AQC-9 Boiler Erection Schedule

SL.NO

DESCRIPTION
AQC-IX Boiler

DURATION
192

GROUND ASSEMBLY OF SUPPORTING STRUCTURE

15

ERECTION OF LOWER STRUCTURE ASSEMBLY

15

ERECTION OF STAIRS AND PLATFORMS

40

ERECTION HP SUPERHEATER ASSEMBLY WITH HANGING ARRANGEMENT

ERECTION OF TOP STRUCTURE ASSEMBLY

ERECTION OF LP STEAM DRUM WITH INTERNALS

ERECTION HP HEAT WATER SEGMENT ASSEMBLY WITH HANGING ARRANGEMENT

ERECTION HP ECONOMISER ASSEMBLY WITH HANGING ARRANGEMENT

ERECTION HP EVAPORATOR-1 ASSEMBLY WITH HANGING ARRANGEMENT

10

ERECTION LP EVAPORATOR-2 ASSEMBLY WITH HANGING ARRANGEMENT

11

ERECTION OF HP BOILER DOWN COMERS

15

12

ERECTION OF HP BOILER RISERS

15

13

ERECTION OF HP BOILER SUPER HEATER I/L AND O/L LINKS

15

14

ERECTION OF ALL PRESSURE PARTS SUPPORTS

10

15

COMPLETEION OF HP BOILER HP WELDING

25

16

COMPLETION OF RADIOGRAPHY

17

LOCAL HYDRO TEST

18

INSULATION WORK FOR HP BOLIER

19

ERECTION LP ECONOMISER ASSEMBLY WITH HANGING ARRANGEMENT

20

ERECTION LP EVAPORATOR-1 ASSEMBLY WITH HANGING ARRANGEMENT

21

ERECTION LP EVAPORATOR-2 ASSEMBLY WITH HANGING ARRANGEMENT

22

ERECTION OF SUPER HEATER ASSEMBLY WITH HANGING ARRANGEMENT

23

ERECTION OF LP STEAM DRUM WITH INTERNALS

24

ERECTION OF LP BOILER DOWN COMERS

15

25

ERECTION OF LP BOILER RISERS

15

26

ERECTION OF INTEGERAL LINKS

15

27

ERECTION OF ECO I/L & O/L LINK

15

28

ERECTION OF ALL PRESSURE PARTS SUPPORTS

10

29

COMPLETEION OF LP BOILER HP WELDING

10

30

COMPLETION OF RADIOGRAPHY

15

31

ALL VENT & DRAIN VALVES FIXING

32

ALL VALVES FIXING IN LP & HP BOILER

33

LOCAL HYDRO TEST

38

INSULATION WORK FOR LP BOLIER

20

34

AQC BOILER INLET GAS DUCTING WITH DAMPERS & BELLOWS ERECTION

10

35

AQC BOILER OUTLET GAS DUCTING WITH DAMPERS & BELLOWS ERECTION

10

36

AQC BOILER BYPASS DAMPER WITH BELLOW

10

20

SL.NO

DESCRIPTION

DURATION

37

ERECTION OF ALL DUCTING SUPPORTING STRUCTURE

10

39

ERECTION OF ASH HOPPER

15

41

ASH CONVEYING SYSTEM

15

42

ERECTION OF HP/LP DOSING SYSTEM

10

43

ERECTION OF STEAM SAMPLING SYSTEM

10

44

ERECTION OF HP/LP STEAM HEADERS

10

45

ERECTION OF SILENCERS WITH PIPINGS

10

46

ERECTION OF BLOW DOWN TANK WITH ACCESSARIES

48

REFRACTORY WORK

51

ALKALI BOILOUT

52

STEAM BLOWING

7
27

C-9 Boiler Erection Schedule


START

FINISH

16-May-13

24-Nov-13

16-May-13

31-May-13

3-Jun-13

18-Jun-13

7-Jun-13

17-Jul-13

1-Aug-13

8-Aug-13

8-Aug-13

15-Aug-13

15-Aug-13

22-Aug-13

22-Aug-13

29-Aug-13

29-Aug-13

5-Sep-13

5-Sep-13

12-Sep-13

12-Sep-13

