You are on page 1of 140

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar Street, Zamboanga City
Project
Location
Scope of Work

:
:
:

PROP. PVC PIPE RACK, DISMOUNTING TYPE


Soft-Ball Field, Pasonanca, Zamboanga City

I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. SUPPLY/FABRICATION OF 270- UNITS OF 200MM X 200MM X 150MM CO
V. SUPPLY/CONSTRUCTION OF 6 - UNITS PVC PIPE RACK
Supply/Construction of 6 - Units 12.60m x 5.00m PVC Pipe Rack
VI. SCAFFOLDING WORKS
VII. TRUSSES WORKS
Supply/Fabrication of 30 - Units of 19mm G.I. Pipe, Sch. 40 Trusses
VIII. ROOFING WORKS
Supply/Installation of 101.00 Sq.m. Roofing Area
IX. CONSTRUCTION OF 88.55 LINEAR METER BARBWIRE FENCE
X. ELECTRICAL WORKS
XI. CONSTRUCTION OF ELECTRICAL POST
Supply/Construction of 15 - Units Electrical Post
XIII. DEMOBILIZATION
Cost of Project

Php

2,308,507.00
BILL OF MATERIALS & COST ESTIMATES

Item Description

Qty.

I. MOBILIZATION

II. HAULING OF MATERIALS


A. Laborers
### - Laborers

B. Equipment Rental/Fuel:
### - Unit - Boom Truck
Diesel Fuel
Direct Cost
OCM
TOTAL COST OF ITEM II
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
A. Materials:
31 pcs. - 2" x 3" x 10' Coco Lumber
15 pcs. - 2" x 3" x 8' Coco Lumber
4" C.W. Nail
Nylon Chord
12mm Clear Hose
B. Labor:
### - Carpenters
Direct Cost
OCM
TOTAL COST OF ITEM III

1
30

155
60
3
2
20

IV. SUPPLY/FABRICATION OF 270- UNITS OF 200MM X 200MM X 150MM CONCRETE BASE BLOCK
A. Materials:
Portland Cement
17

Sand
Gravel
10mm x 6.00m Deformed Reinforcing Steel Bars
Hacksaw Blade
12mm thk x 1.20m x 2.40m Ordinary Plywood
2" C.W. Nail
B. Labor:
### - Mason
### - Welder
### - Carpenters
### - Laborers
Direct Cost
OCM
TOTAL COST OF ITEM IV
V. SUPPLY/CONSTRUCTION OF 6 - UNITS PVC PIPE RACK
A. Materials:
3.9mm thk x 38mm (I.D.) x 6.00m G.I. Pipe, (Sch. 40)
38mm x 38mm M.S. Pipe Clamp/Scaffolding Clamp
B. Labor:
### - Carpenters
### - Laborers
Direct Cost
OCM
TOTAL COST OF ITEM V

1
2
27
2
15
4

2
2
2
2

678
2,223

10
10

VI. SCAFFOLDING WORKS


A. Materials:
100pcs - 2" x 4" x 10' Coco Lumber
60pcs - 2" x 3" x 10' Coco Lumber
60pcs - 2" x 2" x 10' Coco Lumber
4" C.W. Nail
B. Labor:
### - Laborers
### - Carpenters
Direct Cost
OCM
TOTAL COST OF ITEM VI
VII. TRUSSES WORKS
A. Materials:
3.91mm thk x 19mm (I.D.) x 6.00m G.I. Pipe, (Sch. 40)
Hacksaw Blade
6011 Welding Rod
B. Equipment Rental:
### - Unit Welding Machine
B. Labor:
### - Welder
### - Laborers
Direct Cost
OCM
TOTAL COST OF ITEM VI
VIII. ROOFING WORKS
A. Materials:
1.83m x 50.00m Tarpulin
Ga. 14 x 50mm x 75mm x 6.00m C-Purlins
#16 G.I. Tie-wire
B. Labor:
### - Carpenters
### - Laborers
Direct Cost
OCM
TOTAL COST OF ITEM VIII
IX. CONSTRUCTION OF 88.55 LINEAR METER BARBWIRE FENCE
A. Materials:
1. Barbwire Fence
Portland Cement
Sand
Gravel
3.91mm thk x 38mm (I.D.) x 6.00m G.I. Pipe, (Sch. 40)
30.00 Meters Barbwire (Large)
Hacksaw Blade
2. Steel Gate
Portland Cement
Sand
Gravel
5.5mm thk x 100mm x 6.00m G.I. Pipe (Sch. 40)
50mm x 6.00m G.I. Pipe, Sch. 40

667
300
200
18

6
6

93
5
8

4
4

8
26
178

2
2

5
0.15
0.30
14
17
5

7
0.30
0.60
1
4

5mm thk. X 100mm x 6.00m Flat Bar


12mm x 6.00m Plain Round Bar
12mm x 150mm Standard Turn Buckle
#10 x 75mm Mesh x 1.83m Interlink Wire (6m/roll)
10mm x 6.00m Plain Round Bar
16mm x 6.00m Deformed Reinforcing Steel Bars
10mm x 6.00m Deformed Reinforcing Steel Bars
#16 G.I. Tie-wire
12mm thk x 1.20m x 2.40m Ordinary Plywood
6pcs. - 2" x 3" x 10' Coco Lumber
2" C.W. Nail
4" C.W. Nail
6011 Welding Rod
B. Labor:
### - Mason
### - Welder
### - Carpenter
### - Contractual Laborers
C. Equipment Rental:
### - Unit Welding Machine
Direct Cost
OCM
TOTAL COST OF ITEM IX

1
1
2
1
3
5
4
3
1
30
1
1
2

5
5
5
5

X. ELECTRICAL WORKS
A. Materials:
Kiliwatthour Meter (Analog), 230 Volts, Single Phase, Assembly, GE Class 100

50 Amperes Main Circuit Breaker, Single Phase,


220 volts enclosed in Powder Coated Finished Panel Board
with 5 Single Phase Branches of:
3 sets - 20 Amps. Branch
8.0mm THW Stranded Wire
2

1
16

5.5mm2 THW Stranded Wire (perimeter line)

3.5mm THW Stranded Wire

3U Electronic CFL with Diffuser, Daylight, 23W Assembly

31

Ceiling Socket with screw

Duplex Convenience Outlet w/ plate (flush type)

Toggle Switch 2-Gang w/ plate (weather-proof type) and roof cover

25

mm

(3/4") RSC Entrance Cap

25mm (3/4") x 3m RSC Electrical Conduit

25

mm

(3/4") x 90 RSC Electrical Conduit Elbow Long Sweep

25mm (3/4") RSC Locknut

25

(3/4") RSC Male Adaptor

20

(1/2") PVC Flexible Electrical Conduit

25

20mm (1/2") x 3.00m PVC Electrical Conduit

50

mm
mm

20

mm

(1/2") x 90 PVC Electrical Conduit Elbow Long Sweep

20mm(1/2") PVC Electrical Coupling Connectors

10

20mm (1/2") PVC Male Adaptor

62

20mm (1/2") PVC Lock Nut (Zinc Coated)

62

20mm (1/2") nylon cable tie

38

mm

x 12

mm

G.I. Bell Reducer, Sch. 40

5.5mm2 Wire Connector

2 wire w/ spool Secondary rack


2" x 4" x 2" PVC Utility Box ( H.D.)
4" x 4" x 2" PVC Junction Box ( H.D.) w/ Cover

8
2
7
25

#16 G.I. Tie Wire

6" x 6" x 4" Gal. Pull Box

PVC Solvent Cement

1/2" Camridge / Mica Tube

3/4" Polytype Electrical Tape

3/4" Rubber Tape

B. Equipment Rental

### - Unit Power Drill

C. Labor:

### - Electrician
### - Contractual Laborers

5
5

Direct Cost
OCM
TOTAL COST OF ITEM X
XI. CONSTRUCTION OF ELECTRICAL POST
A. Materials:
Portland Cement
Sand
Gravel
10mm x 6.00m Deformed Reinforcing Steel Bars
#16 G.I. Tie-wire
3.91mm thk x 38mm (I.D.) x 6.00m G.I. Pipe (Sch. 40)
B. Labor:
### - Mason
### - Carpenter

21
1
2
35
5
8

3
3

### - Contractual Laborers


Direct Cost
OCM
TOTAL COST OF ITEM XI
XII. PAINTING WORKS
(Note: Painting works includes the Steel Gate, Fence, and Electrical Post)
A. Materials:
Red Lead Metal Primer
QDE Aluminum Silver Paint
Paint Thinner
2" Paint Brush
1" Paint Brush
Steel Brush
B. Labor:
### - Skilled Worker
### - Contractual Laborers
Direct Cost
OCM
TOTAL COST OF ITEM XII
XIII. DEMOBILIZATION

3
6
2
4
4
2

3
3

SUMMARY
I. MOBILIZATION
II. HAULING OF MATERIALS
III. FINAL STAKING/LAY-OUTING/LINE AND GRADE
IV. SUPPLY/FABRICATION OF 270- UNITS OF CONCRETE BASE BLOCK
V. SUPPLY/CONSTRUCTION OF 6 - UNITS PVC PIPE RACK
VI. SCAFFOLDING WORKS
VII. TRUSSES WORKS
VIII. ROOFING WORKS
IX. CONSTRUCTION OF 88.55 LINEAR METER BARBWIRE FENCE
X. ELECTRICAL WORKS
XI. CONSTRUCTION OF ELECTRICAL POST
XII. PAINTING WORKS
XIII. DEMOBILIZATION
TOTAL PROJECT COST

Prepared by:

Reviewed & Checked by:

FELIXBERTO R. CAARE, JR.


Researcher/Analyst A (J.O.)

MARIE CLAIRE C. BONGO


Officer-In-Charge
Planning & Development Section

Approved by:

Certified as to Availability of Funds:

CARLOS L. PEREZ, SR.


Officer-In-Charge
Engineering Department

ROBERTO R. MENDOZA
Officer-In-Charge
Accounting & Treasury Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

ublic of the Philippines


NGA CITY WATER DISTRICT
Street, Zamboanga City

0MM X 200MM X 150MM CONCRETE BASE BLOCK

COST ESTIMATES
Unit
lot

Unit Cost

Sub-Total

Total Cost

10,000.00

10,000.00

10,000.00

317.00

634.00

634.00

day
liters

5,000.00
49.00

5,000.00
1,470.00

bd.ft.
bd.ft.
kgs.
rolls
l.m.

17.00
17.00
65.00
50.00
10.00

2,635.00
1,020.00
195.00
100.00
200.00

366.00

732.00

226.00

3,842.00

day

day

ONCRETE BASE BLOCK


bags

7,104.00
7,738.00
774.00
8,512.00

4,150.00

732.00
4,882.00
488.00
5,370.00

cu.m.
cu.m.
pcs.
pcs.
shts.
kgs.

650.00
650.00
161.00
52.00
550.00
65.00

650.00
1,300.00
4,347.00
104.00
8,250.00
260.00

days
days
days
days

366.00
366.00
366.00
317.00

732.00
732.00
1,464.00
1,268.00

2,075.00
80.00

1,406,850.00
177,840.00

366.00
317.00

14,640.00
6,340.00

pcs.
pcs.

days
days

18,753.00

4,196.00
22,949.00
2,295.00
25,244.00

1,584,690.00

20,980.00
1,605,670.00
160,567.00
1,766,237.00

bd.ft.
bd.ft.
bd.ft.
kgs.

17.00
17.00
17.00
65.00

11,333.00
5,100.00
3,400.00
1,170.00

days
days

317.00
366.00

3,804.00
8,784.00

pcs.
pcs.
kgs.

988.00
52.00
145.00

91,884.00
260.00
1,160.00

93,304.00

days

2,160.00

8,640.00

8,640.00

days
days

366.00
317.00

1,464.00
3,804.00

rolls
pcs.
kgs.

7,750.00
990.00
65.00

62,000.00
25,740.00
11,570.00

days
days

366.00
317.00

2,928.00
1,268.00

bags
cu.m.
cu.m.
pcs.
rolls
pcs.

226.00
650.00
650.00
2,075.00
1,650.00
52.00

1,130.00
98.00
195.00
29,050.00
28,050.00
260.00

bags
cu.m.
cu.m.
pc.
pcs.

226.00
650.00
650.00
4,800.00
2,238.00

1,582.00
195.00
390.00
4,800.00
8,952.00

21,003.00

8,784.00
29,787.00
2,979.00
32,766.00

5,268.00
107,212.00
10,721.00
117,933.00

99,310.00

4,196.00
103,506.00
10,351.00
113,857.00

58,783.00

pc.
pc.
pcs.
roll
pcs.
pcs.
pcs.
kgs.
pc.
bd.ft.
kg.
kg.
kgs.

1,142.00
261.00
51.00
570.00
168.00
381.00
161.00
65.00
550.00
17.00
65.00
65.00
145.00

1,142.00
261.00
102.00
570.00
504.00
1,905.00
644.00
195.00
550.00
510.00
65.00
65.00
290.00

22,722.00

days
days
days
days

366.00
366.00
366.00
317.00

1,830.00
1,830.00
1,830.00
3,170.00

8,660.00

days

2,160.00

4,320.00

4,320.00
90,165.00
9,017.00
99,182.00

assy.

3,210.00

3,210.00

unit

3,360.00

3,360.00

mtrs.

95.00

1,520.00

rolls

95.00

380.00

rolls

4,183.00

16,732.00

sets

656.00

20,336.00

sets

25.00

50.00

set

253.00

253.00

sets

114.00

684.00

pcs.

253.00

506.00

pcs.

253.00

1,012.00

pcs.

18.00

36.00

pcs.

9.00

36.00

pcs.

9.00

18.00

mtrs.

6.00

150.00

pcs.

201.00

10,050.00

pcs.

13.00

78.00

pcs.

6.00

60.00

pcs.

8.00

496.00

pcs.

3.00

186.00

110.00

550.00

packs
pcs.

55.00

440.00

pcs.

171.00

1,368.00

pcs.

255.00

510.00

pcs.

17.00

119.00

pcs.

22.00

550.00

kgs.

65.00

130.00

pcs.

554.00

1,108.00

qrts.

370.00

740.00

pcs.

30.00

180.00

pcs.

25.00

100.00

pcs.

105.00

210.00

61,948.00

day

300.00

300.00

300.00

days

366.00
317.00

1,830.00
3,170.00

bags
cu.m.
cu.m.
cu.m.
kgs.
pcs.

226.00
650.00
650.00
161.00
65.00
2,075.00

4,746.00
650.00
1,300.00
5,635.00
325.00
16,600.00

days
days

366.00
366.00

1,098.00
1,098.00

days

5,000.00
67,248.00
6,725.00
73,973.00

29,256.00

days

317.00

1,902.00

gals.
gals.
gals.
pcs.
pcs.
pcs.

