Toolbox4Planning
Where Planning Resources and Techniques are
Home
About
Download
Tutorials
E-mail Adress:
ARCHIVES
INDEX
Baseline
Constraint Date
Construction Planning
Construction schedule
EPC planning
Project Plan
Template
1
Share
32
Excel Tutorial
Lookahead Schedule
Maintenance Planning
Maintenance schedule
Planner's Resources
Primavera P6
Primavera P6 Tutorial
Primavera Tutorial
Progress Calculation/Measurement
Sample Layout
Sample WBS
Sample Work Activity
Schedule Control
schedule design
Schedule development
Schedule Options
Schedule Report
The following steps should be taken when the progress curve is updated.
1. Update actual physical progress for each activity or deliverables
2. Calculate percent completion
Tank Construction
Normally in an EPC project, Engineering, Procurement and Construction Progress Curve and Overall progress
curve are produced and used to monitor the project performance. The three WBS element ( Engineering,
Procurement and Construction ) are WBS level 1. Overall is a project level WBS called level 0.
Assume that a project scope includes design, procurement and construction of pump station and additonal
pipelines for a refinery plant.
According to that project scope, the following documents could be produced for engineering stage.
1. Basic Engineering Data
2. P&ID drawings
3. Line list
4. Piping MTO list
5. Piping GA drawings
6. Pump GA drawings
7. Mechanical Seal drawing
8. Structure GA drawings
9. Pump Foundation drawings
10. Electrial drawings
11. Instrument drawings
12. Construction Requisition and so on
POPULAR POSTS
How to Get Resource Loading Histogram/S
Curve in Primavera P6
Develop engineering schedule based on the agreed deliverable list. Assign the planned man hour on each activity
to be produced engineering documents. Suppose the total man hour to be spent for engineering is 11,500 hrs and
the schedule is 6 month. Engineering planned percent complete can be calculated by dividing man hour
distribution over time line and total engineering man hour. Man hour distribution would be different according to
work load.
Example; man hour distribution over the time line is as follows;
50 hrs (in 1st week), 100 hrs (in 2nd week), 150 hrs (in 3rd week) and so on.
Therefore percent complete for 1st week ; 50/11,500= 0.4%
2nd week; 100/11,500=0.9%
3rd week; 150/11,500=1.3%
-----
16-05-2015 09:39
2 of 3
http://www.toolboxforplanning.com/2010/12/working-with-progress-s-...
----Final week; 120/11,500=1% and percent complete for total weeks should be 100%.
Then, progress s-curve can be produced using charting tool in excel. See creating progress S-curve
When the actual work is started, the actual progress data should be calculated. Update the physical percent
complete on each activity/step for each document. Multiply document progress and document weightage. Finally,
total percent complete can be calculated by doing sum-up the weightage progress for each document.
Project Engineering
Project Resource Planning
Project Report
Ads by Google
Construction Contract
Earned Value Formula
Project Resource Planning
Find us on Facebook
Toolbox4Planning
Like
FOLLOWERS
4. Calculate the percent complete by dividing the distributed hour over the time line and the total construction
hours ( man hour and equipment hour) . The distributed hours would be different depending on work load in
a time frame. Assume the total construction hour is 160,000 and schedule is one and half years.
Example; planned hour over the time line is as follows;
4,000 hrs (in 1st week), 4,500 hrs (in 2nd week), 5,000 hrs (in 3rd week) and so on.
Therefore percent complete for 1st week ; 4,000/160,000 =2.5%
2nd week; 4,500/160,000 =2.8%
3rd week; 5,000/160,000 =3.1%
The accumulated percent complete up to three week is 8.4 percent. Then the percent complete by the end of the
project is 100%.
Update the physical construction progress when the actual work is started. Update the actual percent complete on
each work step for each activity.Multiply the physical progress of each activity and its weightage (activity hour/total
construction hour) . Finally, total percent complete can be calculated by doing sum-up the weightage progress for
each activity.
WELCOME
Hi, my name is Min Oo. Thank you for visiting my site and
welcome to my blog. I have been working in different roles
in projects, maintenance planning & scheduling and
engineering in the oil & gas and petrochemical industry
over the last 12 years. The greatest value of
Toolbox4Planning is sharing ideas, tool & techniques and
best practices that can be applied in industries involved in
engineering, construction, manufacturing, maintenance and
research. You can find tutorials and templates related to
planning & scheduling and project control at
Toolbox4Planning which would help you improve your
planning knowledge and skills. Grab a cup of your favourite
beverage, browse the blog, share your thoughts / leave
comments. Email: admin@toolboxforplanning.com
The overall progress data (planned and actual) can be calculated as follows;
1. Calculate Engineering , Procurment and Construction cost
2. Calculate relative weightage for Engineering, Procurement and Construction. example; for engineering
weightage - total engineering cost/total project cost
3. Get engineering weightage progress by multiplying engineering physical progress and engineering
weightage
4. Get procurement weightage progress by multiplying procurement physical progress and procurement
weightage
5. Get construction weightage progress by multiplying construction physical progress and construction
weightage
6. Sum-up all weightage progress (EPC)
Then, use the charting tool in excel to produce progress curve. See creating progress s-curve.
Progress
Calculation
Procedure for
Developing