19-Sep-13

19-Sep-13

4-Oct-13

19-Sep-13

4-Oct-13

19-Sep-13

4-Oct-13

4-Oct-13

14-Oct-13

19-Sep-13

14-Oct-13

14-Oct-13

21-Oct-13

21-Oct-13

24-Oct-13

24-Oct-13

13-Nov-13

1-Aug-13

8-Aug-13

8-Aug-13

15-Aug-13

15-Aug-13

22-Aug-13

22-Aug-13

29-Aug-13

29-Aug-13

5-Sep-13

5-Sep-13

20-Sep-13

5-Sep-13

20-Sep-13

5-Sep-13

20-Sep-13

20-Sep-13

5-Oct-13

5-Oct-13

15-Oct-13

20-Sep-13

30-Sep-13

20-Sep-13

5-Oct-13

5-Oct-13

10-Oct-13

5-Oct-13

10-Oct-13

10-Oct-13

13-Oct-13

13-Oct-13

2-Nov-13

13-Oct-13

23-Oct-13

23-Oct-13

2-Nov-13

23-Oct-13

2-Nov-13

START

FINISH

2-Nov-13

12-Nov-13

13-Oct-13

28-Oct-13

28-Oct-13

12-Nov-13

10-Oct-13

20-Oct-13

20-Oct-13

30-Oct-13

30-Sep-13

10-Oct-13

30-Sep-13

10-Oct-13

30-Sep-13

7-Oct-13

23-Oct-13

19-Nov-13

19-Nov-13

21-Nov-13

21-Nov-13

24-Nov-13

TG SCHEDULE AS SUBMITTED BY APT


Description
Duration

S.No.

TURBINE AT SITE
TURBINE DURATION

Start

Complete
21-Aug-13
17-Oct-13

62

16-Aug-13

Site Mobilization

16-Aug-13

17-Aug-13

Preparation of Foundation

18-Aug-13

20-Aug-13

ii

Leveling of packers plates

21-Aug-13

23-Aug-13

iii

Lifting of turbine base plate and bearing


pedestals keeping on foundation

23-Aug-13

25-Aug-13

iv

Leveling of bottom casing and keeping on the


foundation

26-Aug-13

26-Aug-13

Lifting of turbine & generator rotor and keeping


on 8 MT floor

27-Aug-13

27-Aug-13

vi

Cleaning of bottom and top casings

28-Aug-13

30-Aug-13

vii

Leveling of generator packer plates and sole


plates

16-Sep-13

18-Sep-13

viii

Lifting of generator and keeping on sole plates

19-Sep-13

19-Sep-13

ix

Leveling of bottom casing & rotor and centering


reading

31-Aug-13

2-Sep-13

x
xi

Bedding of generator rotor bearings


Insertion of generator rotor

2
2

19-Sep-13
21-Sep-13

20-Sep-13
22-Sep-13

xii

Alignment of turbine and generator rotor

23-Sep-13

24-Sep-13

Checking of axial & radial clearance


Checking of rotor movements
Checking of generator air gaps
Final boxing up of turbine
Generator end covers fixing
Exciter air gap and assembly
Grouting of TG set & querying

3
3
1
2
2
1
6

3-Sep-13
6-Sep-13
25-Sep-13
26-Sep-13
28-Sep-13
30-Sep-13
1-Oct-13

5-Sep-13
8-Sep-13
25-Sep-13
27-Sep-13
29-Sep-13
30-Sep-13
6-Oct-13

xx

Checking of final alignment and fixing of coupling

6-Oct-13

7-Oct-13

xxi

Bearing clearance and final assembly of bearing

8-Oct-13

9-Oct-13

xxii

Bearing covers interferences

10-Oct-13

11-Oct-13

xxiii

Fixing of instruments(inside the bearing


housings)

