPlantportionof
theMontereyPeninsulaWaterSupplyProject.ThestudywasconductedattheofficesofCalifornia
AmericanWaterinMonterey,CaliforniaJuly7through11,2014.ThisExecutiveSummaryprovidesan
overviewofthesubjectproject,summaryresultsoftheVEteamsanalysis,andthealternatives
developedbytheVEteam.
PROJECTSUMMARY
LedbyCaliforniaAmericanWaterCompany(CAW),theMontereyPeninsulaWaterSupplyProject
(MPWSP)isacomplex,multicomponentprogramthatisnecessarytoreplacealargepercentageof
thelocaldrinkingwatersupplythatcurrentlyoriginatesfromtheCarmelRiver.StateWater
ResourcesControlBoard(SWRCB)Order9510requiresCAWtoreducediversionsfromtheCarmel
Riverbyapproximately70%nolaterthanDecember31,2016.
InordertomeetthecutbackrequirementsandprovideadequatewatertotheMontereyPeninsula
communities,CAWplansincludethreeprojectstoaddressthisregionalwatercrisis:
DesalinationofseawaterfromwellsdrawingwaterfromMontereyBay
GroundwaterReplenishment(GWR)withadvancedtreatmentofwastewaterbytheMonterey
RegionalWaterPollutionControlAuthorityPlant
AquiferStorageandRecovery(ASR)
ThisVEstudyfocusedsolelyonthedesalinationplantportionofthewatersupplyproject.
Treatmentatthedesalinationplantwillconsistofoxidationwithsodiumhypochlorite,granular
mediafiltration,dechlorination,pHadjustmentwithsulfuricacid,cartridgefiltration,afirstpassof
seawaterreverseosmosis(SWRO),apartialsecondpassofbrackishwaterreverseosmosis(BWRO),
disinfectionwithultravioletlight,poststabilizationtreatmentwithcarbondioxideandhydratedlime,
pHadjustmentwithsodiumhydroxide,additionofanorthophosphatecorrosioninhibitorandpost
chlorinationwithsodiumhypochlorite.
CDMSmithwasselectedastheconsultantforthedesalinationplantdesignbuildproject.Theirwork
willincludethedesign,constructionandcommissioningoftheproposedseawaterdesalinationplant.
Theplannedfacilitiesincludethetreatmentplant,treatedwaterstorageandpumping,and
concentratestorageanddisposalfacilities.
Constructioncostsforallelementsofthedesalinationplantarecurrentlyestimatedat$74,029,943.
PROJECTPURPOSEANDNEED
TheprimarypurposeoftheoverallMPWSPistoreplaceexistingwatersuppliesthathavebeen
constrainedbylegaldecisionsaffectingtheCarmelRiverandSeasideGroundwaterBasinwater
- 1 -
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
resources.ThepurposeofthedesalinationplantportionoftheMPWSPistotreatthewatersupplied
bytheseawaterintakewellssufficienttomeettheapplicablewaterqualitystandards.
VESTUDYBASIS
TheVEstudywasbasedonthe30%DesignSubmittaldocumentspreparedbytheprojectsdesign
buildcontractor,CDMSmith,datedJune,2014.
VESTUDYOBJECTIVES
TheVEteamwastaskedwithexploringideastoimproveprojectvalueby:
Reducingprojectcostwithoutsacrificingfunctionality
Identifyingopportunitiestoimprovethedesalinationplantsoperationsandreliability
Identifyingrecommendationsforreducinglongtermoperationalcosts
Improvingtheoverallmaintainabilityofthefacility
EVALUATIONOFBASELINECONCEPT
ThefirstdayoftheVEstudyincludedmeetingswithCDMSmithand
otherprojectstakeholderrepresentatives.DuringtheVEteamsanalysis
ofthebaselineconcept,anumberofanalyticaltoolsandtechniques
wereusedtodevelopathoroughunderstandingofthefunctional
requirementsoftheprojectandhowwellthebaselineconceptwas
performingthefunctions.Amajorcomponentofthisanalysiswasthe
useofValueMetrics,whichseekstoassesstheelementsofcost,
performance,time,andriskastheyrelatetoprojectvalue.These
elementsrequiredadeeperlevelofanalysis,theresultsofwhichare
detailedintheProjectAnalysissectionofthisreport.Thekey
performanceattributesidentifiedfortheprojectarelistedinthetable
ontheright,PerformanceAttributes.
