Top-down or bottom-up?

By: Chris Vandersluis



We need project management Ummm, I meant portfolio management Ummm, I really
mean task management Oh heck, we need all of them, is a battle cry I hear often. Its not a
lack of definitions of these three concepts that causes confusion, its their similarity.

Those of us who have worked in IT for many years tend to see things from a technical
perspective and sometimes it doesnt serve us well. If we look at data from Portfolio
Management, Project Management, and Task Management, it might look very similar. Ive got
an ID field, a description field, and a start and end date in all three. Linking all three of these
should be natural then.

Perhaps not.

Lets take these three concepts one at a time. Its easy to see their similarities, but there are
fundamental differences in the three perspectives.

Portfolio Management a top-down approach
People can mean a lot of different things by portfolio management, but the most meaning
common is probably project selection and prioritization. The principles ultimately affect
everyone in the organization, but the
process is of great interest to senior
executives. Management starts off
with certain constraints, such as a
total available budget and a need to
answer the question, What can we
and should we accomplish with this
amount of money? If the portfolio
management process is sufficiently
mature, this analysis might include
not just new ideas but also existing
projects.

To create a portfolio selection and
prioritization process, management
must confront what business criteria
drive the company and agree in
advance on the metrics that will be considered when looking at new and existing projects.
Should return on investment be a key metric? Perhaps we should consider effects on client
satisfaction or staff retention or alignment with strategic objectives. Whatever the key metrics
are, management has to weigh each project initiative with a view to how that project can
advance those objectives and how each project compares with alternate initiatives on which the
money could be spent.

This is a highly analytic process even if its done in ones head. Its certainly highly analytic
when you are using project portfolio management software. Even once the analysis from
software arrives in a report or a view, there is virtually always some management-level oversight
where a final decision on priorities gets made. When that is complete, the final results must be
transmitted to those who will do project management of each of the projects. The effects of


these decisions will be to fund some projects and not to fund others, to make available
resources on a higher priority to some projects and not to others, and to advance the schedule
of some projects and to delay others.

Project Management top-down and bottom-up
Once a project is approved, it moves into a different realm altogether. Now the more classic
view of project scheduling comes into focus. Now we have to actually build the thing we
described in our business justification before it was approved.

A project manager starts thinking in terms of project scope and deliverables. The project
manager knows the final product that must be created, whether it is a piece of software or a
building ready for occupancy. They
may think of the major phases of that
project and create a work breakdown
structure.

A critical path of logical steps required
to complete the project gets designed.
The project manager also knows that he
or she will be held to account for the
schedule that is produced, so he or she
consults a range of subject matter
experts in the project. The project
manager creates a bottom-up view of the project by looking task by task and summarizing those
tasks up to project phases and eventually to the project itself. At this time the project manager
might also start allocating resources by
skill, by department, or even by name.
These resources might have costs
associated with them. The result of
calculating the duration of the tasks, the
resources required, and their rates gives
us a bottom-up estimate of the project.

So far, so good.

But when we look at the top-down
approach of the project portfolio
selection process, there was a cost, too.
In fact, the estimated cost of the project
was part of the business justification that
management considered when it approved the project. If were just getting the bottom-up
estimate of the project from combined expertise of the subject matter experts now, what did they
use in the project selection up in the executive suite?

Its a good question. In some organizations, the project will be given a rough estimate from the
project department in order to create a business justification for the project. In other
organizations, a complete bottom-up estimate is created prior to considering the project in the
portfolio process. The problem with both of these approaches is that they take effort. A
complete estimate may take a lot of effort and yet the project has yet to receive approval for
funding any effort. So, in many organizations, someone in management simply makes a guess
as to what the costs of this project will be.



So the process looks all integrated but there may be a bit of a catch-22 here. Which comes
first, the work spent on doing the estimate or the selection of the project in order to be able to
spend time on the project?

