You are on page 1of 54

|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Revision Log Register

Document Number : PHEONWJIPRC-0005

Document Title

: Topside Inspection Procedure: Pressure Vessel

Revision

: 0

Pag

All

All
All
7

Date
Previous

27-Oct-

2009

17-Jan-

2010

17-Jan-

2010

13 to
17-Jan-

40
2010

24Feb-2010

24-Feb-2010

24-Feb-2010

Revise
Newly

developed Procedure, pages

remain the same as in previous IFA

revision

BPWJ to PHE ONWJ

Thorough

changes of any BP leftover

in both content and headers/footers

Added: The Inspector should at least

have attended FFS workshop level 1

and gain the related certificates

Rewriting and rearrangement of almost

all the contents and sections to

properly suit the need and workflow of

inspection, plus comments from PHE

ONWJ

Added in section 7 : Inspection and

Migas Recertification

Added in Section 1 : This procedure also

can be used for Migas recertification.

Added in section 7 : Inspection and

Migas Recertification Procedure

PHE ONWJ Reviewer

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 2 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Table of Contents

Topside Inspection Procedures: Pressure Vessel.......................................................1


Revision Log Register ....................................................................................................2
Table of Contents............................................................................................................3
1. Purpose........................................................................................................................6
2. Scope ...........................................................................................................................6
3. Responsibilities...........................................................................................................8
4. Definitions....................................................................................................................8
5. References...................................................................................................................9
6. Safety Requirements ..................................................................................................9
7. Inspection and Migas Recertification Procedures...................................................9

7.1. General................................................................................................................................. 9
7.2. Preparations....................................................................................................................... 10
7.2.1. Reviewing Documents................................................................................................. 10
7.2.1.1. Operating Permit ..................................................................................................10
7.2.1.2. Documents Dossier..............................................................................................10
7.2.1.3. Owner Documentation..........................................................................................10
7.2.1.4. Records................................................................................................................11
7.2.2. Inspection Preparation ................................................................................................ 11
7.3. Inspection Methods............................................................................................................ 11

8. Visual Inspection.......................................................................................................13

8.1. Internal Inspection.............................................................................................................. 14


8.1.1. Internally Lined Vessel:............................................................................................... 15
8.1.2. Loose Lining:............................................................................................................... 15
8.1.3. Integral Lining:............................................................................................................. 15
8.1.4. Protective Coating:...................................................................................................... 15
8.2. Main Points for Internal Visual Inspection.......................................................................... 15
8.2.1. Corrosion..................................................................................................................... 15
8.2.2. Erosion ........................................................................................................................ 15
8.2.3. Dents........................................................................................................................... 16
8.2.4. Distortion ..................................................................................................................... 16
8.2.5. Cuts or Gouges ........................................................................................................... 16
8.2.6. Linings......................................................................................................................... 16
8.2.7. Vessel Connections..................................................................................................... 16
8.2.8. Vessel Closures .......................................................................................................... 16
8.2.9. Vessel Internals........................................................................................................... 16
8.3. External Visual Inspection.................................................................................................. 16
8.3.1. Shell and Head............................................................................................................ 16
8.3.2. Manways, Nozzles, and Other Vessel Connections................................................... 17
8.3.3. Drains.......................................................................................................................... 17
8.3.4. Piping........................................................................................................................... 17
8.3.5. Safety Controls............................................................................................................ 17
8.3.6. Pressure Safety Relief Valve....................................................................................... 17
8.3.7. External Corrosion - General:...................................................................................... 17
8.3.8. Lined Vessel:............................................................................................................... 17
8.3.9. External Coating:......................................................................................................... 18
8.3.10. Corrosion/Pitting:....................................................................................................... 18
8.3.11. Insulation or Other Coverings:................................................................................... 19
8.3.12. Intrusion:.................................................................................................................... 20
8.3.13. Foundation, Supports, Skirts, Attachments including Bolts & Nuts:.......................... 21
8.3.14. Weld Joints................................................................................................................ 21
8.3.15. Non-welded Joints:.................................................................................................... 22
8.3.16. Mechanical Damage:................................................................................................. 22
8.3.17. Dissimilar Metals:...................................................................................................... 22
8.3.18. Vibration: ................................................................................................................... 22
8.3.19. Non-Conformity to design:......................................................................................... 22
8.4. Digital Photography:........................................................................................................... 22

9. Non-Destructive Examinations (NDE).....................................................................23

9.1. Commonly Used NDE Techniques .................................................................................... 23

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 3 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.1.1. UT Compression Technique (UT Wall Thickness Measurement)............................... 23


9.1.2. Liquid Penetrant Examination ..................................................................................... 23
9.1.3. Magnetic Particle Examination.................................................................................... 23
9.1.4. In-situ Metallographic Examination............................................................................. 24
9.1.5. Infrared Thermographic Examination.......................................................................... 24
9.2. Determination on the Location of Deterioration ................................................................. 24
9.3. Marking, Identification, and Numbering Method ................................................................ 24
9.3.1. Reference Location Marking: ...................................................................................... 24
9.4. Rubbing Name Plate.......................................................................................................... 25
9.5. Determining Locations for Wall Thickness Measurements................................................ 25
9.5.1. Shell............................................................................................................................. 26
9.5.1.1. Longitudinal Orientation........................................................................................26
9.5.1.2. Circumferential Orientation...................................................................................26
9.5.2. Head............................................................................................................................ 28
9.5.2.1. Ellipsoidal Head....................................................................................................28
9.5.2.2. Flat / Disk Head...................................................................................................30
9.5.3. Nozzle Blind Flanges and Couplings .......................................................................... 30
9.5.4. Special Condition ........................................................................................................ 31
9.6. Ultrasonic Scanning for Flaw Detection & Corrosion Survey............................................. 31
9.6.1. Oil and Gas Separator / Heat Exchanger.................................................................... 31
9.6.1.1. Horizontal Installation...........................................................................................31
9.6.1.2. Vertical Installation ...............................................................................................32
9.6.2. Water Tank and Diesel Fuel Storage.......................................................................... 32
9.6.2.1. Horizontal Installation...........................................................................................32
9.6.2.2. Vertical Installation ...............................................................................................33
9.7. Weld Joint Inspection......................................................................................................... 33
9.7.1. "T" joint........................................................................................................................ 33
9.7.2. Longitudinal Weld Joint (excluding "T" joint)............................................................... 34
9.7.3. Circumferential Weld Joint .......................................................................................... 34
9.8. Magnetic Particle Inspection.............................................................................................. 34
9.9. Hardness Tests.................................................................................................................. 34
9.9.1. Shell Side .................................................................................................................... 35
9.9.2. Head Side.................................................................................................................... 35
9.9.3. Nozzle and Reinforcement Pad................................................................................... 35
9.10. Combination of UT Scan and Wall Thickness Measurement .......................................... 35
9.10.1. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

General Head and Shell Sketch for WTM:........................................................... 35


9.10.2. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 1 ID or OD of up to 18 inches:....................................................................... 36
9.10.3. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 2 ID or OD of over 18 inches up to 48 inches: .............................................. 37


9.10.4. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 3 ID or OD of over 48 inches up to 144 inches: ............................................ 37


9.10.5. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 4 ID or OD of over 144 inches up to 288 inches: .......................................... 38


9.11. Insulated Vessels............................................................................................................. 39
9.11.1. Size of Wall Thickness Measurement Windows in Insulated Vessels...................... 39
9.11.2. Location of Wall Thickness Measurement Windows in Insulated Vessels ............... 39

15. Reviews and Revisions ..........................................................................................44

Attachments and Reference Forms ........................................................................... 44

10. Corrosion Rate Calculation....................................................................................40


11. Calculations of the Maximum Allowable Pressure (MAWP) ...............................40
12. Unknown Document Record..................................................................................41
13. Conclusions and Acceptance Criteria ..................................................................42
14. Reports and Recommendations............................................................................42

14.1. Reports............................................................................................................................. 42
14.2. Recommendations........................................................................................................... 44

Attachment A. Vessel Inspection Report ....................................................................... 45


Attachment B. Vessel Thickness Measurement Report ............................................... 46

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 4 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Attachment C. Change of Pressure Vessel Condition Form ........................................ 47

Attachment D. History Card ............................................................................................. 48

Attachment E. Quick Opening Closure Visual Inspection Report ..................... 49 - 54

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 5 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

1. Purpose

This procedure was developed for general topside facility inspection as well as risk

based inspection of pressure vessels / equipment operated in PHE ONWJ. This

procedure also can be used for Migas recertification. It was intended to ensure that all

inspections are carried out to the correct standards, and in a safety and uniform manner.

