You are on page 1of 21

1 of 21

TECHNCAL
8PECFCATON
FOR
8AND/MURRUM
FLLNG WORK8
















2 of 21



1.0 SCOPE

1.1 This Specification covers classification of soil for earth work in excavation
and filling for site grading work.
2.0 ORDINARY SOIL
2.1 Soft Soil/loose Soil
Generally any soil which yields to the ordinary application of pick and
showel, or to phawara, rake or other ordinary digging implements such as :
Sand, gravel, loam, clay, mud, black cotton soil.
Vegetation or organic soil, turf, peats, soft shale or loose murrum.
Mud concrete below ground level.
Any mixture of soil below ground level.
2.2 Hard / Dense Soil
Generally any soil which requires the close application of picks or Jumpers
or scarifier and rippers to loosen the same. Such as:
Stiff heavy clay, hard shale or compact murrum requiring grafting tool
and/ or pick and shovel.
Shingle and river or nallah bed boulders.
Soling or roads, paths, etc and hard core.
Macadam surface of any description(water bound, grouted tarmac ,
etc)
Lime concrete, stone masonry in lime or cement mortar below ground
level.
Soft conglomerate.
3.0 SOFT ROCK

This is fissured / disintegrated rocky strata, boulders (volume less than 0.4
Cu.M and more than 0.028 Cu.M) and also which cannot be
quarried/excavated by using above manual Tools but can be quarried
/excavated manually by using crow bars is classified as soft rock. Soft rock
shall include all kinds of stiff and stratified rock such as shales, laterite, hard
conglomerate, lime stone, sand stone, and unreinforced cement concrete
below ground level. Soft rock may be quarried or split with crow bar or picks
3 of 21

and can also be excavated by rippers, dozers and other mechanical
equipment but without the aid of blasting.

4.0 EXCAVATION

4.1 This specification covers in general the scope of excavation for this
tender only which is to be carried out as per drawings and as directed
by EIC.

4.2 The excavation mainly has to be carried out in soft soil / top soil i.e. to
the required line level and as directed by EIC

4.3 The site will be handed over to contractor with Vegetation/ bushes/
shrubs/ trees etc. Contractor shall visit the site to ascertain the nature
of ground prior to bidding to accept all the responsibilities. The removal
of the above is included in the scope of excavation and no additional
payment will be made on this account.

4.4 HPCL shall hand over the Bench Marks at site only . The proceeding
activities for setting out of work like plotting grid points with Brick
Pedestals on the land, fixing the center point for tanks as per drawing
with physical verification with existing structures/land marks for
distances measurement purpose, setting out the two permanent centre
lines for each tank along with RL of main B.M. on brick pedestals etc
to the satisfaction of EIC after stripping / clearing the ground complete
in all respect . All the survey equipment like total station/theodolite etc,
skilled & qualified surveying manpower, recording & maintaining the
measurement book, tools & tackles etc completely at contractors cost
to the best satisfaction of HPCL.

4.5 The contractor shall provide at his own cost all the assistance which
EIC may require for checking the setting out of works. The contractor
shall be solely responsible for the horizontal & vertical alignment,
correctness of level, and correctness of every part of work and shall
rectify any errors or imperfection therein on instruction of EIC.

4.6 Prior to commencing the excavation, requisite block ground levels of
entire plot grid co-ordinate wise shall be taken by contractor at 5 meter
intervals in consultation & presence of EIC. The proper duly signed
record for the same shall be maintained.

4.7 Excavation shall be carried out once setting out of work by Contractor
is approved by HPCL. Contractor shall excavate the soil as per
approved drawings which enumerate the levels to be achieved. The
carting away and leveling of excavated earth shall be carried out as
per specifications and as directed by EIC with in the premises. To
minimize / avoid side sloughing and collapse sufficient side slope has
4 of 21

to be maintained by Contractor. The excavation for side slope to avoid
sloughing and collapse will not be entertained for payment. Royalty
payment, if any to be made towards excavation shall be made by the
Contractor as quoted rates are deemed to include the same.

4.8 Soil strata received as above shall be rolled thoroughly by 10T roller till
95% standard proctor maximum laboratory dry density is attained as
directed by EIC. Thereupon at corresponding co-ordinates at 5m
interval, level shall be taken to ascertain the excavated height as
instructed by EIC.

