You are on page 1of 7

Project : Studio Works - Retaining Walll Page : 1

Taker off : Rubby Dean Ref : RETWL/SD


5/9/2014
Item No Code No. Description Unit
Class A : General Items
1 A111 Performance Bond Sum
2 A121 Insurance of the works Sum
3 A123 SOCSO/Workmen compensation insurance Sum
4 A213 Laboratory Sum
5 A511 Contractor's requirement, facilities, office Sum
Class C : Traffic Management and Control
6 C221 Heavy duty water/sand-filled PVC barrier Nr
7 C231 Cone Nr
Class F : Earthworks
8 F111 Excavate top soil, 200mm thick M2
9 F135 Cut and dispose, unsuitable material M3
Class G : Geotechnical Work
10 G110 Provision Sum
11 G120 Moving and handling Sum
12 G130 Temporary staging Sum
13 G241 Reinforced soil wall, wall facing M2
14 G242 Reinforced earth filling M3
15 G243 Reinforced granular dilling M3
16 G244 Reinforced soil wall, levelling pad M
17 G245 Reinforced soil wall, pull out test Nr
18 G351 Horizontal drain in earth M
19 G510.1 Vertical drain at top M
20 G510.2 Vertical drain at centre M
21 G510.3 Vertical drain at bottom M
Taking Off List
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 1
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
Class A : General Items
A110 Contractual requirements; bond, performance Sum 18,000.00 18,000.00
bond
A121 Contractual requirement, insurance, insurance Sum 25,000.00 25,000.00
of the Works
A123 Contractual requirement, insurance, SOCSO Sum 10,000.00 10,000.00
/ Workmen compensation insurance
A213 Engineer/S.O/P.D's requirements, facilities Sum 10,000.00 10,000.00
for the Engineer/S.O/P.D/s representative
laboratories 36 m2 area
A511 Conctractor's requirement, facilities, office Sum 15,000.00 15,000.00
Total Carried to Summary of Class A 78,000.00
ITEMS DIMENSIONS COST
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 2
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
Class C : Traffic Management and Control
C221 Temporary road furniture, barriers and Nr 10 10 500.00 5,000.00
barricades, heavy duty water/sand-filled PVC
barrier new jersey tipe
C231 Temporary road furniture, barriers and Nr 3 3 150.00 450.00
barricades, PVC cone with reflector
Total Carried to Summary of Class C 5,450.00
ITEMS DIMENSIONS COST
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 3
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
Class F : Earthworks
F111 Excavation, stripping, topsoil average 200mm M2 61.60 6.80 418.88 3.00 1,256.64
thick
F135 Excavation, cut and dispose, unsuitable M3 61.60 6.80 13.50 5,654.88 11.00 62,203.68
material
Total to Summary of Class F 63,460.32
ITEMS DIMENSIONS COST
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 4
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
Class G : Geotechincal Works
G110 Plant and equipment, provision Sum 5,000.00 5,000.00
G120 Plant and equipment, moving and handling Sum 2,000.00 2,000.00
G130 Plant and equipment, temporary staging Sum 3,000.00 3,000.00
G241 Retaining structure, reinforced soil wall, M2 61.60 12.80 788.48
wall facing 8m height
G242 Retaining structure, reinforced soil wall, M3 61.60 6.80 13.50 5,654.88
reinforced earth filling
G243 Retaining structure, reinforced soil wall, M3 61.60 3.60 2.80 620.93
granular filling
G244 Retaining structure, reinforced soil wall, M 61.60 61.60
levelling pad
G245 Retaining structure, reinforced soil wall, Nr 6 6.00
pull out test
G351 Slope stabilisation, horizontal drain, in earth M 61.60 61.60
100mm diameter open drain
Total to Summary of Class G1 B/F 10,000.00
ITEMS DIMENSIONS COST
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 5
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
C/F 10,000.00
Glass G : Geotechnical Work (Cont'd)
G510.1 Ground treatment, vertical drain 100mm M 20 1.00 20.00
diameter weep hole at top
G510.2 Ground treatment, vertical drain 100mm M 20 0.85 17.00
diameter weep hole at centre
G510.3 Ground treatment, vertical drain 100mm M 20 0.70 14.00
diameter weep hole at bottom
Total to Summary of Class G2 10,000.00
ITEMS DIMENSIONS COST
JABATAN UKUR BAHAN, FAKULTI ALAM BINA
UNIVERSITI TEKNOLOGI MALAYSIA, SKUDAI, JOHOR Date: 5/9/2014
Project: Retaning Wall Taker off: Rubby Dean Squared by; Rubby Page: 6
Checked by: Revised by; Ref No: RETWL.SD
QUANTITIES
Code Descriptions Unit No. L W H Total Rates RM
Summary of Retaining Wall
Class A : General Items 78,000.00
Class C : Traffic Management and Control 5,450.00
Class F : Earthworks 63,460.32
Class G: Geotechnical Work 10,000.00
Total Carried to Summary 156,910.32