2. Scope

This procedure applies to pressure equipment constructed in accordance with the API /

ASME codes, and other recognized pressure vessel codes. The procedure is applicable

to both new pressure vessels and those already placed in service. The pressure

vessels to be inspected and re-certified are those considered to be in good condition to

be re-certified (no repair works are required).

Scope of the procedure covers:

External inspection,

Internal inspection,

Repair,

Alteration,

Re-rating,

PSV re-testing,

Evaluation, and

Work team coordination.

Normally, all inspections should be conducted without opening up the equipment. The

pressure vessels need only be opened up for thorough internal inspection when:

a. It is not possible to carry out a meaningful inspection using non-intrusive inspection

techniques applied externally (i.e. capable of detecting those defects which might

reasonably be expected to exist), and

b. Internal inspection becomes a requirement, i.e. when a probability of deterioration

mechanisms related to process environment induced cracking exists , and where

critical there is a requirement to inspect internal parts (i.e. tubes, baffle plate , etc).

Followings are the reasons when inspection becomes a requirement:

ACTIVITIES

Un-Insulated Vessel:

Head

Manways

Nozzles

External inspection of shell

Foundation & Support

Attachments support feet/skirt

Associated platforms and access

ladders

Earth connections

Anchor Bolts

Auxiliary Equipment (Bridle)

REASONS

Possible cracks, blister, bulges, and

other sign of deterioration

Possible breakdown of External paint

coating

Corrosion at water traps

Evidence of leakage

Presence and tightness of holding

down bolts

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 6 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

ACTIVITIES

The table is continued from the previous page

For skirted Vessel with fire proofing

Examine for cracking or detachment of

fire-proofing

Evidence of staining from corrosion

product

Adequacy of weather sealing

For insulated Vessel:

Head

Sample area insulation removal at

lagging intrusions around nozzles and

shell attachments

At discretion of Inspection Authority:

Shell, Head, and Nozzles

Key point thickness survey of vessel

shell and nozzles

If stress survey identifies high stress

connections:

External crack check on weld and HAZ

areas

If vessel is lined:

An internal inspection is required

REASONS

Deterioration of fireproofing allowing

access of moisture with subsequent

hidden corrosion.

Moisture ingress with subsequent

corrosion. Evidence of shell paint

coating breakdown

Internal general corrosion

For insulated vessel, also checked for

external corrosion at key-point plugs

Detachment of lining or breakdown of

coating

Bulging of either lining or coating

Corrosion of lining or cladding

material

Internal inspection of all attachments to


Localized preferential corrosion at

lining or shell

coating breakdown or discontinuities

Failure of attachments

Crack detection on all internal welds of


Stress cracks in weld and Heat

identified high stress nozzles

Affected Zone

If vessel is not lined or cladded:

Close visual inspection of all welds/HAZ

for corrosion or cracking

Note: Every window of opportunity should be taken for conducting internal inspection; for

example, when the pressure vessel is opened up for process clean up, or for the

recharge of catalysts or other bed materials.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 7 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

3. Responsibilities

3.1. Authorized Inspector (AI) is responsible for issuing this procedure, as required for

the implementation of recertification program, RBI assessment result and ad hoc

inspection.

3.2. Only Authorized Inspector/s shall perform internal and / or external visual inspection,

in accordance with this procedure

3.3. Only Certified Examiner/s, using a qualified Procedure that has been reviewed and

endorsed by the related Authorized Inspector, shall carry out Non Destructive

Examination in accordance with this procedure.

3.4. The Inspector should at least have attended FFS workshop level 1 and gain the

related certificates.

4. Definitions

Alteration

: A physical change in any component or a rerating that has

design implications that affect the pressure-containing

capability of a pressure vessel beyond the scope of the

items described in existing data reports.

Authorized Inspector (AI) :


Personnel who is qualified and certified to perform

the functions specified in API 510.

Consequence Rating : The consequence of failure based on the evaluation of 8

criteria representing operational, economic and

environmental factor. Consequence rating is divided into 3

categories: high, medium & low.

Criticality Rating
: Risk ranking on the basis of risk matrix, that representing

risk as the result of probability of failure and the

consequence of failure.

Inspector
: An authorized Pressure Vessel inspector.

MAWP
: Maximum Allowable Working Pressure for a Vessel is the

maximum gauge pressure permissible at the top of the

vessel in its normal operating position at the designated

coincident temperature specified for that pressure.

NDT Examiner
: Person who assist AI in performing specific Non Destructive

Examination. The examiner shall hold the related NDT

certification to the method being used.

Probability Rating
: The probability of failure based on the evaluation of

appropriate failure modes according to a model or a set of

agreed rules. Probability rating is divided into 3 categories:

high, medium & low.

RBI
: Risk Based Inspection

Repair
: A repair is the work necessary to restore a pressure vessel

to a condition suitable for safe operation at the design

conditions.

Rerating
: A change in either or both the design temperature or the

maximum allowable working pressure of a pressure vessel.

TMLs
: Thickness Measurement Locations, designated areas of

pressure vessels where periodic inspections and thickness

measurements are conducted.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 8 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

5. References

Keputusan Direktur Jenderal MIGAS No. 84.K/38/DJM/1998

NBIC ~ 23 National Board Inspection Code

API ~ Guide for Inspection of Refinery Equipment, Chapter II, Conditions Causing

Deterioration of Failures

API 510 ~ Pressure Vessel Inspection Code

API RP 572 ~ Inspection of Pressure Vessel

API 579 ~ Fitness for Service Standard

API RP 580 ~ Risk-Based Inspection

API Publication 581 ~ RBI Resource Based Document

API 660 ~ Shell & Tube Heat Exchanger for General Refinery Service

API 750 ~ Management of Process Hazard

ASME ~ Section II, V, VIII, and IX

ASME ~ Boiler & Pressure Vessel Code Sect. V-1, Non Destructive Examination

ASME ~ Boiler & Pressure Vessel Code Sect. VIII Div.1, Pressure Vessels

ASME ~ Boiler & Pressure Vessel Code Sect. X, Welding and Brazing Qualification

ASNT ~ SNT-TC-IA, Standard of Qualification & Certification of Non Destructive

Testing Personnel

NACE RP-0169 ~ Control of External Corrosion on Underground of Submerged

Metallic Piping System

TEMA ~ Standard of Tubular Exchanger Manufacturing Association

TEMA Class "R" for Heat Exchanger

PHEONWJ-PRC-201-A ~ Procedure of Pressure Vessel for Inspection and

Recertification

NDT Manual No. PHEONWJ-PRC-211-A

ARII Specification: ARII-MS-600 for Air Cooler Heat Exchanger

ARII Specification : ARII-MS-250 for Unfired Pressure Vessel

Other Code and Practices, Standard, Specification related to design, construction,

and maintenance of In-Service Pressure Vessels.

6. Safety Requirements

The Inspection of Pressure Vessel may be performed in both on stream or shutdown

conditions. If the Pressure Vessel is insulated, the user shall prepare the access

windows to perform NDT. Details of inspection windows are attached in Section 8.3.2.

The implementations of this procedure, either related to Personnel, Equipment, Methods,

or Techniques, shall fully comply with all the requirements of Health Safety and

Environmental (HSE) Standards & Practices, without jeopardizing any of Government

Regulation and Legislation.

7. Inspection and Migas Recertification Procedures

7.1. General

The Inspection and recertification of Pressure Vessels consist of 4 main activities, i.e.:

Inspection Preparations, which include reviewing documents and supporting

data,as well as other pre-inspection activities, such as removing inspection plugs,

Performing actual Field Inspection,

Preparing Recommendations, and

Reporting & Documenting.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 9 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

For the sake of this procedure, the Pressure Vessels (PVs) are classified into 4 groups,

based on their diameter (either internal or external), as the followings:

Group 1
Group 2
Group 3
Group 4

:
:
:
:

for PV of up to 18-inches in diameter (internal or external),

for PV of over 18-inches up to 48-inches in diameter,

for PV of over 48-inches up to 144-inches in diameter, and

for PV of over 144-inches up to 288-inches in diameter.

7.2. Preparations

In this preparation section, two major items are gathering and reviewing the information,

and the pre-inspection activity which mainly involve the removal of inspection plugs.