Contractor shall maintain adequate drainage facilities at site at all
times during the execution of work. Additional ditches, drains & such
other temporary means to achieve this, over and above what is shown
in drawings, will be provided and maintained by Contractor at his own
cost. Adequate dewatering facilities like dewatering pumps, piping etc
will also be provided by the Contractor for this work and also for
dewatering during excavation etc. at his own cost.

5.0 : DELETED

6.0 CLEARING AND STRIPPING

The areas including depressions, where filling or cutting is to be
carried out shall be cleared and stripped completely of bushes, roots,
vegetation, plantation trees, shrubs, trees, organic and other
objectionable materials. All these shall be completely uprooted and
virgin soil exposed not merely scrapped at the surface. The roots of
trees shall be removed to a minimum depth of 1 m below existing
ground level and holes, hollows filled up with selected approved
available earth within all leads and lifts and compacted to obtain 90% of
laboratory dry density of soil and levelled as directed by Engineer-in-
charge. All soft patches must be worked out to remove soft soil and
selected approved earth must be filled back and the areas (areas
coming under filling ) compacted to obtain 90% of maximum laboratory
dry density of soil, as per IS:2720 part vii. The depth of stripping shall
be generally 50 to 150 mm as decided by Engineer-in-charge.

Material obtained from clearing shall be disposed off as directed by
Engineer-in-charge and in line with local bye laws/ statutory
requirements.

Payment

No separate payment shall be made for clearing, stripping and disposal
of materials obtained from clearing .This shall be considered as part of
5 of 21

cutting work in areas of cutting and filling work in areas of filling and the
rates quoted under the respective items of:

i. Earthwork in Excavation/cutting.

ii. Earthwork in filling (Both with available earth & earth obtained
from approved borrow areas ), shall be inclusive of clearing and
stripping with all operations described above in clause no.5 in
respective areas of cutting and filling.

No separate payment shall be made for cleaning, stripping and disposal
of materials obtained from clearing of borrow areas for earth as directed
by Engineer-in-charge.This shall be considered a part of filling work in
area of filling and the rate quoted under the respective items.


7.0 EARTHWORK IN EXCAVATION / CUTTING

After clearing, stripping of areas as specified above, spot levels at
intervals and pattern as decided by Engineer in charge shall be taken
jointly with the Contractor and Engineer in charge, and Excavation /
cutting shall commence only after the levels are signed by the
contractor as token of acceptance.

Excavation/ cutting for this work shall be carried out strictly as per the
instructions of Engineer in charge

If the contractor excavates / cuts beyond the required level, additional
quantity of earthwork shall not be paid for .The excavation taken
below the specified level shall be made good by filling with approved
material to the required compaction at contractors cost.

The final bed and sides of excavation must be levelled, dressed and
compacted. In case of areas under excavation for Site Grading, the
final surface shall be levelled, dressed and consolidated by means of
sheep foot/ power driven rollers to obtain maximum compaction.
However, no test control is required in such areas.


Provision for dewatering shall be governed by relevant clauses.

Payment

Payment for excavation shall be on the basis of volume of excavation
Calculated on the basis of joint level taken for initial and the final
finished grade levels, the volume being calculated by the trapezoidal
rule.
6 of 21


8.0 SPECIFICATION FOR SAND FILLING

Contractor shall submit the sample of Sand to be used for filling to
HPCL. This sand sample shall be tested in HPCL approved soil
laboratory by contractor for following characteristics:- Mechanical
analysis, specific gravity, grain size distribution, soil test data sheet
etc to calculate minimum and maximum density as per clause no. 3.6
IS 2720. The sample test report of earlier job is attached for
reference.