379.00
495.00
325.00
28.00
12.00
16.00

1,137.00
2,970.00
650.00
112.00
48.00
32.00

days
days

366.00
317.00

1,098.00
1,902.00

10,000.00

10,000.00

lot

4,098.00
33,354.00
3,335.00
36,689.00

4,949.00

3,000.00
7,949.00
795.00
8,744.00
10,000.00

SUMMARY
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php

Php

10,000.00
8,512.00
5,370.00
25,244.00
1,766,237.00
32,766.00
117,933.00
113,857.00
99,182.00
73,973.00
36,689.00
8,744.00
10,000.00

2,308,507.00

Submitted by:

MARLI P. ACOSTA-DE FIESTA


Officer-In-Charge
Planning & Design Division
Recommending Approval for
Project Implementation:

ALEJO S. ROJAS, JR.


Assistant General Manager for Operations

V. 40GPD HYPOCHLORINATOR WITH 100 LTRS SOLUTION TANK & COMPLETE ACCESSORIES:

"CHEM-TECH" heavy Duty Hypochlorinator with 100 liters Solution Tank


with stirrer, series 200, designed to deliver 40 GPD(max) vs. 125 psig,
mechanical diaphragm type and oil bathed gear assembly, driven by
electric motor, 230V, single phase, 60 Hz. With complete standard
suction & discharge accessories:
- 4 ft. Suction Tubing, clear PVC, 7/16"OD
- 8 ft. Discharge Tubing, P.E., 1/2"OD
- 1 set Back check Valve & Injection Fittings
- 1 set Foot Valve with strainer
- 1 pc. Bleed Valve

Lumpsum Amount
Overhead Expenses
Price & Physical C
Miscellaneous
Contractor's Profit
Value Added Tax

H 100 LTRS SOLUTION TANK & COMPLETE ACCESSORIES:

Duty Hypochlorinator with 100 liters Solution Tank


designed to deliver 40 GPD(max) vs. 125 psig,
type and oil bathed gear assembly, driven by
ngle phase, 60 Hz. With complete standard
cessories:
ear PVC, 7/16"OD
, P.E., 1/2"OD
e & Injection Fittings

### unit

90,000.00

90,000.00

90,000.00
3,600.00
4,500.00
900.00
9,000.00
12,960.00
120,960.00

Republic
ZAMBOANGA
Pilar St.,

Project
:
Location
:
Scope of Work :

Project Cost :

PROPOSED ZSCMST SUMP TANK ELECTRO-MECHANICAL


Rio Hondo, Zamboanga City

1. Package Supply, Installation, Testing & Commissioning of 15KW (20Hp) S


Controls & accessories, Discharge pipings, Appurtenances and Fittings, to
2. Supply, Installation, Testing & Commissioning of 100mm Electro-magnet
complete with accessories.
3. Supply, Installation, Testing & Commissioning of 38 KVA Rated Standby P
4. Supply, Installation, Testing & Commissioning of Automatic Transfer Switch
5. Supply Installation Testing & Commissioning of 40 GPD Hypochlorinator w

3,341,749.00

Materials Breakd

I. PACKAGE SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 15 KW (20HP) SU


MOTOR CONTROL, RISER COLUMNS, DISCHARGE PIPINGS, APPURTENANCES, FITT
COMPLETE ACCESSORIES:
A. SUBMERSIBLE PUMP & RISER COLUMNS/ACCESSORIES:

- Submersible Pump with capacity of 200 GPM (45 m3/hr) against a TDH of 82
Pump outlet diameter of 4 inches diameter, Stainless Steel Body constru
- 1 pc. of 100 mm(4") x 3.5 meters B.I. Sch. 40 riser column, flange-type, a
- B.I. Flanges, 16mm thick x 112mm ID x 212mm OD with 6 (Six) of 17mm
both ends of 100 mm B.I. riser column, to be bolted with 16mm SS bo
(Note: See attached Construction Detail of Flange Shop Drawing)
- 1 pc. 100mm(4") x 0.30m sch.40 Stainless steel Adaptor with one end we
Flange & threaded at the other end 4" that matches with the Pump outle
- 1 pc. 100mm (4") x 1.00m. B.I. pipe sch. 40 heavily welded with brace to t
and 100mm (4") x 90 B.I. Long Sweep Elbow which is heavily welded @
thru the center of the steel sanitary seal and with one (1) 64mm hole pro
all in anti-rust & epoxy-enamel coated (Blue). (Refer construction drawing
- 8 pcs. 19mm x 350mm. G.I. bolts with nuts and washers.
- 1 pc. 250mm (10") x 90 PVC elbow with flange coupling for water inlet.
(Note: Pump Setting @ 5.73 meters below sump top level)
B. SUBMERSIBLE ELECTRIC MOTOR & CONTROLS:

15 KW (20Hp), 3-phase, 230VAC, 60 Hz, 3500 RPM, Variable speed Drive S


Circuit Breaker Industrial type (Heavy duty) 230 V, 150 A, 3
Automatic Combination Motor Soft Starter with By-pass contactor and overlo
with desired motor protection such as:
Electronic over/under voltage Protection Relay, Motor thermal state with Pha
Electronic over/underload & Out-Of-Sequence Protection Relay, Lock Rotor M
Additional motor control for Earth Leakage, short circuit, external protection r
the control for the water hammer and cavitation, Liquid level controller type L
start and stop push buttons and pilot lights, Ammeter (0-300A), Voltmeter (0with Current Transformer (300:5 x'former ratio) which matches the ammeter,
circuit breakers & contactor all in NEMA 3R Steel enclosure. 30 meters (38m
spliced to the motor leads using standard resin type 3M brand (82-A2 Kit No.
splicing kit, with 2 rolls each of # 23 & #33 tapes.
(Note: Splicing to be done at project site)
Submerssible pump & Motor
Cables & Accessories
Motor controls
Riser columns/Accessories
Labor
Lumpsum Amount

Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

C. SUPPLY & INSTALLATION OF DISCHARGE PIPINGS, APPURTENANCES & FITTINGS:

100mm C.I. Body Check Valve w/ counter weight (PN16), F/F


with two (2) mating flanges and rubber gaskets (Imported brand)
100mm C.I. Body Gate Valve (PN16), NRS, F/F with two (2)
mating flanges and rubber gaskets (Imported brand)
16mm thick x 112mm ID x 212mm OD, 19mm 8 (Eight) Holes Steel Ring Flange
Php 35.00 100mm Std. Sleeve Type Flexible Coupling Spl.
100mm Std. Sleeve Type Flexible Coupling (for B.I. pipe) w/ harness
16mm x 50mm full threaded Stainless Bolt & Nut with washer

100mm x 6 mtrs. B.I. Pipe, sch.40 with anti-rust & epoxy-enamel coated "blue"
100mm x 100mm B.I Tee, sch.40, F/F (Fabricated w/ anti-rust & epoxy-enamel coated)
100mm x 6 mtrs. G.I. Pipe, sch.40 with anti-rust & epoxy-enamel coated "blue"
100mm x 150mm PVC Increaser
(Note: Amount of B.I. Tee is purely the cost of welding works only, and pipe
materials for fabrication to get portion from supply of B.I. pipes)
100mm x 90 B.I. Elbow, sch.40 , F/F
25 mm Air Release - Air Vacuum Assy. w/ fittings (PN16)
Provision for Chlorinator Injection Fittings:
2" G.I. Coupling, sch. 40
2" x 6" G.I. Nipple, sch. 40
2" G.I. Cap
3/4" G.I. Coupling, sch.40
3/4" x 1/2" G.I. Bushing
1/2" G.I. Plug
Pressure Gauge Assembly:
1/2" G.I. Tee, sch.40
1/2" G.I. Coupling, sch.40
1/2" x 4" G.I. Nipple, sch. 40
1/2" x 1/4" G.I. Bushing
1/4" G.I. Plug
1/2" Brass Ball Valve
2-1/2" Oil-filled Pressure Gauge (0-150 psi)
Labor: Cutting & Welding works of B.I. Discharge Pipes, installation of Appurtenances,
preparation of Pressure Gauge assy. and provision for Chlorinator Injection Fittings.

Php

2.00 Lumpsum Amount

Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

II. PACKAGE SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF 100mm ELECT


WITH WALL-MOUNTED TYPE SIGNAL CONVERTER AND FULLY INTEGRATED GSM D

WITH THE SENSOR EM FLOWMETER, ALL UNITS WITH COMPLETE ACCESSORIES.

A. Supply, Installation, Testing & Commissioning of one (1) unit 100mm ElectroMagnetic Flowmeter, Flange-type, with two (2) mating flanges and with
wall-mounted type signal converter complete with accessories.
B. Supply & installation of Integrated GSM Data Logger 2 flow MK3 (flow & pressure)
compatible with the sensor EM Flowmeter with a recording
interval programmable between 1 second & 1 hour,
900 MHz with remote downloading powered by lithium battery pack dischargeable
with a minimum life span of 5 years. Housing fully water proofed (IP68).
Data can be accessed remotely using a standard GSM mobile telephone thru simple
text message to the host computer provided with a windows-based software (one modem
The unit includes the following accessories:
Flow input cable (30 meters), Communication cable from logger to Personal
computer (5 meters), Windows-based configuration software for PC's,
Two-channel flow splitter cable (30 meters), Helicoil hose fitting for pressure
recording, 30 meters hose for pressure line with fittings (Quick fit connection).
(Logger Lumpsum Amount includes Orientation & Training of personnels)
LABOR

Lumpsum Amount
Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

III. SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF ATLAS COPCO 38 KVA RAT
TRAILER-MOUNTED, CLOSED-TYPE, GENERATOR SET, QAS 35KD-FlX WITH GENSET
A.

GENSET TECHNICAL SPECIFICATIONS:

A) Model
Voltage Configuration
Prime Rated Power
Standby Power

QAS 38KD-FIX
220 V-3-60 Hz
34.5KVA
38KVA

Frequency
60 Hz.
Speed
1800 RPM
Rated Current @ 220 V/60 Hz
90.5 A
Fuel Tank Capacity
102 L
Fuel Anatomy
12 h
Fuel Consumption @ Full Load
6.9 l/h
Sound Pressure Level @7m, 75% Load 70 db(A)
Performance Class acc.ISO 8528-3: 199 G2
Sinlge Load Capability (O-PRP)
100%
Voltage Regulation Accuracy
1%
Seed Regulation Accuracy
0.25%

B) Engine:
Model
Standards
Rated Output
Cooling Systems
Cylinders
Speed Governor
Combustion System
Aspiration
Starting System

Kubota
V3300DI
ISO 3046; ISO 8528-2
30.7 KW
Water Cooled
Php 4.00
Electronic
Direct Injection
Natural
Electric, 12Vdc

C) Alternator:
Model
Standards
Degree of Protection
Insulation Class
Rated Output
No. of wires

Leroy Somer
LSA 42.2 L9
IEC 34-1; ISO 8528-3
IP 23
Class H with marine impregnation
38 KVA
###

Standard Internal Combustion Engine using Diesel Fuel with fuel filter, wate
With Emergency Engine Shutdown (protects against too high cooling water
1. Fuel pre-filter with water separator protects against solid and li
2. Dry-type air filter including maintenance indicator.
3. Residencial type silencer that conforms to the manufacturer's r
D) Steel Canopy:

Weatherproofed Factory Original Enclosure. Rigid in construction that withstand


With noise reducing foam plastic liners that allows operation in noise-restricted
Canopy openings with wide easy access to all compartments.
E) Base Frame:
Compact Trailer-Mounted Power Pact.
Easy to install and to transport by means of towing.
F) Accessories:
Monitoring Device
3 x AC Amphere Meter, AC Voltmeter, VM Selector Sw
Engine Coolant Temp. Gauge, Engine Oil Press. & Fu
Control Device
Mode Selector Switch for ON/OFF (Remote), Automa
High Coolant Temp., Low Lube Oil Pressure, Overspe
Engine Controls & Lamps Fuse, Alternator Charging, AC Shutdown, Engine Coo
Temp. Fault Indicator, Engine Oil Pressure Fault Indic
Main Circuit Breaker, Emergency Stop Button.
Separate Hand Pump
Manually refills genset fuel tank from outside fuel con

Note:
1. The unit & its accessories should be brand new and supplied with mannuals and standa
2. The Supplier should provide Factory Acceptance Test Certificate and Training of staff on
& maintenance of the unit.
3. The Supplier should make available the electrical wires, accessories and all other mate
necessary for the Testing & Commissioning of the generator set.
4. The Supplier should provide the Electrical plans & Diagrams of the Genset Electrical Sy
5. The Supplier should provide enough spare Fuel Filters, Pre-Fuel Filters, Air Filters & En
for the maintenance during the break-in period..

LUMPSUM COST
Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

IV. SUPPLY, INSTALLATION, TESTING & COMMISSIONING ONE (1) UNIT AUTOMATIC TRANSFER

Automatic Transfer Switch 460 VAC, 3-Phase, 60 Hz.