Moreover, what happens if the bottom-up estimate doesnt match the estimate of the portfolio
selection process? If the estimate is less, theres probably no issue, but if the work cant
possibly be completed in the time or budget estimated by the portfolio selection people, there is
a conflict.

You might think that the natural thing to do would be to reconvene senior management and just
discuss the problem, but there are a lot of situations where that isnt as easy as it seems.

First of all, the portfolio selection committee is rarely the project management staff. Senior
project management staff members are almost always included in the portfolio selection
committee, but the group itself is usually very senior executives who find it challenging to
organize time to all be together. Secondly, the selection committee may meet irregularly, so
getting them back together to discuss all the ramifications of a mismatched cost for one project
versus the estimate might be a big challenge. Finally, there are some corporate cultures where
it will not be a career-advancing move to have to deliver the news to the senior executive that
their guess is completely wrong on what the appropriate schedule and budget for this project is.

Task management a bottom-up approach
When we think of task management, we tend to think very operationally, and that most often
brings us to our daily agenda and a
product like Outlook.

Now were working at an individual or a
small team member level. We dont
see the tasks in context. We see those
things weve committed to or perhaps
those things weve asked a team
member to commit to. This is not an
analytic view at all. There are tasks to
do and the individual has promised to
do them.

At its core, task management is very
straightforward. You do the task and
when youre done you tell the person
who gave you the task to do that it is
complete. All the functionality for this is
already in Outlook.

The mischief of similar data
Theres a saying, If it looks like a duck and quacks like a duck, it must be a duck. Thats true
for ducks, but it isnt always true for task-based data.

Lets consider these three levels of project-oriented data:


At the portfolio level, we have a project and perhaps phases below that project. The
phase information might have a code number, a description, a duration, a start date, and
an end date.

At the project level, we have a project and tasks below the project. The task information
might have a code number, a description, a duration, a start date, and an end date.

At that task management level, we have a task and the task information might have a
code number, a description, a duration, a start date, and an end date.

They sure look the same, but in fact, the perspective of the data makes each of these rather
common records serve a very different purpose.

Im often asked, Can I move data from the portfolio view to the project view to Outlook and
back.

The short answer to that question is Yes.

But in our firm we have a mantra we say to ourselves when were giving technical advice: Dont
tell me how to do it, tell me why you should do it.

1. To make the point, imagine this example. We make an entirely integrated environment.
At the top end of the scale we have a list of projects organized by portfolio. Not only do
we select these projects, but we integrate even further, following them after theyve been
activated into live projects from the EPM system. To do this, we use functionality
already available to us to move the project and phase definitions from the Portfolio side
of our integrated system to the project side of the system. The data looks identical.
2. In our enterprise project management system we now make a more detailed definition,
using the original phases from the portfolio definition that was pushed from the top down.
Doing this allows that summary to be updated in the portfolio system when we update
our projects. We make many tasks and assign many resources. We now do a
resource-leveling analysis to determine our capacity across many projects.
3. We use our resource assignments to push task and assignment data to each user as an
Outlook task or calendar event. Users no longer need to go to a project management
system. They are now able to see their data in their daily agenda. The data looks just
like it does in the project list and is linked further upstream to the portfolio view.
4. Progress from these tasks and availability from Outlook is moved back from the
individual to the project management system along with estimates on when this work will
be completed. The data looks just like it does in the other two systems, so moving the
data is relatively easy.

Creating such a system is technically very straightforward using the tools available to us today
along with a bit of configuration and development. And it would demonstrate beautifully.

We get asked for exactly this type of structure on a regular basis. But, even though we can do
it, should we?

Imagine that at the task level, an individual takes the morning off for an emergency dental visit
and updates her Outlook that she will not be available this morning. Thats bad news for him
but the ripple effects to the project could be massive. Now, the project system calculates that
the task that was scheduled to be done this morning wont be completed today; it will be


completed only at mid-day tomorrow. It dutifully looks at the critical path and all tasks
downstream from this one and pushes them forward by four hours. Perhaps hundreds of tasks
were affected. The result might be pushing the end date of the project a half day later. Other
projects are also affected as other people working on this project must now have their tasks re-
arranged and the portfolio view itself slides forward a few pixels.