Material - SAND
Sand Shall be clean, dry, coarse, hard, angular river sand free from
coatings of clay, dust and mix of vegetable and organic matters and
shall conform to IS:383 Grade-III.
Use of dust like sand and sea sand for this job is prohibited. It is
recommended to wash the sand prior to use.
After the excavation i.e. reduced level of virgin soil shall be taken on
a grid of 5Mx5M, co-ordinate wise w.r.t benchmark, job includes
setting out of work like fixing of B.M. for 0 deg, 90 deg, 180 deg and
270 deg for area desgnated. The same shall be plotted on
construction drawing, to be prepared by contractor for HPCLs
approval on AUTOCAD.
QAP/ITP for the job shall be drawn by contractor for HPCLs
approval.
Sand Layer shall be laid in 300mm loose layer thoroughly compacted
to achieve 85% Relative density as per IS : 2720 Part XIV. Principle
method for compaction using vibratory table as explained vide clause
no. 3 of IS:2720 part XIV will be used for ascertaining the compaction
i.e. 85% relative density as per clause 3.6.4 of IS:2720 part XIV. For
compaction purpose plate vibrator/ vibro roller shall be deployed.
Each layer one test has to be done @500 sqm of area and top layer
has to be tested by any HPCL approved third party.

After clearing, stripping and consolidation of areas as specified in
clause 6, spot levels at intervals and pattern as decided by Engineer-
in-charge shall be taken jointly with the Contractor and Engineer-in-
charge and filling shall commence only after the levels are signed by
the Contractor as the token of his acceptance .Approved fill material
shall be spread in uniform layers not exceeding 30 cms in loose depth.
The contractor has to make his own approach and access roads from
the borrow area to the demarcated filling areas. While the contractor
may make use of such short cuts as may be available to him for earth
movement from borrow areas to the filling areas, the Owner does not
guarantee any pass way or the right of way for the Contractor work
other than available at site. No claim shall also be admissible to the
Contractor on the account of his having taken longer leads or routes
7 of 21

for earth movement, than envisaged by him, either due to any road
cuttings, non-availability of routes, or any other grounds whatsoever.

All clods, lumps etc , shall be broken before compaction.

Successive layers of filling shall not be placed until the layer below has
been thoroughly compacted to satisfy the requirements laid down in
the specification.

After adjusting the moisture content as described ,the layers shall be
thoroughly compacted by either sheep foot roller or power driven roller
or vibratory roller or plate vibrator or EIC as approved by Engineer-in-
charge till the specified maximum laboratory dry density is obtained.

Each layer shall be tested in field for density and accepted by
Engineer-in-charge subject to achieving the required density before
laying the next layer. A minimum of one test per 500m2 for each layer
shall be conducted.

If the layer fails to meet the required density, it shall be reworked or
the material shall be replaced and method of construction altered as
directed by Engineer-in-charge to obtain the required density.

The filling shall be finished in conformity with the alignment, levels,
cross section and dimensions as shown in the drawing. Earthen
embankment shall be filled 300mm on both sides, where height is
more than 1m, and this extra filling shall be dressed, after compaction ,
in conformity with alignment, level, cross section and dimensions as
shown in drawing to achieve proper compaction in the slope. No extra
payment shall be made in this regards.

All the royalty payments etc. as deemed admissible to statutory / govt.
authorities will be paid by contractor for all the earth brought for HPCL
works. It shall be the responsibility for the contractor to produce all such
payments, documents to Engineer-in-Charge during submission of
running bill. At the end of work no objection certificate from relevant
authorities will be submitted to ensure that HPCL is kept free from all
encumbrances

Extra material shall be removed and disposed off as directed by
Engineer-in-charge .

Tolerances
General site grading including cutting and filling in depressions shall be
carried out to within up down tolerance of+/- 2 cms of final lines grades
and slopes.
8 of 21



PROCEDURE FOR SAND COMPACTION /CALCULATIONS

PROCEDURE FOR FIELD COMPACTION OF SAND LAYER.
Equipment type: vibrating base plate contactor/ vibro roller
Application: for coarse grained sand/soil

Procedure: loose filling of sand layer is spread on the filling area of max.
300 mm thick. Moisture content of the sand is maintained below 5%.the
compaction should be carried out with single pads or plates of min. 90 kg
may be used tender where working plate available. Vibratory frequency
shall be greater than 1600 cycles per minute. Minimum no. of passes or
coverages shall be 3. Relative density of the sand layer is measured in
field /lot and no. of passes or coverages are executed to obtain 85%
relative density. The next layer is filled on compacted layer and above
procedure is repeated until it reaches the desired level.

