Professional Documents
Culture Documents
Prepared by:
Surname and Initials: Van Rooyen, U. A.
Employee Code: POL00154
Date: 12.02.2014
Prepared for:
Mr N. v. d. Mescht
Stefanutti Stocks, Contracts Director,
(Student Mentor)
Table of Contents:
1. Introduction:...................................................................3
2. Objectives of this study:.....................................................3
3. Test methods used in this study:............................................3
3.1. APPARATUS:........................................................................................3
3.2. METHOD STATEMENT:.............................................................................3
3.3. TASK EXECUTION:.................................................................................4
5. Conclusion:.....................................................................7
6. Recommendations:............................................................7
7. References:.....................................................................7
1. Introduction:
This report has been compiled to explain the techniques used for setting out of the stubs
used in the foundations, which the Lattice tower structures (strain towers) that carry the
overhead power line conductors, are attached to.
The report was requested by Mr N. v. d. Mescht, Stefanutti Stocks Power, Contracts
Director.
The report was requested on the 7th February 2014.
The report was compiled by U. A. Van Rooyen.
6. The positions of pegs will be marked by driving wooden poles painted white on the
upper end, into the ground within 100 mm of the survey peg. The length of the
wooden pegs is variable but must be long enough to be visible above any grass/brush
in the area.
7. Excavation types will have been identified through soil nominations and design
approved. This will identify the type per location and will indicate the survey
requirements for marking out the excavation boundaries.
8. The surveyor will indicate the centre of the line crossing each boundary fence as to
mark the fence where an access gate will be installed. The centre on the fence will be
clearly marked.
Discussion of results:
The stubs settings form a very important role in the lattice tower structure, if it is
misaligned it can cause the tower to be out of the power line alignment or it can cause
difficulties when tower is assembled as bolt patterns are not aligned.
5. Conclusion:
The practical observation done, has helped to further explain, the procedures used when
doing setting out of stubs and how they are done. It is a fairly sophisticated job and
requires skill and a lot of patience. It is also a very team orientated job so it requires very
skilful and experienced team to do successfully.
The stub settings was done using the correct apparatus and following the procedures as
stated in the SSP Safe Work Procedures and the project tower schedule, thus the results
obtained were satisfactory and according to specifications.
6. Recommendations:
When excavations are done, it should be monitored more carefully in order to avoid
over excavation, resulting in difficulty when using the props.
The use of bracing should be used to support excavations in loose or unstable soil
situations.
The use of a laser measuring device should be used to eliminate inaccuracies.
Scaffolding should be used in order to make to getting in and out of excavations easier
and well as for general navigation around the excavations.
7. References:
Information:
1. STEFANUTTI STOCKS, 2013/2014. Sere Wind Farm, Safe Work Procedures. South Africa.
Illustrations:
1. VAN ROOYEN, U. A. 2014. Stub Setting Layout.