BelowisasummaryofthemajorobservationsandconclusionsidentifiedduringtheVEteamsinitial
analysisofthebaselineconceptwhichledtheVEteamtoidentifythealternativesresultingfromthis
studyandpresentedherein.
Buildingsarelocatedontheareaofthesitemostpronetosettlementduringaseismicevent.
Theprojectisassumingdeepdynamicsoilcompactiontoaddresscollapsiblesoils.
UVtreatmentappearstobeincludedtoaddresstemporaryuncertaintyregardingtreatment
processandconcernswithobtainingsufficientlogremovalforpathogenremoval.
Thecurrentdesignincludesdirectfeedfromintakestopressurefilterswhichcouldresultin
sandanddepositscloggingthesystem.
Thebaselineconceptassumesaportionoftheintakewatermustbereturnedaftertreatment
toagricultureproperties.
PerformanceAttributes
Maintainability
PlantOperations
FutureFlexibility
EnvironmentalImpacts
Sustainability
Aesthetics
- 2 -
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
TheprojectwillusegranularpressurefiltersforpretreatmentofseawaterpriortotheRO
membranestoremoveironandmanganese.
Thecurrentdesignisprovidingstoragetanksforfilteredwaterinordertomaintainconstant
pumpheadthroughtheROprocess.
Theprojectassumesabrinedisposalbasinwillbenecessarywhenwastewatertreatment
plant(WWTP)dischargeoutfallisnotavailable.
Thedesalinationplantmayhaveanissueremovinglargeequipmentformaintenancerelative
toaccessandequipmenttransport.
Thecurrentdesignshowspumpsinchemicalstoragesumps.Itisnotfullyunderstoodwhere
thepumpsdischarge.
Theprojectiscurrentlyplanningforrigorousacceptancetestproceduresandrequirements.
Theinstallationofpreengineeredmetalbuildingswillrequiretreatmenttopreventcorrosion
andwillrequiremaintenanceoverthelifeofthefacility.
Thecurrentprocessdesignisrecapturing45%ofthefirstpasstreatmentwaterand90%of
thesecondpasstreatmentwater(averageof43%totalrecoveryfortheplant).
Additionally,sustainabilityevaluationswereconductedtoassessthebaselineconceptagainstthe
sustainabilityrequirementsofboththeU.S.GreenBuildingCouncil(LEED)andtheInstitutefor
SustainableInfrastructure(Envision).TheresultingsustainabilityassessmentisincludedintheProject
Analysissectionofthisreport.
RISKANALYSIS
AqualitativeriskanalysiswasperformedinconjunctionwiththeVEstudytoidentifyrisksrelatedto
projectcost,time(schedule),andabilitytoperformitsrequiredfunctions.TheVEteamalso
discussedandidentifiedpossibleriskmitigationstrategiesinanefforttoreducetheoverallrisk
profileoftheproject.RiskRegistersweredevelopedfortheprojectandareprovidedintheProject
Analysissectionofthisreport.TheseRiskRegistersprovidealloftheinformationforeachrisk
includingdescriptions,probabilities,impactsandpotentialriskresponsestrategies.
Thefollowingarethekeylessonslearnedidentifiedasaresultoftheriskanalysisexercise:
Thereiscurrentlynorawwaterqualitydataavailable.Waterqualitymayimpactthe
assumptionsrelativetotheplantstreatmentprocessesandcapacities.
Plantcapacityrequirementsaredependentontheimplementationandsuccessofthe
groundwaterreplenishmentprojectwhichiscurrentlybeingdeveloped.
Approvaloftheenvironmentaldocumentsandregulatorypermitsmayrequirerevisionsto
theprojectdesign.
- 3 -
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
Amajorityoftherisksidentifiedarebeingactivelymonitoredandmanagedbytheprojectdesign
teamandprojectmanagementteams.KeyriskmitigationstrategiesidentifiedbytheVEteam
includedmembranepretreatmenttomitigatetheriskassociatedwithunknownsourcewaterquality,
andrevisingtheconstructionscheduletoallowtherespectivefeaturestimetoberevisedwhen
informationbecomesavailable.
VESTUDYRESULTS
TheVEteamidentified33VEAlternativesand13DesignCommentstosupportoverallprojectvalue.