1. Procedure for the determination of minimum density
The pouring device and mould should be selected according to the
maximum size of particle as indicated in Table 1 of IS:2720 Part XIV.The
mould should be weighed and the mass recorded .Ovendry soils should
be used. Soil containing particles smaller than 4.75mm should be placed
as loosely as possible in the mould by pouring the soil through the spout
in a steady stream.The spout should be adjusted so that the height of
free fall of the soil is always 25mm.While pouring the soil the pouring
device should be moved in a spiral motion from the outside towards
centre to form soil layer of uniform without segregation.The mould should
be filled approximately 25mm above the top and leveled by making one
continous pass with the steel straight edge .If all excess matter is not
removed,an additional continous pass should be made.Great care shall
be exercised to avoid jarring the mould during the entire pouring and
trimming operation.The mould and the soil should be weighed and the
mass recorded.
Soil containing particles larger than 4.75mm should be placed by means
of a large scoop(or shovel) held as close as possible to and just above
the soil surface to cause the material to slide rather than fall into the
previously placed soil.If necessary ,large particles may be held by hand
to prevent them from rolling off the scoop.The mould should be filled to
overflowing but not more than 25mm above the top .The surface of the
soil should be leveled with the top of the mould using the steel
straightedge(and the fingers ,if necessary) in such a way that any slight
projection of the larger particles above the top of mould shall
9 of 21

approximately balance the larger voids in the surface below the top of the
mould.The mould and the soil should be weighed and the mass recorded.

2. PROCEDURE FOR DETERMINATION OF MAXIMUM DENSITY.
The maximum density may be determined by dry method.

The guide sleeve should be assembled on top of the mould and clamp
assemblies tightened so that the inner surfaces of the walls of the mould
and the sleeve are in the line. The lock nuts on the two set screws
equipped with them should be tightened. The third clamp should be
loosened, the guide sleeve removed, the empty mould weighed and its
mass recorded.
The mould should be then filled the thoroughly mixed oven dry sand by
the procedure explained as above. The mould filled for the determination
of minimum density can also be used for this test. The guide sleeves
should attached to the mould and surcharge base plate should placed on
the soil surface. The surcharge weight then should be lowered on the
base plate using the hoist in the case of the 15000 cm3 mould. The
mould should be fixed to the vibrator deck assembly. The vibrator control
should be set at max. Amplitude and the loaded specimen should be
vibrated for 8 minutes.

Calculations:

Minimum density-
the minimum density, Y min, in g/cm3 should be calculated as follows:
Y min = W gm/Vc
Where,
Wgm = mass of dry soil in the minimum density test in gram ; and
Vc = caliberated volume in the mould in cm3.
Maximum density-
The maximum density calculated as follows:
Y max = Ws/Vs
Where:
Ws= mass of dry soil in the maximum density test in grams.
Vs=volume of soil in maximum density test in cm3 = Vc-(Di-Df)A;
Di = initial dial guage reading in cm
Df= final dial guage reading on the surcharge plate.
Density index (relative density):
The density index expressed as a percentage should be calculated as
follows: Id (or Dr) = Y max (Y d - Y min)/ Y d ( Y max- Y min)
In terms of void ratio Id= ( [ emax-e]/[emax-emin])*100
emax=void ratio of the soil in loosest state
e=void ratio of the soil in the field
emin=void ration of the soil in the densest state


10 of 21



Payment

Payment for filling shall be made on cubic metre of volume calculated
on the basis of cross-section plotted from the levels of ground, where
filling is to be carried out and the levels reached after filling is duly
consolidated, volume being calculated by trapezoidal method.

Partial bill will be processed only after submission of duly certified
copy of proof of payment towards royalty.

Final bill will be processed only after submission of No objection
certificate from relevant statutory authorities towards payment of
royalty.

No extra payment shall be made towards testing charges.

