TITLE OF SOP

WORK INSTRUCTIONS FOR THE CALIBRATION OF ABSOLUTE PRESSURE


TRANSMITTER

CHANGE RECORD

Issue
Date
No.

1.0

Change Description

Prepared by

Reviewed by

Name/
Sign
Designation Date

Name/
Sign
Designation Date

Approved by
Name/
Designation

Sign
Date

PURPOSE:

The purpose of this work instruction is to describe the calibration of Absolute Pressure Transmitter
which is done to ensure accurate measurement of Absolute Pressure and generation of electronic
signal proportional to Absolute pressure

TITLE OF SOP

2.0

SCOPE:
This procedure is applicable for all instruments directly affecting the
production/dispatches of Ammonia/Urea

3.0

DEFINITIONS:
Write down definition of terms used in this SOP

4.0

RESPONSIBILITIES:

Unit Manager (Instrument) will ensure that calibration procedure is established per standard
practice which is as under

5.0

6.0

REQUIREMENT OF ENVIRONMENT, HEALTH AND SAFETY STANDARD:


5.1

Environment:

5.2

Health:

5.3

Safety:

PROCEDURE
3.1

Data sheet of pressure transmitter

3.2

Preparations

3.3

Calibration

3.4

Documentation & record

3.1

Data Sheet of pressure transmitter


Pressure

------------------------

Temperature

------------------------

Density

------------------------

Measuring Range

6.2

------------------------

Output signal

4 ~ 20 mA DC

Loop Code

Logic, Control or Indication

Preparations
3.2.1 Obtain permit to work and put the loop on Manual Control in CCR.
3.2.2 Isolate and depressurize the transmitter then remove it from line.
3.2.3 Arrange 24Volt DC supply, communicator & multimeter

TITLE OF SOP

3.2.4 Ensure that all equipment is in good working condition.

3.3

Calibration
3.3.1 Make connections as shown in diagram.
3.3.2 Enter zero adjustment modes, enter zero value & set 4mA.
3.3.3 Save the zero calibration and escape mode.
3.3.4 Enter re-arrange mode and feed the required Lower Range Value (LRV)
and Upper Range Value (URV).
3.3.5 Save data and escape mode.
3.3.6 Enter mA calibration mode and set out put at 4mA for corresponding
LRV.
3.3.7

Then set 20 mA for corresponding URV & save calibration data.

3.3.8 Enter different pressure readings & check corresponding mA out put.

24 VDC supply

250

Multimeter

Transmitter

Communicator

3.4.

Document &Record
Enter the observations of section 3.3 in the following table.

TITLE OF SOP

CALIBRATION SHEET FOR ABSOLUTE PRESSURE TRANSMITTOR

Manufacturer:
Model No:

Tag No:
Calibration Range:
Calibration Date:
Transmitter output
(mA DC)

Input Pressure
Sr. No.

(Kg/cm
)

1
2
3
4
5
6
7
8
9

(%)

Standard

0
25
50
75
100
75
50
25
0

4
8
12
16
20
16
12
8
4

Deviatio
n

Measured

Obsevations / Remarks.

7.0

PRECAUTIONARY STEPS

8.0

RELATED DOCUMENTATION

9.0

REFERENCES:
-

Quality System procedure for Engineering. QSP-02-0


Quality System Procedure job Laboratory. QSP-03-1