PERI ACS Method Statement

PERI ACS System will be used for the construction of the Core Wall of Kohinoor Square
Project. ACS means Automatic Climbing System in which the shutter panels are mounted
over ACS brackets and moved hydraulically independent of the crane. For the wall formwork
PERI VARIO GT24 wall formwork will be used. The shutter height is 4.0m. These shutter
panels are designed for a concrete pressure of 50 kN/sqm.
Please find the below Core layout from Basement Level-3 to Basement Level-2 (Refer PERI
drg. 01-0313740-B001, Sheet-1, Rev-b). The typical basement floor to floor height is
3100mm. These 2 basements will be completed in 2 pours of 3950mm (1 st pour) and 2250mm
(2nd pour). The 2 walls along the door openings have a thickness of 1800mm, which will get
reduced to 900mm from Basement Level-1 onwards.

The box-outs for the door openings are made by conventional system using plywood, HBeams & props. The shutter panels are of various types such as E panel (external), I panel
(internal), EC panel (external corner) and IC panel (internal corner). A total of 74 panels are
required for the 1st pour and extra 4 panels for the 2nd pour.

PERI

Kohinoor Square Project, L&T

Page 1 of 10

Below is the list of shutter panels showing their quantity, unit weight and the corresponding
steel waler to be used:

The walers shown with Red colour are the small panels and these can be easily handled with
small mobile crane. These small panels maximum weighs upto 1158 kgs. The walers shown
in Green colour are the big panels and these require tower crane / suitable crane for handling
purpose during assembly sequence. These big panels maximum weighs upto 2243 kgs.

PERI

Kohinoor Square Project, L&T

Page 2 of 10

All the shutter panels are to be assembled very close to the core so that during erection the
handling distance is reduced. A Tower Crane is to be used for the shutter erection procedure.
A usage of fully dedicated crane would result in faster erection. The pour height is 3950mm.
Below is the layout of the VARIO GT24 shutter panels for the 1 st pour (Refer PERI drg no.
01-0313740-B006, Sheet-1, Rev-0). Also refer drg no. 01-0313740-B007, Sheet-1, Rev-0, for
typical section at 1st pour.

Room-3

Room-4

Room-2

Room-1

Room-5

Room-6

Please find the below Shutter Panel erection sequence. The erection should be done room
wise. So the internal panels & internal corners are to be erected first. The external panels and
external corners are to be erected with respect to the rooms getting completed.

PERI

Kohinoor Square Project, L&T

Page 3 of 10

600

900

300

550

450

3100

2250

250

550

450

300

4200

3900

900

rh =
fo
0
9
3

1800

9350

3950

G T2 4l =3 ,90m

3100

Floor
heights

G T2 4l =3 ,90m

rh =
fo
0
9
3

G T2 4l =3 ,90m

rh =
fo
0
9
3

600

4150

Pour
heights

1800

Climbing cones will be installed on the shutter panels before casting of 1 st pour. These cones
will be used later on for anchoring ACS brackets.
After the 1st pour, giving required curing time, the DW15 tie rods are to taken out and
deshuttering has to be done. ACS-R & ACS-P main platforms will be assembled. Shutter
panels to be mounted over platforms. Since the ACS-R & ACS-P platforms are to be
assembled around & inside the core respectively so all the shutter panels are to be moved out
of the core and stacked vertically one after another on the raft. The best way is to stack the
panels vertically by resting them on the sides of the columns on raft. While stacking care is to
be taken so that the plywood does not get damaged and panels are be placed so that the
plywood faces each other. The finishing platforms are to be assembled and kept on the raft
top. These will get attached to the main platforms once the system climbs up.
Below is a typical section showing the formwork and ACS arrangement during 2 nd pour
(Refer PERI drg no. 01-0313740-B007, Sheet-1,scale
Rev-0).
1:50
s ee d ra wi ng C 04 0 for
p os itio n of l ea di ng anchors
a t fo rmwork

