Professional Documents
Culture Documents
1
Online Box up
1.0
1.
Introduction
Online Boxups are carried out to rectify leakages from weld joints, valve
bodies / bonnets / glands, flanges or process lines by installing the boxup arrangement at the source of leakage to save production loss.
Installation of box up arrangement at heat treated / stress relieved
lines, valves or equipment (s) is limited and subject to the approval of
Sub SOC(M).
2.
I.
II.
III.
3.
4.
Depending upon the requirement and nature of leakage, one of the under
mentioned methods is used:-
-1-
7.
8.
9.
10. Sealant injection is continued using different injection points until the
inner space of clamp is completely filled and the leakage is removed.
11. Cap nuts with copper washers are provided on flange nuts, in case
leakage establishes a path through them.
12. If cap nuts / copper washers of proper size are not readily available then
nuts / bolts are seal welded.
Welding Box up
13. Box-up by welding pad / sleeve with nipple is employed to remove
leakages that can not be rectified by peening / welding.
14. Small pad, sleeve (in two halves) can be used to box-up, depending upon
the situation. Valve and nipple assembly is also required to drain / vent
the condensate / vapors. Material and thickness of pad / sleeve is always
in accordance with line specification and rating.
15. Inspection section measures the thickness at the area to be welded and
after comparing this with the actual thickness, size of the pad / sleeve is
selected so that it covers the whole affected area.
16. Welding procedure is provided by PTE(GM) / Inspection Sections.
17. After selecting the size, pad / sleeve is fabricated. Its contour is matched
with the contour of line / valve as far as possible. In case of heavy / high
pressure leakage, valve and nipple assembly is welded on the pad /
sleeve. The pad / sleeve assembly is placed on the line / valve body and
welded as per proper welding procedure.
18. In case of a valve, if the leakage through the body is not removed by
above described means, then valve is boxed up completely
19. Box up arrangement is designed by Project Engineering against a verbal
request from Maintenance.
20. Design is reviewed / discussed & approved by Sub SOC (M).
21. Fabrication and machine Shops fabricate the box up arrangement against
MWR initiated by Area Engineer (E/M). Area Engineer is responsible to
coordinate and follow up the job.
22. After fabrication, box up arrangement is installed in the area. Proper
procedure is used for welding.
TIME :-------------------AREA:------------------
INSP.
MECH.
-------
-------
-------
------
2.
Clamp/Sleeve design OK
-------
-------
3.
Type of sealant
-------
-------
o
o
Form - 2
Form - 4
o
o
Form - 3
Form - 5
4.
-------
-------
5.
-------
-------
FOR OPERATION
OPERATION
6.
-------
-------
7.
-------
-------
8.
(INSPECTION) (MAINTENANCE)
-------
-------
Chapter
2
Hot Tapping
Introduction
1. This procedure is used to get an off - take or branch connection
from a process line or a vessel which is in service.
2.
Hot Tapping is not allowed on lines containing flammable liquids / gases, below
atmospheric pressure or on lines containing a combustible mixture at any pressure.
3.
4.
5.
6.
7.
8.
to check / scan the thickness of line where nozzle for hot tap is to
be welded.
10. Welding of hot tapping nozzle on the line is the most critical step
from safety point of view. In order to do this safely, ensure that :I.
II.
III.
IV.
11. Ensure material, size and rating of nozzle is in accordance with line
specifications (length of nozzle is kept at minimum possible). Weld
the hot tapping nozzle on the line / vessel as per welding procedure.
12. The nozzle is accurately aligned with the flange face parallel to the
pipe axis with a diametric tolerance of 1/32 of an inch (0.795mm).
The center line of the nozzle accurately intersects the center - line
of the pipe longitudinally. For angled branch connections nozzle size
shall be at least one pipe size smaller than the main line size.
13. All the welds are full strength welds. If specified on the drawing, install
reinforcing pad.
Installation of Tapping Valve
14. Ensure that size, rating and material of valve is in accordance with
the line specifications.