TheVEAlternativesareorganizedbytheprimarytopicorprojectaspecttowhichtheyrefer:
BuildingDesignandSiteAlternatives
WaterTreatmentEquipmentandEquipmentLayoutAlternatives
MaintainabilityAlternatives
RiskMitigationandScheduleAlternatives
TreatmentProcessAlternatives
Ofthesealternatives,16wereselectedandrecommendedbytheVEteamasacumulatively
implementablealternativestrategyfocusedonenhancingoverallvaluepotentialfortheproject.The
alternativeshavebeensummarizedinthefollowingsectionofthisreport.Thetotalnetpotential
costsavingsoftheVEStrategyisapproximately$9millionininitialcostsavingsand$23millioninlife
cyclecostsavings.Itshouldbenotedthatanumberofthesealternativeswouldincreasetheinitial
projectcosts;however,theyinturnprovidebenefitstoprojectperformanceorinthereductionof
maintenanceandenergyusage.
ToevaluatetheperformanceoftheVEStrategy,theVEteamconsideredthecombinedeffectofall
VEalternatives.Thetotalperformancescoresreflecttheperformanceratingforeachattribute
multipliedbyitsoverallpriority(weight)expressedusingaratioscale.Thefollowingchartcompares
thetotalperformancescoresforthebaselineconceptandtheEnhancedValueVEStrategy.
ComparisonofPerformance
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
EnhancedValueCombination
BaselineConcept
Maintainability PlantOperations FutureFlexibility
EnvironmentalImpacts Sustainability Aesthetics
- 4 -
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
ThetablebelowsummarizesthesavingsassociatedwiththeEnhancedValueStrategy.The
performancescoresweredividedbythetotalcostscoresforthestrategytoderiveavalueindex.The
valueindexfortheVEStrategywasthencomparedagainstthevalueindexofthebaselineconcept
andthedifferenceisexpressedasapercentchange.
SummaryofVEStrategy
StrategyDescription InitialCostSavings
LCC
Savings
Performance
Change
Value
Change
EnhancedValueCombination $9,161,000 $23,204,000 +13% +29%
TheComparisonofValuechartbelowsummarizesthetotalimpacttoprojectvalueresultingfromthe
VEStudy.Thebluebarsrepresenttotalprojectperformanceandthegreenbarsrepresenttotalcost.
DetailsandadditionalanalysisofthebaselineconceptandVEStrategyperformanceratingsare
includedintheProjectAnalysissectionofthisreport.
ComparisonofValueBaselineConceptandVEStrategy
VEALTERNATIVEIMPLEMENTATION
VEstudiesareworkingsessionswiththepurposeofidentifyinganddevelopingalternative
approachestoagivenproject,thenpresentingthemtoallprojectstakeholdersforconsideration.
DuringtheVEStudy,aSpecialJointMeetingoftheMontereyPeninsulaWaterSupplyProject
GovernanceCommitteeandMontereyPeninsulaRegionalWaterAuthoritywasheldtopresentand
discussthepreliminaryresultsoftheVEStudy.Themeetingwasopentothepublicandattendees
hadtheopportunitytoquestionandcommentontheVEstudyresults.
0%
29%
0%
5%
10%
15%
20%
25%
30%
35%
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
Baseline EnhancedValue
C
h
a
n
g
e
i
n
V
a
l
u
e
R
e
l
a
t
i
v
e
S
c
o
r
e
s
Performance Cost/TimeRating ChangeinValue
- 5 -
MontereyPeninsulaWaterSupplyProjectDesalinationPlant ExecutiveSummary
Detailedfeasibilityassessment,determinationoftheVEalternativesimplementation,andfinal
designdevelopmentwillbemadefollowingsubmittalofthisFinalVEStudyReport.
VETEAM
ParticipantsontheVEteamincludedindependenttechnicalexpertsfromHDREngineering,Inc.and
WaterGloberepresentingArchitecture,PlantOperations/Maintenance,Sustainability(LEEDand
Envision),Civil/StructuralEngineering,Electrical/Instrumentation&Controls,andWaterTreatment
Processes.RepresentativesfromCaliforniaAmericanWateralsoparticipatedtoprovideinsightinto
theirPlantOperationsandMaintenanceproceduresaswellastheirengineeringstandardsand
requirementsfortheproject.ThepublicinterestswererepresentedbyMontereyPeninsulaRegional
WaterAuthorityandMontereyPeninsulaWaterManagementDistrict.Afulllistofparticipantsinthe
VEstudyisincludedfollowingtheValueEngineeringProcesssectionofthisreport.
- 6 -
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 9.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and provide direction on the power purchase
agreement between Cal Am and the Monterey Regional Waste
Management District (MRWMD).
RECOMMENDATION:
It is recommended that the Water Authority Board receive a report on the status of
negotiations between Cal Am and the Monterey Regional Waste Management District
(MRWMD) for renewable electrical power for the Desalination (Desal) facility.