9.0 MISCELLANEOUS & ENABLING WORKS

The sand filling work shall be commenced in following sequence.

a. Taking spot levels and marking grid pillars and clearing bushes &
vegetation.
b. Identifying Borrow areas and obtaining laboratory results regarding
nature of soil, Optimum moisture content (OMC) and max dry density.
c. Submission of sand/murrum filling and excavation procedure.
d. Earthwork in excavation and filling. The filling shall be done in layers not
exceeding 300mm (loose) and compacted with 8-10T roller/ vibro roller
so as to achieve 95% dry density or 85% relative density as applicable.
The field testing shall be done for every layer per 500sqm.
e. The borrow area sand/murrum brought from outside should also be
commenced simultaneously (only after it is ensured that the excavated
earth within premises shall be utilized in filling fully). Whenever there is a
change in source of sand/ murrum, fresh laboratory test shall be carried
out and submitted.
f. Proper watering should be ensured during filling and compaction
operation so that moisture content is near OMC.
g. Party should ensure that all royalty and other cess are paid before earth
is brought to site for filling operation.
h. The trees cut within premises should be uprooted up to 1m below ground
level and the branches to be chopped to small sizes and stacked at
designated place within premises.
i. Coordination with other contractors, creating front for others for execution
of job.


11 of 21



10.0 SPECIFICATION FOR MURRUM FILLING

1.0 This covers the specification for external borrowed earth material i.e.
MURRUM for land filling purposes..

2.0 Only Material considered suitable by HPCL shall be employed for the
construction and that consider unsuitable shall be disposed of, as
directed by Engineer-in-Charge, at contractors cost and no claim for
compensation will be entertained.

3.0 The contractor shall give 4 to 5 samples minimum to cover the best
material available in around the vicinity to Engineer-in-Charge / HPCL
prior to collection and use for approval The test for following
characteristic for all the samples shall be done in a laboratory / test
house as guided by Engineer-in-Charge:

i ) Mechanical analysis are grain size distribution as per IS:2720 part IV.
ii ) Liquid limit as per IS:2720 part V
iii ) Plastic limit as per IS: 2720 part V
iv) Moisture density relationship as per IS: 2720 part VII

4.0 The murrum used for filling shall be free from boulders, lumps, tree
roots, rubbish or any organic deleterious materials.

5.0 Murrum approved by HPCL shall only be used for filling purpose. Non
plastic material will not be permitted

6.0 Murrum having standard proctor laboratory maximum dry density of
less than 1.8 gms/cc shall not be used. The murrum shall have a
Plasticity Index of 7-17(medium Plastic) and not more than
20%Fines,i.e., Clay. Particle size grading shall be 20mm and down
size.

7.0 Care shall be taken to see that waste material from murrum is disposed
of in such a manner that there is no likely hood of its getting mixed with
the material proposed to be used for filling.

8.0 The contractor has to make own approach and access roads in the
borrow areas(Outside Plant Premises) and to the demarcated filling
area(Inside Plant Premises).

9.0 All the royalty payments etc. as deemed admissible to statutory / govt.
authorities will be paid by contractor for all the murrum brought for
HPCL works. It shall be the responsibility for the contractor to produce
all such payments, documents to Engineer-in-Charge during
12 of 21

submission of running bill. At the end of work no objection certificate
from relevant authorities will be submitted to ensure that HPCL is kept
free from all encumbrances.

10.0 Approved murrum material shall be spread in uniform layers not
exceeding 30 cm in loose thickness and watered as per OMC.

11.0 After checking the moisture through moisture tester by calcium carbide
method in field for OMC, the layers shall be thoroughly compacted by
vibratory roller as approved by Engineer-in-Charge till 95% of Standard
proctor maximum laboratory dry density is achieved. Each layer shall
be tested in field for density and accepted by HPCL subject to 95% of
Standard proctor maximum laboratory dry density being achieved. A
minimum of 1 test per 500 sq. mt. of compacted area in field shall be
conducted for dry density. Required equipments like Moisture Tester,
Oven, Electronic weighing machine, proctor apparatus shall be
supplied by Contractor.

12.0 Successive layers of filling and watering will not be permitted until the
layer below has been compacted thoroughly to satisfy the
requirements of the specifications. If the layer fails to meet the required
density, it shall be reworked till the required density is achieved.

13.0 The filling shall be finished in conformity with alignment levels, cross
section and dimension as shown in the drawing. Earthen embankment
shall be filled suitably on both sides to achieve the required
compaction and this extra filling shall be dressed after compaction, in
conformity with alignment, levels, cross section and dimensions as
shown in the drawing. No extra payment shall be made in this regard.