4200

3900

G T2 4l =3 ,90m

rh =
fo
0
9
3

rh =
fo
0
9
3

3100

3950

3100

2250

G T2 4l =3 ,9 0m

G T2 4l =3 ,9 0m

550

G T2 4l =3 ,9 0m

250

300

300

rh =
fo
0
9
3

G T2 4l =3 ,30m

Floor
heights

PERI

ACS-R7

ACS-P5

Kohinoor Square Project, L&T

ACS-P2

ACS-R2

Page 4 of 10

Pour
heights

The pour height is 2250mm. With this pour the Basement Level-2 gets completed. The top of
this pour is the end of the wall, of thickness 1800mm. After the pour of 2250mm is over, a
timber starter is to be made over this pour on the external side of 1800mm thick wall. An
additional pour of 300mm is to be done.
Please refer the below drg (Refer PERI drg no. 01-0313740-B007, Sheet-1, Rev-0). This
additional pour is must since the next pour of 3900mm along with this additional 300mm will
accommodated the ACS Brackets.
scale 1:50
Form for kicker
by site

Working Platform ACS-P


Lev el +1

4200

3900

G T2 4l =3 ,90m

Access Platform ACS-R


rh
fo

0
9
3
=

rh
fo

Level +1

0
9
3
=

0
9
3
=

3100

2250

GT2 4l =3 ,90m

GT2 4l =3 ,90m

G T2 4l =3 ,90m

300

rh
fo

Main Working Platform ACS-P


Level 0

3100

3950

Lev el 0

Lev el -1
G T2 4l =3 ,30m

Floor
heights

ACS-R7

ACS-P5

ACS-P2

Pour
heights

ACS-R2

After the additional pour of 300mm, wall shutter panels will be rolled back. Using the trolley
installed in ACS-P inside platform the shutters will be rolled back and using the formwork
carriage of ACS-R outside platform the shutters will be retracted back. Climbing shoes are to
be fixed to the climbing cones. Please refer the below drg (Refer PERI drg no. 01-0313740B007, Sheet-2, Rev-0).

4200

3900

GT2 4l =3 ,90m

rh =
fo
0
9
3

0
9
3
=

rh
fo

0
9
3
=

3100

3950

3100

2250

GT2 4l =3 ,90m

250
550

GT2 4l =3 ,90m

G T2 4l =3 ,90m

300

rh
fo

GT2 4l =3 ,30m

Floor
heights

PERI

ACS-R7

ACS-P5

Kohinoor Square Project, L&T

ACS-P2

ACS-R2

Page 5 of 10

Pour
heights

Climbing Rails are to be installed with the help of crane from top for ACS-R & ACS-P
platforms. The Climbing Rail is guided by the climbing shoes. Please refer the below sketch.

scale 1:50

4200

3900

G T2 4l =3 ,90m

rh =
fo
0
9
3

0
9
3
=

rh
fo

0
9
3
=

3100

3950

3100

2250

G T2 4l =3 ,90m

250
550

G T2 4l =3 ,90m

G T2 4l =3 ,90m

300

rh
fo

G T2 4l =3 ,30m

Floor
heights

ACS-R7

ACS-P5

ACS-P2

Pour
heights

ACS-R2

The ACS-R outside & ACS-P inside platforms are hydraulically climbed to the next
anchoring level. After climbing operation, all the Climbing Rails are removed from the
system using crane. This required for closing the shutters in concreting position. Please refer
the sketch below.

GT2 4l =3 ,90m

rh =
fo
0
9
3

rh =
fo
0
9
3

3900

0
9
3
=

3100

3950

3100

2250

250
550

300

GT2 4l =3 ,90m

G T2 4l =3 ,90m

G T2 4l =3 ,90m

4200

rh
fo

GT2 4l =3 ,30m

Floor
heights

PERI

ACS-R7

ACS-P5

Kohinoor Square Project, L&T

ACS-P2

ACS-R2

Page 6 of 10

Pour
heights

Reinforcement for the entire core is completed. At the location of 1.8m thick wall the external
shutter panels are lifted by crane and positioned on the wall for the next pour. At these
locations the shutter panels are aligned by push pull props from the platform. The shutter
panels on the core sides (900mm thick) remain mounted over the ACS-R platform through
the formwork carriage. The inside shutter panels are rolled back by trolley of ACS-P system.
Tie rods are fixed and shutter aligned. Finishing platforms of ACS-P (Level -1) is fixed to the
system. Please refer the sketch below.
G T2 4l =3 ,90m

rh
fo

0
9
3
=

3100

3950

V T2 0K l= 4,90m

V T2 0K l= 4,90m

3100

2250

300

GT2 4l =3 ,90m

3900

rh =
fo
0
9
3

G T2 4l =3 ,90m

0
9
3
=

GT2 4l =3 ,90m

4200

rh
fo

G T2 4l =3 ,30m

Floor
heights

ACS-R7

ACS-P5

ACS-P2

ACS-R2

Pour
heights

The inside shutter panels are retracted by trolleys of ACS-P. Climbing Rails for ACS-P is
installed with crane. Climbing shoes are fixed on the leading anchors for inside & outside.
The lower climbing shoes are removed from the wall. ACS-P platforms are climbed
hydraulically upwards to the next level. The external shutter panels at the 1.8m thick wall is
removed and kept on the raft. The ACS-R units at this location are moved by crane to the next
anchoring level. Please refer the below sketch.