DISCUSSION:
With support from the Water Authority, Cal Am and the staff of the MRWMD have
diligently worked on a term sheet and power purchase agreement to allow Cal Am to
acquire between 3.5 and 4.5 megawatts of renewable electrical power for the Desal
facility from the landfill. An electrical power study, funded by Cal Am, determined how
best to provide power "over the fence" and what equipment would be required.
The power purchase agreement that the MRWMD currently has with PG&E expires his
fall, and the District needs to obtain new customers for that power now. Unfortunately,
the current schedule for a CPCN decision by the CPUC prevents Cal Am from entering
into a purchase agreement at this time.
However, an agreement was reached by which MRWMD will seek short-term (3-5 year)
customers for its power allowing Cal Am to be considered as a longer term customer in
the 2017-2019 time frame. That will provide sufficient time for the Desal permitting
process to be completed, the CPCN issued, and for construction to advance far enough
along for Cal Am to be able to enter into a power purchase agreement and actually
utilize the renewable power. The attached staff report to the MRWMD board seeking
approval to advertise for power sales provides a good summary of the situation.
EXHIBIT:
A-MRWMD Staff Report on RFP for Renewable Power dated July 11, 2014
neral Manager
Memorandum
DATE:
TO:
FROM:
SUBJECT:
Reviewed by:
July 11, 2014
General Manager
Assistant General Manager
Issuance of a Request for Proposals for the Sale of Renewable Power
RECOMMENDATION: That the Board authorize issuance of a Request for Proposals for the sale of 8.2
megawatts of Renewable Power generated from the Landfill Gas to Energy Facility.
BACKGROUND
The District presently produces bundled renewable electricity and renewable energy credits (RECs) from the 5-
megawatt (MW) Landfill Gas (LFG) Power Plant located on site in Marina, CA. The current Power Sales
Agreement (PSA) for this is set to expire on February 28, 2015. In a parallel effort, the District is the process
of obtaining a new interconnection agreement with local utility PG&E for the ability to produce an additional up
to 3.2 MWs of LFG power in subsequent years. This would bring the District's total LFG power production up
to 8.2 MWs in future years. In order to finalize this new interconnection agreement, the District must make a
decision regarding anticipated power sale strategy for this new generation by September 2014.
DISCUSSION
District consultant Brennen Jensen has been working with staff to explore options for sale of the District's
renewable power produced from LFG, to include the existing 5 MWs (minus what the District uses on-site) plus
an additional 3.2 MW of new power to be produced from LFG. The District's current PSA (for 5 MWs) expires
early in 2015. The additional 3.2 MWs is anticipated to be phased in over time in two subsequent phases, based
on actual availability of LFG following the full installation of the permanent flare already underway. The first
phase anticipates the installation of 1.6 MWs within 18-24 months. The second phase anticipates an additional
1.6 MW within five years. At this time, the District is exploring options for a multi-year agreement for the sale
of this power, associated Renewable Energy Credits (RECs), and associated green attributes as summarized
below:
1. Marina LFG Facility (Up to 5 MWs, available beginning March 1, 2015)
o Bundled Renewable Electricity and Renewable Energy Credits (Bucket 1)
o Associated Green Attributes
2. Marina LFG Facility (Additional up to 3.2 MWs; installed in two phases, planned availability beginning in
2016)
o Bundled Renewable Electricity and Renewable Energy Credits (Bucket 1)
o Associated Green Attributes
14201 DEL MONTE BLVD
k BOX 1670 MARINA, CA 93933-1670 831/384-5313, FAX 831/384-3567 * www.mrwmd.org
PRINTED ON RECYCLED PAPER USING SOY-BASED INK
12
Issuance of RFP for Sale of LFG Renewable Energy
July 11, 2014
Page 2
One of the options for selling the District's power in the future, is to sell 5 MWs (more or less) "over the
fence" to the proposed CalAm Desalination Plant. On June 23', staff met with CalAm representative Ian
Crooks, and with Monterey Peninsula Regional Water Authority Executive Director Jim Cullem to allow each
to provide a status update. CalAm has continued interest to purchase the District's renewable power. Mr.
Crooks reported that their draft EIR will be released in August 2014, and final EIR approval is anticipated for
February 2015. CalAm would consider discussing a PPA in November or so of 2014 and could possibly
finalize a PPA by March 2015, if there are no delays in the EIR approval process. CalAm would not be
prepared to accept power from the District for at least three to five years, or more. This timing does not
integrate well with the District's need to respond to ongoing PG&E requirements to add additional generating
capacity and to replace the soon to expire PPA. The CalAm representative has indicated that CalAm is
supportive of this approach by the District and they plan to attend the Board meeting to voice that support.