12-Oct-13

13-Oct-13

3
1

14-Oct-13
17-Oct-13

16-Oct-13
17-Oct-13

xiii
xiv
xv
xvi
xvii
xviii
xix

xxiv
xxv
I

Final box up of bearing housings


TG ready for barring gear
AUXILIARIES & ERECTION OF PIPING
Preparation of auxiliary foundations

18-Aug-13

20-Aug-13

ii

Erection of oil skid & Over head , Low level oil


tank

22-Aug-13

26-Aug-13

iii

Erection of generator air coolers

16-Sep-13

18-Sep-13

iv

Erection of gland coolers & surge tank

24-Aug-13

26-Aug-13

Fabrication & Erection of oil piping

20

26-Aug-13

14-Sep-13

xi

Fabrication & Erection of gland steam piping

13

2-Sep-13

14-Sep-13

xii

Air cleaning of oil piping and oil tank cleaning

15-Sep-13

16-Sep-13

xiii

Fill up fresh oil and oil fleshing

17-Sep-13

23-Sep-13

xiv

Removing of oil and refilling of oil through


centrifuge

24-Sep-13

26-Sep-13

xv

Starting of oil pumps and Checking of oil pressure

16-Oct-13

16-Oct-13

xvi

Oil system ready for bearing gear

17-Oct-13

17-Oct-13

Commissioning, testing and synchronization

17-Oct-13

17-Oct-13

Note: 1. The above schedule is tentative only and may be changed to suit site conditions and project excution.
2. The above schedule is subject to readiness of all civil fronts like Roof and side walls.
3. EOT Crane and Control room shall be ready

TURBINE ERECTION SCHEDULE GPP-4

S.No.
Description
Turbine Erection and Commissioning(Duration)

Days
60

Start
6-Sep-13

Complete
5-Nov-13

1
2

Turbine at site
Completion of Turbine Deck Civil work

0
0

6-Sep-13
30-Jul-13

6-Sep-13
30-Jul-13

3
4
5

Preparation of Foundation
Leveling of packers and grouting
Lifting of base plate and keeping on foundation

2
6
2

25-Aug-13
6-Sep-13
12-Sep-13

27-Aug-13
12-Sep-13
14-Sep-13

Leveling of bottom casing on the foundation and piano wire


centering

14-Sep-13

20-Sep-13

Rotor positioning w/o internals and leveling and centering and


bearing bedding check

20-Sep-13

26-Sep-13

8
9

Placement of top casing and Parting plane checking


Placement of all internals, check level

2
5

26-Sep-13
26-Sep-13

28-Sep-13
1-Oct-13

10

Placement of rotor & check axial, radial check of Blades & glands
also bearing clearance

1-Oct-13

8-Oct-13

11

Placement of top internals for oil check lead wire clearances

16

8-Oct-13

24-Oct-13

12
13

Generator at site
Completion of Generator Deck Civil work

0
0

6-Sep-13
30-Jul-13

6-Sep-13
30-Jul-13

14
15

Preparation of Foundation
Leveling of packers

2
3

25-Aug-13
9-Sep-13

27-Aug-13
12-Sep-13

16
17

Lifting of generator stator with Base Plate and leveling on the


foundation
HT of Air coolers

5
6

12-Sep-13
17-Sep-13

17-Sep-13
23-Sep-13

18

Generator rotor coupling face blue matching

23-Sep-13

25-Sep-13

19
20
21

Bedding of generator rotor bearings and insertion of rotor


COMBINED OPERATION ON TG SET
Alignment of turbine and generator rotors

24-Sep-13

2-Oct-13

23-Sep-13

2-Oct-13

22

Bearing cover interferences

2-Oct-13

8-Oct-13

23

Generator air gap & exciter air gap and protocols

2-Oct-13

8-Oct-13

24
25

Placement of turbine top internals and box up of turbine


Grouting of TG set

7
2

8-Oct-13
15-Oct-13

15-Oct-13
17-Oct-13

26

Checking of final alignment and fixing at coupling bolts

17-Oct-13

19-Oct-13

27
28

final box up of bearings with all thermo elements and RTD's


AUXILIARIES

19-Oct-13

23-Oct-13

29
30
31

Foundation Preparation
Erection of oil coolers, Oil Pumps, etc
Erection of oil console