15. The tapping valve to be used must provide a clean full-round opening
at least 3.20mm larger than the OD. of the specified cutter.
16. Install the valve using new gasket as per required specifications.
Before starting the actual hot tapping Operation, hot tapping check
list (Production / Mechanical / Inspection) CK-4.09-002-XX-346) and
Mechanical Check List For Hot Tap CK-4.09-001-XX-306 latest
revision are filled and signed by relevant sections. Operation Dept.
keeps the record of Check Lists in original and copy is retained by E/M
Section.
Tapping Operation
17. Install the tapping machine with proper adapter on the tapping
valve. The machine is adequately supported in order to prevent
over-stressing the hot tapping nozzle. The bleeder of the machine
CK-4.09-001-XX-306
CHECKPOINTS
YES
NO
REMARKS
------- ------2
------- ------3
4
------- -------
------- ------5
------- ------6
7
------- -------
Maximum
diametric
tolerance
------- -------
CK-4.09-001-01-306
Sr.
No.
CHECKPOINTS
YES
NO
REMARKS
___________
Date:
__________________
Name & Signature of
Technician
__________________
Signature of E/M Area
Engineer
CK-4.09-002-XX-306
10
Checked by
Production
Checked by
Maintenance
Verified by
Inspection
Yes / No
Yes / No
Yes / No
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
-------------- --------------
--------------
and
CK-4.09-002-XX-306
11
Checked by
Production
Checked by
Maintenance
Verified by
Inspection
Yes / No
Yes / No
Yes / No
-------------- --------------
--------------
Chapter
3
Exchanger Repair
1.
2.
3.
4.
5.
Install blinds /test rings and hook up leak test assembly to carry out leak
test.
6.
7.
8.
Tube Leakage
9. Arrange plugs in specific size and material.
10. Plug both ends of the leaking tube (s) using relevant procedure (s) welding or any other.
Tube - Tube Sheet Joint Leakage
11. If leakage is through tube to tube sheet joint of one or more tubes, first
grind strength welding all around the tube end up to the sound surface of
tube sheet with the help of pencil grinder and cutting burrs.
12. Inspection section identifies the leaking point.
13. Weld the ground portions according to the welding procedure provided.
Tube Sheet Ligament Crack Repair
14. If inspection / tests reveal that the crack (s) are in the tube sheet
ligament, first grind the tube sheet at crack location so that the crack is
completely removed. Manufacturer is also consulted if required.
15. Inspection section will carry out liquid penetrant test to ensure that
grinding to the sound metal has been achieved.
16. Clean the ground surface (use acetone for urea grade and titanium
material).
17. Weld the tube sheet ground portion according to welding procedure
provided for the purpose.
18. After repairing leakage points using above mentioned repair procedure
(s), Inspection section will again perform leak test to ensure that the
leakage has been removed.
19. Before boxup ensure that all the seating and sealing surfaces are clean
and free from scratches or other defects.
20. Clean studs/bolts and apply molykote or anti-seize on stud bolts.
21. Use new / reclaimed gaskets and place / fix them on their position.
22. Tighten stud / bolts according to standard tightening sequence and
torque. Any overlap of head covers/flanges should be checked and
corrected at this stage.
23. Remove isolation blinds and boxup nozzles using new/reclaimed gaskets.
Chapter
4
Exchanger Cleaning
H.P. Jetting
1.
2.
3.
4.
Hang and firmly fasten canvas sheet or tarpaulin in front of tube sheet to
restrict the water jet coming out from the other end of exchanger
5.
6.
7.
8.
Apart from normal personal protectives use face shield, and protection
suit while doing H.P. jetting.
9.
17. Before boxup ensure that all the seating and sealing surfaces are clean
and free from scratches or other defects.
18. Install head covers using new gaskets, clean stud bolts and appropriate
hoisting arrangement.
19. Tighten fixed tube sheet side before floating side in exchangers of
floating tube sheet design.
20. Check and correct any overlap of head cover / flanges before final
tightening.