If we imagine this in real time, the problem is magnified. Hundreds or thousands of people are
making changes all through the day, and the EPM view, the resource leveling view, and the
portfolio view animate back and forth with the effects.

In reality this doesnt happen. First of all, the hapless dental patient will be back at her post at
noon and may just work a few hours later tonight to make sure this critical path is caught up and
all will be back on track in the morning.

Plus, even though the data looks the same, it is never integrated this way because of exactly
this effect.

Data Context the perspective matters
When we look at data, the context of the data is critical. Data that may look the same from a
record-to-record schema is used for very different purposes based on the perspective of the
application.

In a top-down portfolio view, we are making strategic decisions of where to put our resources to
maximize our return on investment. We might make choices that a project manager wouldnt
make. In my own organization, we have sometimes chosen projects that are completely outside
our existing skill set, knowing that we would be terribly ineffective at accomplishing them but
doing so because we wanted to improve those very skills. The return on investment wasnt an
effective installation, it was trained installers. This is an analytic view.

In a tactical project view, we are making operational decisions about where to get the best
throughput of our personnel and to get our projects completed as quickly and efficiently as
possible. A project managers eye is always to the future. What happened in the past is only of
interest to the project manager insofar as it improves his or her view of the future. This is also a
highly analytic view.

In a task management view like an agenda, we are not analytic. An agenda is a commitment
system. We promise ourselves or others that we will do a particular thing at a particular time.
This might fit the analytic view. And it might not.

Mixing these perspectives and contexts without understanding the impact can cause chaos.

Top-down or bottom-up?
There is, as usual, no right answer. Some aspects of your project management system really
need to come from the bottom-up. After all, in the end, it is individuals who will build whatever
your project is about. But some decisions are, and should be, made from the very top and are,
as a necessity, top-down.



When you keep the distinctions of what each level of the project management paradigm is for, it
does become clearer to see if some of these systems should really be integrated or not. If the
process and thinking of one level
doesnt have direct benefit by being
fully integrated from another level, then
integration is not the best play. Its
important to walk through how such
integration would work in a real-world
context and whether the frequency and
detail from one level delivers any value
to the other.

If, for example, a steering committee
only meets once a quarter to make
big-play decisions about which
projects to move forward and which
not, then what is the benefit to
updating their view every day, every week, or even every month?

Does the enterprise project management resource-leveling algorithm really need to see the
dental appointment of an individual or is it enough to know the approximate availability of that
individual?

And yet, if we could send an assignment to an individuals agenda or timesheet screen directly,
would that save them a few minutes each day having to go into a different system and interface
to see the same data?

So, top-down is right in some circumstances and bottom-up is right in others. You have to look
at your own situation to see where integrating these tools and concepts can pay back the right
dividends before tying them together.




About the Author

Chris Vandersluis is the president and founder of Montreal, Canadabased HMS Software, a
Microsoft Certified Partner. He has an economics degree from McGill University and over 24
years experience in the automation of project control systems. He is a long-standing member of
the Project Management Institute (PMI) and helped found the Montreal, Toronto, and Quebec
chapters of the Microsoft Project Users Group (MPUG). Publications for which Chris has written
include Fortune, Heavy Construction News, Computing Canada magazine, and PMIs
PMNetwork, and he is a regular columnist for Project Times. He teaches Advanced Project
Management at McGill University and often speaks at project management association
functions across North America and around the world. HMS Software is the publisher of the
TimeControl project-oriented timekeeping system and has been a Microsoft Project Solution
Partner since 1995.



Chris Vandersluis can be contacted by e-mail at: chrisv@hmssoftware.ca