Professional Documents
Culture Documents
Rev.0 12-Nov-2014
1.0 Mechanical
completion
Stage of completion
when all new works
have been erected
and installed in
accordance with
drawings,
specifications,
applicable codes and
standards. This will
include the following:
Checking the
tagging and
completeness of
components
against project
drawings,
Checking the
condition and
status of each
individual
component and
vendor
packages.
Completion of
certain tests on
individual
components
such as
instrument
calibration,
pump alignment,
uncoupled motor
checks, piping
pressure testing,
etc.
No.
EPC Contractor
Commissioning
Team
Project
Management
Team
(PMT/PMC)
Commissioning
Specialist Team
Site
Operations
Team
1.1
Mechanical Completion of
various systems.
A
(BY
PMC/TPA)
1.2
A
(BY
PMC/TPA)
1.3
A (BY TPA)
1.4
A (BY TPA)
1.5
A (BY TPA)
1.6
1.7
1.8
1.9
Identification of all
commissioning and start-up
related drawings / documents
which require site operations
approval / signature
2.1
Pre-commissioning of
individual systems (piping,
electrical, mechanical,
instrument, HVAC, telecom
systems etc.)
2.2
2.3
2.0 Precommissioning
Stage of completion
that include but not
limited to:
All cold
alignment
checks, cleaning
and testing of
machinery
In-line
Activities
Page 1 of 4
volunteer
instruments
installed, All
motors reconnected
Electrical and
instrumentation
systems
checked
Instrument cold
loop checks
completed,
All pipe work
and equipment
pressure-tested,
flushed, and if
necessary
chemically
cleaned
All electrical
continuity and
earthing tests
completed.
2.4
Tripartite walk of
PMT/EPC/OPS team to
witness selected pre-com
activities and raise necessary
punchlists.
2.5
Implementation of all
recommendations from safety
studies (PHSER, HAZID,
HAZOP) at site.
2.6
2.7
2.8
2.9
2.10
3.1
3.2
3.3
Supply of required
documentation for MAXIMO
& Initial Quality Assurance
3.4
Implementation in MAXIMO
system
3.5
Availability of all
commissioning /start-up
spares.
3.6
3.0 Commissioning
Verify
completion of
pre-com
activities.
Review of
punchlist, asbuilt drawings
Function/logic
test electrical /
instrument
(ESD, F&G ,
DCS) systems
after energising
them.
Do necessary
SATs.
Perform OTPs
for hydrocarbon
systems with
inert substances
or fluids.
Bringing all
utility systems to
operational state
and
performance
test them, for
preliminary
handover to ops.
Pre-start-up
activitiesinerting, loading
of chemicals,
leak test,
blowdown test
with inert fluid
etc.
Rev.0 12-Nov-2014
3.7
3.8
3.9
Page 2 of 4
volunteer
Rev.0 12-Nov-2014
3.10
3.11
3.12
3.13
3.14
3.15
3.16
3.17
Page 3 of 4
volunteer
4.1
4.2
Arranging / coordinating
engineering resources and
vendor support for a
safe/efficient start up, final
commissioning, ramp up and
performance testing of
facilities.
4.3
4.4
4.5
4.6
4.7
Attendance/Rectification of
leaks.
4.8
4.9
De-spading of hydrocarbon
lines.
4.10
Introduce hydrocarbons to
the system by opening
relevant valves.
4.11
4.12
4.13
4.0 Start-up:
Carry-out final safety
tests OTPs for
hydrocarbon systems
Achieve steady state
operation
Performance test
Rev.0 12-Nov-2014
Page 4 of 4