21. Tighten studs/bolts according to standard tightening sequence and
torque.
22. Remove isolation blinds.
23. Check nozzle flange gasket facings are clean and scratch free.
24. Boxup nozzles, using new gaskets.
25. Remove scaffolding.
Chapter
5
Exchanger Cleaning - Mechanical
Mechanical Cleaning Of Heat Exchangers With Cooling Water On Shell
Side
1. Erect scaffolding at both sides of exchanger (if required).
2.
Remove stud bolts of cooling water side nozzles and tube side nozzles.
3.
Place studs / bolts and RJ gasket (if any) properly in a tray and arrange
their cleaning.
4.
5.
Place the exchanger between two dead ends and fix the rear side of
exchanger with one dead end.
6.
7.
Remove end/ head cover (s) by opening studs / blots using appropriate
tools and hoisting equipment.
8.
Attach pulling slings with tubesheet with the help of eyebolts screwed into
tube sheet.
9.
If the tubesheet does not have the tapped holes or they have been worn
out, a sling is passed through tubes. A bearing plate or wooden log is
placed under the slings on the tube sheet face (to avoid damage to tube
end.).
10. The tube bundle is pulled with wire jack, come along or chain block using
sliding support trolleys and placed on the ground for cleaning.
11. Clean the tube bundle thoroughly using scrapers, water jet etc. SS
scrapers are used for SS tube exchangers.
12. After the tube bundle is satisfactorily cleaned, place it on the sliding
saddle and align it with the shell.
13. Before inserting tube bundle back in the exchanger , check and ensure
the following:I.
II.
III.
It is properly supported.
IV.
The correct gasket between shell and bundle has been installed
before insertion of bundle, and gasket surfaces are clean.
14. Insert the tube bundle gently and carefully into the shell. Use two come
alongs or chain blocks in parallel.
15. Ensure equal force is applied on both the sides so that insertion of tube
bundle is parallel and it does not stick into the shell.
16. When the tube bundle reaches its position, install head cover (s). For
floating tube heat exchangers, always install fixed head side before
installation of floating side.
17. Ensure that:I.
II.
III.
IV.
18. Install studs / bolts. Ensure that proper tightening sequence and torque is
applied to the bolts using appropriate tools.
19. Prepare the exchanger for hydraulic test by installing pressure blinds on
tube side, hooking up hydraulic test assembly and hydraulic pump.
20. Production unit will pressurize the exchanger. Eqt. Maint. will assist by
operating the hydraulic pump.
21. Inspection section will carry out the hydraulic test.
22. If hydraulic test is satisfactory, proceed further , otherwise repair leakage
point as per Chapter 3
23. Remove pressure blinds.
24. Lift the exchanger from ground and place it on the saddle supports with
the help of appropriate hoisting tools.
25. Install and tighten saddle support nuts after aligning the exchangers with
inlet /outlet nozzle.
26. Boxup all nozzles using new gaskets (or reclaimed ones in case of good
RJ), clean stud bolts and after ensuring that all surfaces are clean and
free from damage.
FAUJI FERTILIZER CO. LTD
- 17 -
Chapter
6
Guide lines for working in
Confined Spaces
1.
2.
Arrange ladders (Rope, wooden or steel), cradles and other items for
entry/access to repair location if applicable.
3.
4.
5.
Use special safety harness & ensure 2nd life line for working in vertical
vessels having single entry on top, if required.
6.
II.
Purging/draining of vessel.
IV.
V.
VI.
7.
Obtain vessel entry and work permits as per work permit procedure
depending upon nature of job (i.e., Cold & Hot).
8.
Light oxy-acetylene torch outside the vessel and then send inside. Bring
torch outside after heating/Cutting. Do not leave extinguished oxyacetylene torch/Hose inside.
9.
10. Keep one person as watchman out side the manhole while work is in
Progress. (The numbers may be increased depending on nature and type
of job).