The following information should be made available to support the inspection, and

inspection results evaluation:

Process Description and Process Flow Diagram

Process and Instrument Diagram (P&ID)

Design and Operating Condition Data

Pressure Vessel Manufacturing Design & Inspection Data Report

Service and Fluid Composition Data, if required

Insulation Material Specification, if any

Protective Coating Specification

Corrosion Control & Corrosion Monitoring Data, if any

Pressure Vessel Inspection, Repair, Alteration & Maintenance Historical Data

7.2.1. Reviewing Documents

The following document should be reviewed before the inspection:

7.2.1.1. Operating Permit

Date of the last inspection

Design pressure and temperature

Location of installation

Item and Serial number

Current jurisdictional inspection certificate (if any)

National Board and/or jurisdictional registration number (SKPP)

7.2.1.2. Documents Dossier

Manufacturer data report / Form U1

ASME Code Symbol Stamping or mark of code of construction

Item and Serial number

Material of the shell, head, nozzle, etc.

Corrosion Allowance

Design pressure and temperature

As built drawings

Copy of Name plate

7.2.1.3. Owner Documentation

Inspection Organization Chart

Quality Assurance Inspection Manual

Maintenance Record / History Card

P&ID Drawings

Non Conformity Record

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 10 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

HSE Manual

PSV Data Sheet I Certificate

7.2.1.4. Records

A review of any Pressure Vessel logs, maintenance records, or any other tests

should be made by the inspector. The owner or user should be consulted

regarding repairs made since the last inspection. The inspector should review

such repairs for compliance with applicable requirements.

Besides, the following records shall also be reviewed prior to performing

inspection

History of operating condition,

Normal contents of the vessel,

Records of wall thickness checks and corrosion monitoring data, especially on

vessel where corrosion is a consideration.

7.2.2. Inspection Preparation

Special preparation should be performed as requirement to support the inspection,

especially for complete internal inspection during shutdown:

1. Inspection plugs and covers should be removed.

2. Vessel should be sufficiently cleaned to allow for visual inspection of internal and

external surfaces.

If the pressure vessel has not been properly prepared for an internal inspection, the

works shall be postponed.

7.3. Inspection Methods

The Consequence of Failure shall determine the extent of the inspection High

Consequence items require a more extensive of inspection than Medium or Low

Consequence items.

Each Examination shall incorporate an evaluation of the various inspections:

visual and supplemental NDT carried out on the vessel during the previous

endorsement period,

a review of operating parameters, and any changes in duty, which may have

occurred, and

an assessment of any corrosion monitoring measurements taken during the

endorsement period (if any).

The inspection scope should include an external visual inspection and assessment of

internal condition. Internal inspection may not be required, if the vessels internals

condition can be accurately assessed by using non-intrusive inspection methods (such

as ultrasonic mapping). Alternately, at may be possible to utilize supplemental visual

inspection aids (such as video cameras or boroscopes), to negate the need for full

vessel entry.

Table 1 suggests minimum requirements for Limited, Partial and Close (Detailed) Scope

of internal assessment. The selection of method should be done during inspection

planning based on the technology available and on an economic assessment of cost and

benefit of non intrusive inspection.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 11 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Table 1. Minimum Requirements for Internal Assessment

Low Consequences of

Medium Consequences of

Failure Limited

Failure General Assessment

Assessment

Boroscope

Boroscope and External NDT

Or

Or

High Consequences of

Failure Detailed

Assessment

External NDT and

Corrosion Monitoring and

Process Review

Or

External NDT

Internal Entry

Internal Entry

Process Review

Process Review & External NDT

Or

Or

The choice of non-destructive inspection method is based on the probability of failure.

Methods are chosen to detect the likely failure modes.

The guidance is shown on Table 2. The final selection of method should be made at the

time that inspection is being planned based on the available technology and on

economic choice.

Table 2. NDT Inspection Methods

Failure Mode

Mechanisms

NDT Methods

Internal Wall Thinning

Internal Corrosion

Erosion

Cavitations

Weld Corrosion

External Corrosion

Corrosion Under Insulation

Ultrasonic

Radiography

External Wall Thinning

Cracking

Other

Visual Inspection

Radiography

Thermography

Advanced Eddy

Current Test

Fatigue

Ultrasonic

Stress Corrosion Cracking

Radiography

Wet Hydrogen Damage

Magnetic Particle

Liquid Penetrant

Creep

Ultrasonic

Hot Hydrogen Damage

Radiography

High Temperature Embrittlement


Magnetic Particle

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 12 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Table 3 shows the Summary of Inspection Plan developed for Pressure Vessels as

recommended following the results of RBI assessment tools.

Table 3. Summary of NDT Inspection Plan

No.

Damage Mechanism

External Corrosion (Corrosion Under

Insulation) for Carbon Steel Material

2
3
4
5

Inspection Methods

External Visual, and Infrared

Thermography, or Advance Eddy

Current Test as required

External Crack (SCC due to Corrosion


External Visual, and (Liquid Penetrant

Under Insulation) for Austenitic

Test, as required) and (Infrared

Stainless Steel Material

Thermographv, as required)

Internal Crack (Stress Corrosion

Internal Visual, and Liquid Penetrant

Cracking)

Test or Magnetic Particle Test (and In-

situ Metallographic, if found)

Internal Crack (Wet Hydrogen Cracking)


Internal Visual and Wet Magnetic

for Carbon Steel Material

Particle Test (and In-situ metallographic,

if found)

Internal Corrosion
Internal Visual or (Ultrasonic Corrosion

Scanning) and Corrosion Monitoring (for

High Consequences Ratings)

8. Visual Inspection

The extent of visual inspection includes:

Shell and Head:

The surface of a shells and heads of possible cracks, blisters, bulges and other

evidence of deterioration, giving particular attention to the skirt and to support

attachment and knuckle region of the heads. If evidence of distortion is found, it

may be necessary to make a detailed check of the actual contours and

dimensions with the original design details. A detailed check on the contours

may be performed using a contour gauge.

Quick Opening Closures:

The quick opening closures include pig launchers and pig receivers doors.

Depending on the type of the closures, the visual inspection of these quick

opening closures should cover:

- caps

- cap pins

- hinges/davits

- weld joints

- hinge bolts and nuts

- handles

- head lugs

- cam handle

- eye bolt

Man-ways, nozzles and other openings:

Inspect the surface of man-ways, nozzles, and other openings for possible

distortion, cracks and other deteriorations. Examine accessible flange faces for

distortion and to determine the condition of gasket seating surfaces.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 13 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Drains:

Check the drainage is provided where required. Where provided and when

practicable, the drain should be opened to ensure that it function properly.

Piping:

Piping components attached to the vessel should be checked for indications of

inadequate support or provisions for expansion, which may cause excessive

loading on the vessel.

Appendages:

Any safety and instrument device installed for safety of the vessel should

demonstrate it function by verification of its correct and proper operation.

Pressure Relieving Device

Should be checked for the set pressure, and the date of the last inspection

against the requirements

Insulation:

Where there is evidence of leakage shown on the coverage or through the

insulation, the insulation shall be removed to the extend necessary, to make a

complete investigation.

Vessel Identification:

Inspect and ensure that all marking (included name plate and other

stamps/marking) are meeting the related statutory/legislation requirements.

The Authorized Pressure Vessel Inspector, using his experience and judgement to

determine the extent of the inspection during the development of the work-pack.

8.1. Internal Inspection

The vessel needs to be opened up for thorough internal inspection when it is not

possible to carry out a meaningful inspection using non-intrusive inspection

techniques applied externally (i.e. capable of detecting those defects which might

reasonably be expected to exist).

In addition, internal inspection is a requirement when a probability of deterioration

mechanisms related to process environment induced cracking exists.

In the event that internal access is necessary, it may require the removal of internal

fittings to enable access to all internal surfaces. In case of shell-and-Tube with

retractable tube-bundle type Heat Exchanger, internal inspection is conducted on

shell, channel and other parts of the exchanger, once tube-bundle is fully or partially

retracted on shell. The vessel shall be clean and free from deposits, which may

mask a likely defect. It is essential that Inspectors are aware of the condition prior to

cleaning and have the opportunity to collect deposit samples for later analysis should

it prove necessary. In addition, the effects of such deposits on the local corrosion

regime must be assessed and the examination requirements modified accordingly. In

such cases, care shall be taken of any hazard the deposits may pose to individuals

handling them and that all necessary precautions are taken to prevent any harm

coming to these individuals.