Issuance of a RFP for the sale of 8.2 MWs of renewable power generated from the LFG to Energy Facility will
help to ascertain what opportunities are currently present within the marketplace for the existing and anticipated
LFG to energy power production, following the expiration of the current PSA.
FINANCIAL IMPACT
There is no financial impact to this request. Following the completion of the RFP process, staff will
recommend actions based on the responses provided. The RFP does not commit the District to entering into
any agreement with any responding party.
STRATEGIC PLAN
This item is in line with the Renewable Energy Production Policy within the strategic plan.
CONCLUSION
It is recommended that the Board authorize the issuance of a RFP for the sale of 8.2 MWs of renewable power
generated from the LFG to Energy Facility. Proposals will be due on August 15, 2014 and a staff report and
recommendation is anticipated for the August or September Board meeting.
o: \ If\ Ifg\ Ifg rfp board memo 714.docx
LFG PSA REP DRAFT
Monterey Regional Waste Management District
Request for Proposals for the Purchase of Renewable Electricity, Renewable Energy
Credits and Related Green Attributes at
Monterey Regional Waste Management District
(Marina, CA)
BACKGROUND
The Monterey Regional Waste Management District (District) is an award - winning 62- year - old
Special District and Joint Powers Authority (JPA), covering 853 square miles, representing eight member
agencies and comprising seventeen communities on the Monterey Peninsula from Moss Landing to Big
Sur. The District provides services to populations across the four counties of Monterey, Santa Cruz, San
Benito and Santa Clara. The District's mission is to provide the highest quality, cost- efficient, integrated
waste management services to the greater Monterey Peninsula, while preserving the environment and
protecting the public health through the reduction, reuse, recycling, and safe disposal of the region's
waste stream. The award winning agency has adopted and implemented a multitude of innovative and
integrated programs and policies over its extensive history, resulting in such prestigious recognitions as:
A Best Solid Waste System in North America by Solid Waste Association of North America
(SVVANA), 1998
Gold Excellence Award for Landfill Gas Utilization by SWANA, 2007
A pioneer in Landfill Gas (LFG) to Renewable Energy, the District established one of the first such plants
in the nation in 1983. For over 30 years, the District has practiced continued innovation in LFG capture
and beneficial utilization. The District currently generates 5MW of LFG renewable energy, and is in the
process of expanding the current plant to increase generation an additional 3.2 MW over the next several
years. The District further has a long- standing Renewable Energy Production Policy as a core objective
within their current strategic plan. As part of this continued commitment, the District also launched the
first in California dry fermentation anaerobic digester (AD) in 2013, using SmartFerm technology to
convert food scrap organics into Renewable Energy and high- quality soil amendment.
The District presently produces bundled renewable electricity and renewable energy credits (RECs) from
the 5MW LFG Power Plant located on site in Marina, CA. The current Power Sales Agreement for this
set to expire on February 28, 2015. The District is exploring options for a multi- year agreement for
the sale of the following products:
1. Marina LFG Facility (Up to 5MW, available beginning March 1, 2015)
o Bundled Renewable Electricity and Renewable Energy Credits (Bucket 1)
o Associated Green Attributes
Marina LFG Facility (Additional up to 3.2MW; installed in two phases, planned availability
beginning in 2016
o Bundled Renewable Electricity and Renewable Energy Credits (Bucket 1)
o Associated Green Attributes
The District is seeking Proposals for the purchase of any or all of these products for any duration of time.
Interested parties should express their interest including additional buyer requirements in their response.
Version: 7/11/14
LFG PSA RFP DRAFT
Responses that include creative options to maximize District revenue will also be considered. Reponses to
this Request for Proposals shall be used as the basis to enter into negotiations with selected respondents.
TENTATIVE SCHEDULE:
Supply Available:
Term of Agreement:
Product Available:
RFP Release Date
Proposals Due
Complete Proposal Review, Select Best Candidate(s), Begin Interviews
and/or Negotiations
Finalize Agreement(s) for Renewable Power Sales with selected
Candidate(s)
New PSA brought before MRWMD Board for final approval Jan 2015
Existing PSA Expires
New PSA Effective Date
LFG Renewable Energy
Monterey Regional Waste Management District
Reliable supplier of LFG renewable energy for over 30 years
Up to 8.2 MW-
5 MW, available immediately upon start date March 1, 2015;
Additional up to 3.2 MW available shortly thereafter in two phases:
(1.6 MW by 2016 + 1.6 MW anticipated circa 2020).