Complete with the following:
2 units - Magnetic Contactor (Heavy duty) 250 Amps max. rating

460 vac coil voltage, industrial type; Complete with Electrical


Interlock; Pilot Lights; Push Buttons; Selector Switches; Timer;
Voltmeter; Protective Relays (Voltage Monitor for Normal & Genset Power, Out of S
& Thermal Overload Relay (120A-180A range) ; Intelligent Circuit with NEMA-1 Met

LUMPSUM COST
Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

C. SUPPLY OF MATERIALS, LABOR & CONSTRUCTION OF GENSET SHED:

Supply & Construction of shed framing, polycarbonate sheets


a. Materials:
1.Roof Framing:
8mmThk. x 1.22m x 4.87m Polycarbonate Sheet
4mm x 50mm Tek Screw (Full Thread Type)
Silicon Sealant
50mm x 6.00m G.I. Pipe, Sch. 40
38mm x 6.00m G.I. Pipe, Sch. 40
20mm x 6.00m G.I. Pipe, Sch. 40
12mm x 6.00m G.I. Pipe, Sch. 40
3mmThk. x 38mm x 38mm x 6.00m MS Angle Bar Purlins
6mmThk. x 38mm MS Flat Bar
16mm x 200mm MS Bolt w/ Nut & Washer
10mmThk. x 150mm x 150mm (w/ 4 bolt holes) MS Sole Steel Plate
6011 Welding Rod
Welding Machine Rental

2.Column & Footings:


Portland Cement
Sand
Gravel (G1)
16mm x 6.00m Deform Rein. Steel Bar
10mm x 6.00m Deform Rein. Steel Bar
#16 G.I. Tie Wire
b. Labor:

Supply & Construction of Genset Base Foundation including excavation & steel w
a. Materials:
Portland cement
Sand
Gravel (G1)
12mm x 6.00m Deform Rein. Steel Bars
#16 G.I. Tie Wire
16mm x 480mm Anchor Bolt w/ Nut & Washer
12mmThk. x 1.20m x 2.40m Ordinary Plywood
20 pcs. - 50mm x 50mm x 3.00m Coco Lumber
4" C.W. Nail
2 - 1/2" C.W. Nail
2" C.W. Nail
b. Labor:

Lumpsum Amount
Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

V. 40GPD HYPOCHLORINATOR WITH 100 LTRS SOLUTION TANK & COMPLETE ACCESSORIES:

"CHEM-TECH" heavy Duty Hypochlorinator with 100 liters Solution Tank


with stirrer, series 200, designed to deliver 40 GPD(max) vs. 125 psig,
mechanical diaphragm type and oil bathed gear assembly, driven by
electric motor, 230V, single phase, 60 Hz. With complete standard
suction & discharge accessories:
- 4 ft. Suction Tubing, clear PVC, 7/16"OD
- 8 ft. Discharge Tubing, P.E., 1/2"OD

- 1 set Back check Valve & Injection Fittings


- 1 set Foot Valve with strainer
- 1 pc. Bleed Valve

Lumpsum Amount
Overhead Expenses
Price & Physical Contingencies
Miscellaneous
Contractor's Profit
Value Added Tax

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City

ANK ELECTRO-MECHANICAL EQUIPMENT

g & Commissioning of 15KW (20Hp) Submersible pump/motor, Riser Columns, Motor


pipings, Appurtenances and Fittings, to include the supply & construction of pipe supports.
missioning of 100mm Electro-magnetic Flowmeter & GSM Data Logger

missioning of 38 KVA Rated Standby Power, Trailer-Mounted, Closed Type Generator Set. w/ genset Shed &
missioning of Automatic Transfer Switch (ATS).
ssioning of 40 GPD Hypochlorinator w/ 100 Ltrs. Solution tank & Complete Accessories

Materials Breakdown & Cost Estimates

COMMISSIONING OF 15 KW (20HP) SUBMERSIBLE PUMP/MOTOR,


RGE PIPINGS, APPURTENANCES, FITTINGS AND WITH

CESSORIES:

00 GPM (45 m3/hr) against a TDH of 82m., 6-stages, within 75% Efficiency,
iameter, Stainless Steel Body construction or its equivalent;
I. Sch. 40 riser column, flange-type, anti-rust & epoxy-enamel coated (blue);
D x 212mm OD with 6 (Six) of 17mm holes per flange welded @
umn, to be bolted with 16mm SS bolts complete with 1/4" thick rubber gasket;
etail of Flange Shop Drawing)
ainless steel Adaptor with one end welded with19mm x 112mm ID x 212mm OD B.I.
4" that matches with the Pump outlet diameter.
sch. 40 heavily welded with brace to the 25mm thick x 400mm x 400mm steel sanitary seal
weep Elbow which is heavily welded @ top end of B.I. column pipe which passes
seal and with one (1) 64mm hole provision for motor cable,
ed (Blue). (Refer construction drawing of 25mm thick x 400mm x 400mm steel sanitary seal)
ith nuts and washers.
w with flange coupling for water inlet.
elow sump top level)

Hz, 3500 RPM, Variable speed Drive Submerssible Motor complete with the following:
duty) 230 V, 150 A, 3
rter with By-pass contactor and overload relay (42A-80A)

n Relay, Motor thermal state with Phase Failure & Unbalance Protections,
quence Protection Relay, Lock Rotor Motor Protection, Surge Arrester,
age, short circuit, external protection relay for current overload including
avitation, Liquid level controller type LH/RH with electrodes, Electronic Power-on/Delay timer,
ghts, Ammeter (0-300A), Voltmeter (0-500V), H-O-A Selector Switch,
er ratio) which matches the ammeter, Lightning Arrester, Desired molded case
A 3R Steel enclosure. 30 meters (38mm) # 1/3 double jacketed submersible cable
ard resin type 3M brand (82-A2 Kit No.)
#33 tapes.

INGS, APPURTENANCES & FITTINGS:

N16), F/F
mported brand)

ght) Holes Steel Ring Flange

pipe) w/ harness
th washer

Qty
Unit
Php 1.00 unit
Php 3.00 units
Php 16.00
Php 5.00
Php 3.00
Php120.00

pcs.
pcs.
unit
pcs.

poxy-enamel coated "blue"


w/ anti-rust & epoxy-enamel coated)
poxy-enamel coated "blue"

Php
Php
Php
Php

5.00
2.00
5.00
1.00

pcs.
pc.
pc.
pc.

ng works only, and pipe


supply of B.I. pipes)

es, installation of Appurtenances,


on for Chlorinator Injection Fittings.

Php 5.00 pcs.


Php 1.00 unit
Php
Php
Php
Php
Php
Php

1.00
1.00
1.00
1.00
1.00
1.00

pc.
pc.
pc.
pc.
pc.
pc.

Php
Php
Php
Php
Php
Php
Php
Php

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

pc.
pc.
pc.
pc.
pc.
pc.
pc.
l.s.

COMMISSIONING OF 100mm ELECTRO-MAGNETIC FLOWMETER


RTER AND FULLY INTEGRATED GSM DATA LOGGER COMPATIBLE

TS WITH COMPLETE ACCESSORIES.

one (1) unit 100mm Electromating flanges and with


th accessories.
gger 2 flow MK3 (flow & pressure)
a recording

lithium battery pack dischargeable


ly water proofed (IP68).
d GSM mobile telephone thru simple
h a windows-based software (one modem per unit).

able from logger to Personal


tion software for PC's,
icoil hose fitting for pressure
fittings (Quick fit connection).
& Training of personnels)

SIONING OF ATLAS COPCO 38 KVA RATED STAND-BY POWER,


OR SET, QAS 35KD-FlX WITH GENSET SHED & FOUNDATION.

QAS 38KD-FIX
220 V-3-60 Hz

Qty
Unit
Php1.00 unit

Php1.00 unit

1800 RPM

SO 3046; ISO 8528-2

Water Cooled

Electronic
Direct Injection

Electric, 12Vdc

Leroy Somer
LSA 42.2 L9
EC 34-1; ISO 8528-3

Class H with marine impregnation

gine using Diesel Fuel with fuel filter, water separator and 12V storage battery.
n (protects against too high cooling water temperature and too low oil pressure).
ter separator protects against solid and liquid impurities.
uding maintenance indicator.
ncer that conforms to the manufacturer's recommendations.

osure. Rigid in construction that withstands rough handling.


s that allows operation in noise-restricted areas.
ss to all compartments.

ns of towing.

here Meter, AC Voltmeter, VM Selector Switch, Frequency/RPM Meter, Hour Meter,


lant Temp. Gauge, Engine Oil Press. & Fuel Guage.
tor Switch for ON/OFF (Remote), Automatic Engine Shutdown on:
nt Temp., Low Lube Oil Pressure, Overspeed, Under Voltage, Under Freq.
ator Charging, AC Shutdown, Engine Coolant
Indicator, Engine Oil Pressure Fault Indicator,
Breaker, Emergency Stop Button.
ills genset fuel tank from outside fuel container/drum.

w and supplied with mannuals and standard set of tools.


ce Test Certificate and Training of staff on the use, service

cal wires, accessories and all other materials and equipment


the generator set.
ns & Diagrams of the Genset Electrical System.
el Filters, Pre-Fuel Filters, Air Filters & Engine coolant

ING ONE (1) UNIT AUTOMATIC TRANSFER SWITCH (ATS):

ase, 60 Hz.
250 Amps max. rating

plete with Electrical


ctor Switches; Timer;
nitor for Normal & Genset Power, Out of Sequence or Phase Reversal Relay
nge) ; Intelligent Circuit with NEMA-1 Metal Enclosure

Php 1.00 Unit

N OF GENSET SHED:

ycarbonate sheets

arbonate Sheet
ead Type)

MS Angle Bar Purlins

bolt holes) MS Sole Steel Plate

Qty.
Php 3.00
Php150.00
Php 4.00
Php 5.00
Php 6.00
Php 2.00
Php 2.00
Php 8.00
Php 2.00
Php 16.00
Php 4.00
Php 5.00
Php 1.00

Unit
shts.
pcs.
tubes
pcs.
pcs.
pcs.
pcs.
pcs.
pcs.
sets
pcs.
kgs.
l.s.

Php
Php
Php
Php
Php
Php

bags
cu.m.
cu.m.
pcs.
pcs.
kgs.

2.00
0.20
0.20
4.00
2.00
3.00

undation including excavation & steel works


.

Php
Php
Php
Php
Php
Php
Php
Php
Php
Php
Php

27.00
1.50
3.00
25.00
4.00
4.00
4.00
67.00
2.00
2.00
2.00

bags
cu.m.
cu.m.
pcs.
kgs.
sets
shts.
bd.ft.
kgs.
kgs.
kgs.

TION TANK & COMPLETE ACCESSORIES:

or with 100 liters Solution Tank


r 40 GPD(max) vs. 125 psig,
d gear assembly, driven by
With complete standard

###

unit

pe supports.

nerator Set. w/ genset Shed & Foundation

ccessories

OD B.I.

el sanitary seal

el sanitary seal)

-on/Delay timer,

347,712.00
40,000.00
200,000.00
20,000.00
17,386.00
625,098.00

25,003.92
31,254.90
6,250.98
62,509.80
90,015.00
840,133.00

Unit Cost
65,000.00

Amount
65,000.00

18,000.00

54,000.00

1,000.00
3,500.00
2,500.00
80.00

16,000.00
17,500.00
7,500.00
9,600.00

6,000.00
1,500.00
4,000.00
1,420.00

30,000.00
3,000.00
20,000.00
1,420.00

4,000.00
10,000.00

20,000.00
10,000.00

52.00
91.00
63.00
11.00
11.00
6.00

52.00
91.00
63.00
11.00
11.00
6.00

11.00
9.00
15.00
10.00
13.00
442.00
2,000.00
25,675.00

11.00
9.00
15.00
10.00
13.00
442.00
2,000.00
25,675.00
282,429.00
2,935,188.00

3,944,892.60
438,321.40

117,407.52
146,759.40
29,351.88
293,518.80
422,667.00

577,810.00

Unit Cost
350,000.00

Amount
350,000.00

75,000.00

75,000.00

425,000.00
21,250.00
446,250.00
17,850.00
22,312.50
4,462.50
44,625.00
64,260.00
599,760.00

750,800.00
30,032.00
37,540.00
7,508.00
75,080.00
108,115.00

1,009,075.00

50,000.00
2,000.00
2,500.00
500.00
5,000.00
7,200.00

67,200.00

Amount
4,600.00
4.00
345.00
1,940.00
1,320.00
575.00
460.00
288.00
345.00
115.00
800.00
130.00
1,500.00

Total Amount
13,800.00
600.00
1,380.00
9,700.00
7,920.00
1,150.00
920.00
2,304.00
690.00
1,840.00
3,200.00
650.00
1,500.00

210.00
1,300.00
640.00
350.00
140.00
70.00

420.00
260.00
128.00
1,400.00
280.00
210.00
48,352.00
16,923.00

65,275.00

226.00
1,000.00
1,000.00
200.00
70.00
58.00
560.00
20.00
60.00
60.00
60.00

6,102.00
1,500.00
3,000.00
5,000.00
280.00
232.00
2,240.00
1,340.00
120.00
120.00
120.00
20,054.00
9,024.00
29,078.00

1,680,000.00
201,600.00

1,400,000.00
56,000.00
70,000.00
14,000.00
140,000.00
201,600.00
1,881,600.00

90,000.00

90,000.00

90,000.00
3,600.00
4,500.00
900.00
9,000.00
12,960.00
120,960.00

Php

120.00

218,191.00

2,500.00
256,754.00
246,429.00
24,643.00

Php

288.00

###

100 hp

74hp

50hp

pump

390,000.00 565,000.00 200,000.00

motor/m. cables

328,250.00

riser columns/acces
soft-starter control

40,000.00

18,210.00 225,750.00
###

40,000.00

380,000.00 368,000.00 300,000.00


1,138,250.00 991,210.00 765,750.00

2,500.00

256,754.00

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRI
Pilar Street, Zamboanga City

Project
:
PROP. CONSTRUCTION OF ZONE 4 BOOSTER STATION (PHASE 1)
Location
:
ZSCMST Compound, Rio Hondo, Zamboanga City
Scope of Work:
A. NON ENGINEERING BASIC COST
I. PERMIT FEE
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. TESTING OF MATERIALS
IV. CONSTRUCTION OF TEMFACIL
V. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. CLEARING & DEMOLITION WORKS
III. HAULING OF MATERIALS
IV. FINAL STAKING/LAY-OUTING & CLEARING
V. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM
1. EXCAVATION WORKS (3.98 Cu.M.)
2. CONCRETE WORKS (8.50 Cu M.)
3. REINFORCED STEEL WORKS (1,093.10 KGS.)
4. MASONRY WORKS
5. CARPENTRY WORKS
6. SCAFFOLDING & FORM WORKS
7. PLUMBING WORKS
8. GLASS WORKS (LUMP SUM)
VI. CONSTRUCTION OF (2.56 SQ.M.) GUARD HOUSE
1. EXCAVATION WORKS
2. CONCRETE & REINFORCED STEEL WORKS
3. MASONRY WORKS
4. CARPENTRY WORKS
5. GLASS WORKS (LUMP SUM)
6. STEEL WORKS (WINDOW GRILLES)
7. PLUMBING WORKS
8. WATERPROOFING WORKS (LUMP SUM)
9. PAINTING WORKS
10. CONSTRUCTION OF SEPTIC VAULT (6.50 CU.M.)
VII. CONSTRUCTION OF 75 LN. MTR. PERIMETER FENCE
1. EXCAVATION/BACKFILLING WORKS
2. REINFORCED STEEL WORKS
3. CONCRETING WORKS (18.00 CU. M.)
4. SCAFFOLDING WORKS
5. MASONRY WORKS (134.00 SQ. M.)
6. STEEL WORKS
7. PAINTING WORKS
8. FABRICATION AND INSTALLATION OF PANAFLEX
VIII. PIPE LAYING WORKS (PIPE LAYING OF 125 LINEAR METER - 100MM DIST
IX. CONSTRUCTION OF 250MM RCCP DRAINAGE SYSTEM(L=125.0 Ln. Mtr.)
X. CONSTRUCTION OF CONCRETE DRIVE WAY
XI. LANDSCAPING WORKS
XII. ELECTRICAL WORKS
XVIII. MECHANICAL WORKS