If internal inspection has been demanded, the following areas or components shall be

subject to a visual inspection to detect evidence of corrosion or stress or deformation:

All internal plate surfaces with particular attention paid to areas associated

with:

a) External support attachments, and

b) Liquid interfaces and

c) Internal deposits;

All nozzle attachments with particular attention paid to those with external

re-enforcing pads or those, which are subject to high or fluctuating stresses;

All shell attachments for internal fittings.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 14 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

8.1.1. Internally Lined Vessel:

Where a vessel is internally lined, every effort shall be made to adopt inspection

techniques, which will negate the need for internal entry, as this could have a

detrimental effect on the condition of the lining. If an examination cannot be

carried out without an internal inspection being performed, the internal and

external requirements shall be modified, having consideration of the following:

8.1.2. Loose Lining:

Any perforation may result in severe corrosion in the void between shell and

lining. Examination practices shall therefore seek to detect both the perforations

and the consequent corrosion. This will require the application of a range of NDT

techniques applied internally and externally. Where tell-tale holes are provided

in the shell, evidence of lining perforation should be sought on a routine basis

during operation.

The results of such monitoring inspections must be considered before a thorough

examination is carried out.

8.1.3. Integral Lining:

Should the lining be of the integral type (i.e. hot roll clad; explosive bond or weld

deposit) wall thickness measurement is likely to detect the-lining-to-shell

interface and may prove unsatisfactory. In these cases, both internal and

external measurements must be taken where areas of disbanding are significant.

Particular attention shall be paid to vessel heads. Since these areas have been

formed after lining application, disbandment is likely to be significant. In the

case of lining of the weld deposit type, visual inspections of surfaces shall seek

to find areas of localized corrosion at weld deposit inclusions or areas of weld

metal dilution from parent plate.

8.1.4. Protective Coating:

Where a protective coating has been applied to the internal surfaces, a visual

inspection shall be carried out to determine whether any coating breakdown,

blistering or other coating defects have occurred.

8.2. Main Points for Internal Visual Inspection

Pressure Vessels containing non-corrosive substances may require only an External

Inspection. Such Vessels may not be provided with manholes or other Inspection

openings. In this case the Inspector may accept nondestructive testing (NDT)

methods of examination to determine the condition of the Vessels. All of the visual

inspection finding shall be documented using digital camera. The Inspector should

check the surfaces of the shells, heads, man ways, nozzles and other opening for

possible deterioration on the Internal of Vessel as follows:

8.2.1. Corrosion

Where active or excessive Corrosion is found, remedial action should be taken.

The Inspector should thoroughly examine the Vessel for the following types of

Corrosion:

Pitting

Line Corrosion

General Corrosion

Grooving

Galvanic Corrosion

8.2.2. Erosion

The Inspector should note any action caused by abrasives and high velocity

streams which may erode the surfaces of the metal.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 15 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

8.2.3. Dents

Dents in a Vessel are deformations caused by their coming in contact with a

blunt object in such a way that the thickness of metals is not materially impaired.

In some cases, a Dent can be repaired by mechanically pushing out the

deformation.

8.2.4. Distortion

If any Distortion is suspected or observed, the overall dimensions of the Vessels

shall be checked to determine the extent and seriousness of the Distortion.

8.2.5. Cuts or Gouges

Cuts or Gouges are caused by contact with sharp objects in such a way as cut

into the metal decreasing the wall thickness. Cuts and Gouges can cause high

stress concentrations and depending upon the extent of the defect, it may be

necessary to repair the area by welding or patching. Blend grinding may be a

useful method of eliminating some minor types of Cuts or Gouges.

8.2.6. Linings

Where evidence on the lining is found, it may be necessary to make a detailed

check with nondestructive testing methods.

8.2.7. Vessel Connections

Threaded connections should be inspected to ensure that an adequate number

of threads are engaged. All openings leading to external fittings or controls

should be examined as thoroughly as possible to ensure they are free from

obstruction.

8.2.8. Vessel Closures

Any special closures including those on autoclaves, normally termed quick

actuating (quick opening) closures which are used frequently in the operation of

a pressure vessel, should be checked by the Inspector for adequacy and wear.

A check should also be made for cracks at areas of high stress concentration.

8.2.9. Vessel Internals

Where pressure vessels are equipped with removable internals, these internals

need not be completely removed, provided assurance exists that deterioration in

regions rendered inaccessible by the internals is not occurring to an extent that

might constitute a hazard or to an extent beyond that might constitute a hazard

or to an extent beyond that found in more readily accessible parts of the vessel.

If a preliminary inspection reveals unsafe conditions such as loose or corroded,

internals or badly corroded internal ladders or platforms, steps should be taken

to remove or repair such parts so that a detailed inspection may be made.

8.3. External Visual Inspection

The examination consists of an external visual examination supported by

supplemental non-intrusive NDT on those areas most likely to suffer deterioration.

Operating conditions shall be confirmed as remaining substantially the same and any

excursions from normal operation shall be reviewed for their on corrosion or other

failure mechanisms. The external inspection should be able to report the following

items:

8.3.1. Shell and Head

Inspect the surfaces of shells and heads for possible cracks, blisters, bulges and

other evidence of deterioration, giving particular attention to the skirt and to

support attachment, and knuckle regions of the heads. If evidence of distortion

is found, it may be necessary to make a detailed check of the actual contours

and dimensions with the original design details.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 16 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

8.3.2. Manways, Nozzles, and Other Vessel Connections

Manholes, reinforcing plates, nozzles or other connections should be examined

for cracks, deformation or other defects. The bolts and nuts should be checked

for corrosion or defects. The weep holes in reinforcing plates should remain

open to provide visual evidence of leakage as well as to prevent pressure build

up between the vessel and the reinforcing plate.

Also inspect the surfaces of manways (including ladders, platform, walkways,

and stairways), nozzles, and other openings for distortion, cracks, and

accessible defects. Examine accessible flange faces for distortion and to

determine the condition of gasket seating surfaces including the condition of

bolts. Also check yhe anchot bolts and grounding connections.

Any auxiliary equipment should also be checked for its condition.

8.3.3. Drains

Check that drainage is provided where required. Where provided and when

practicable, the Inspector should have the drain opened to ensure that it

functions properly.

8.3.4. Piping

Piping components attached to the Vessel should be checked for indications of

inadequate support or provisions for expansion which may cause excessive

loading on the Vessel shell.

8.3.5. Safety Controls

Any safety device (pressure gauge, temperature gauge, level glass, etc) installed

for safety of the Vessel should be demonstrated by operation for verification of

correct and proper operation.

8.3.6. Pressure Safety Relief Valve

The Inspector should check that the required set pressure and the date of the

last Inspection. The Valve should be removed from service at the time of

shutdown or at a frequency agreed to by the Owner and the Inspector.

8.3.7. External Corrosion - General:

Where the vessel is un-insulated, atmospheric corrosion must be considered at:

pipe support attachments,

platform attachments,

expansion bellows,

and other locations where moisture traps are possible.

Note:

Where the associated piping materials are subject to Stress Corrosion Cracking

or Corrosion Fatigue, supplemental NDT such as:

liquid penetrant testing,

magnetic particle testing, or

eddy current testing

should be applied at those nozzle areas most likely to exhibit the deterioration.

If deterioration is found, the remaining life of the component must be assessed,

although in the case of Stress Corrosion, the material shall be considered

unsuitable for any further service regardless of whether or not leakage is found.

8.3.8. Lined Vessel:

Where "tell-tale" holes are provided, these shall be checked for evidence of

leakage. In the event that these are fitted with valves, they should be checked as

being open and clear. Any closed valves should have been logged in the

operating records and this must be checked.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 17 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Note: If either leakage or close valves are found, external NDT should be

applied to detect corrosion at the inner shell surface.

8.3.9. External Coating:

The condition of the external coating on the various coating on the various

components shall be reported against the following criteria, which shows the

percentage of area having coating breakdown in comparison to the total coated

area. If the equipment is insulated, the condition of any exposed steel shall be

reported against the same criteria.

(G) Good : 0% 5% Coating Breakdown

(F) Fair : 5% 20% Coating Breakdown

(P) Poor : 20% 70% Coating Breakdown or a breakdown of coating in soil

encroachment areas

(B) Bad : 70% 100% Coating Breakdown

(G) and (F) are considered Acceptable but (P) and (B) should be reported.