3-5 year term desirable, with option to extend (March 1-2015 to February
28, 2018/2020); Proposers may submit terms of any length as terms of
shorter or longer duration will be considered based on responses received.
Bundled Renewable Power & Renewable Energy Credits (Bucket 1) and
Associated Green Attributes
July 18, 2014
August 15, 2014
September 12, 2015
December 22, 2014
January 16(23), 2015
February 28, 2015
March 1, 2015
SUMMARY OF REQUEST:
Power:
Supplier:
Agreement Start Date: March 1, 2015
INTERESTED PARTIES
Interested parties should respond to this notice with a brief proposal providing the following minimum
information, including any additional buyer requirements:
1. Company Name and Primary Contact Information including: Name, Address, Phone, and Email.
2. Company Qualifications
3. Products of Interest
4. Desired Term
5. Breakdown Price Offering
6. Identify All Other Terms requested in PSA (Especially those which may affect Price Paid)
Version: 7111/14
LFG PSA REP DRAFT
7. Other Considerations, or Creative Offerings
SUBMISSION INSTRUCTIONS:
Proposals are due Friday August 15, 2014 @ 4pm PST. Proposals can be mailed, emailed or hand-
delivered.
Submit proposals to:
Mail Delivery:
Email Delivery:
Hand-Delivery:
Monterey Regional Waste Management District
Attn: Becky Aguilar, Administrative Support Supervisor
PO Box 1670
Marina, CA 93933
Please email submissions to both:
Becky Aguilar, Administrative Support Supervisor
baguilar@mrwmd.org
Tim Flanagan, Assistant General Manager
tflanagan@mrwmd.or2
Monterey Regional Waste Management District
Attn: Becky Aguilar, Administrative Support Supervisor
14201 Del Monte Blvd
Marina, CA 93933
[Note, site gates close at 4pm; proposals due by 4pm]
ADDITIONAL INFORMATION:
Additional facility information is available upon request. Please contact Brennen Jensen at
bjensen emergingecologies.com
or (831) 917-3720. Site visits can be arranged if requested.
Version: 7/1 1 /14
Monterey Peninsula Regional Water Authority
Agenda Report
Date: August 14, 2014
Item No: 10.
06/12
FROM: Executive Director Cullem
SUBJECT: Receive report, discuss, and provide direction on the City of Marina test
slant well Coastal Development Permit (CDP) and the current schedule for
Coastal Commission CDP.
RECOMMENDATION:
Staff recommends that the Water Authority receive an update from Cal Am on the
Marina Mitigated Negative Declaration (MND) for the Test Slant Well and discuss the
approval process and schedule to be followed in obtaining a City of Marina CDP and a
Coastal Commission CDP. The Authority should also receive an update on the National
Ocean and Atmospheric Administration (NOAA) Monterey Bay National Marine
Sanctuary (MBNMS) Environmental Assessment (EA).
DISCUSSION:
The City of Marina Planning Commission considered the MND and Marina CDP at its
meeting of July 10, 2014 but was unable to come to a decision. Accordingly, Cal Am
appealed the failure to act to the Marina City Council. The Council is scheduled to hear
the appeal at a special meeting on August 26.
In parallel with the Marina processing, Monterey Bay National Marine Sanctuary
(MBNMS) has circulated its draft federal Environmental Assessment (EA). The
Executive Director commented to the MBNMS in favor of the EA on behalf of the Water
Authority.
To keep the schedule on track and to conduct as much work as possible concurrently,
Cal Am brought the Request for Proposal (RFP) for the test slant well construction to
the Governance Committee on July 16, 2014.
The current Marina schedule for approval and construction of the test well and for the
hearing at the Coastal Commission is at Exhibit A.
Cal Am has been requested to brief the Water Authority on the status of the schedule.
EXHIBITS:
A- Cal Am schedule for approval and construction of the test slant well
FULL SCALE EIR & CCC/LCP SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 8:34:55 PM MST
CEMEX TEST WELL SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:06:15 PM MST
Exported on July 6, 2014 9:06:15 PM MST
FULL SCALE PLANT & PIPELINES SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:12:23 PM MST
POTRERO CONTINGENCY PERMITTING SCHEDULE - [WORKING PRODUCT & SUBJECT TO CHANGE]
Exported on July 6, 2014 9:10:38 PM MST