Page 63 of 140

Total Cost of Project

4,766,735.00

Page 64 of 140

BILL OF MATERIALS & COST ESTIMATES


Item Description
A. NON ENGINEERING BASIC COST
I. PERMIT FEE
1. Building Permit
2. ECC Requirement
2.1. Processing Fee
2.2. Support Fund
TOTAL COST OF PERMIT FEE
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
1. Signages
4' x 8' Tarpaulin (Project Signage) (Including Printing & Layout)
4 - pcs. 2" x 2" x 10' Coco Lumber
4 - pcs. 2" x 3" x 10' Coco Lumber
1" C.W. Nail
3" C.W. Nail
4" C.W. Nail
2. A-Frame Barricades (20 units)
a. Materials:
Caution Tape 3"W x 300m/Roll
40 - pcs. 2" x 2" x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
3" C.W. Nail
4" C.W. Nail
Flat Enamel Paint
Quick Dry Enamel Paint (Lamp Black)
Quick Dry Enamel Paint (Caterpillar Yellow)
Paint Thinner
2" Paint Brush
3" Paint Brush
3" Width Reflectorized Sticker
b. Labor:
1 - Skilled Worker
2 - Laborer
TOTAL COST OF HEALTH & SAFETY
III. TESTING OF MATERIALS
Portland Cement Quality Test (28 Days)
Concrete Flexural Test
Coarse Aggregates (Complete Test)
Fine Aggregates (Complete Test)
100mm Concrete Hollow Block
150mm Concrete Hollow Block
250mm RCCP
Deformed Steel Bar (Tensile & Yield Test)
10mm Deformed Steel Bar
12mm Deformed Steel Bar
16mm Deformed Steel Bar
Tie Wire
TOTAL COST OF TESTING OF MATERIALS

Page 65 of 140

IV. CONSTRUCTION OF TEMFACIL


a. Material:
16 - pcs. 2" x 4" x 10' Coco Lumber
16 - pcs. 2" x 3" x 10' Coco Lumber
20 - pcs. 2" x 2" x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
Ga. No. 26 x 10'. Corr. G.I. Sheet
3-1/2" Loose Pin Hinges
4" C.W. Nail
3" C.W. Nail
1-1/2" C.W. Nail
b. Labor:
2 - Skilled Worker
4 - Contractual Laborer
TOTAL COST OF CONSTRUCTION OF TEMFACIL
V. SUPERVISION
a. Manpower:
1 - Engineering Assistant
TOTAL COST OF SUPERVISION
TOTAL NON ENGINEERING BASIC COST
B. ENGINEERING BASIC COST
I. MOBILIZATION

II. CLEARING & DEMOLITION WORKS


a. Laborers
8 - Contractual Laborers
b. Equipment Rental/Fuel:
1 - Power Saw (w/ Fuel & Operator)
1 - Unit Dump Truck (w/ Fuel & Operator)
TOTAL DIRECT COST OF CLEARING & DEMOLITION WORKS

Page 66 of 140

III. HAULING OF MATERIALS


a. Laborers
4 - Contractual Laborers
b. Equipment Rental/Fuel:
1 - Unit Hauling Truck (w/ Fuel & Operator)
TOTAL DIRECT COST OF HAULING OF MATERIALS
IV. FINAL STAKING/LAY-OUTING & CLEARING
a. Materials:
10 pcs. - 2" x 2" x 10' Coco Lumber
10 pcs. - 2" x 3" x 10' Coco Lumber
4" C.W. Nail
3" C.W. Nail
2" C.W. Nail
Nylon Chord No. 100
12mm Clear Hose
b. Labor:
2 - Skilled Worker
2 - Contractual Laborers
TOTAL DIRECT COST OF FINAL STAKING/LAY-OUTING & CLEARING
V. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM
1. EXCAVATION WORKS (3.98 Cu.M.)
b. Labors:
2 - Laborer
TOTAL DIRECT COST OF EXCAVATION WORKS
2. CONCRETE WORKS (8.50 Cu M.)
a. Materials:
F2 (2 Units)
Portland Cement
Washed Sand
Gravel (G1)
C2-A (2 Units)
Portland Cement
Washed Sand
Gravel (G1)
WF (11.00 ln.m.)
Portland Cement
Washed Sand
Gravel (G1)
Floor Lintel Beam (11.00 ln.m.)
Portland Cement
Washed Sand
Gravel (G1)
Slab on Fill (0.10m x 12.65 Sq.m.)
Portland Cement
Washed Sand

Page 67 of 140

Gravel (G1)
Door/Window Lintel Beam (10.00 ln.m.)
Portland Cement
Washed Sand
Gravel (G1)
RCB
Portland Cement
Washed Sand
Gravel (G1)
Roof Slab (18.70 sq.m.)
Portland Cement
Washed Sand
Gravel (G1)
False Beam (10.50 ln.m.)
Portland Cement
Washed Sand
Gravel (G1)
b. Labors:
1 - Mason
6 - Laborer
c. Equipment Rental:
1 - Unit One - Bagger Mixer
1 - Unit Concrete Vibrator
TOTAL DIRECT COST OF CONCRETE WORKS

3. REINFORCED STEEL WORKS (1,093.10 KGS.)


Note: Other Column Footing, Column, Wall Footing & Floor Lintel Beam are already included in Perimeter Fence E
a. Materials:
F2 (2 Units)
16mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade

Page 68 of 140

C2-A (2 Units)
16mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
WF (11.00 ln.m.)
12mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
Floor Lintel Beam (11.00 ln.m.)
12mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
Slab on Fill (0.10m x 12.65 Sq.m.)
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
Door/Window Lintel Beam (10.00 ln.m.)
12mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
RCB
16mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
Roof Slab
12mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
False Beam (10.50 ln.m.)
12mm x 6.00m Def. Reinforcing Steel Bars
10mm x 6.00m Def. Reinforcing Steel Bars
#16 G.I. Tie-wire
Hacksaw Blade
b. Labors:
2 -Steelman
2 -Contractual Laborers
c. Equipment Rental:
1 - Unit Bar Bender
TOTAL DIRECT COST OF REINFORCED STEEL WORKS
4. MASONRY WORKS

Page 69 of 140

4.1. Laying & Plastering of CHB


(Includes CHB Laying & Plastering Works)
a. Materials:
Portland Cement
Washed Sand
Fined Sand (For Plastering)
100mm x 200mm x 400mm Hollow Block (NLB)
150mm x 200mm x 400mm Hollow Block (LB)
10mm x 6.00m. Def. Steel Bars
# 16 G.I. Tie Wire
Hacksaw Blade
b. Labors:
2 - Mason
2 - Laborer
4.2. Tile Works (31.80 sq.m.)
a. Materials:
200mm x 200mm Ceramic Tiles (White)
400mm x 400mm Granite Tiles (White)
Tile Adhesive (25Kg/Bag)
Tile Grout (2 Kg./Pack)
PVC Tile Trim (White)
4" Grinding Wheel
b. Labor:
2 - Mason
2 - Laborer
c. Equipment Rental:
1 - Unit Tile Cutter
1 - Unit Angular Grinder
TOTAL DIRECT COST OF MASONRY WORKS
5. CARPENTRY WORKS
a. Materials:
5.1. Installation of Door Frame/Pannel Door & Window Jamb
Pre-Fabricated 0.80m x 2.10m x 50mm x 150mm Mahogany Wood Door Jamb
Pre-Fabricated 0.80m x 2.10m Mahogany Wood Panel Type Door
w/ 50mm x 100mm Door Frame & 37.5mm Thk Door Board
Pre-Fabricated 0.60m x 2.10m PVC Door w/ Door Jamb & Hinges w/ Screw
Pre-Fab. 1.165m x 1.45m x 50mm x 150mm 2 Panel Mahogany Wood Window Jamb
5.2. Cabinet & Table:
1-Unit Cabinet
Cabinet Handle (Chrome)
Cabinet Concealed Hinges w/ Screw
12mm. x 6.00m G.I. Pipe, ASTM A53-90A Heavy Gauge Standard
3 pcs. - 1" x 1" x 10' Mahogany Lumber
19mm Thk x 1.20m x 2.40m Plyboard
6mm Thk x 1.20m x 2.40m Plyboard
3" C.W. Nail
1" C.W. Finishing Nail
1-Unit Table

Page 70 of 140

Drawer Handle (Chrome)


3 pcs. - 1" x 1" x 10' Mahogany Lumber
19mm Thk x 1.20m x 2.40m Plyboard
1" C.W. Finishing Nail
5.3. Hardware :
4" x 3" Loose Pin Hinges (Heavy Duty) w/ Screw
2" x 2" Cabinet Hinges w/ Screw
Stainless Door Knob (Heavy Duty)
Drawer Lock (Heavy Duty)
4" C. W. Nail
2-1/2" C. W. Nail
2" C. W. Nail
1" C. W. Nail
1" Finishing Nail
b. Labor:
1 - Carpenter
1 - Laborer
TOTAL DIRECT COST OF CARPENTRY WORKS
6. SCAFFOLDING & FORM WORKS
a. Materials:
12mm Thk x 1.20m x 2.40m Ordinary Plywood
100 pcs. - 2" x 2" x 10' Coco Lumber
80 pcs. - 2" x 3" x 10' Coco Lumber
60 pcs. - 2" x 4" x 10' Coco Lumber
4" C. W. Nail
3" C. W. Nail
1-1/2" C. W. Nail
b. Labor:
1 - Carpenter
2 - Laborer
TOTAL DIRECT COST OF SCAFFOLDING & FORM WORKS
7. PLUMBING WORKS
a. Material:
7.1. Storm Drainage Pipe
50mm x 3.00m PVC Pipe, Series 1000
50mm x 900 PVC Bend, Series 1000
50mm PVC Coupling, Series 1000
PVC Solvent Cement
7.2. Sanitary Pipe
100mm x 3.00m PVC Pipe, Series 1000
100mm x 450 PVC Sanitary Elbow, Series 1000
100mm x 900 PVC Sanitary Elbow, Series 1000
100mm x PVC Clean Out, Series 1000
100mm PVC Sanitary Coupling, Series 1000
50mm x 3.00m PVC Pipe, Series 1000
50mm PVC Sanitary Coupling, Series 1000
50mm x 900 PVC Bend, Series 1,000
100mm x 100mm PVC Sanitary Tee, Series 1000

Page 71 of 140

100mm x 100mm PVC Sanitary Wye, Series 1000


100mm x 50mm PVC Sanitary Tee, Series 1000
50mm x 50mm PVC Sanitary Tee, Series 1000
PVC Cement Solvents
7.3. Cold Pipe
12mm x 6.00m G.I. Pipe ASTM A53-90A Heavy Gauge Standard
12mm x 900 G.I. Elbow, ANSI B16.3 Class 150 Standard
12mm x 12mm G.I. Tee, ANSI B16.3 Class 150 Standard
12mm Brass Faucet
12mm G.I. Union Patent ANSI B16.3 Class 150 Standard
25mm Thread Seal Tape
7.4. Sanitary Fixtures:
Flush Type Water Closet w/ Complete Fittings & Accs.
Wall Mounted Type Lavatory w/ Complete Fittings & Accs.
Ceramic Tissue Holder
Ceramic Soap Holder
12mm Shower Head
12mm Shower Valve
100mm x 100mm Stainless Double Strainer Floor Drain
6mm Thk. x 0.6m x 0.6m Beveled Frameless Mirror
b. Labors:
1 -Plumber
2 - Laborer
TOTAL DIRECT COST OF PLUMBING WORKS
8. GLASS WORKS (LUMP SUM)
Supply & Installation of 5.5mm Thk x 13 Blades Smoke x 0.65m width Glass Jalousies
w/ Aluminum Holder
Supply & Installation of 5.5mm Thk x 6 Blades x 0.60m width Smoke Glass
Jalousies w/ Aluminum Holder
TOTAL DIRECT COST OF GLASS WORK
9. STEEL WORKS (WINDOW GRILLES)
a. Materials:
W-1 (1 Unit)
10mm x 10mm x 6.00m. M.S. Square Bar
12mm x 12mm x 6.00m. M.S. Square Bar
6mm thk. x 20mm x 6.00m. M.S. Flat Bar
Hack Saw Blade
6011 Welding Rod
W-2 (2 Units)
10mm x 10mm x 6.00m. M.S. Square bars
12mm x 12mm x 6.00m. M.S. Square bars
6mm thk. x 20mm x 6.00m. M.S. Flat bars
Hacksaw Blade
6011 Welding Rod
b. Labors:
1 -Welder
1 - Laborer

Page 72 of 140

c. Equipment:
1 - Unit Welding Machine w/ Cutting Outfit
1 Unit Angular Grinder
4" Grinding Disk
TOTAL DIRECT COST OF STEEL WORKS (Window Grilles)
10. WATER PROOFING WORKS (LUMP SUM)
Bituminous Membrane Polyester Reinforced Water Proofing
TOTAL DIRECT COST OF WATER PROOFING WORKS (LUMP SUM)
11. PAINTING WORKS (120.00 Sq. M.)
a. Materials:
Concrete Neutralizer
Solvent Based Acrylic Paint Primer
Solvent Based Acrylic Cast
Solvent Based Acrylic Paint Top Coat White Gloss
Solvent Based Acrylic Reducer
Lacquer thinner
Body Filler w/ Hardener
Sand paper#150
Sand paper#120
Red Tinting Color for Solvent Based Acrylic Paint
Raw Sienna Tinting Color for Solvent Based Acrylic Paint
Thalo Blue Tinting Color for Solvent Based Acrylic Paint
Lamp Black Tinting Color for Solvent Based Acrylic Paint
Red Lead Paint Primer
Quick Dry Enamel (Royal Blue)
7" Roller Brush w/ Handle
7" Paint Tray
2" Steel Brush
3" Paint Brush
2" Paint Brush
b. Labors:
1 - Painter
1 - Laborer
TOTAL COST OF PAINTING WORKS

TOTAL COST OF OPERATOR'S ROOM

Page 73 of 140

VI. CONSTRUCTION OF (2.56 SQ.M.) GUARD HOUSE


1. EXCAVATION WORKS
a. Laborers
2 - Laborers
TOTAL COST OF EXCAVATION WORKS
2. CONCRETE & REINFORCED STEEL WORKS
a.Materials:
2.1 Footing
Portland Cement
Washed Sand
Gravel (G1)
150mm Boulder
16mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

5.096
0.2156
0.4312
0.392
3
0.5

2.2 Column
Portland Cement
Washed Sand
Gravel (G1)
16mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

2.9484
0.12474
0.24948
8
9
1

2.3 Wall Footing


Portland Cement
Washed Sand
Gravel (G1)
12mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