The following table of photos illustrates the ratings based on coatings condition:

Ratings Example 1

Example 2

8.3.10. Corrosion/Pitting:

The condition of the exposed steel shall be reported against the following

criteria:

(G) Good : No evidence of corrosion taking place affected should be

carefully noted for future inspection and possible removal.

(F) Fair : Some light surface corrosion has taken place but only sufficient

to produce a light, powdery corrosion product.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 18 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

(P) Poor : Scattered patches of corrosion/pitting producing a significant rust

film.

(B) Bad : Large areas of corrosion/pitting have resulted in thick corrosion

products.

(G) and (F) are considered Acceptable but (P) and (B) should be reported.

Where the condition is (P) Poor or (B) Bad, the report shall detail the location,

extent and depth of the anomaly together with the thickness of the adjacent

pipe/pipe, fitting/vessel wall.

The following table of photos illustrates the ratings based on visual inspection

of corrosion level:

Ratings Example 1

Example 2

8.3.11. Insulation or Other Coverings:

If it is found that the external coverings such as insulation and corrosion

resistant linings are in good condition and there is no reason to suspect any

unsafe condition behind them, it is not necessary to remove them for inspection

of the vessel.

However, where there is evidence of leakage of gas, vapor, or liquid showing

on the coverage or through the insulation, the cover should be removed to the

extent necessary to make a complete investigation until the source is

established.

For an evidence of damage on the surface painting, the surface should be re-

painted.

The condition of the insulation on the various components shall be reported

against the following criteria:

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 19 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

(G) Good

: No signs of damage are apparent and there is no

evidence of water ingress or corrosion having occurred.

(F) Fair
: Slight damage has occurred to the cladding e.g. small

indents, buckling etc. but with no loss of seal integrity.

(P) Poor : Significant damage has occurred such that water ingress

could occur. Underlying insulation is not exposed.

(B) Bad
: Significant damage has occurred such that water ingress

could occur. Underlying insulation is exposed to the

elements.

(B1) Staining : The outer cladding or adjacent steel is showing signs of

rust staining indicative of corrosion of the underlying steel

having occurred. (Care must be taken when reporting on

this that the staining is not caused by another source, e.g.

due to chemical).

(B2) Exposed : The condition of the cladding is good but areas have

either been removed or have never been installed such

that the underlying steel or insulation is exposed, e.g.

where insulation is terminated at a flanged joint.

(B3) Wet
: The underlying insulation is observed and found to be wet.

When damaged insulation is to be repaired and opened for inspection, pay

attention to check the condition of the underlying steel and see if water has

ingressed or corrosion has occurred. The following picture shows an example

of an opened insulation to inspect the underlying steel.

See illustration below.

8.3.12. Intrusion:

It is important that the condition of the insulation around any intrusions into the

insulation (i.e. pipe hangers, supports, branch connections etc.) is reported as

these sites are the ones most likely to allow water ingress to occur. The areas

affected should be carefully noted for future inspection and possible removal.

Please note if removal would cause any specific problems in that area.

(G) and (F) are considered Acceptable but (P) and (any B) are reportable. Where

the condition is (P) Poor, (B) Bad, (B1) Staining, (B2) Exposed, or (B3) Wet the

report shall detail the location and nature of anomaly.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 20 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

8.3.13. Foundation, Supports, Skirts, Attachments including Bolts & Nuts:

Foundation and supporting components attached to the Vessel should be

checked for indications of inadequate support or provisions for expansion that

may cause excessive loading on the Vessel shell. The pressure vessel

mountings should be checked for adequate allowance for expansion and

contraction, such as provided by slotted bolts holes or unobstructed saddle

mountings. Attachments of legs, saddles, skirts or other supports should be

examined for distortion or cracks at welds.

The condition of supports, skirts, non-pressure attachment, including bolting shall

be reported against the following criteria:

(G) Good : No evidence of deterioration, no thread loss

(F) Fair : Powdery corrosion product easily removed to reveal little or no

loss of thread integrity.

(P) Poor : Several areas where scale fills thread.

(B) Bad : Significant build-ups of scale showing significant loss of thread

and beyond.

The following table of photos illustrates the criteria for attachments:

Ratings Example 1

Example 2

If corrosion and scale build up has occurred on bolts, obviously the inspection

can only be carried out on exposed surfaces. (G) and (F) are considered

Acceptable but (P) and (B) are Reportable. Where the condition is (P) Poor

or (B) Bad the report shall cover details of its (their) location(s), extent, and depth

relative to the threads.

8.3.14. Weld Joints

Welded joints and the adjacent heat affected zones should be examined for

cracks or other defects, Magnetic particle or liquid penetrant examination is a

useful means for doing this.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 21 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

8.3.15. Non-welded Joints:

Anomalies shall be reportable where the following criteria have been met or

exceeded:

Leakage of gas or liquid

Visible degradation of sealing medium e.g. evidence of the gasket being wet,

dirty etc

Loose or missing fittings/attachments

Deformation of joint or adjacent pipe work

Details about the location, extent, size, and orientation of the anomaly should be

given in the comments box.

8.3.16. Mechanical Damage:

Mechanical damage shall be reported when the vessel wall has sustained

damage resulting in distortion, flattening, indent, buckling etc.

Details about the location, extent, size, and orientation of the anomaly should be

given in the comment / report.

8.3.17. Dissimilar Metals:

Where dissimilar metals are found to be in direct contact with each other e.g.:

a) stainless fitting to carbon steel on a Pressure Vessel that contains liquid,

b) an insulating gasket set is not fitted, or

c) an insulating set has been fitted but is found to be incomplete or

damaged.

If either of these conditions is found, the report shall contain:

detailed location,

nature of the anomaly,

the metals involved,

the description of the circumstances, and

the geometry.

8.3.18. Vibration:

Vibration shall be reportable where visible movement is evident.

If vibration is found, detail and the extent of any movement should be reported.

8.3.19. Non-Conformity to design:

Non-Conformity to design shall be reported when it is apparent that any part of

the vessel has been changed. Any changes note will be checked against the

latest revisions of Drawings.

Detail of the location and nature of the anomaly should be reported.

8.4. Digital Photography:

Any defects or suspect locations shall be photographed using a digital camera. The

camera should have a minimum of 8 (eight) mega pixels of resolution in order to have

a good quality detail. A camera with 5 (five) X optical zoom is highly recommended.

The number of photographs taken will depend on the length of the pipe and severity

of its condition but the first frame shall be a general photograph such that plant north

is to the top left-hand corner of the photograph wherever possible.

Where this is not practical, the orientation shall be recorded in the "comments"

section.

A log shall be kept of photograph numbers. This sequential number should be written

in the photographic log sections of the Pressure Vessel Inspection Report and the

front summary sheet.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 22 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9. Non-Destructive Examinations (NDE)

The Inspector should examine welded joints and the adjacent heat affected zones for

cracks or other defect with NDT methods such as Ultrasonic testing; Magnetic Particle,

or Liquid Penetrant Testing.

9.1. Commonly Used NDE Techniques

9.1.1. UT Compression Technique (UT Wall Thickness Measurement)

An Ultrasonic Compression Technique (UT wall thickness Survey) is carried out

periodically as determined by the requirements of the Operational Criticality

Assessment. The scheduling is dictated by the operational criticality of the

equipment, and the system attached to it.

A wall thickness survey may consist of point thickness checks, hand scans or

more sophisticated computer based scanning techniques according to the

anticipated level and mode of internal damage mechanism.

It is recommended that RBI Assessment Tools be used to support the activity.

The Assessment Tools will incorporate all the vessels and tag numbers. The

vessel selected for inspection and the locations on these vessels will then be

configured within the RBI Assessment in the development of the inspection

program. The selected locations can then be downloaded into an Automated UT

device, if such device is to be used.

When a defect of significant metal loss is found, an FFS (Fit for Service)

assessment is to be conducted. An area of 25 X 25 shall be prepared, within

which webs of 1.5 X 1.5 area are to be drawn. Progressive UT wall thickness

measurements are to be performed in this webs, and the results are plotted both

horizontally and vertically to statistically see the extent of metal loss. The web

creation is shown in the illustration provided here:

In addition, alternative FFS grid system based on API-579 can be used to plot

the inspection results.

Only a Qualified Examiner using a Qualified Procedure in accordance to ASME

Section V Article 5 Code should do the examination.

