Professional Documents
Culture Documents
1. Introduction
Yokohama Bay Bridge, ordinary national road No. 357, is a long, large-scale bridge of
2,160 m in length. It consists of a three-span cable stayed bridge, a steel truss bridge and
steel box girders. It is of a double deck structure: the upper deck is used as a route of the
Metropolitan Expressway, and the lower deck is used as ordinary national road No. 357,
and called Yokohama Bay Bridge (called YBB below). This report describes the paving
work done on the lower deck or YBB (Photograph 1 and Figure 1).
YBB is part of the Tokyo Bay Shore Road. It is an arterial road connecting the
Honmoku and Daikoku piers, and carries a large volume of container cars and other
heavy vehicles. To alleviate the degree of fatigue of this bridge and prevent its steel
deck plate from being damaged, the conditions of the existing mastic asphalt pavement
were surveyed. As a result, it was found that the rigidity of the deck plate needed to be
increased. Specifically, it was decided that stud dowels be installed at the ends of the
steel deck plate to prevent drying shrinkage and temperature changes in the concrete
from causing a displacement, and that steel fiber reinforced concrete (called SFRC
below) be laid on the existing steel deck plate to integrate SFRC and the deck plate into
a single-piece structure using adhesive material.
This report describes the results of our study, aimed at making a practical method of
preventing fatigue damage of the steel deck plate, using SFRC paving, and at reporting
the conditions of paving work done on YBB and the results of testing.
Figure 1
-1-
Standard cross-sectional
view of YBB
Tire
Deck plate
Crack
line
Asphalt pavement
U-rib
U-rib
Figure 2 Mechanism of fatigue damage of the
steel deck plate
6,000()
(worked by machinery)
150
Vertical seam
Stud
SFRC
pavement
Epoxy resin
150
Working direction
200
Filter
Separation drum
Frame
Concrete
Wooden framework
Suction hose
Vacuum
hose
Suction hole
Vacuum mat
3
0
0
@
3
3
2
=
9
9
,6
0
0
300@19=5,700
Vacuum pump
Plastic plate
Cover plate
Filter cloth
325.0
282.9
1400
1200
1000
212.9
2
200
800
150
600
480
100
400
50
200
0
0
1040
250
Amount of wear
300
(kgf/cm )
350
10
1.2
1.1
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0.0
1.105
Cross
chain
(test time: 90 minutes)
:90
0.700
0.631
0.187
0.113
Side
chain
(test
:90
time:
90minutes)
5(0.5 l/m2)
0.121
10(1.0 l/m2)
Prior to the SFRC paving work, the effectiveness of the vacuum dehydration method
was evaluated, and it was presumed that vacuum dehydration would increase the surface
hardness of SFRC and decrease the amount of wear and that, as a result, the
requirements for pavement surface performance could be met.
The amount of dehydration was about 500 cc/m2 during the dehydration period of 7.5
minutes.
-3-
W/C
mm
15
%
47.3
S/a
%
60
Target
slump value
cm
8.0
Target air
volume
value
%
5.0
Percentage
of SF
dilution
%
1.5
High-earlystrength
cement
389
Unit amountkg/m3
Fine
Coarse
Swelling
Water aggreaggreagent
gate
gate
30
198
980
673
Admixture
Steel
fiber*
kg
4.2
120
* 0.5*0.5*30mm, with ribs for increased adhesion in accordance with the standard concrete
specifications issued by the Japanese Society of Civil Engineers
The paving work was carried out by first grinding the surface of the deck plate and then
cleaning it by shot blasting. SFRC base concrete was prepared at a factory and
transported to the work site with agitator trucks. It was then pumped up to the deck of
the bridge (H = 40 m). On the deck, it was again loaded onto agitator trucks while fibers
were mixed with it by blowing air. The area was then coated with 1 L/m2 of epoxy resin,
and the base concrete was laid and leveled using a special concrete finisher and a
leveling machine. The initial curing was done by first spraying a coating curing agent
and then vacuum dehydration and the surface was then finished using trowels. The final
curing was done over one week by covering the surface with plastic sheets, heat
insulating mats, flameproof sheets, and nets.
6. Results of the paving work
Table 2 shows the results of adhesive strength tests. The target adhesive strength was
defined as 1N/mm2 for the materials, whose age was 7 days. Skid resistance tests were
conducted 4 months after the paving work was completed. The test results were
BPN=61 and 60 (DF tester) = 0.4 which satisfied the specified requirements for
pavement surfaces. The flatness was about 1.2 mm which satisfied the specified
requirement of 3 m < 2.4 mm.
Standard deviation
(quantity)
0.24
(n = 5)
0.15
(n = 4)
Point of fracture
Fracture in the
SFRC layer
Fracture in the
SFRC layer
The results of loading tests show that after the SFRC pavement was laid, the working
stress decreased by 90% in the general and cross sections on the underside of the deck
plate, by about 80% in areas above the vertical ribs in general sections, and by about
50% at the scholarship and three-weldment join sections of vertical ribs.
7. Closing remarks
It was verified that the SFRC paving method is effective in alleviating the degree of
fatigue damage of the steel deck plate. To evaluate the performance of the SFRC
pavement in the long term, we will continue monitoring the conditions using optical
fiber sensors.
-4-