2.7144
0.11484
0.22968
3
2
0.5

2.4. Slab
Portland Cement
Washed Sand
Gravel (G1)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

2.1866
0.09251
0.18502
4
0.5

2.5. Floor Lintel Beam


Portland Cement
Washed Sand
Gravel (G1)
12mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

1.8096
0.07656
0.15312
4
3
1

2.6. Door/Floor Lintel Beam


Portland Cement
Washed Sand
Gravel (G1)
12mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)

1.456
0.0616
0.1232
3
2

Page 74 of 140

#16 G.I. Tie Wire

2.7. Concrete Wings


Portland Cement
Washed Sand
Gravel (G1)
12mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

4.004416
0.1694176
0.3388352
2
20
1

2.8. Roof Beam


Portland Cement
Washed Sand
Gravel (G1)
16mm x 6.00m. Deform Reinf. Bars (Grade 33)
10mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

2.015
0.08525
0.1705
6
5
1.5

2.9. Roof Slab


Portland Cement
Washed Sand
Gravel (G1)
Concrete Admix
Concrete Water Proofing Compound
12mm x 6.00m. Deform Reinf. Bars (Grade 33)
#16 G.I. Tie Wire

2.34
0.099
0.198
2.34
2.34
9
1.4485714286

b. Labor:
1 - Mason
1 - Steel Man
2 - Contractual Laborers
c. Equipment/Fuel:
1 - Unit Bagger Mixer
1 - Unit Concrete Vibrator
1 - Unit Water Pump
Premium Gasoline
TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS
3. MASONRY WORKS
1. CHB LAYING & PLASTERING WORKS
a.Materials:
100mm x 200mm x 400mm CHB (NLB)
150mm x 200mm x 400mm CHB (LB)
Portland Cement
Washed Sand
Fine Sand (For Plastering)
10mm dia x 6.00m Deform Bar (Grade 33)
#16 G.I. Tie Wire
b.Labor:
1 - Mason
2 - Contractual Laborers
TOTAL COST OF MASONRY WORKS

Page 75 of 140

4. CARPENTRY WORKS
a. Materials:
4.1. Installation of Door, Door Jambs & Window Jambs:
Pre-Fabricated 0.70m x 2.10m x 50mm x 150mm Mahogany Wood Door Jamb
Pre-Fabricated 0.70m x 2.10m Mahogany Wood Panel Type Door
50mm x 100mm Door Frame & 37.5mm Thk Door Board
Pre-Fab. 0.60m x 1.165m x 50mm x 150mm 1 Pannel Mahogany Wood Window Jamb
4.2. Fabrication of Cabinet
6mm Thk x 1.20m x 2.40m Plywood
20mm Thk x 1.20m x 2.40m Plyboard
3 - pcs. 1" x 1" x 10' Mahogany Lumber
4.2.Forms & Scaffolding Works
80 - pcs. 2" x 4" x 10' Coco Lumber
60 - pcs. 2" x 3" x 10' Coco Lumber
40 - pcs. 2" x 2" x 10' Coco Lumber
4.5. Hardware
4" x 3" Loose Pin Hinges w/ Screw
2" x 2" Cabinet Hinges w/ Screw
Stainless Door Knob (Heavy Duty)
Drawer Lock (Heavy Duty)
Drawer Handle (Chrome Plated)
4" C.W. Nail
3" C.W. Nail
2-1/2" C.W. Nail
2" C.W. Nail
1" C.W. Nail
2" Finishing Nail
b.Labor:
1 - Carpenter
2 - Contractual Laborers
TOTAL DIRECT COST OF CARPENTRY WORK
5. GLASS WORKS (LUMP SUM)
Supply & Installation of 5.5 mm Thk x 13 Blades x 0.60m width Smoke Glass Jalousies
w/ Aluminum Holder
TOTAL DIRECT COST OF GLASS WORK (LUMP SUM)
6. STEEL WORKS (WINDOW GRILLES)
a. Materials:
10mm x 10mm x 6.00m. Square bars
12mm x 12mm x 6.00m. Square bars
6mm thk. x 20mm x 6.00m. Flat bars
Hack Saw Blade
6011 Welding Rod
b. Labors:
1 -Welder
2 -Contractual Laborers
c. Equipment/Fuel:
1 - Unit Welding Machine

Page 76 of 140

1 - Unit Disk Grinder


4" Grinding Wheel
TOTAL DIRECT COST OF STEEL WORKS (Window Grilles)
7. PLUMBING WORKS
a. Materials:
50mm x 3.00m. PVC Sanitary Pipe Series 1000
50mm x 900 PVC Sanitary Elbow, Series 1000
50mm PVC Coupling, Series 1000
PVC Solvent Cement
100mm x 100mmStainless Floor Drain
b. Labors:
1 - Plumber
2 - Contractual Laborers
TOTAL DIRECT COST OF PLUMBING WORKS
8. WATERPROOFING WORKS (LUMP SUM)
Bituminous Membrane Polyester Reinforced Waterproofing
TOTAL DIRECT COST OF WATERPROOFING WORKS (LUMP SUM)
9. PAINTING WORKS
a. Materials:
Concrete neutralizer
Solvent Based Acrylic Paint Primer
Solvent Based Acrylic Cast
Solvent Based Acrylic Paint Top Coat White Gloss
Solvent Based Acrylic Paint Reducer
Lacquer Thinner
Body Filler w/ Hardener
Sand paper#150
Sand paper#120
Red Tinting Color for Solvent Based Acrylic Paint
Raw Sienna Tinting Color for Solvent Based Acrylic Paint
Thalo Blue Tinting Color for Solvent Based Acrylic Paint
Lamp Black Tinting Color for Solvent Based Acrylic Paint
7" Roller Brush Tray
7" Roller Brush w/ Handle
2" Steel Brush
3" Paint Brush
2" Paint Brush

Page 77 of 140

1.5
1.5

b. Labors:
1 - Painter
1 - Contractual Laborers
TOTAL COST OF PAINTING WORKS
TOTAL COST OF CONSTRUCTION OF GUARD HOUSE

10. CONSTRUCTION OF SEPTIC VAULT (6.50 CU.M.)


10.1. CONCRETE & REINFORCED STEEL WORKS
a.Materials:
2.1.1. Bottom Slab
Portland Cement
Washed Sand
Gravel (G1)
Water Proofing Compound (900g)
2.1.2. Top Slab
Portland Cement
Washed Sand
Gravel (G1)
12mm x 6.00m. Def. Reinf. Steel Bars (Grade 33)
#16 G.I. Tie Wire
b.Labors:
1 - Mason
2 - Contractual Laborer
TOTAL COST OF CONCRETE & REINFORCED STEEL WORKS
10.2. MASONRY WORKS
a.Materials:
100mm x 200mm x 400mm CHB (NLB)
Portland Cement
Washed Sand
Fine Sand (For Plastering)
Water Proofing Compound (900g)
Hydraulic Cement
12mm x 6.00m. Def. Reinf. Steel Bars (Grade 33)
#16 G.I. Tie Wire
b.Labors:
1 - Mason
1 - Contractual Laborer
TOTAL COST OF MASONRY WORKS
10.3. CARPENTRY WORKS
a.Materials:
Forms & Scaffolding
12mm Thk x 1.20m x 2.4m Ordinary Plywood
40 - pcs. 2" x 2" x 10' Coco Lumber
40 - pcs. 2" x 3" x 10' Coco Lumber
4" C.W. Nail
3" C.W. Nail
1-1/2"" C.W. Nail
b.Labor:
1 - Carpenter
2 - Contractual Laborers

Page 78 of 140

lic of the Philippines


A CITY WATER DISTRICT
reet, Zamboanga City

METER - 100MM DISTRIBUTION LINE & 125 LINEAR METER-100MM SUPPLY LINE)
M(L=125.0 Ln. Mtr.)

Page 79 of 140

Page 80 of 140

COST ESTIMATES
Qty. Unit

Unit Cost

Sub-Total

1 lot

15,000.00

15,000.00

1 lot
1 lot

4,000.00
9,600.00

4,000.00
9,600.00

2 units
13 bd.ft.
20 bd.ft.
1 kg.
1 kg.
1 kg.

800.00
21.00
21.00
77.00
67.00
67.00

1,600.00
273.00
420.00
77.00
67.00
67.00

2,504.00

1 roll
133 bd.ft.
3 shts.
2 kgs.
2 kgs.
2 gals.
1 gal.
1 gal.
1 gal.
1 pc.
1 pc.
20 ln.ft.

1,260.00
21.00
861.00
67.00
67.00
649.00
504.00
567.00
300.00
54.00
89.00
37.00

1,260.00
2,793.00
2,583.00
134.00
134.00
1,298.00
504.00
567.00
300.00
54.00
89.00
740.00

10,456.00

5 days
5 days

366.00
317.00

1,830.00
3,170.00

3 tests
2 test
1 test
1 test
1 test
1 test
1 test

1,500.00
1,500.00
1,350.00
1,350.00
600.00
600.00
700.00

4,500.00
3,000.00
1,350.00
1,350.00
600.00
600.00
700.00

2 tests
2 tests
2 tests
1 test

1,200.00
1,200.00
1,300.00
500.00

2,400.00
2,400.00
2,600.00
500.00

Page 81 of 140

Total Cost

28,600.00
28,600.00

5,000.00
17,960.00

20,000.00
20,000.00

107 bd.ft.
80 bd.ft.
67 bd.ft.
12 shts.
12 pcs.
2 pcs.
3 kgs.
3 kgs.
2 kgs.

21.00
21.00
21.00
861.00
470.00
57.00
67.00
67.00
75.00

2,247.00
1,680.00
1,407.00
10,332.00
5,640.00
114.00
201.00
201.00
150.00

4 days
4 days

366.00
317.00

2,928.00
5,072.00

210 days

524.00

110,040.00

21,972.00

8,000.00
29,972.00

110,040.00
110,040.00

186,572.00

1 lot

20,000.00

20,000.00

20,000.00
20,000.00

4 days

317.00

10,144.00

10,144.00

2 days
2 days

1,000.00
9,016.00

2,000.00
18,032.00

Page 82 of 140

20,032.00
30,176.00

4 days

317.00

5,072.00

5,072.00

4 days

9,600.00

38,400.00

38,400.00
43,472.00

33 bd.ft.
50 bd.ft.
1 kg.
1 kg.
1 kg.
8 rolls
50 l.m.

21.00
21.00
67.00
67.00
70.00
137.00
16.00

693.00
1,050.00
67.00
67.00
70.00
1,096.00
800.00

1 day
1 day

366.00
317.00

732.00
634.00

2 days

317.00

1,268.00

6 bags
0.25 cu.m.
0.5 cu.m.

278.00
1,050.00
945.00

1,668.00
262.50
472.50

2,403.00

7 bags
0.5 cu.m.
0.75 cu.m.

278.00
1,050.00
945.00

1,946.00
525.00
709.00

3,180.00

5 bags
0.25 cu.m.
0.5 cu.m.

278.00
1,050.00
945.00

1,390.00
263.00
473.00

2,126.00

4 bags
0.25 cu.m.
0.5 cu.m.

278.00
1,050.00
945.00

1,112.00
263.00
473.00

1,848.00

12 bags
0.5 cu.m.

278.00
1,050.00

3,336.00
525.00

Page 83 of 140

3,843.00

1,366.00
5,209.00

1,268.00
1,268.00

1 cu.m.

945.00

945.00

4,806.00

3 bags
0.25 cu.m.
0.25 cu.m.

278.00
1,050.00
945.00

834.00
263.00
236.00

1,333.00

12 bags
0.5 cu.m.
1 cu.m.

278.00
1,050.00
945.00

3,336.00
525.00
945.00

4,806.00

23 bags
1 cu.m.
2 cu.m.

278.00
1,050.00
945.00

6,394.00
1,050.00
1,890.00

9,334.00

4 bags
0.25 cu.m.
0.25 cu.m.

278.00
1,050.00
945.00

1,112.00
263.00
236.00

1,611.00

5 days
5 days

366.00
317.00

1,830.00
9,510.00

11,340.00

5 days
5 days

1,500.00
500.00

7,500.00
2,500.00

436.00
84.00
85.00

1,744.00
84.00
170.00

10,000.00
52,787.00

ded in Perimeter Fence Estimates

4 pcs.
1 kg.
2 pcs.

Page 84 of 140

1,998.00

8 pcs.
11 pcs.
1 kg.
2 pcs.

436.00
176.00
84.00
85.00

3,488.00
1,936.00
84.00
170.00

5,678.00

3 pcs.
5 pcs.
2 kgs.
2 pcs.

251.00
176.00
84.00
85.00

753.00
880.00
168.00
170.00

1,971.00

9 pcs.
7 pcs.
2 kgs.
2 pcs.

251.00
176.00
84.00
85.00

2,259.00
1,232.00
168.00
170.00

3,829.00

19 pcs.
1 kg.
3 pcs.

176.00
84.00
85.00

3,344.00
84.00
255.00

3,683.00

4 pcs.
4 pcs.
1 kg.
1 pc.

251.00
176.00
84.00
85.00

1,004.00
704.00
84.00
85.00

1,877.00

22 pcs.
30 pcs.
7 kgs.
10 pc.

436.00
176.00
84.00
85.00

9,592.00
5,280.00
588.00
850.00

16,310.00

65 pcs.
6 kgs.
10 pcs.

251.00
84.00
85.00

16,315.00
504.00
850.00

17,669.00

5 pcs.
8 pcs.
3 kgs.
3 pcs.

251.00
176.00
84.00
85.00

1,255.00
1,408.00
252.00
255.00

3,170.00

15 days
15 days

366.00
317.00

10,980.00
9,510.00

20,490.00

15 days

300.00

4,500.00

Page 85 of 140

4,500.00
81,175.00

73 bags
3.5 cu.m.
2 cu.m.
640 pcs.
230 pcs.
42 pcs.
3 kgs.
12 pcs.

278.00
1,050.00
1,400.00
15.00
19.00
176.00
84.00
85.00

20,294.00
3,675.00
2,800.00
9,600.00
4,370.00
7,392.00
252.00
1,020.00

49,403.00

14 days
14 days

366.00
317.00

10,248.00
8,876.00

19,124.00

618 pcs.
55 pcs.
6 bags
6 bags
7 pcs.
1 pc.

16.00
255.00
305.00
85.00
65.00
180.00

9,888.00
14,025.00
1,830.00
510.00
455.00
180.00

26,888.00

7 days
7 days

366.00
317.00

5,124.00
4,438.00

9,562.00

7 days
7 days

300.00
300.00

2,100.00
2,100.00

1 unit
1 unit

2,500.00
4,800.00

2,500.00
4,800.00

1 unit
2 units

1,900.00
2,300.00

1,900.00
4,600.00

4 pcs.
12 pcs.
1 pc.
2.5 bd.ft.
3 shts.
1 sht.
1 kg.
1 kg.