G T2 4l =3 ,90m

rh =
fo
0
9
3

3100

3950

V T2 0K l= 4,90m

V T2 0K l= 4,90m

3100

2250

300

G T2 4l =3 ,90m

3900

0
9
3
=

G T2 4l =3 ,90m

4200

rh
fo

G T2 4l =3 ,30m

Floor
heights

PERI

ACS-R7

ACS-P5

Kohinoor Square Project, L&T

ACS-P2

ACS-R2

Page 7 of 10

Pour
heights

The ACS-P units will be climbed hydraulically. Reinforcement will be completed. External
shutter panels will be mounted over the ACS-R formwork carriage. Shutter panels to be
closed and aligned. Please refer the below sketch.
G T 2 4l =3 ,90m

rh =
fo
0
9
3

rh =
fo
0
9
3

rh
fo

0
9
3
=

3900

- Conc rete poured

2250

300

V T2 0K l= 4,90m

V T2 0K l= 4,90m

4200

3900

G T2 4l =3 ,90m

G T2 4l = 3 ,90m

G T2 4l = 3 ,90m

3900

- Wall s ec tion reinforced

3100

3950

3100

G T 2 4l =3 ,30m

Floor
heights

ACS-R7

ACS-P5

ACS-P2

P roject

Pour
heights

ACS-R2

S ubject

After the above pour, shutter panels will be retracted by the formwork carriage on outside and
trolleys in inside. Shutter panels will be cleaned and release agent be applied. Climbing shoes
will be fixed on wall. Climbing rails to be inserted for ACS-R units by crane at 1.8m thick
wall location only. Climbing rails of ACS-P units will be climbed hydraulically. The system is
self climbed to next anchoring location. Core wall reinforcement will be completed. Shutter
panels will be closed and aligned. Finishing platform of ACS-R Units (Level -2) will be fixed
to the system. Please refer the below sketch.

G T2
4 l = 3
, 9
m
0

rh =
fo
0
9
3

3900

- Formwork cleaned
- Climbing shoes attached to leading anchors

VT 2
0 K l= 4 ,9 0
m

VT 2
0 K l= 4 ,9 0
m

3900

GT 2
4l = 3
, 9
m
0

G T2
4 l = 3
, 9
m
0

3900

rh =
fo
0
9
3

G T2
4 l = 3
, 9
m
0

3900

rh =
fo
0
9
3

- Wall section reinforced


- Formwork planels closed & aligned
- Concrete poured

3100

3950

3100

2250

300

4200

3900

G T2
4 l = 3
, 3
m
0

Floor
heights

PERI

ACS-R7

ACS-P5

ACS-P2

ACS-R2

Kohinoor Square Project, L&T

Pour
heights

Page 8 of 10

Below sketch shows a typical section of the whole ACS system hydraulically driven. This
will continue till the top of the building.

GT 2
4 l = 3
, 9
m
0

rh =
fo
0
9
3

3900
3900

GT 2
4 l = 3
, 9
m
0

VT2
0 K l= 4 ,9 0
m

VT2
0 K l= 4 ,9 0
m

3900

GT 2
4 l = 3
, 9
m
0

rh =
fo
0
9
3

GT 2
4 l = 3
, 9
m
0

3900

rh =
fo
0
9
3

3100

3950

3100

2250

300

4200

3900

GT 2
4 l = 3
, 3
m
0

Floor
heights

PERI

ACS-R7

ACS-P5

Kohinoor Square Project, L&T

ACS-P2

ACS-R2

Page 9 of 10

Pour
heights

Below is the layout of the ACS-P Units. Openings of 1.5m x 1.5m & 2.0m x 2.0m will be
provided in the ACS-P2 platform for the Placing Boom Mast and Tower Crane Mast,
respectively.

Below is the layout of ACS-R Units on the external sides of the Core. The ACS-R units on
the 1.8m thick wall location need adjustment due to the reduction of wall thickness.

PERI

Kohinoor Square Project, L&T

Page 10 of 10