FAUJI FERTILIZER CO. LTD
- 19 -
Chapter
7
Removal and Reinstallation of
Control Valves and PSVs
1.
2.
Before removing PSV ensure that its vent line is properly supported.
3.
4.
5.
Open studs/ bolts and remove control valve / PSV using appropriate tools
and hoisting arrangement.
6.
7.
8.
9.
10. Install control Valve / PSV using new gaskets, clean stud bolts and
appropriate hoisting arrangement.
11. Check flange misalignment and overlap and correct if necessary.
12. Tighten studs/ Bolts using proper tightening sequence and torque.
Shifting of Control Valves / PSVs from field to instrument shop is the
responsibility of instrument engineer during normal plant operations. During
T/As and shutdowns of duration six days (prod. to prod.) or more it is the
responsibility of concerned Equipment Maintenance Engineer.
Chapter
8
Scaffold Erection
1.
Determine the size and strength of the scaffold to conform with the
required working space and expected working load.
2.
3.
4.
All the posts are in upright condition and all members (i.e. ties, bearers,
runners and bracing) are erected and fixed firmly.
5.
Where required the 1st bottom member (runner) is placed close to the
ground level and 2nd runner clears the man height.
6.
Tie up the scaffold with hand railings / permanent structure of the plant
(to enhance stability) where necessary.
7.
Provide planks on the working platform and tie up with binding wire or
with runners (i.e. horizontal pipes) and enclose the platform with safety
railings.
8.
Chapter
9
Maintenance of Level glasses
1.
2.
3.
4.
5.
6.
Check the condition of gasket, glass (s), mica sheet (if any) and seat of
body for erosion / corrosion.
7.
Is mica sheet, glass or gasket are damaged then replace with new one.
8.
9.
Assemble the level glass parts as per sequence given in the relevant
instruction manual.
10. Tighten the bolts in four steps at 20%, 40%, 75% and 100% of the given
torque value.
11. Use criss-cross tightening sequences starting from center to upper / lower
ends.
12. If after step # 4 there are pitting or erosion / corrosion marks on the
gasket facing remove flange bolts and shift the GLG to shop.
13. Remove the all glasses and send the body to Machine Shop for removal
of irregularities.
14. Repeat step # 7 to 10.
15. After assembling shift the level glass to site and install it at its location
with new gaskets.
16. Carryout hydraulic test of GLG if required.
17. Pre-heat the level gauge to eliminate the thermal stresses (if applicable).
Chapter
10
Hot insulation
1.
2.
Use the correct thickness of Rockwell for hot insulation depending upon
the size of piping and temperature of fluid being handled. For selecting
the Rockwell thickness Insulation Thickness table-I is used.
3.
4.
5.
6.
7.
8.
For stream traced SS lines pieces of asbestos sheet (3mm thk) are
placed between pipe and stream tracing line. For such lines 0.1mm
thickness aluminum foil is wrapped around the steam traced line before
applying the hot insulation.
TABLE-I
INSULATION THICKNESS
PERSONNEL
PROTECTION
HOT INSULATION
OPERATING TEMPERATURE
0
UPTO 151
150 200
201
250
251
300
301
350
351
400
401
450
451
500
501
550
401
500
UPTO
302
393
482
483
572
573
662
663
752
753
842
843
932
753
932
303
392
551
600
601
650
SIZE
INCH
1
30
30
30
30
40
40
50
50
60
60
60
70
30
30
30
30
30
30
40
40
50
50
60
60
70
70
70
30
30
30
30
30
40
40
50
50
60
60
70
80
80
90
30
30
30
30
40
40
50
50
60
60
70
80
80
90
90
30
30
40
30
40
50
50
60
70
70
80
90
90
100
110
30
30
40
40
40
50
60
70
70
80
90
90
100
110
120
30
30
50
10
40
50
60
60
70
80
90
90
100
110
120
130
30
40
50
12
40
50
60
70
70
80
90
100
110
120
120
130
30
40
50
14
40
50
60
70
80
90
90
100
110
120
130
140
40
40
50
16
40
50
60
70
80
90
100
110
110
120
130
140
40
40
50
18
50
60
60
70
80
90
100
110
120
130
140
150
40
40
50
20
50
60
70
80
80
90
100
110
120
130
140
150
40
50
50
22
50
60
70
80
90
100
110
120
130
140
150
160
40
50
50
24
50
60
70
80
90
100
110
120
130
140
150
160
40
50
50
26
50
60
70
80
90
100
110
120
130
140
150
160
40
50
50
28
50
60
70
80
90
100
110
120
130
140
160
170
40
50
50
30
50
60
70
80
90
110
120
130
140
150
160
170
40
50
50
32
50
60
70
90
100
110
120
130
140
150
160
170
40
50
50
34
50
60
70
90
100
110
120
130
140
150
160
170
40
50
50
36
50
60
70
90
100
110
120
130
140
150
170
180
40
50
50
EQUIP
50
60
80
90
100
110
120
130
140
150
170
180
40
50
50
INSULATION THICKNESS mm
Chapter
11
Cold Insulation
1.