160.00
60.00
600.00
34.00
1,100.00
420.00
70.00
75.00

Page 86 of 140

640.00
720.00
600.00
85.00
3,300.00
420.00
70.00
75.00

4,200.00
109,177.00

13,800.00

4 pcs.
2.5 bd.ft.
3 shts.
1 kg.

160.00
34.00
1,100.00
75.00

640.00
85.00
3,300.00
75.00

4 pcs.
8 pcs.
2 sets
4 sets
1 kg.
1 kg.
1 kg.
1 kg.
2 kgs.

140.00
65.00
950.00
60.00
70.00
65.00
65.00
65.00
65.00

560.00
520.00
1,900.00
240.00
70.00
65.00
65.00
65.00
130.00

15 days
15 days

366.00
317.00

5,490.00
4,755.00

18 pcs.
333 bd.ft.
400 bd.ft.
300 bd.ft.
8 kgs.
8 kgs.
4 kgs.

975.00
20.00
20.00
20.00
70.00
70.00
65.00

17,550.00
6,660.00
8,000.00
6,000.00
560.00
560.00
260.00

14 days
14 days

366.00
317.00

5,124.00
8,876.00

6 pcs.
8 pcs.
4 pcs.
2 qrts.

320.00
45.00
90.00
120.00

1,920.00
360.00
360.00
240.00

4 pcs.
6 pcs.
4 pcs.
2 pcs.
2 pcs.
3 pcs.
2 pcs.
1 pc.
4 pcs.

820.00
85.00
90.00
75.00
65.00
320.00
35.00
45.00
170.00

3,280.00
510.00
360.00
150.00
130.00
960.00
70.00
45.00
680.00

Page 87 of 140

10,010.00

3,615.00

10,245.00
37,670.00

39,590.00

14,000.00
53,590.00

2,880.00

2 pcs.
1 pc.
1 pc.
8 qrts.

155.00
130.00
65.00
120.00

310.00
130.00
65.00
960.00

7,650.00

3 pcs.
7 pcs.
4 pcs.
2 pcs.
1 pc.
5 rolls

460.00
15.00
20.00
260.00
20.00
27.00

1,380.00
105.00
80.00
520.00
20.00
135.00

2,240.00

1 unit
1 unit
1 pc.
1 pc.
1 pc.
1 pc.
2 pcs.
1 pc.

4,000.00
2,415.00
270.00
160.00
220.00
250.00
150.00
200.00

4,000.00
2,415.00
270.00
160.00
220.00
250.00
300.00
200.00

7,815.00

8 days
8 days

366.00
317.00

2,928.00
5,072.00

4 sets

800.00

3,200.00

1 set

500.00

500.00

1 pc.
1 pc.
1 pc.
4 pcs.
5 kgs

260.00
311.00
700.00
65.00
160.00

260.00
311.00
700.00
260.00
800.00

2,331.00

1 pc.
10 pcs.
3 pcs.
4 pcs.
8 kgs

260.00
311.00
700.00
65.00
160.00

260.00
3,110.00
2,100.00
260.00
1,280.00

7,010.00

5 days
5 days

394.00
317.00

1,970.00
1,585.00

3,555.00

Page 88 of 140

8,000.00
28,585.00

3,700.00
3,700.00

5 days
2 days
2 pcs.

2,200.00
300.00
180.00

11,000.00
600.00
360.00

11 sq.mtr.

1,000.00

11,000.00

3 gals.
5 gals.
4 gals.
10 gals.
4 gals.
2 gals.
1 gal
1 doz.
1 doz.
2 pints
6 pints
4 pints
2 pints
2 qrts.
2 qrts.
2 sets
1 pc.
1 pc.
1 pc.
1 pc.

320.00
1,050.00
500.00
1,050.00
420.00
250.00
620.00
150.00
150.00
105.00
105.00
105.00
105.00
143.00
155.00
68.00
30.00
25.00
30.00
20.00

960.00
5,250.00
2,000.00
10,500.00
1,680.00
500.00
620.00
150.00
150.00
210.00
630.00
420.00
210.00
286.00
310.00
136.00
30.00
25.00
30.00
20.00

13 days
13 days

366.00
317.00

4,758.00
4,121.00

11,960.00
24,856.00

11,000.00
11,000.00

24,117.00

8,879.00
32,996.00

436,804.00

Page 89 of 140

2 days

317.00

1,268.00

6 bags
0.25 cu.m.
0.5 cu.m.
1 cu.m.
3 pcs.
0.5 kgs.

278.00
1,050.00
945.00
945.00
436.00
84.00

1,668.00
262.50
472.50
945.00
1,308.00
42.00

4,698.00

3 bags
0.125 cu.m.
0.25 cu.m.
14 pcs.
9 pcs.
1 kg.

278.00
1,050.00
945.00
436.00
176.00
84.00

834.00
131.00
236.00
6,104.00
1,584.00
84.00

8,973.00

3 bags
0.125 cu.m.
0.25 cu.m.
3 pcs.
2 pcs.
0.5 kg.

278.00
1,050.00
945.00
251.00
176.00
84.00

834.00
131.00
236.00
753.00
352.00
42.00

2,348.00

3 bags
0.125 cu.m.
0.25 cu.m.
4 pcs.
0.5 kg.

278.00
1,050.00
1,098.00
176.00
84.00

834.00
131.00
275.00
704.00
42.00

1,986.00

2 bags
0.125 cu.m.
0.25 cu.m.
4 pcs.
3 pcs.
1 kg.

278.00
1,050.00
945.00
251.00
176.00
84.00

556.00
131.00
236.00
1,004.00
528.00
84.00

2,539.00

3 bags
0.125 cu.m.
0.25 cu.m.
3 pcs.
2 pcs.

278.00
1,050.00
945.00
251.00
176.00

834.00
131.00
236.00
753.00
352.00

Page 90 of 140

1,268.00
1,268.00

1 kg.

84.00

84.00

2,390.00

4 bags
0.25 cu.m.
0.5 cu.m.
2 pcs.
20 pcs.
1 kg.

278.00
1,050.00
945.00
251.00
176.00
84.00

1,112.00
262.50
472.50
502.00
3,520.00
84.00

5,953.00

3 bags
0.125 cu.m.
0.25 cu.m.
5 pcs.
5 pcs.
1.5 kg.

278.00
1,050.00
945.00
436.00
176.00
84.00

834.00
131.00
236.00
2,180.00
880.00
126.00

4,387.00

3 bags
0.125 cu.m.
0.25 cu.m.
3 packs
3 packs
9 pcs.
2 kgs.

278.00
1,050.00
945.00
36.00
42.00
251.00
84.00

834.00
131.00
236.00
108.00
126.00
2,259.00
168.00

3,862.00

10 days
10 days
10 days

366.00
366.00
317.00

3,660.00
3,660.00
6,340.00

13,660.00

4 days
4 days
2 days
48 ltrs.

1,500.00
1,000.00
800.00
60.00

6,000.00
4,000.00
1,600.00
2,880.00

350 pcs.
36 pcs.
28 bags
2 cu.m.
1 cu.m.
22 pcs.
1 kg.

15.00
19.00
278.00
1,050.00
1,523.00
176.00
84.00

5,250.00
684.00
7,784.00
2,100.00
1,523.00
3,872.00
84.00

366.00
317.00

2,928.00
5,072.00

8 days
8 days

Page 91 of 140

14,480.00
65,276.00

21,297.00

8,000.00
29,297.00

1 unit
1 unit

2,625.00
5,145.00

2,625.00
5,145.00

1 unit

2,415.00

2,415.00

10,185.00

1 sht.
4 shts.
3 bd.ft.

420.00
1,276.00
63.00

420.00
5,104.00
189.00

5,713.00

533 bd.ft.
300 bd.ft.
133 bd.ft.

21.00
21.00
21.00

11,193.00
6,300.00
2,793.00

20,286.00

4 pcs.
6 pcs.
1 set
3 sets
3 pcs.
8 kgs.
6 kgs.
4 kgs.
2 kgs.
1 kg.
1 kg.

227.00
18.00
893.00
189.00
38.00
67.00
67.00
70.00
70.00
77.00
63.00

908.00
108.00
893.00
567.00
114.00
536.00
402.00
280.00
140.00
77.00
63.00

4,088.00

15 days
15 days

366.00
317.00

5,490.00
9,510.00

1,400.00

2,800.00

2 sets

15,000.00
55,272.00

2,800.00
2,800.00

1 pc.
3 pcs.
2 pcs.
4 pcs.
4 kgs

294.00
353.00
158.00
85.00
84.00

294.00
1,059.00
316.00
340.00
336.00

2,345.00

2 days
2 days

366.00
317.00

732.00
1,268.00

2,000.00

2,200.00

2,200.00

1 day

Page 92 of 140

1 day
1 pc.

400.00
180.00

400.00
180.00

8 pcs.
16 pcs.
8 pcs.
2 qrt.
4 pcs.

483.00
47.00
16.00
474.00
207.00

3,864.00
752.00
128.00
948.00
828.00

3 days
3 days

366.00
317.00

1,098.00
1,902.00

2.6 sq.mtr.

1,000.00

2,600.00

1 gal.
2 gals.
2 gals.
4 gals.
1 gal.
1 gal.
1 gal.
1 doz.
1 doz.
1 pint
1 pint
1 pint
1 pint
1 pc.
1 set
1 pc.
1 pc.
1 pc.

488.00
860.00
504.00
1,041.00
449.00
480.00
582.00
284.00
254.00
108.00
124.00
112.00
103.00
106.00
60.00
54.00
89.00
54.00

488.00
1,720.00
1,008.00
4,164.00
449.00
480.00
582.00
284.00
254.00
108.00
124.00
112.00
103.00
106.00
60.00
54.00
89.00
54.00

Page 93 of 140

2,780.00
7,125.00

6,520.00

3,000.00
9,520.00

2,600.00
2,600.00

10,239.00

6 days
6 days

366.00
317.00

2,196.00
1,902.00

4,098.00
14,337.00

187,495.00

5 bags
0.5 cu.m.
0.5 cu.m.
5 packs

278.00
1,050.00
945.00
42.00

1,390.00
525.00
473.00
210.00

2,598.00

5 bags
0.5 cu.m.
0.5 cu.m.
13 pcs.
2 kgs.

278.00
1,050.00
945.00
251.00
84.00

1,390.00
525.00
473.00
3,263.00
168.00

5,819.00

366.00
317.00

1,098.00
1,902.00

15.00
278.00
1,050.00
1,523.00
42.00
1,300.00
251.00
84.00

4,125.00
4,448.00
1,050.00
762.00
420.00
1,300.00
3,514.00
168.00

366.00
317.00

3,294.00
2,853.00

861.00
21.00
21.00
67.00
67.00
75.00

4,305.00
2,793.00
4,200.00
268.00
201.00
75.00

11,842.00

1,830.00
3,170.00

5,000.00

3 days
3 days

275 pcs.
16 bags
1 cu.m.
0.5 cu.m.
10 packs
1 gal.
14 pcs.
2 kgs.

9 days
9 days

5 shts.
133 bd.ft.
200 bd.ft.
4 kgs.
3 kgs.
1 kg.

5 days
5 days

Page 94 of 140
366.00
317.00

3,000.00
11,417.00

15,787.00

6,147.00
21,934.00

PROJECT
Location
Project Cost
Project Duration

T
:
:
:
:

PROP. CONSTRUCTION OF ZONE 4 BOOSTER STATION (PHASE


ZSCMST Compound, Rio Hondo, Zamboanga City

Php

4,766,735.00

TWO HUNDRED TEN (210) CALENDAR DAYS

Particulars

Amounts

Php
A. NON ENGINEERING BASIC COST
I. PERMIT FEE
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. TESTING OF MATERIALS
IV. CONSTRUCTION OF TEMFACIL
V. SUPERVISION
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. CLEARING & DEMOLITION WORKS
III. HAULING OF MATERIALS
IV. FINAL STAKING/LAY-OUTING & CLEARING
V. CONSTRUCTION OF (12.40 SQ. MTR.) OPERATOR'S ROOM
1. EXCAVATION WORKS (3.98 Cu.M.)
2. CONCRETE WORKS (8.50 Cu M.)
3. REINFORCED STEEL WORKS (1,093.10 KGS.)
4. MASONRY WORKS
5. CARPENTRY WORKS
6. SCAFFOLDING & FORM WORKS
7. PLUMBING WORKS
8. GLASS WORKS (LUMP SUM)
VI. CONSTRUCTION OF 80 CU.M. CAPACITY REINFORCED CONCRETE OVERHEAD TANK
1. EXCAVATION WORKS
2. SCAFFOLDING & FORM WORKS
plus 4
3. FOUNDATION WORKS
Php
4. CONCRETE WORKS
Php
5. REINFORCED STEEL WORKS
Php
6. MASONRY WORKS
Php
7. STEEL WORKS
Php
8. PIPES, FITTINGS & APPURTENANCES WORKS
9. DISINFECTION & LEAKAGE TEST
10. PAINTING WORKS
Php
VII. CONSTRUCTION OF 150 CU.M. CAPACITY REINFORCED CONCRETE SUMP TANK
1. EXCAVATION WORKS
2. SCAFFOLDING & FORM WORKS
Php
3. CONCRETE WORKS
Php
4. REINFORCED STEEL WORKS
Php
5. MASONRY WORKS
Php
6. STEEL WORKS
Php
7. DRAINAGE INTERCONNECTION WORKS
8. DISINFECTION & LEAKAGE TEST
Php
9. PAINTING WORKS
Php
VI. CONSTRUCTION OF (2.56 SQ.M.) GUARD HOUSE
1. EXCAVATION WORKS
2. CONCRETE & REINFORCED STEEL WORKS
Php
3. MASONRY WORKS
Php
4. CARPENTRY WORKS
Php
5. GLASS WORKS (LUMP SUM)
6. STEEL WORKS (WINDOW GRILLES)
7. PLUMBING WORKS
8. WATERPROOFING WORKS (LUMP SUM)
9. PAINTING WORKS
IX. CONSTRUCTION OF (2.73 SQ. MTR.) CHLORINE ROOM
1. CONCRETE & REINFORCED STEEL WORKS
2. MASONRY WORKS
3. CARPENTRY WORKS
4. PAINTING WORKS
5. WATER PROOFING WORKS (LUMP SUM)
X. CONSTRUCTION OF (8.66 SQ. MTR.) MOTOR PUMP ROOM
1. CONCRETE & REINFORCED STEEL WORKS
2. MASONRY WORKS
3. CARPENTRY WORKS