9.1.2. Liquid Penetrant Examination

Liquid Penetrant Examination may be required as supplemental to Visual

Examination, where probabilities of Stress Corrosion Cracking of Austenitic

Stainless Steel, fatigue cracks or other types of open to surface discontinuities

are indicated by the RBI Engineering Software results.

Only a Qualified Examiner using a Qualified Procedure in accordance to ASME

Section V Article 6 Code should do the examination.

9.1.3. Magnetic Particle Examination

Supplemental Magnetic Particle Examination may be required if open to surface

or sub-surface discontinuities of ferromagnetic material are indicated by the RBI

Engineering Software results. Wet Magnetic Particle type of examination, such

as white background Magnetic Particle technique is preferable.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 23 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Only a Qualified Examiner using a Qualified Procedure in accordance to ASME

Section V Article 7 Code should do the examination.

9.1.4. In-situ Metallographic Examination

In-situ Metallographic Examination may be required to confirm the morphology of

discontinuities, when either Liquid Penetrant or Magnetic Particle Examination

finds and open to surface defect. Micrographic replication using cellulose acetate

film technique is acceptable method or in-situ metallographic examination

purpose.

Only trained and qualified personnel with enough Scientific Metallurgical

background should conduct the examination.

9.1.5. Infrared Thermographic Examination

Infrared Thermo graphic Examination may be required to survey and define the

piping insulating system anomalies.


This technique may be needed for

selection of insulation section I areas to be opened foe visual examination. This

examination may be required when probability of Corrosion under Insulations

indicated by RBI Engineering Software results.

It should also be noted that the non-invasive technique available for detection of

corrosion under insulation are not definitive and their use must be carefully

judged. Thermograph detects moisture in insulation, not the presence of

corrosion. Insulation is not always wet. The worst corrosion may not be at the

point of greatest moisture content. Conversely, the probability of damaging well

sealed insulation and leading in a search for CUI must be considered.

Only an experienced Qualified Examiner using a Qualified Procedure should

conduct the examination.

9.2. Determination on the Location of Deterioration

The likelihood, where deterioration is most likely to occur will be used for determining the

number and the location of inspection points. Examples of these locations are as follows:

Low points area in liquid space

High points area in vapor service space

Liquid - vapor interface

In the case of thickness measurement location (TML), the examination shall be taken

according to the above regimes. The location, method and extend of the inspection shall

be developed based on the RBI Engineering Software results. It is the Authorized

Inspector responsibility to develop such inspection requirements, and be included in the

Inspection Work Pack.

9.3. Marking, Identification, and Numbering Method

Any Pressure Vessel subject to be inspected shall be referenced with a Pressure

Vessel Record and a Vessel Inspection Sheet (Form), complete with sketch, prior to

any type of inspection being carried out.

Permanent Pressure Vessel Record and Vessel Inspection Sheet forms as shown in

API RP 572 Appendix B may be used for developing such forms.

Reference shall be made on the Pressure Vessels sheet/form to the associated P&ID.

9.3.1. Reference Location Marking:

The reference Point Measurement at Pressure Vessels may be as follows:

The area to be inspected is divided into four quadrants:

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 24 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Area I: between 12 oclock and 3

oclock

Area II: between 3 oclock and 6 oclock

Area III: between 6 oclock and 9

oclock

Area IV: between 9 oclock and 12

oclock

The areas to be inspected are illustrated in the following table:

1
Head of

Pressure

Vessel

2
Shell of

Horizontal

Vessel

(a)
(b)

Area at quadrant I & IV

at between 11 and 1

oclock for vapor

space

Area at quadrant II &

III at between 5 and 7

oclock for liquid space

Scan at least 1 square

foot area (regardless

of vessels size)

3
Opening

(Nozzle)

straight to the

flow

9.4. Rubbing Name Plate

Data resulting from Rubbing Name Plate is to be compared with the manufacturers data.

9.5. Determining Locations for Wall Thickness Measurements

To determine the remaining thickness of sound base material could be using NDT

methods such as Ultrasonic testing. The maximum allowable working pressure (MAWP)

should be based on the remaining thickness.

The following are the locations of thickness measurements:

Shell

Heads

Nozzles

Blind flanges

Manways

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 25 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Reinforcement pads (If any)

9.5.1. Shell

The wall thickness measurement of shell shall be performed on two orientation

side as below:

9.5.1.1. Longitudinal Orientation

If the length of the vessel is less than 6 ft, the number of segment should be at

least 3 (three) segment. This requirement is also applicable for vertical type

installation of pressure vessel.

9.5.1.2. Circumferential Orientation

Group 1 ID or OD of up to 18 inches:

The number indicates the location of measurement point.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 26 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Group 2 ID or OD of over 18 inches up to 48 inches:

Group 3 ID or OD of over 48 inches up to 144 inches:

Group 4 ID or OD of over 144 inches up to 288 inches:

The number indicates the location of measurement point.

9.5.2.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 27 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Head

The
points of thickness measurement on head shall be located in critical area

(knuckle) and distance between segments is an equal.

9.5.2.1. Ellipsoidal Head

Group 1 ID or OD of up to 18 inches:

a. Horizontal pressure vessel orientation (at both


ends)

b. Vertical pressure vessel installation (at the top and bottom view)

Group 2 ID or OD of over 18 inches up to 48 inches:

a. Horizontal pressure vessel orientation (at both ends)

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 28 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

b. Vertical pressure vessel installation (at the top and bottom view)

Group 3 ID or OD of over 48 inches up to 144 inches:

a. Horizontal pressure vessel orientation (at both ends)

30

10

11

12

13

c
d

20

Side view orientation of

points to be inspected

Segment to be inspected

14

b. Vertical pressure vessel installation (at the top and bottom view)

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 29 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Group 4 ID or OD of over 144 inches up to 288 inches:

a. Horizontal pressure vessel orientation (at both ends)

b. Vertical pressure vessel installation (at the top and bottom view)

9.5.2.2. Flat / Disk Head

The number of circle should be regarded to the size of head (diameter)

9.5.3. Nozzle Blind Flanges and Couplings

The wall thickness of nozzles shall be measured including reinforcement pads.

Nozzle sizes and flange ratings shall be included in the report.

There should be at least 8 measurement points for nozzles with diameter of up to

8 inches and 12 points for nozzles with diameter of above 8 inches.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 30 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

For nozzles with reinforcement pads, the pad sizes and thickness shall be

reported. The thickness measurement points on reinforcement pads shall be in

accordance with the number of points on representative nozzle size.

The number of measurement points on blind flanges is 8. The size and rating of

the couplings shall be included in the report.

9.5.4. Special Condition

In case corroded areas are found during the inspection performed on a vessel,

those areas should be inspected intensively. Report all data separately, such as

below:

Corroded area, square inches,

Average remaining thickness, inches, and

The minimum remaining thickness, inches.

9.6. Ultrasonic Scanning for Flaw Detection & Corrosion Survey

The flaw detection and corrosion survey of shell and head wall shall be performed by

using USK 57 ultrasonic flaw detector or equivalent qualified equipment approved by

PHEWJ. The scanning area shall be mapped into segment as directed by third party

inspection on board.

Below is the location on pressure, vessel need to be scanned in accordance with type of

service and installation.

9.6.1. Oil and Gas Separator / Heat Exchanger

9.6.1.1. Horizontal Installation

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 31 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.6.1.2. Vertical Installation

9.6.2. Water Tank and Diesel Fuel Storage

9.6.2.1. Horizontal Installation

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 32 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.6.2.2. Vertical Installation

9.7. Weld Joint Inspection

Spot of weld joint inspection is conducted by using calibrated USK 57 ultrasonic flaw or

equivalent qualified equipment,

Each inspection point should be minimum 6 inches weld length. Sketch drawing below

is an example on determining the location of welds to be inspected.

Area to be scanned:

Facing Side

Opposite Side

Below is weld joint location that must be inspected:

9.7.1. "T" joint

All T joint shall be inspected. Removal of paint/coating is required prior to the

inspection

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 33 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.7.2. Longitudinal Weld Joint (excluding "T" joint)

Every longitudinal weld joint (excluding T joint) should be inspected for every 3

feet distance of weld joint, and at least 1 (one) inspection point for longitudinal

seam with length of less than 3 feet.

9.7.3. Circumferential Weld Joint

Every circumferential weld joint (excluding "T" joint) should be covered by the

minimum inspection point as the following:

Group Pressure Vessel Diameter (ID or OD)


Points

1
up to 18-inches
2
over 18-inches up to 48-inches
3
over 48-inches up to 144-inches
4
over 144-inches up to 288-inches

Minimum

Inspection

1 (one)

2 (two)

2 (two)

3 (three)

This requirement of weld joint inspection is also applicable for vertical pressure

vessel.