11.0 The excavated soil and / or unusable debris from excavation shall be
loaded, transported safely and unloaded at designated spots as
specified/ as per local bye laws. In case of disposal within the premises,
the soil/debris after unloading shall be levelled and dozed keeping a
distance of at least 5m from the Compound wall to give a uniform
appearance. No extra payment shall be made in this regard.

Payment

Payment for filling shall be made on cubic metre of volume calculated
on the basis of cross-section plotted from the levels of ground, where
filling is to be carried out and the levels reached after filling is duly
consolidated, volume being calculated by trapezoidal method.

Partial bill will be processed only after submission of duly certified
copy of proof of payment towards royalty.

13 of 21

Final bill will be processed only after submission of No objection
certificate from relevant statutory authorities towards payment of
royalty.

No extra payment shall be made towards testing charges.


SAFETY REQUIREMENT FOR CONSTRUCTION WORKS
1.0 GENERAL
1.1 This specification deals with the subject matter of safety and
protection to be observed in the Civil Construction. This shall be followed
along with all related statutory requirements/obligation including
Governmental byelaws, codes, ordinance of local or central authorities
related to the construction work.

1.2. In case of complicated work like deep excavation, intricate shuttering
and formwork, excavation in loose soil and below water table, stacking of
excavated earth etc., work plan with necessary drawings and documents
have to be prepared by the Contractor and got approved by the Engineer.

1.3 Necessary reference shall be made to the following Indian Standard
Codes on safety requirements for various type of work :

2.0 INDIAN STANDARD

4130 1991 Demolition of Buildings
3764 1992 Excavation Work
4014 (P-II) 1967 Scaffolding, Steel Tubular
3696 (P-I & P-II) Scaffolds and Ladders 1987 to 1991
4138 1977 Working in Compressed Air
7293 1974 Working with Construction Machinery
8989 1978 Erection of Concrete Framed Structures

3.0 EXCAVATIONS
3.1. No excavation or earth work below the foundation level of an
adjoining building shall be taken up unless adequate steps are taken to
prevent damage to the existing structure or fall of any part.
14 of 21


3.2 Every accessible part of an excavation, pit or opening in the ground
into which there is a danger of persons falling shall be suitably
fenced with a barrier upto a height of one metre suitably placed from
the edge of the excavation as far as practicable.
3.3. No material or load shall be placed or stacked near the edge of the
excavation or opening in the ground. The excavated material shall
not be placed within 1.5 m of the trench or half of the depth of the
trench whichever is more.
3.4 Cutting shall be done from top to bottom. No undercutting of sides of
excavation shall be allowed.
3.5 Materials shall not be dumped against existing walls or partition to a
height that may endanger the stability of the walls.
3.6 While withdrawing piled materials like loose earth, crushed stone,
sand, etc. from the stock piles, no over hanging shall be allowed to
be formed in the existing dump.
3.7 No material on any of the sites of work shall be so stacked or placed
as to cause danger or inconvenience to any person or public or any
other agency at work.

4.0 SCAFFOLDING, LADDERS & SHUTTERING

4.1 For all work that cannot be done from the ground level or from part of
any permanent structure or from other available means of support,
soundly constructed scaffoldings of adequate strength shall be used
as a safe means of access to places of work.

4.2 All scaffolding shall be securely supported or suspended and
wherever necessary be properly braced to ensure stability.

4.3 All working platform and stages from which workers are liable to fall
shall be of adequate width depending on the type of work done and
closely boarded and planked.

4.4 Every ladder shall be securely fixed at top and bottom. A ladder more
than 5 m long shall have a prop.

4.5 No portable single ladder shall be over 8 m in length.

15 of 21

4.6 Unfinished scaffolding which is under construction shall be
prominently marked as unsafe and any access points shall be
closed.

4.7. Shuttering
The above remarks shall be applicable for this also. Shuttering,
particularly for slabs, should be treated as a scaffold. Unfinished
shuttering should be marked as dangerous similarly the finished form
work should be adequately supported, care being taken to avoid trap
door effects.

5.0 SAFETY APPLIANCE

5.1 Those engaged in white washing and mixing or stacking of cement
bags or any materials which is injurious to the eyes, shall be
provided with protective goggles.