28,600.00
17,960.00
20,000.00
29,972.00
110,040.00
20,000.00
30,176.00
43,472.00
5,209.00
1,268.00
52,787.00
81,175.00
109,177.00
37,670.00
53,590.00
Err:509
3,700.00

1.00
5.00
5.00
3.00
1.00

3.00

4.00
4.00
4.00
3.00
2.00
1.00
1.00

1.00
1.00
1.00

0.00
0.00
0.00
3,700.00
3,700.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,331.00
0.00
0.00
0.00
0.00
0.00
0.00
1,268.00
65,276.00
29,297.00
55,272.00
2,800.00
7,125.00
9,520.00
2,600.00
14,337.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

###
###
###
###
###
###
###
###
###

###

4. PLUMBING WORKS
5. GLASS WORKS (LUMP SUM)
6. STEEL WORKS (WINDOW GRILLES)
7. WATER PROOFING WORKS (LUMP SUM)
8. PAINTING WORKS
Err:509
Err:509
10. CONSTRUCTION OF SEPTIC VAULT (6.50 CU.M.)
VII. CONSTRUCTION OF 75 LN. MTR. PERIMETER FENCE
1. EXCAVATION/BACKFILLING WORKS
2. REINFORCED STEEL WORKS
3. CONCRETING WORKS (18.00 CU. M.)
4. SCAFFOLDING WORKS
5. MASONRY WORKS (134.00 SQ. M.)
6. STEEL WORKS
7. PAINTING WORKS
8. FABRICATION AND INSTALLATION OF PANAFLEX
VIII. PIPE LAYING WORKS (PIPE LAYING OF 125 LINEAR METER - 100MM DISTRIBUTION LINE &
IX. CONSTRUCTION OF 250MM RCCP DRAINAGE SYSTEM(L=125.0 Ln. Mtr.)
X. CONSTRUCTION OF CONCRETE DRIVE WAY
XI. LANDSCAPING WORKS
XII. ELECTRICAL WORKS

0.00
0.00
0.00
0.00
0.00
Err:509
50,193.00
22,876.00
177,179.00
129,338.00
57,561.00
135,280.00
225,733.00
51,645.00
29,179.00
364,294.00
191,214.00
118,121.00
184,600.00
870,005.00
0.00

XVIII. MECHANICAL WORKS


SUB-TOTAL
OVERHEAD EXPENSES
PRICE & PHYSICAL CONTINGENCIES
MISCELLANEOUS
CONTRACTOR'S PROFIT
VALUE ADDED TAX (12%)

TOTAL PROJECT COST


CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE

Err:509
Err:509
Err:509
Err:509
Err:509

###
###
###

Err:509
Err:509

273
E
E

Reviewed & Checke

Prepared by:

EDITO M. BAUTISTA, JR.


J.O. - Senior Engineer A (C.E.)
Planning & Development Section

MARIE C

Off
Planning &

Repu

ZAMBOANG

Pilar

ATION (PHASE 1)

Php

15.00

Php

30.00

Php

45.00

Php

60.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###

0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

# # # # # # #

###
#
#

273,788.26
Err:509
Err:509

Reviewed & Checked by:

###
#
#

12,570.72
Err:509
Err:509

###
#
#

14,559.84
Err:509
Err:509

13,316.64
Err:509
Err:509

Submitted by:

MARIE CLAIRE C. BONGO

MARLI P. ACOSTA - DE FIESTA

Officer-In-Charge
Planning & Development Section

Officer-In-Charge
Planning & Design Division

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar St., Zamboanga City

CALENDAR DAYS
Php

75.00

Php

90.00

Php

105.00 Php

120.00 Php

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###

###
###
###
###

###
###
###
###
###
###
###

###

###
###
###
###

# # # # # # # # # # # # # # # # # #
# # # # # # # #
# # # #
0
# # # # # # # # # # # # # # # # # #

0
# # # # # # # # # # # # # # # # # # # # # # # # # # # # #
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
# # # # # # # # # # # # # # # # # # # # # # # # # # # # #
# # # # # # # # # # # # # # # # # #
# # # # # # # # # # # # # # # # #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

##

# # # # # # #

# # # # #

# # # # # # # #

# # # # # # # #

# #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
#
#

###
#
#

11,132.16
Err:509
Err:509

###
#
#

11,536.11
Err:509
Err:509

Approved by:

###
###
#

12,184.29
Err:509
Err:509

###
###
###

92,705.84
Err:509
Err:509

Err:509
Err:509
Err:509

Recommending Approval for

CARLOS L. PEREZ, SR.


Officer-In-Charge
Engineering Department

Assistant Gene

135.00 Php

150.00

Php

165.00 Php

180.00 Php

195.00 Php

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

# # #

# # # #
# # # # # # #
# # # # # # # # # # #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###

##
###
###
###

#
# # # # # #

# # #
# #

# #
# # # # # # # # # #

# #
# # # # # #
#
# # # #

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
# # # # # # # # # # # # # # # # # # # # # # # # # # # #

###
###
###

r:509
r:509
r:509

###
###
###

Err:509
Err:509
Err:509

roval for Project Implementation:

ALEJO S. ROJAS, JR.

ant General Manager for Operations Group

###
###
###

Err:509
Err:509
Err:509

###
###
###

Err:509
Err:509
Err:509

###
###
###

710,644.58
Err:509
Err:509

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

Php

210.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

# #

419,194.95
Err:509
Err:509

Structure
1. Raft Foundation
25mm x 7.50m. Deform bars

Qty.

Unit

724 pcs.

Php

3.43

Remarks:
No Cutting

Item Description

I. EXCAVATION WORKVOLUME:

Qty.

Php 2.35

a. Laborers
### - Laborers

1.18

II. CONCRETE & REINFORCED STEEL WORKS


a.Materials:
1. Footing

Portland Cement
Sand
Gravel
Boulder
16mm dia x 6.0m DB
#16 G.I. Tie Wire

5.10
0.22
0.43
0.39
3.00
0.50

Php
Php
Php
Php
Php
Php

6.00
0.25
0.50
0.50
3.00
0.50

2.95
0.12
0.25
Php 8.00
Php 9.00
Php 1.00

Php
Php
Php
Php
Php
Php

3.00
0.13
0.25
8.00
9.00
1.00

2.71
0.11
0.23
Php 3.00
Php 2.00
Php 0.50

Php
Php
Php
Php
Php
Php

3.00
0.13
0.25
3.00
2.00
0.50

2.19
0.09
0.19
Php 4.00
Php 0.50

Php
Php
Php
Php
Php

3.00
0.22
0.25
4.00
0.50

1.81 Php
0.08 Php
0.15 Php

2.00
0.13
0.25

2. Column

Portland Cement
Sand
Gravel
16mm dia x 7.50m DB
10mm dia x 6.00m DB
#16 G.I. Tie Wire
3. WallFooting

Portland Cement
Sand
Gravel
12mm dia x 7.50m DB
10mm dia x 6.00m DB
#16 G.I. Tie Wire
4. Slab

Portland Cement
Sand
Gravel
10mm dia x 6.00m DB
#16 G.I. Tie Wire
5. Floor Lintel Beam

Portland Cement
Sand
Gravel

12mm dia x 7.50m DB


10mm dia x 6.00m DB
#16 G.I. Tie Wire

4.00 Php
Php 3.00 Php
Php 1.00 Php

4.00
3.00
1.00

6. Concrete Wings

Portland Cement
Sand
Gravel
12mm dia x 7.50m DB
10mm dia x 6.00m DB
#16 G.I. Tie Wire

4.00
0.17
0.34
2.00
Php20.00
Php 1.00

Php
Php
Php
Php
Php
Php

4.00
0.25
0.50
2.00
20.00
1.00

2.02
0.09
0.17
6.00
Php 5.00
Php 1.50

Php
Php
Php
Php
Php
Php

3.00
0.13
0.25
6.00
5.00
1.50

2.34
0.10
0.20
2.34
2.34
2.34
Php 1.00

Php
Php
Php
Php
Php
Php
Php

3.00
0.13
0.25
3.00
3.00
3.00
1.00

Php
Php
Php

8.00
8.00
8.00

7. Roof Beam

Portland Cement
Sand
Gravel
16mm dia x 7.50m DB
10mm dia x 6.00m DB
#16 G.I. Tie Wire
7. Roof Slab

Portland Cement
Sand
Gravel
Concrete Admix
Concrete Water Proofing Compound

10mm dia x 6.00m DB


#16 G.I. Tie Wire
b.Labor:

### - Mason
### - Steel Man
### - Contractual Laborers
III. MASONRY WORKS
1. CHB LAYING & PLASTERING WORKS

tiles?

a.Materials:

100mm x 200mm x 400mm CHB


150mm x 200mm x 400mm CHB
Portland Cement
Sand
Fine Sand (For Plastering)
10mm dia x 6.00m DB
#16 G.I. Tie Wire

Php
Php
Php
Php
Php
Php

350.00
36.00
28.00
1.50
0.50
22.00

b.Labor:

### - Mason
### - Contractual Laborers

Php
Php

10.00
10.00

IV. CARPENTRY WORKS


a. Materials:
4.1. Door Jambs:
### - pcs. -2" x 6" x 10' Mahogany Wood

20

4.2. Door Frames :


### - pcs. -2" x 4" x 10' Mahogany Wood
19mmThk. x 1.20m. x 2.40m. Plyboard

13
3

4.3. Window Jambs(W1, W2):


### pcs. -2" x 6" x 10' Mahogany Wood

50

4.4. Cabinet
6mm Thk x 1.20m x 2.40m Plywood
20mm Thk x 1.20m x 2.40m Plyboard
### - pcs. 1" x 1" x 10' Lauan Lumber

1
4.00

Php

4.5. Hardware
Loose Pin Hinges (Stanley) - 4" x 3"
Cabinet Hinges - 2" x 2"
Heavy Duty Door Knob
Drawer Lock (Yale)
Drawer Handle
Common Wire Nail 4"
Common Wire Nail 3"
Common Wire Nail 2-1/2"
Common Wire Nail 2"
Common Wire Nail 1"

2.50

4
6
1
3
3
8
6
4
2
2

b.Labor:

### - Carpenter
### - Contractual Laborers

Php
Php

10.00
10.00

V. GLASS WORKS
12 Blades Smoke Glass Jalousies
TOTAL DIRECT COST OF GLASS WORK
VI. STEEL WORKS (WINDOW GRILLES)
a. Materials:
10mm x 6.00m. Square bars

12mm x 6.00m. Square bars


6mm thk. x 20mm x 6.00m. Flat bars
Hack Saw Blade
6011 Welding Rod
b. Labors:
### -Welder
### -Contractual Laborers
TOTAL DIRECT COST OF STEEL WORKS (Window Grilles)
VII. PLUMBING WORKS
a. Materials:
PVC Sanitary Pipe 50mm x 3.00m. Series 1000
PVC Sanitary Elbow 90o x 100mm Series 1000
PVC Sanitary Elbow 90o x 50mm Series 1000
PVC Solvent Cement
Stainless Floor Drain 4" x 4"
b. Labors:
### - Plumber
### - Contractual Laborers
TOTAL DIRECT COST OF PLUMBING WORKS

VII. PAINTING WORKS


a. Materials:
Concrete neutralizer
Liquid tile primer
Liquid tile cast
Liquid tile top coat white gloss
Liquid tile reducer
Lacquer thinner
Easytite
Sand paper#150
Sand paper#120
Liquid tile tinting color Raw Sienna
Liquid tile tinting color Burnt Umber
Liquid tile tinting color Toluodine Red
Liquid tile tinting color Lamp Black
Roller Brush Tray
Roller Brush 7" w/ Handle
Steel Brush
Paint Brush 3"
Paint Brush 2"

3
2
4
4
4
4

6
4
2
4

1
1

1
2
2
4
2
2
1
1
1
2
2
2
2
1
1
1
1
2

b. Labors:
### - Painter
### - Contractual Laborers
TOTAL COST OF PAINTING WORKS

5
5

Unit

Unit Cost

days

Sub-Total

317.00

745.27

Total Cost

745.27

bags
cu.m.
cu.m.
cu.m.
pcs.
kgs.

Php
Php
Php
Php
Php
Php

230.00
900.00
900.00
850.00
450.00
60.00

Php
Php
Php
Php
Php
Php

1,380.00
225.00
450.00
425.00
1,350.00
30.00 Php

3,860.00

bags
cu.m.
cu.m.
pcs.
pcs.
kg.

Php
Php
Php
Php
Php
Php

230.00
900.00
900.00
950.00
165.00
60.00

Php
Php
Php
Php
Php
Php

690.00
112.50
225.00
7,600.00
1,485.00
60.00 Php

10,172.50

bags
cu.m.
cu.m.
pcs.
pcs.
kg.

Php
Php
Php
Php
Php
Php

230.00
900.00
900.00
950.00
165.00
60.00

Php
Php
Php
Php
Php
Php

690.00
112.50
225.00
2,850.00
330.00
30.00 Php

4,237.50

bags
cu.m.
cu.m.
pcs.
kg.

Php
Php
Php
Php
Php

230.00
900.00
900.00
165.00
60.00

Php
Php
Php
Php
Php

690.00
193.50
225.00
660.00
30.00 Php

1,798.50

bags
cu.m.
cu.m.

Php
Php
Php

230.00 Php
900.00 Php
900.00 Php

460.00
112.50
225.00

pcs.
pcs.
kg.

Php
Php

Php
165.00 Php
60.00 Php

495.00
60.00 Php

1,352.50

920.00
225.00
450.00
3,300.00
60.00 Php

4,955.00

bags
cu.m.
cu.m.
pcs.
pcs.
kg.

Php
Php
Php
Php
Php

230.00 Php
900.00 Php
900.00 Php
Php
165.00 Php
60.00 Php

bags
cu.m.
cu.m.
pcs.
pcs.
kg.

Php
Php
Php
Php
Php
Php

230.00
900.00
900.00
950.00
165.00
60.00

Php
Php
Php
Php
Php
Php

690.00
112.50
225.00
5,700.00
825.00
90.00 Php

7,642.50

bags
cu.m.
cu.m.
packs
packs
pcs.
kg.

Php
Php
Php
Php
Php
Php
Php

230.00
900.00
900.00
30.00
35.00
165.00
60.00

Php
Php
Php
Php
Php
Php
Php

690.00
112.50
225.00
90.00
105.00
495.00
60.00 Php

1,777.50

days
days
days

Php

366.00 Php

Php

317.00 Php

pcs.
pcs.
bags
cu.m.
cu.m.
pcs.
kgs.