9.8. Magnetic Particle Inspection

The parts of pressure vessel that will be subjected to MPI are:

"T" weld joints,

The weld joint between nozzles / couplings and shells,

Weld joint between reinforcement pad and shell or head.

Below is the list of nozzles that needs to be MPI-ed:

Manholes or hand hole nozzles,

Oil inlet nozzles,

Gas inlet nozzles,

Oil outlet nozzle, and

Water inlet / outlet nozzles.

The sketch drawing of weld joint to be inspected such as follows (for examples):

Weld joints to be

inspected

This requirement is also applicable for vertical pressure vessels. In such cases where

the MPI cannot be performed because of the unavailability of access points, the dye

penetrant test shall be carried out as an alternative to MPI.

9.9. Hardness Tests

This inspection is required to identify the material strength of a pressure vessel that has

no material specification records or the records have been missing.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 34 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.9.1. Shell Side

Each segment of shell wall between two adjacent weld joint shall be measured at

least on 20 (twenty) different location.

9.9.2. Head Side

Each segment of head between two adjacent weld joint shall be measured at

least on 20 (twenty) different location.

9.9.3. Nozzle and Reinforcement Pad

Each segment of nozzle or reinforcement pad between two adjacent weld joint of

head wall shall be measure at least on 10 (ten) different location.

9.10. Combination of UT Scan and Wall Thickness Measurement

When UT Scan is used in combination with wall thickness measurements, the inspected

areas for both applications are as recommended in the mapping summary provided on

the following pages.

Each map is categorized by the vessels group, as mentioned earlier in the procedure,

which is based on the vessels diameter.

To avoid discrepancies, vessels nameplate (NP) is used as the reference point.

9.10.1. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

General Head and Shell Sketch for WTM:

a) Horizontal

b) Vertical

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 35 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

c) Flat Head

9.10.2. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 1 ID or OD of up to 18 inches:

d) Horizontal

e) Vertical

9.10.3.
PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 36 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 2 ID or OD of over 18 inches up to 48 inches:

a) Horizontal

b) Vertical

9.10.4. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 3 ID or OD of over 48 inches up to 144 inches:

a) Horizontal

b) Vertical

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 37 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

9.10.5. Map for Combination of UT Scan and Wall Thickness Measurements (WTM),

Group 4 ID or OD of over 144 inches up to 288 inches:

a) Horizontal

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 38 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

b) Vertical

9.11. Insulated Vessels

For insulated vessels, inspection windows have to be provided for periodic NDE.

The size and locations of the windows are described below.

9.11.1. Size of Wall Thickness Measurement Windows in Insulated Vessels

The size of wall thickness measurement windows to be prepared is 8 in x 6 in

(200 mm x 150 mm).

9.11.2. Location of Wall Thickness Measurement Windows in Insulated Vessels

Below is the sketch of accessibility windows to be prepared before performing

inspection on insulated pressure vessel:

1. Head

The windows are located in knuckle area on 2 (two) sides of the heads (if any

and if possible), at 0, 90, 180, 270 and centered positions.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 39 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

2. Shell

The windows on the shell are to be located at 0, 90, 180, and 270

positions. The distance of point to point (example A to B) is 5 feet (1.5

meter) from the left side and minimum measurement is 2 (two) point

(pressure vessel size less than 10 feet).

Horizontal Pressure Vessel

Vertical Pressure Vessel

270

90

180

Shell

The physical condition of insulation shall be examined and particular attention

shall be paid to damage resulting from maintenance activities or walk-on i.e.

where personnel have stood on insulation and damaged the outer cladding to

allow the ingress of water (vertical vessel top heads are very likely to suffer such

damaged). A thermo graphic scan may be carried out to determine whether

there are areas of wet insulation if the vessel operates either above or below

ambient temperature. Any such areas shall be investigated for corrosion.

10. Corrosion Rate Calculation

Corrosion rate calculation should be based on average value (spot value is not valid to

be used for estimating the corrosion rate calculation). The method of arithmetic means

shall be used to determine the average value.

11. Calculations of the Maximum Allowable Pressure (MAWP)

To determine the Pressure Vessel MAWP, the following formula shall be used:

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 40 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

MAWP (Shell) =

MAWP (Head) =

S x E x t

(Ri + CA) + 0.6 x t

2 X S x E x t

(Di + 2 x CA) + 0.2 x t

t = ta CA

Where: S
E
Ri
Di
t
ta
CA

=
=
=
=
=
=
=

Maximum Allowable Stress

Joint Efficiency

Inside Radius before corroded

Inside Diameter before corroded

calculated thickness

Actual Thickness

Corrosion Allowance

The existing MAWP of the nozzles are to be determined as well. The MAWP is by

definition calculated in the corroded condition and at the operating temperature.

However, there is not a single equation available for calculating the Nozzles MAWP.

ASME Section VIII and BS 5500 refer to different charts and factors. Several criteria

must be met when determining the MAWP of a nozzle, which include:

a. The nozzle wall thickness (UG-47),

b. The vessel wall thickness (UG-47),

c. The reinforcing area required (which cannot exceed the reinforcing area available),

d. UG-45 minimum nozzle wall thickness,

e. UG-41(b)(1) weld strength calculations,

f. UW-16 minimum weld size requirements,

g. For large openings, the rules of Appendix 1-7 of ASME section VIII are applied, and

h. Stresses due to pressure combined with external nozzle loads (WRC-107 & PVP Vol.

399)

Because multiple criteria must be met there is no single equation that provides a direct

calculation of the nozzle MAWP. The use of computer-aided tools is recommended to

solve nozzles MAWP by iteration. The inspectors are to determine suitable tools.

12. Unknown Document Record

When the pressure vessel is found to have no nameplate, or has minimal or no design/

construction documentations, the following steps may be used to verify its operating

integrity:

Perform inspection to determine condition of the vessel.

Define design parameters and prepare drawing and design calculation.

Base calculation on applicable codes and standards on the allowable stress value

shall use allowable stress for SA-283 Grade C; and for alloy and nonferrous

materials, use x-ray fluorescence analysis to determine type on which to base

allowable stress value.

When the extent of originally performed radiography is not known, use joint factor of

0.7 for butt weld.

Perform pressure test as required by code of construction used for design calculation.

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 41 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

13. Conclusions and Acceptance Criteria

The Inspector should discuss with the owner or user, any defect or deficiencies in

condition, maintenance practices or misuse of the Pressure Vessel and, if necessary,

recommend corrective action. All repairs should be carried out in accordance with the

applicable codes.

Acceptance criteria of Discontinuity shall be in accordance with the reference

documents.

14. Reports and Recommendations

The Inspector should make reports and recommendations based on the results of the

inspection, and the key points are to be described in a document called Executive

Summary. For recertification, the report should be submitted to government to obtain

the new/updated operating permit.

For MiGas purposes, the report shall be in Migas format and contains:

Manufacturer data report (form U1),

Result of inspection,

As built drawings, and

Previous report/certification.

Results of inspection shall be contented with:

Technical data,

Calculation evaluate of remained thickness,

Field inspection report, and

Recommendations.

For PHEWJ purposes, the reports shall contain the followings:

1. Third Party Certificate of Inspections,

2. Record of Wall Thickness Measurements,

3. Report of all other NDTs (non destructive tests),

4. Report of Visual Inspections,

5. Design Reviews, and

6. Report of Pressure Test (if any).

The inspector shall prepare the summary of pressure vessels latest condition based on

the results of inspection in forms given in attachments.

The contractor shall be responsible for re-certification process in Dit. Jen. MiGas and

obtain the certificates. Once re-certification is completed, the contractor shall provide

the company with 1 (one) original and 1 (one) copy of inspection reports.

All data that will be used in RBI assessment were obtained from General Inspection and

MIGAS Re-certification Inspection.

14.1. Reports

All reporting should be as brief as possible. However, it is imperative to use the

"Comment" section to even provide fuller details where necessary. A report form should

be developed for traceability purposes, which may contain:

A cross-reference to any other forms of NDT, which may

NDT Report Number

have been carried out on the Pressure Vessel Part.