5.2. The Contractor shall not employ men below the age of 18 and
women on the work of painting with products containing lead in any
form. Whenever men above the age of 18 are employed on the work
of lead painting the following precautions shall be taken :

5.3. All necessary personnel safety equipment such as safety helmets,
safety boots, safety belts, leather gloves for welders, clear glass
safety goggles etc., as considered adequate by the Engineer have to
be kept available for the use of persons employed at the site of work
and maintained in condition suitable for immediate use and
Contractor shall take steps to ensure proper use of equipment by the
workers.

5.4 Sign boards 1 x 1.5 m in size with the following wording shall be
erected at the access to these areas. CONSTRUCTION AREA,
HELMET REQUIRED BEYOND THIS POINT.

5.5 Arrangement for rendering prompt and adequate first aid to the
injured persons shall be maintained at every work site under the
guidance of a medical officer-in-charge of the project. Depending
upon the magnitude of the work the availability of an ambulance at a
very short notice (a telephone call) shall be ensured.

16 of 21

First-aid arrangements commensurate with the degree of hazard and
with the number of workers employed shall be maintained in a readily
accessible place throughout the working hours. At least one
experienced first-air attendant with his distinguishing badge shall be
available on each shift to take care of injured persons. Arrangements
shall be made for calling the medical officer, when such a need may
arise. It is recommended that foreman/assistant foreman /supervisor
/permanent workmen who are normally present at each working
phase in each shift are given adequate training on first-aid methods
to avoid employment of a separate attendant.


6.0 MISCELLANEOUS

6.1 The Contractor shall provide necessary fencing and lights to protect
the public from accident.

6.2 To ensure effective enforcement of the rules and regulations relating
to safety precautions, the arrangements made by the Contractor
shall be open to inspection by the Engineer and Owner.

6.3. All sources of ignition shall be prohibited in areas where flammable
liquids are stored, handled and processed. Suitable warning and NO
SMOKING signs shall be posted in all such places. Receptacles
containing flammable liquids shall be stacked in such a manner as to
permit free passage of air between them.
6.4 All combustible materials shall be continuously removed from such
areas where flammable liquids are stored, handled and processed.
All spills of flammable liquids shall be cleared up immediately.
Containers of flammable liquids shall be tightly capped.

7.0 REPORTING OF ACCIDENT

7.1 All accidents, major or minor must be reported immediately. The
Contractor, will provide first aid to the injured person immediately and
the injured person shall report to the first aid station along with the
INJURED ON WORK form duly filled in quintuplicate and submit to
the Medical Officer of the First Aid Station.

7.2. Serious Injury
17 of 21

In case of serious injury, the following procedure shall be adopted by
the Contractor:

a) Provide First Aid at his own First Aid Station.

b) Take the injured person to the Hospital along with the INJURED
ON WORK form duly filled in.

c) Reporting the accident to the Owner/Engineer by the Contractor.

7.3 Fatal Accident

Fatal accident must be reported immediately to the Engineer/Owner
as well as to the Police.

8.0 PENALTY

Failure to observe the Safety Rules will make the Contractor liable to
penalty by way of suspension of work, fine and termination of
contract.









18 of 21






STANDARD

INSPECTION & TEST PLAN

(I T P )

FOR

SAND/MURRUM FILLING












19 of 21

STANDARD INSPECTION & TEST PLAN (I T P ) FOR SAND & MURRUM
FILLING WORKS

1.0 GENERAL NOTES:

Inspection and Test Plan(ITP) given herein is indicative only. The
Contractor shall prepare and submit ITP for all activities The provisions
indicated herein for stage wise inspection are minimum and the Engineer-in-
Charge may decide to increase the Hold Point / Witness Point. Contractor
has to prepare ITPs for any of the activities not covered herein, submit the
same to HPCL and obtain their approval.

Contractor to prepare required reporting formats and job procedures for
each activity i.e. Setting out of work, levels at 5x5m grid co-ordinate wise
and as per technical specifications, submission of min. 5 nos. Sand /
Murrum samples meeting tender specifications along with soil lab. test
report, watering, OMC, Rolling , carting away earth etc to HPCL for approval
well in advance prior to commencement of activity. Any deviation to ITP
shall be subjected to HPCLs written approval. Contractor to carry out 100%
examination of all activities and proper records shall be maintained and
made available to HPCL Officers requirement at any time of inspection
during the contract period.

