You are on page 1of 6

FOR A BETTER BUILT ENVIRONMENT

ZUBER AHMED
E-mail id
zuber@aswatheswara.co.in, zuber.dce85@gmail.com
Permanent Address H.No.738, Mandi, Railway Road, Pilkhuwa,
District Hapur (U.P.) INDIA - 245304.
Mobile No.
+91-9741391757(KA), +91-9911935757(DEL)

OBJECTIVE:
To perform in a challenging key position in a growing organization with an environment, where
my skills, knowledge and efforts will be rewarded with career advancement.

Core Competencies & Strengths:


Capable of Project Management, Planning & Control Systems and Management
Information System. Awareness of financial side of the Project Operations.
Have Versatility in divergent Project areas such as Execution, Planning, Costing &
Budgeting.
Possess Analytical skills & Technical knowledge to handle day to day operations and
make decisions.
Capable to energize the team for common goals, lead a group of sub-ordinates with
direction, association and delegation and actively participate in team building events.
Can control the Operations/Process with task oriented approach.
Presentation skills in progress review meetings with customers to demonstrate plans
and progress and quarterly review meetings with higher management to present project
performance.
Have excellent communication skills Making correspondence with clients/vendors,
convene meetings with sub-ordinates and sub-contractors to communicate strategies,
plans and review.
Espousing organizational values such as customer satisfaction, quality, safety, etc.
1

VALUE & NATURE OF PROJECTS

| ZUBER AHMED

FOR A BETTER BUILT ENVIRONMENT

PROFILE:
Working with Aswathanarayana & Eswara since January, 2012 to till date for
Construction and development in all facets of industrial building projects.
Experience of preconstruction to final handover of the project of varied nature viz.
Commercial Construction, Industrial Building, etc.
Proven track record of lead role in independently handling the projects - Achievement of
objective / deliverables with regards to time schedules, cost, safety, quality and
customer satisfaction.
Building positive rapport with clients, designers, vendors, consultants, inspectors,
Government Officials.
Pre-Construction Phase Have experience in Project Visualization, Planning &
Scheduling, Construction Methodologies, Accepted Cost Estimate, Financial Budgeting,
etc.
Construction Phase Experienced in Organizing, Resource Mobilization, Procurement,
Sub-contractor & Vendor Management, Co-ordination of agencies, Shop drawings and
method statements, Co-ordinate drawings, Effective resource utilization, Project
Monitoring and Controlling, Performance Report, Corrective and preventive measures,
Follow-up of contractual circumstances, Cost effective and value added measures,
Notification of claims and variations, Timely Invoicing.
Project Close-Out Have carried out project close-out activities viz. Demobilization, As
built documentation, Handover to Customer Satisfaction, Settlement of Variations,
Claims and Support in making Final Accounts, Project Report with Photos.
Implementation of Systems Awareness and capability of implementing Management,
planning & control systems, Management Information Systems, Budgeting Systems,
Quality Management System.
Construction Management of Civil & Architectural works in Industrial Buildings.
External works Area Development, Roads, Pavements, Landscaping works, etc.
Coordination for interfacing Mechanical & Electrical Services HVAC System, Force
Ventilation System, Electrical Power, Fire Detection System, Fire Fighting System,
Communication System, Instrumentation Equipment Erection, UG Piping, etc.
Working with companies of good reputation like Redington India Limited (Village
Gaaland, Ghaziabad), American Axle Manufacturing (Village Supa, Ahmednagar) and
currently with Gulbarga Textiles Park Pvt. Ltd. (Village Nandur Kesaratgi, Gulbarga)

VALUE & NATURE OF PROJECTS

| ZUBER AHMED

FOR A BETTER BUILT ENVIRONMENT

Computer Skills:
MS Office

Good

Enterprises Resources Planning

Medium

AutoCAD

Medium

Microsoft Project

Medium

Primavera

Learner

Construction Software (RESIST)

Learner

3D Home Architect

Learner

LIST OF PROJECTS HANDLED JANUARY, 2012 TO TILL DATE:


OCT 2013 TO NOV 2013 & AUG 2014 TO TILL DATE(Eleven Months)
Name Of The Project

Gulbarga Textile Park Pvt. Ltd.(INDUSTRIAL TEXTILE)

Client

GTPPL/SPV/IL&FS Clusters

Designation

Senior Project Manager

Architect

Aswathanarayana & Eswara LLP

PMC

Aswathanarayana & Eswara LLP

Contractor

NS MULGE Contractors

Location of Posting

Plot No.40 to 48 & 70 Part


Nandur Kesaratgi Industrial Area, Gulbarga

Job/Work Awarded

Site Grading, Construction of Roads, Culverts,


Compound Walls, Borewells and Storm Water Drainage.