2.
3.
4.
Apply two layers of vapor barrier mastic with fiber glass fabric
(glass gauge) in between the layers.
5.
TABLE-I
INSULATION THICKNESS
COLD INSULATION
OPERATING TEMPERATURE
0
+20
0
-1
20
-21
-40
-41
-60
-61
-80
-81
-100
-101
-120
-121
-140
-141
-160
-161
-180
+68
+32
+31
-4
-5
-40
-41
-76
-77
-112
-113
-148
-149
-184
-185
-220
-221 -257
-256 -292
SIZE
INCH
1
25
30
40
40
50
60
70
70
80
80
25
30
40
50
50
60
70
80
80
90
25
30
40
50
60
70
80
90
90
100
25
30
40
50
60
80
90
90
100
110
25
40
50
60
70
80
100
100
110
120
25
40
50
60
80
90
100
110
120
130
10
25
40
50
70
80
90
110
120
130
130
12
25
40
50
70
80
100
110
120
130
140
14
25
40
60
70
80
100
110
130
130
140
16
25
40
60
70
90
100
120
130
140
150
18
25
40
60
70
90
110
120
130
140
150
20
25
40
60
80
90
110
120
140
150
160
22
25
40
60
80
90
110
130
140
150
160
24
25
50
60
80
100
110
130
140
150
160
26
30
50
60
80
100
120
130
150
160
170
28
30
50
60
80
100
120
130
150
160
170
30
30
50
60
80
100
120
140
150
160
170
32
30
50
60
80
100
120
140
150
160
170
34
30
50
70
80
100
120
140
150
160
170
36
30
50
70
80
100
120
140
160
170
170
EQUIP
40
60
80
90
110
130
150
170
180
190
INSULATION THICKNESS mm
Chapter
12
Coating And Wrapping
1.
Following instructions are followed for the coating and wrapping of under
ground lines using polyethylene coated tapes :-
Surface Preparations
2. Remove welding slag, sludge, rust and hard scale from pipe surface
using grinder, power brush, scraper, emery, etc. Use detergent or
kerosene to remove oil and grease.
Primer Application
3. Immediately after surface cleaning apply a uniform coat of primer
(bitumen + thinner) which is free of drippings and holidays. Always apply
primer on dry and clean surface.
Tape Application
4. When the primer is dried-out, apply the wrapping tapes in the following
sequence :
i.
ii.
Use the correct tape size selected from the following table.
Nominal Pipe Size
12
14-20
>20
Tape Size
4-6
12
Tape Overlap
1/2
3/4
1 1/2
6.
7.
Visual check and holiday test to be carried out to ensure the coating
continuity by Inspection Section.
Chapter
13
Refractory Repair & Insulation
1.
2.
3.
4.
ii.