8
6
4

6-Aug-13
6-Sep-13
6-Sep-13

14-Aug-13
12-Sep-13
10-Sep-13

32
33

FABRICATION & ERECTION PIPING


Fabrication & Erection of oil piping

15

10-Sep-13

25-Sep-13

34
35

ELECTRICAL
Placement of all Panels in the control room

22-Sep-13

30-Sep-13

36
37

Placement of all local panels & JB's


Cable laying and termination

8
7

30-Sep-13
8-Oct-13

8-Oct-13
15-Oct-13

38
39
40

Electrical loop test


Function checks
LUBE OIL FLUSHING

4
4
5

15-Oct-13
19-Oct-13
23-Oct-13

19-Oct-13
23-Oct-13
28-Oct-13

41
42

FILLUP FRESH OIL AND FLUSHING


GOVERNING CHECKUP

1
2

29-Oct-13
30-Oct-13

30-Oct-13
1-Nov-13

43
44

INSTRUMENTATION
Field mounted gauges and transmitters and LGB

18-Oct-13

21-Oct-13

45
46
47

Cable laying termination and loop checks


Calibration of pickup etc.
Protection & Interlock etc. check

4
4
10

21-Oct-13
25-Oct-13
18-Oct-13

25-Oct-13
29-Oct-13
28-Oct-13

48
49

PUTTING ON BARRING GEAR


MECHANICAL RUN TEST

2
2

30-Oct-13
1-Nov-13

1-Nov-13
3-Nov-13

50

SYNCHRONIZATION & LOADING

3-Nov-13

5-Nov-13

SL.NO
1
2
3
4
5

DESCRIPTION
AQC-X Boiler
ERECTION OF LOWER STRUCTURE ASSEMBLY
ERECTION OF STAIRS AND PLATFORMS
GROUND ASSEMBLY OF ASH SUPER HEATERS
ERECTION OF TOP STRUCTURE ASSEMBLY
ERECTION OF LP STEAM DRUM WITH INTERNALS

AQC-10 Boiler Erection Schedule


DURATION
153
30
60
20
2
1

ERECTION HP HEAT WATER SEGMENT ASSEMBLY WITH HANGING


ARRANGEMENT

ERECTION HP ECONOMISER ASSEMBLY WITH HANGING ARRANGEMENT

ERECTION LP EVAPORATOR-1 ASSEMBLY WITH HANGING ARRANGEMENT

ERECTION LP EVAPORATOR-2 ASSEMBLY WITH HANGING ARRANGEMENT

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31

ERECTION OF LP BOILER DOWN COMERS


ERECTION OF LP BOILER RISERS
ERECTION OF ALL PRESSURE PARTS SUPPORTS
COMPLETEION OF LP BOILER HP WELDING
COMPLETION OF RADIOGRAPHY
LOCAL HYDRO TEST
ERECTION OF SUPER HEATER ASSEMBLY
ERECTION HP EMPTY ZONE CASING BOX & ALIGNMENT
ERECTION HP EVAPORATOR-1 ASSEMBLY
ERECTION HP EVAPORATOR-2 ASSEMBLY
ERECTION OF HP STEAM DRUM WITH INTERNALS
ERECTION OF HP BOILER DOWN COMERS
ERECTION OF HP BOILER RISERS
ERECTION OF INTEGERAL LINKS
ERECTION OF ECO I/L & O/L LINK
ERECTION OF HP BOILER SUPER HEATER I/L AND O/L LINKS
ERECTION OF ALL PRESSURE PARTS SUPPORTS
COMPLETEION OF HP BOILER HP WELDING
COMPLETION OF RADIOGRAPHY
ALL VENT & DRAIN VALVES FIXING
ALL VALVES FIXING IN LP & HP BOILER
LOCAL HYDRO TEST