Report should be sequenced in a logical numerical order

The number of sketch used for the inspection locations

Sketch Number

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 42 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Minimum Recorded Wall


Record the lowest reading taken on the pressure vessel

part

Thickness

Enter the location where the lowest reading was

At TML Number

recorded

Inspection Requirements
The type of inspection to be carried out on this vessel

Inspection Comments
Comments regarding any reportable aspect of the

inspection

The report details of all photographs taken

Photographic Log

General Condition of
Report the results of the visual inspection. Refer to the

visual inspection procedure for details on this

Line

The inspection location cannot be accessed from

Access Required

ground level

If an anomaly is reported

Anomaly Reported

A unique number should be allocated to every

Report No.

inspection report

Inspector

Name, sign and date

Information relating to the wall thickness may be summarized as follows:

Nominal Wall Thickness


Nominal manufacturing wall thickness for this pressure

vessel part

Corrosion allowance as specified in the pressure vessel

Corrosion Allowance

design

Maximum allowable wall thickness loss permissible for

Maximum Loss

the section

Minimum Wall Thickness


Minimum wall as calculated using the hoop stress

calculation defined in the Original Code of the

construction

Retirement Thickness
Minimum acceptable wall thickness for the pressure

vessel

Wall Thickness readings

Location

The location number should match that recorded on the

pressure vessel inspection sheet

Wall Thickness Reading


Record the minimum reading at areas as defined in

Chapter 7.3.4. All readings will be in inches

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 43 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel

Note:

Based on the AI recommendation, additional inspection, repair, alteration or rerating

shall be conducted in accordance to a qualified procedure authorized by an Authorized

Piping Inspector, and consulted with the piping engineer, where required. The procedure

shall meet all the requirements of API 510.

14.2. Recommendations

Following the RBI evaluation, Inspection Tasks in accordance to this Guide shall be

conducted by the appropriate Inspection Personnel, outlined in Chapter III

Responsibilities and shall be comprehensively reported.

Based on the results of the above Inspection, the Authorized Pressure Vessel Inspector

shall prepare recommendation for any inspection, repair, alteration or rerating that might

be required, to comply with the API 510 requirement, so that the Pressure Vessel can be

safely operated until nest endorsement period.

All of the inspection results, reports, recommendation and repair, alteration or rerating

shall be recorded against a traceable documented procedure.

It is important that historical record be developed and maintained for every Pressure

Vessels to be inspected in accordance on this Guide.

15. Reviews and Revisions

This procedure shall be reviewed for compliance and effectiveness and revised as

necessary (Refer to Technical Document Control Procedure PHEONWJ-G-PRC-1001

every two years).

ATTACHMENTS and REFERENCE FORMS

Attachment A.
Attachment B.
Attachment C.
Attachment D.
Attachment E

Vessel Inspection Report

Vessel Thickness Measurement Report

Change of Pressure Vessel Condition Form

History Card

Quick Opening Closure Visual Inspection Report (sheets 1 to 6)

PHEONWJ-I-PRC-0005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 44 of 54

Tag

No.

Serial

Attachment A

Label

P & ID Number
Year(s) Built
Material Spec.
Insulation Code
Content

VESSEL INSPECTION REPORT

Location :

:
:
:
:
:

Op. Pressure
Op. Temp.
Op. Low Temp.
Nom. Wall Thick.
Corr. Allowance

External

Acceptable

:
:
:
:
:

psig
F
F
inches
inches

Design Pressure
Design Temp.
Des. Low Temp.
Design Code
Test Pressure

Vessels Condition

Reportable

Manway/Pig Launcher Door


Head/Dome End/Exchanger End Box
Shell/Plate Exchanger Frame
Protective Coating/Paint
Nozzles
Insulation
Fire Proofing
Bolted Attachment etc.
Welded Attachments
Reinforcement Pad Pipe over 4
Name Plate
Earting
Support
Ladders
Platform
Level Gauge
Pressure Gauge
Temperature Gauge
Pressure Safety Valve

Internal

:
:
:
:
:

psig

Acceptable

Manway/Pig Launcher Door


Head/Dome End/Exchanger End Box
Shell/Plate Exchanger Frame
Protective Coating
Nozzles
Tubes
Tubeplate
Welded Attachments
Bolted Attachment
Strainers/Filter

psig

Reportable

Comments

Use this section to comment on all reportable items. Record the details of all photographs taken, drawing references etc. Attach sketches if necessary.

Also record any remedial actions which have been carried out and Personnel who have been informed.

Inspectors Details

I declare that the above equipment has been inspected in accordance with the relevant procedures and that this document is a true report of

the inspection carried out.

Inspected by:

Inspection Date:

Approved by:

|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Attachment B

VESSEL THICKNESS MEASUREMENT REPORT

User
Requested By
P & ID Number
Label
Tag No.
Serial No.
User
Design Pressure
Operating Pressure
Design Temperature
Operating Temperature

RISK BASED INSPECTION

psig
psig
F
F

Equipment
Serial No
Type Of Probe
Test Block
Couplant
Date of Inspection
Location
Report No
Sheet Number
Year(s) Built
Remaining Life

Detailed Measurements, all dimensions are in inches

Part

Ident.

Thickness Measurement Point, Oclock


12
3
6
9
Center

Size of Corrosion

Length
Width

Years

Depth of

Pitting

Nom.

Thick.

Min.

Thick.

Inspectors Details

I declare that the above measurements have been done in accordance with the relevant procedures and that this document is a true report of

the thickness measurements.

Inspected by:

Reviewed by:

Approved by:

|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Attachment C

CHANGE OF PRESSURE VESSEL CONDITION FORM

Original Vessel Identification Number


: .

1. Original Vessel Location


: .

2. Manufacturer
: .

3. Serial No.
: .

4. See attachments for additional data?


Yes
No

5. Original Maximum Allowable Working Pressure


:
Year Built : .

6. Original Design Temperature


: ...
Year Used : .

7. Original Minimum Design Metal Temperature


: ...
At Pressure : .

8. Original Test Pressure : .


Fluid : .
Position : ....

9. Shell Material
: .
Head Material
:

10. Shell Thickness


: .
Head Thickness :

11. Original Joint Efficiency : .

12. Original Radiography


: .
Yes
No

13. Original PWHT:


Yes
No

If yes, .F .. Hrs

14. Original Corrosion Allowance


: ..

15. Pressure Vessel Condition


:

Operational
Shutdown
Not Used
Not Exist/Not Found
Tag No.not Valid

16. New Vessel Identification Number (If Applicable)


: ..

17. New Vessel Location (If Applicable)


: ..

18. New Maximum Allowable Working Pressure


: ..

19. New Design Temperature


: ..

20. New Minimum Design Metal Temperature


:
At Pressure: ..

21. New PWHT:


Yes
No
F .. Hrs

22. New Joint Efficiency, If Applicable E


=

23. New Pressure Test If Yes, Pressure


: .
Test Medium
Test Position .

24. New Corrosion Allowance


: .....

25. Describe work performed (attach drawings, calculation, and other pertinent data):

..........

Statement of Compliance

We certify that the statements made in this report are correct and conform to the MAXIMO DATA, P&ID, Name Plate and

actual condition pressure vessel.

PHE Field Representative

Signed :

Name :

Date :

Statement of Inspection:

I, the undersigned, an inspector employed by PT. RADIANT UTAMA INTERINSCO Tbk., having inspected the pressure vessel

above

|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment D

Description
Tag No.
Serial No.
Location
Type of Vessel
Dimensional
Manufactured by
Design Pressure
Design Temperature
Max. Allow. Working Pressure
Test Pressure
Nominal Shell Thickness
Nominal Head Thickness
Year Built I Year Used
Code and Standard Used

Date of

No.
Inspection

HISTORY CARD

:
:
:
:
:
:
:
:
:
:
:
:
:
:
:

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

.........................................................................................

INSPECTION & MAINTENANCE RECORD

Fact Finding

Recovery Action

Taken

Inspection

Report

Initial

Inspector

Date of

Insp.

Shell (mm)
1
2
3

Head (mm)
1
2
3

Nozzle (mm)
1
2
3

Remarks

Insp.

Prepared by:

Reviewed by:

Approved by:

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 48 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 1

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 49 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 2

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 50 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 3

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 51 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 4

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 52 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 5

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 53 of 54

PHE ONWJ Ltd.

Topside Inspection Procedure: Pressure Vessel }

Attachment E Sheet 6

PHEONWJ-I-PRC-1005 Rev 0
|DOCUMENTUM|4/8/2010|Paper Copies are Uncontrolled|

Page 54 of 54

You might also like