The panels are cured for 24 hours and hammer tested as per the
procedures given herein :-
a. The forms are disassembled and the panels used are crosssectioned (2-directions). There shall be no indications of voids,
laminations and honeycombs.
b. A section about 150mm square is cut from any one of the four cut
sections from each panel. These 150mm sections are then dried
for 18 hours at 1050C and weighed and measured to determine
density.
c. Three compressive strength and one linear change specimens are
cut from any one of the four cut sections of the panel. The
specimens are tested for compliance with the specified linear
change, and compressive strength.
FAUJI FERTILIZER CO. LTD
- 30 -
5.
Clean the shell surface before the castable installation. Install the
new anchors and coat them with bitumen mastic. Use clean tools
for casting.
6.
Ensure that forms / shuttering is rigid and well braced. Nonabsorbent materials such as ply-wool, steel, plastics, etc are used
for shuttering. Forms are made sufficiently tight and water proof to
prevent leakage. The surfaces in contact with concrete are uniform,
smooth and well oiled. Forms are constructed / assembled so as to
facilitate their removal without damage to the concrete.
7.
8.
9.
- 31 -
Chapter
14
Painting
PAINT:
This may be defined as any liquid material containing drying oils alone or in
combination with natural resins and pigments which when applied to a
suitable substrate, will combine with oxygen from the air to form a solid,
continuous film over a substrate. This provides a weather resistant decorative
surface. This also prevents corrosion or disintegration of the structure by the
environment.
Following general instructions are followed for various painting jobs.
Surface preparation:
All foreign matter having potential of negatively effecting paint adhesion and
painting result like grease, oil, petroleum, mill scale, old loose paint and other
substances are removed by using coarse cloth, emery paper, power brush or
sandblasting.
Primer application:
Application of specified thickness of primer on various steel surface
(structure, vessels, pipe etc.) is carried out according to manufacturers
specification. Dry film thickness should be checked. Primer may be applied
by brush and spray gun. Number of coats to be applied is determined by total
dry film thickness required as per recommendation of the manufacturer.
Paint application:
Application of specified thickness of paint on various steel surface (structure,
vessels, pipe etc.) is carried out according to manufacturers specification. Dry
film thickness should be checked. Paint may be applied by brush and spray
gun. Number of coats to be applied is determined by total dry film thickness
required as per recommendation the of manufacturer.
INSPECTION AND TESTING
The following inspection and testing shall be performed during and after
completion of application of paint system.
a)
- 32 -
b)
c)
d)
DEFECTS
If, during above inspections, painting or surface preparation defects are
observed, the job shall be redone to meet acceptable standards.
COLOUR
Colours for structure, Equipment, lines etc. of various services are selected
according to the Annex.I.
SURFACES NOT TO BE PAINTED
The following surfaces shall not be painted, except if specifically asked.
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
Concrete surfaces
Masonary surfaces
Aluminum surfaces
Galvanized steel surfaces
Stainless steel surfaces
Monel surfaces
Copper surfaces
Brass surfaces
Glasses of level gauges
Equipment nameplates
Piping and equipment to be insulated
Surfaces with concrete fireproofing
- 33 -
Annex.I
S.NO.
01
02
03
04
05
06
07
08
09
10
EQUIPMENT/LINE
Surface of uninsulated piping and
equipment
with
an
operating
temperature upto 70 oC.
(Fire fighting excluded)
Surface of uninsulated piping and
equipment
with
an
operating
temperature over 70 oC.
Piping and equipment for fire
fighting
Natural Gas Line
Uninsulated machinery with an
operating temperature upto 70 oC.
Uninsulated machinery with an
operating temperature upto 70 oC
Structural steel, pipe supports
Ladders,
stairways,
walkways,
handrails
Furnaces
Tanks
- 34 -
COLOUR
GRAY
CODE
RAL-7035
ALUMINUM
RAL-9006
RED
RAL-3002
YELLOW
GRAY
RAL-1016
RAL 7035
ALUMINUM
RAL-9006
GRAY
YELLOW
RAL-7010
RAL-1016
GREEN
GRAY
RAL-6021
RAL-7035
- 35 -