10
10
7
25
25
3
7
7
3
3
3
10
10
7
5
5
2
25
30
5
5
3

32

AQC BOILER INLET GAS DUCTING WITH DAMPERS & BELLOWS ERECTION

50

33

AQC BOILER OUTLET GAS DUCTING WITH DAMPERS & BELLOWS ERECTION

10

34
35
36
37
38
39
40

AQC BOILER BYPASS DAMPER


ERECTION OF ALL DUCTING SUPPORTING STRUCTURE
ERECTION OF ASH HOPPER
ASH CONVEYING SYSTEM
ERECTION OF HP/LP DOSING SYSTEM
ERECTION OF STEAM SAMPLING SYSTEM
ERECTION OF HP/LP STEAM HEADERS

10
15
40
25
5
5
2

SL.NO
41
42
43
44
45

DESCRIPTION
ERECTION OF SILENCERS WITH PIPINGS
ERECTION OF BLOW DOWN TANK WITH ACCESSARIES
REFRACTORY WORK
ALKALI BOILOUT AND RESTORATION
STEAM BLOWING

DURATION
7
5
30
7
10

AQC-10 Boiler Erection Schedule


START
18-Feb-14
18-Feb-14
10-Mar-14
25-Mar-14
20-Apr-14
28-Mar-14

FINISH
21-Jul-14
20-Mar-14
9-May-14
14-Apr-14
22-Apr-14
29-Mar-14

24-Mar-14

25-Mar-14

25-Mar-14

26-Mar-14

26-Mar-14

27-Mar-14

27-Mar-14

28-Mar-14

1-Apr-14
1-Apr-14
22-May-14
28-Mar-14
2-Apr-14
27-Apr-14
15-Apr-14
19-Apr-14
26-Apr-14
29-Apr-14
2-May-14
5-May-14
5-May-14
5-May-14
12-May-14
17-May-14
17-May-14
22-May-14
22-May-14
21-Jun-14
21-Jun-14
26-Jun-14

11-Apr-14
11-Apr-14
29-May-14
22-Apr-14
27-Apr-14
30-Apr-14
22-Apr-14
26-Apr-14
29-Apr-14
2-May-14
5-May-14
15-May-14
15-May-14
12-May-14
17-May-14
22-May-14
19-May-14
16-Jun-14
21-Jun-14
26-Jun-14
26-Jun-14
29-Jun-14