2.0 LEGEND :

2.1 HP: HOLD POINT

A point which requires inspection/verification and acceptance by HPCL
before any further processing is permitted.
The contractor shall not process the activity/item beyond the Hold Point
without written approval from Engineer-in-Charge.

2.2 W : Witness Point

An Activity which requires witness by HPCL when activity is performed.

2.3 RW : Review of Contractors Documentation

2.4 S : Surveillance Inspection by HPCL

Monitoring of observations to verify whether or not materials/items/services
confirms to specified requirement. Surveillance activities may include audit,
inspection, witness of testing, review of quality documentation & records,
personnel qualifications, etc.
2.5 WC: 100% examination by Contractor.

3.0 The Indicative Inspection and Test Plan(ITP) is as given below:
20 of 21


Sr.
No.
ACTIVITY CONTRACTOR HPCL
1.0 SAND FILLING
1.1 Fixing of co-ordinates with respect to HPCL Bench
Mark (B.M.) as per HPCL lay out , Setting out of
various Control point & alignment, grid levels
5mx5m and as per tender specifications, Co-
ordinates wise survey & recording. The readings
will be taken on same co-ordinates in subsequent
activity. Clearing of vegetation, shrubs etc and
disposal of the same outside premises and make
surface ready for further activities.
WC







HP

1.2
Collection of Sand samples from various
borrow areas locally available river sand sample
lab analysis as per IS 383 , submission to HPCL
for approval with all requisite details. Sand to be
approved by HPCL Required data for testing at
field the relative density for compaction as per
IS2720 PART XIV.
WC HP
1.3 (A) SAND LAYING :
- 300mm loose layer checking it with
templates/tools at various co-ordinates &
recording.
- Watering the layer as guided by
Procedure as per requirements
(B) COMPACTION :
-Procedure to be given by HPCL to achieve
85% Relative density at site
-Rolling/ Compaction by Plate Vibrator/ Vibro
roller, maintenance of moisture content in sand
below 5%.
- Testing for compaction to confirm its 85%
relative density achieved co-ordinate wise,
Recording the levels co-ordinate wise min. one test
@500 sqm . (Min. 1 no test per 25 sq. Mtr.) and on
positive test result, next layer commencement. -


WC


WC


HPCL

WC




WC



W


W


HP

W




HP

2.0

MURRUM FILLING

2.1 Fixing of co-ordinates with respect to HPCL B.M.
as per HPCL lay out , Setting out of various Control
point & alignment, grid levels 5mx5m and as per
tender specifications, Co-ordinates wise survey &
recording. The readings will be taken on same co-
ordinates in subsequent activity. Clearing of
vegetation, shrubs etc and disposal of the same
WC HP
21 of 21

outside premises and make surface ready.
.

2.2
Collection of Murrum samples from various borrow
areas, lab analysis of samples, submission of test
reports to HPCL for approval with all requisite
details.
WC HP
2.3 Excavation, if any as per approved drawings and
as directed by EIC & carting away unusable earth
as per instructions of HPCL within Plant premises.
WC W
2.4 (A) Rolling of sub grade/ sub base & testing
for 95% max. lab dry density in case of soil or 85%
relative density in case of sand as applicable.
WC



W


2.5

(A) MURRUM LAYING :
- 300mm loose layer checking it with
templates / tools at various co-ordinates &
recording.
- Watering the layer, checking the OMC
through Moisture Tester & recording co-ordinate
wise.
(B) COMPACTION :
- Rolling the OMC watered layer
immediately once tested for OMC till 95%
Standard Proctor dry density achieved.
- Testing for compaction to confirm its 95%
Standard Proctor dry density achieved co-ordinate
wise, Recording the levels co-ordinate wise . (Min.
1 no test per 500 sq. Mtr.)
- Offering Tested layer to HPCL to inspect &
witness to give clearance for next layer.

WC


WC



WC




WC


WC

W


W



W




W


HP
2.6 Final profile of Murrum surface to receive
further courses per Approved levels/coordinates
and Construction drawing to be prepared by
Contractor based on general civil detail drawing
furnished in this tender duly approved by HPCL, to
be executed as per 2.5 above, cutting / making of
edges for embankments etc & complete as per EIC
instructions.


WC


W/
HP

You might also like