Nature of Job

Execution, Co-ordination, Checking Contractors Bills,


Maintaining Weekly Reports, BOQ, Specifications,
Planning, Costing, Budgeting, Timely Invoicing,
Monitoring & Controlling, Tendering & Awarding, etc.

Project Value

Rs.100 Million.

Project Type

Item Rate Contract.

VALUE & NATURE OF PROJECTS

| ZUBER AHMED

FOR A BETTER BUILT ENVIRONMENT

NOV 2013 TO JULY 2014 (Eight Months)


Name Of The Project

AAM PMF EXPANSION/RENOVATION WORK


(INDUSTRIAL MANUFACTURING FACTORY)

Client

AAM INDIA ASIA CORPORATION

Designation

Senior Project Manager

Architect

Aswathanarayana & Eswara LLP

PMC

Aswathanarayana & Eswara LLP

Contractors/Vendors

Zamil Steel/ SS Design/ Tuljai Associates/ WIPRO/


BPERGO/ Universal Electricals/ Globe Gas Pvt. Ltd./
Green Finger Landscapes/ Crystal Ventilations

Location of Posting

Gat No. 787 & 788, Village Hunga , Taluka Parner,


District Ahmednagar, Maharashtra 414301

Nature of Job

Execution, Co-Ordination, Checking Contractors Bills,


Maintaining Daily-Weekly-Monthly Reports, BOQ,
Specifications, Comparison Statement, Planning &
Scheduling, Construction Methodologies, Accepted Cost
Estimate, Sub-contractor & Vendor Management,
Co-ordination of agencies, Shop drawings and method
Statements, Co-ordinate drawings, Effective resource
utilization, Project Monitoring and Controlling,
Performance Report, Corrective and preventive
measures, Follow-up of contractual circumstances,
Cost effective and value added measures, Notification
of claims and variations, Timely Invoicing, Project closeout like Demobilization, As built Documentation,
Handover to Customer Satisfaction, Settlement of
Variations, Claims and Support in making Final
Accounts, Area Development, Landscaping works,
HVAC System, Force Ventilation, System, Equipment
Erection, Electrical Power, Fire Detection System,
Fire Fighting System, Communication System,
UG Piping, Finally project report of the same.

Project Value

Rs.35 Million

Project type

Item Rate Contract.

VALUE & NATURE OF PROJECTS

| ZUBER AHMED

FOR A BETTER BUILT ENVIRONMENT

JAN 2012 TO OCT 2013(Twenty Two Months)


Name Of The Project

Compound Wall Construction, RIL ADC, Delhi


(INDUSTRIAL WAREHOUSE)

Client

Redington India Limited

Designation

Senior Project Manager

Architect

Aswathanarayana & Eswara LLP

PMC

Aswathanarayana & Eswara LLP

Contractor

Syringa Engineers Pvt. Ltd./VASCON Engineers Ltd.

Location of Posting

RIL ADC, Village Gaaland, Reliance Road,


Pargana Dasna, District Ghaziabad (U.P.) - 201302

Nature of Job

Execution, Checking Contractors Bills, Checking DailyWeekly-Monthly Reports, Comparison Statement,


BOQ, Specifications, Co-ordination, Construction
Methodologies, Planninng & Scheduling, Accepted Cost
Estimate, Vendor Management, Shop Drawings &
Method Statement, Performance Report, Project
Monitoring & Controlling, Timely Invoicing,
Follow-up of contractual circumstances, Notification of
claims and variations, Cost effective and value added
measures, Project close- out like Demobilization, As
built Documentation, Handover to Customer
Satisfaction, Settlement of Variations, Claims and
Support in making Final Accounts, Finally making project
completion report of the same.

Project Value

Rs.15 Million.

Project Type

Item Rate Contract.

VALUE & NATURE OF PROJECTS

| ZUBER AHMED

FOR A BETTER BUILT ENVIRONMENT

Personal Details:
Fathers Name

Mr. Iqbal Ahmed

Date Of Birth

18th May,1985

Languages

Hindi, English, Urdu, Arabic, Kannada(Beginner)

Nationality

Indian

Marital Status

Married

Date: 13th May,2015


Place: Gulbarga, INDIA

VALUE & NATURE OF PROJECTS

(Zuber Ahmed)

| ZUBER AHMED

You might also like