1-Apr-14

21-May-14

21-May-14

31-May-14

31-May-14
31-May-14
26-Feb-14
7-Apr-14
26-Jun-14
26-Jun-14
17-May-14

10-Jun-14
15-Jun-14
7-Apr-14
2-May-14
1-Jul-14
1-Jul-14
19-May-14

START
19-May-14
26-May-14
31-May-14
1-Jul-14
9-Jul-14

FINISH
26-May-14
31-May-14
30-Jun-14
8-Jul-14
19-Jul-14

AQC-9 Boiler Erection Schedule


Target Schedule
SL.NO

DESCRIPTION

DURATION

START

FINISH

AQC-IX Boiler

94

23-Aug-13

25-Nov-13

GROUND ASSEMBLY OF SUPPORTING STRUCTURE

15

16-May-13

31-May-13

ERECTION OF LOWER STRUCTURE ASSEMBLY

15

3-Jun-13

18-Jun-13

ERECTION HP SUPERHEATER ASSEMBLY WITH


HANGING ARRANGEMENT

23-Aug-13

28-Aug-13

ERECTION OF TOP STRUCTURE ASSEMBLY

28-Aug-13

2-Sep-13

ERECTION OF LP STEAM DRUM WITH INTERNALS

2-Sep-13

7-Sep-13

ERECTION HP HEAT WATER SEGMENT ASSEMBLY


WITH HANGING ARRANGEMENT

7-Sep-13

12-Sep-13

ERECTION HP ECONOMISER ASSEMBLY WITH


HANGING ARRANGEMENT

12-Sep-13

17-Sep-13

ERECTION HP EVAPORATOR-1 ASSEMBLY WITH


HANGING ARRANGEMENT

17-Sep-13

22-Sep-13

10

ERECTION LP EVAPORATOR-2 ASSEMBLY WITH


HANGING ARRANGEMENT

22-Sep-13

27-Sep-13

ERECTION OF STAIRS AND PLATFORMS

30

27-Sep-13

27-Oct-13

11

ERECTION OF HP BOILER DOWN COMERS

13

27-Sep-13

10-Oct-13

12

ERECTION OF HP BOILER RISERS

13

27-Sep-13

10-Oct-13

13

ERECTION OF HP BOILER SUPER HEATER I/L AND O/L


LINKS

15

27-Sep-13

12-Oct-13

14

ERECTION OF ALL PRESSURE PARTS SUPPORTS

10

13-Oct-13

23-Oct-13

15

COMPLETEION OF HP BOILER HP WELDING

20

27-Sep-13

17-Oct-13

16
17

COMPLETION OF RADIOGRAPHY & SR


LOCAL HYDRO TEST

7
3

17-Oct-13
24-Oct-13

24-Oct-13
27-Oct-13

19

ERECTION LP ECONOMISER ASSEMBLY WITH


HANGING ARRANGEMENT

23-Aug-13

28-Aug-13

20

ERECTION LP EVAPORATOR-1 ASSEMBLY WITH


HANGING ARRANGEMENT

28-Aug-13

2-Sep-13

21

ERECTION LP EVAPORATOR-2 ASSEMBLY WITH


HANGING ARRANGEMENT

2-Sep-13

7-Sep-13

22

ERECTION OF SUPER HEATER ASSEMBLY WITH


HANGING ARRANGEMENT

7-Sep-13

12-Sep-13

23

ERECTION OF LP STEAM DRUM WITH INTERNALS

12-Sep-13

17-Sep-13

24

ERECTION OF LP BOILER DOWN COMERS

13

27-Sep-13

10-Oct-13

25
26

ERECTION OF LP BOILER RISERS


ERECTION OF INTEGERAL LINKS

13
15

27-Sep-13
27-Sep-13

10-Oct-13
12-Oct-13

SL.NO

DESCRIPTION

DURATION

START

FINISH

12-Oct-13

14-Oct-13

27

ERECTION OF ECO I/L & O/L LINK

28

ERECTION OF ALL PRESSURE PARTS SUPPORTS

10

14-Oct-13

24-Oct-13

29

COMPLETEION OF LP BOILER HP WELDING

15

10-Oct-13

25-Oct-13

30
31
32
33

COMPLETION OF RADIOGRAPHY
ALL VENT & DRAIN VALVES FIXING
ALL VALVES FIXING IN LP & HP BOILER
LOCAL HYDRO TEST

16
7
5
3

10-Oct-13
26-Oct-13
26-Oct-13
31-Oct-13

26-Oct-13
2-Nov-13
31-Oct-13
3-Nov-13

34

AQC BOILER INLET GAS DUCTING WITH DAMPERS &


BELLOWS ERECTION

15

20-Oct-13

4-Nov-13

35

AQC BOILER OUTLET GAS DUCTING WITH DAMPERS


& BELLOWS ERECTION

4-Nov-13

9-Nov-13

36

AQC BOILER BYPASS DAMPER WITH BELLOW

4-Nov-13

11-Nov-13

37

ERECTION OF ALL DUCTING SUPPORTING


STRUCTURE

15

11-Nov-13

26-Nov-13

39
41

ERECTION OF ASH HOPPER


ASH CONVEYING SYSTEM

15
10

16-Oct-13
31-Oct-13

31-Oct-13
10-Nov-13

42
43
44
45

ERECTION