Php
Php
Php
Php
Php
Php
Php

15.00
18.00
230.00
900.00
1,300.00
165.00
60.00

Php
Php
Php
Php
Php
Php
Php

2,928.00
10,144.00 Php

5,250.00
648.00
6,440.00
1,350.00
650.00
3,630.00
-

13,072.00

day
day

Php
Php

366.00 Php
317.00 Php

7,320.00
6,340.00

bd.ft.

58.00

1,160.00

1,160.00

bd.ft.
shts.

30.00
1,239.00

400.00
3,717.00

4,117.00

bd.ft.

58.00

2,900.00

2,900.00

shts.
shts.

bd.ft.

400.00
600.00
40.00

400.00
2,400.00
100.00

pcs.
pcs.
set
sets
pcs.
kgs.
kgs.
kgs.
kgs.
kgs.

140.00
60.00
680.00
56.00
30.00
50.00
52.00
51.00
51.00
56.00

560.00
360.00
680.00
168.00
90.00
400.00
312.00
204.00
102.00
112.00

days
days

Php
Php

366.00 Php
317.00 Php

3,660.00
6,340.00

sets

1,200.00

2,400.00

pcs.

180.00

180.00

2,988.00

10,000.00

2,400.00
2,400.00

pcs.
pcs.
pcs.
kgs

65.00
145.00

260.00
580.00

days
days

366.00
317.00

1,464.00
2,536.00

lghts.
pc.
lghts.
qrt.
pcs.

306.00
86.00
29.00
334.00
68.00

1,836.00
116.00
668.00
272.00

days
days

366.00
317.00

366.00
634.00

gal.
gals.
gals.
gals.
gals.
gals.
qrts.
doz.
doz.
pint.
pint.
pint.
pint.
pc.
set
pc.
pc.
pcs.

485.00
655.00
434.00
829.00
369.00
426.00
567.00
126.00
126.00
103.00
103.00
103.00
103.00
30.00
68.00
19.00
40.00
20.00

485.00
1,310.00
868.00
3,316.00
554.00
639.00
567.00
126.00
126.00
206.00
206.00
206.00
206.00
30.00
68.00
19.00
40.00
40.00

1,020.00

4,000.00
5,020.00

1,000.00
1,000.00

9,012.00

days
days

317.00
317.00

1,585.00
6,340.00

7,925.00
16,937.00

Water Stop

900/Can

10Lbs. Or 4 Litrs/can

plyboard not marine plywoood


Check number of jelousie
Check for tinting color

Concrete Pad, Plastered surface or not?

1:10 Sand

Ask sir ton about boulder on foundation


beam at chlorine room & Ope room not yet included

Where to Include Water Proofing Compound? Ask Master Primo Felix

94pcs

Length
1.05m

340pcs

.6m

Part of Structure
Column Ties of Sump Tank (4 Column)

overhead tank column

Soil Bearing Test from Soil Bearing Test Conducted at Fisheries

50KPa

###
###
###
###
###
###

Part of Structure
Column
Braces
Tie-Beam
Floor Beam
Wall
Footing & Soil

Volume
Php
38.12

Weight (KN)
Php 899.51

Php

899.51

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
Project

PROP. ZONE 4 BOOSTER STATION AT ZSCMST COMPD., RIO HONDO


(PILE DRIVE TEST FOR OVERHEAD TANK FOUNDATION)
ZSCMST Compound, Rio Hondo, Zamboanga City

Location
Scope of Work

:
:
A. NON-ENGINEERING BASIC COST
I. PERMIT FEE
II. PUBLIC SAFETY/SIGNAGES
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. CLEARING & LAYOUTING OF FOUNDATION
III. PREPARATION OF CRANE WAY
IV. EXCAVATION WORKS
V. PILE DRIVE TEST
VI. PREPARATION & DELIVERY OF PILE TEST REPORT
VII. DEMOBILIZATION

Cost of Project

450,121.33

A. NON-ENGINEERING BASIC COST


I. PERMIT FEE
1. ECC Requirement
1.1. Processing Fee
1.2. Support Fund
TOTAL COST OF PERMIT FEE
II. PUBLIC SAFETY/SIGNAGES
1. Signages
a. Materials:
### - Unit of 4' x 8' Tarpaulin (Project Signage)
### - pcs. 2" x 2" x 10' Coco Lumber
### - pcs. 2" x 3" x 10' Coco Lumber
3" C.W. Nail
4" C.W. Nail
b. Labor:
### - Skilled Worker
### - Laborer
TOTAL COST OF HEALTH & SAFETY
III. CONSTRUCTION OF TEMFACIL
a. Material:
### - pcs. 2" x 6" x 10' Coco Lumber
### - pcs. 2" x 4" x 10' Coco Lumber
### - pcs. 2" x 3" x 10' Coco Lumber
### - pcs. 2" x " x 10' Coco Lumber
12mm Thk x 1.20m x 2.40m Ordinary Plywood
4" C.W. Nail
3" C.W. Nail

1-1/" C.W. Nail


20ft. x 30ft. Tarpaulin
b. Labor:
### - Skilled Worker
### - Laborer
TOTAL COST OF CONSTRUCTION OF TEMFACIL
IV. SUPERVISION/MONITORING
a. Manpower:
### - Engineering Assistant
TOTAL COST OF SUPERVISION
TOTAL INDIRECT COST
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. CLEARING & LAYOUTING OF FOUNDATION
a. Materials:
### - pcs. 2" x 2" x 8' Coco Lumber

### - pcs. 2" x 3" x 8' Coco Lumber


3" C.W. Nail
4" C. W. Nail
Nylon #100
b. Equipment:
### - Power Saw
c. Labor:
### - Skilled Worker
### - Contructual Laborer
TOTAL COST OF CLEARING & LAYOUTING OF FOUNDATION

III. PREPARATION OF CRANE WAY


a. Equipment:
### - Power Saw
b. Labor:
### - Skilled Worker
### - Contructual Laborer
TOTAL COST OF PREPARATION OF CRANE WAY

IV. EXCAVATION WORKS


a. Labor:
### - Skilled Worker
### - Contructual Laborer
b. Equipment:
### - Unit Backhoe
### - Unit Payloader
### - Unit Dump Truck
TOTAL COST OF EXCAVATION WORKS
V. PILE DRIVE TEST
1. FABRICATION OF PRECAST CONCRETE PILE
1- Units of 300mm x 300mm x 6.00m Precast Concrete Starter Pile
3- Units of 300mm x 300mm x 6.00m Extension Precast Concrete Pile
a. Materials
Portland Cement (Type 1P)
Washed Sand
Gravel (G1)
Concrete Addmix (150g)
20mm x 6.00m. Deform bars (Grade 40)
16mm x 6.00m. Deform bars (Grade 40)
10mm x 6.00m. Deform bars (Grade 40)
#16 G.I. Tie Wire
32mm x 6.00m G.I. Pipe, Schedule 40
25mm Plain Round Bar (Grade 40)
Welding Rod (6011)
Fabricated 9mm Thk x 300mm x 300mm MS Steel Plate
### - pcs. 2" x 4" x 10' Coco Lumber

### - pcs. 2" x 3" x 10' Coco Lumber


### - pcs. 2" x 2" x 10' Coco Lumber
3" C.W. Nail
4" C.W. Nail
b. Laborer:
### - Skilled Worker
### - Contructual Laborer
2. PILE DRIVING WORKS
Lump Sum
TOTAL COST OF PILE DRIVE TEST
VI. PREPARATION & DELIVERY OF PILE TEST REPORT

VII. DEMOBILIZATION

SUMMARY
A. NON-ENGINEERING BASIC COST
I. PERMIT FEE
II. PUBLIC SAFETY/SIGNAGES
B. ENGINEERING BASIC COST
I. MOBILIZATION
II. CLEARING & LAYOUTING OF FOUNDATION
III. PREPARATION OF CRANE WAY
IV. EXCAVATION WORKS
V. PILE DRIVE TEST
VI. PREPARATION & DELIVERY OF PILE TEST REPORT
VII. DEMOBILIZATION
SUB-TOTAL
OVERHEAD EXPENSES
PRICE & PHYSICAL CONTINGENCIES
MISCELLANEOUS
CONTRACTOR'S PROFIT
VALUE ADDED TAX (12%)
TOTAL PROJECT COST

Prepared by:

EDITO M. BAUTISTA, JR.


JO- Senior Engineer A (C.E.)
Planning & Development Section

Approved by:

Reviewed & Checked by:

MARIE CLAIRE C. BONGO


Officer-In-Charge
Planning & Development Section

Certified as to Availability of Funds:

CARLOS L. PEREZ, SR.


Officer-In-Charge
Engineering Department

ROBERTO R. MENDOZA
Assistant General Manager for FAG

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

e Philippines
WATER DISTRICT
mboanga City

D., RIO HONDO

1
7
10
0.5
0.5

unit
bd.ft.
bd.ft.
kg.
kg.

1 day
1 day

100
133
100
67
6
4
3

bd.ft.
bd.ft.
bd.ft.
bd.ft.
shts.
kgs.
kgs.

4,000.00
9,600.00

4,000.00
9,600.00

1,200.00
20.00
20.00
60.00
60.00

1,200.00
133.33
200.00
30.00
30.00

366.00
317.00

366.00
634.00

20.00
20.00
20.00
20.00
700.00
60.00
60.00

2,000.00
2,666.67
2,000.00
1,333.33
4,200.00
240.00
180.00

13,600.00
13,600.00

1,593.33

1,000.00
2,593.33

2 kgs.
2 units

60.00
2,500.00

120.00
5,000.00

3 days
3 days

366.00
317.00

2,196.00
3,804.00

25 days

524.00

13,100.00

17,740.00

6,000.00
23,740.00

13,100.00
13,100.00

53,033.33

### lot

### bd.ft.

10,000.00

10,000.00

20.00

5,340.00

10,000.00
10,000.00

###
###
###
###

bd.ft.
kgs.
kgs.
roll

20.00
60.00
60.00
150.00

8,000.00
120.00
120.00
150.00

13,730.00

### days

2,000.00

12,000.00

12,000.00

### days
### days

366.00
317.00

4,392.00
19,020.00

### days

2,000.00

12,000.00

### days
### days

366.00
317.00

4,392.00
19,020.00

### day
### day

366.00
317.00

732.00
1,902.00

### day
### day
### day

10,400.00
10,400.00
9,000.00

10,400.00
10,400.00
9,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###

bags
cu.m.
cu.m.
packs
pcs.
pcs.
pcs.
kgs.
pc.
pc.
kgs.
units
bd.ft.

226.00
900.00
900.00
34.00
620.00
450.00
165.00
65.00
1,534.00
950.00
145.00
2,500.00
20.00

6,780.00
900.00
1,800.00
1,020.00
9,920.00
900.00
5,775.00
520.00
1,534.00
950.00
580.00
17,500.00
8,000.00

23,412.00
49,142.00

12,000.00

23,412.00
35,412.00

2,634.00

29,800.00
32,434.00

###
###
###
###

bd.ft.
bd.ft.
kgs.
kgs.

20.00
20.00
60.00
60.00

6,000.00
4,000.00
240.00
240.00

66,659.00

### days
### days

366.00
317.00

5,856.00
15,216.00

21,072.00

### ln.mtr

4,000.00

92,000.00

92,000.00
179,731.00

### lot

2,000.00

2,000.00

2,000.00
2,000.00

### lot

10,000.00

10,000.00

10,000.00
10,000.00

MARY

harge
pment Section

13,600.00
2,593.33
10,000.00
49,142.00
35,412.00
32,434.00
179,731.00
2,000.00
10,000.00
334,912.33
3,349.00
13,396.00
16,746.00
33,491.00
48,227.00
Php

450,121.33

Submitted by:

MARLI P. ACOSTA-DE FIESTA


Officer-In-Charge
Planning & Design Division

Recommending Approval for:

MENDOZA
anager for FAG

D. VASQUEZ
nager

ALEJO S. ROJAS, JR.


Assistant General Manager for Operations

PROJECT
Location
Project Cost
Project Duration
Manpower Requirements

A
:

R T
PROP. ZONE 4 BOOSTER STATION AT ZSCMST COMPD., RIO HO
(PILE DRIVE TEST FOR OVERHEAD TANK FOUNDATION)

:
:
:
:

ZSCMST Compound, Rio Hondo, Zamboanga City

Php

450,121.33

CALENDAR DAYS

MANPOWER ( 1- Project Engineer, 10-Laborers, 1- Mason, 1- Steelman/Welder & 1- Carpe

Particulars

no.
of
days

Amounts
Php

A. NON-ENGINEERING BASIC COST


13,600.00
2,593.33

I. PERMIT FEE
II. PUBLIC SAFETY/SIGNAGES

B. ENGINEERING BASIC COST


I. MOBILIZATION
II. CLEARING & LAYOUTING OF FOUNDATION
III. PREPARATION OF CRANE WAY
IV. EXCAVATION WORKS
V. PILE DRIVE TEST

1. FABRICATION OF PRECAST CONCRETE PILE


2. PILE DRIVING WORKS
VI. PREPARATION & DELIVERY OF PILE TEST REPORT
VII. DEMOBILIZATION

SUB-TOTAL
OVERHEAD EXPENSES

Php5.00
Php6.00

###
Php2.00
Php1.00
Php2.00

10,000.00
49,142.00
35,412.00
32,434.00
179,731.00
87,731.00
92,000.00
2,000.00
10,000.00
334,912.33
3,349.00

PRICE & PHYSICAL CONTINGENCIES


MISCELLANEOUS
CONTRACTOR'S PROFIT
VALUE ADDED TAX (12%)

Php 450,121.33

TOTAL PROJECT COST


CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE

Prepared By:

EDITO M. BAUTISTA, JR.


Senior Engineer A
Planning & Development Section

13,396.00
16,746.00
33,491.00
48,227.00

Php

Checked & Reviewed By:

Submitted By:

MARIE CLAIRE C. BONGO


Officer-In-Charge
Planning & Development Section

MARLI P. ACOST
Officer-In-Charge
Planning & Design

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar St., Zamboanga City

MPD., RIO HONDO


ATION)

n/Welder & 1- Carpenter)


CALENDAR DAYS
16.00

Php

Php

0.00%
0.00%

Submitted By:

Approved By:

MARLI P. ACOSTA - DE FIESTA


Officer-In-Charge
Planning & Design Division

CARLOS L. PEREZ, SR.


Officer-In-Charge

Engineering Department

Recommending Approval for

ALEJO S. ROJAS, J
Assistan General M

DAR DAYS
Php

32.00

Php

0.00%
0.00%

mmending Approval for Project Implementation:

ALEJO S. ROJAS, JR.


Assistan General Manager-Operations Group

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

You might also like