ERECTION
ERECTION
ERECTION

10
5
8
10

31-Oct-13
10-Nov-13
25-Oct-13
25-Oct-13

10-Nov-13
15-Nov-13
2-Nov-13
4-Nov-13

46

ERECTION OF BLOW DOWN TANK WITH


ACCESSARIES

25-Oct-13

1-Nov-13

48

REFRACTORY WORK

13

4-Nov-13

17-Nov-13

51
52

ALKALI BOILOUT
STEAM BLOWING

2
3

17-Nov-13
19-Nov-13

19-Nov-13
22-Nov-13

53

SAFETY VALVE FLOATING and Synchronization

22-Nov-13

25-Nov-13

OF
OF
OF
OF

HP/LP DOSING SYSTEM


STEAM SAMPLING SYSTEM
HP/LP STEAM HEADERS
SILENCERS WITH PIPINGS

Remark

Complete
Complete
Complete
Complete
Complete

Complete

Complete

Complete

Complete
U/P
Fab u/p.
Fab u/p.
Fab u/p.

Complete

Complete

Complete

Complete
Complete
fab u/p
Complete

Remark

complete
material awaited
Material awaited
Material awaited
Complete
Material awaited
Material awaited
Material awaited

GREEN POWER PROJECT-4 SUMMARY SCHEDULE


Unit-IX

S.No.
Activity

Unit-X

Duration
(Days)

Start Date

Finish date

Duration
(Days)

Start Date

Remark

Finish date

Civil (RCC)+ Finishing Job

TG Building

22/Jan/13

10/Feb/14

RCC completed date 19-Nov-13. Finishing work


u/p. Plastering work u/p. Area clearance required for
misc jobs.

ACC

25/Jan/13

30/Jan/14

RCC completed date 19-Jul-13. Finishing work u/p.


6/14 nos soiling & PCC completed. Wall puttey work u/p.

PH Boiler

7/Dec/12

15/Jan/14

203

1/Jul/13

20/Jan/14

U-IX RCC completed date 4-May-13. U-IX MCC,


conveyor padestal & flooring balance. U-X slab
shuttering work u/p, revised drawings received from CCE
on 24.12.2013.

AQCBoiler

25/Mar/13

5/Jan/14

83

1/Nov/13

23/Jan/14

U-IX RCC completed date 25-May-13. U-IX Flooring


& lift foundation. U-X 90% complete upto plinth beam lvl.

Unit -10 pipe rack support(42 nos)

65

12/Dec/13

15/Feb/14

6 nos column upto 0.00mtr lvl completed

WTP Building & equipment foundation

Mechanical

PH Boiler

86

1/Jan/14

28/Mar/14

180

25-Sep-13

24-Mar-14

Excavation U/p

139

Casing and hammering system & riser downcomer


erection u/p.

17-May-14

AQC Boiler Refractory material delivery delayed and still


pending. Cement plant shutdown required for AQC
boiler hookup. Outlet duct erection and hopper Ca-Si
application u/p.

AQC Boiler

157

23-Aug-13

27-Jan-14

ACC (First Street)

179

7-Jul-13

2-Jan-14

Air test completed. Turbine exhaust duct


connection u/p.

ACC (Second Street)

207

7-Jul-13

30-Jan-14

Manifold duct welding, end cap, riser duct erection and


welding, fans, internal walkway, fin cleaning system etc
balance.

Turbine on barring

101

18-Sep-13

28-Dec-13

TG Synchronization

2-Jan-14

5-Jan-14

Interconnection Piping (HP & cond piping only)

E&I (Unit-IX AQC Boilers)

Instrumentation interlock check u/p. Fresh oil filup


and flushing u/p.
TG synchronization after ACC-Ist way
commissioning and HP steam blowing target plate
clearance by Dalian. Requires 60 hours for line
hookup with turbine.
HP piping commissioned on 10-Dec-13 and LP piping
commissioned on 15-Dec-13. LP piping restoration
completed. HP piping blowing u/p.

Completed
29-Sep-13

19-Feb-14

15-Jun-14

103

87

27-Jan-14

10-Jan-14

TG and ACC E&I under completion