You are on page 1of 29

UNESCO-NIGERIA TECHNICAL &

VOCATIONAL EDUCATION
REVITALISATION PROJECT-PHASE II

NATIONAL DIPLOMA IN
BUILDING TECHNOLOGY

BUILDING SCIENCE AND


PROPERTIES OF MATERIALS II
COURSE CODE: BLD102
YEAR I- SE MESTER II
PRACTICAL
Version 1: December 2008

TABLE OF CONTENT
WEEK 1
Electrical Effects: Electro- Dynamic Effects
Experiment
WEEK 2
Clay Brick
WEEK 3
Hand - Made Bricks
WEEK 4
Pressed Bricks Experiment
WEEK 5
Determination of Crushing Strength of Bricks
Week 6
Strength Tests on Limes
WEEK 7
Effect of Grading of Aggregate on the Properties Of
Concrete
WEEK 8
Slump Test
WEEK 9
Compacting factor test

WEEK 10
V.B Consistometer test
WEEK 11
Determination of the Strength of Concrete
WEEK 12
Soundness of Cement Test
Week 13
Field Setting Test to Determine Silt Content
WEEK 14
Soundness of Cement Test
Week 15
Students Excursion

WEEK 1
ELECTRICAL EFFECTS: ELETRO- DYNAMIC EFFECTS ;EXPERIMENT
Electric currents and magnetic fields have important mutual effects.
.If an electric current is passed through a wire that is situated in a magnetic field
as shown in the figure below in {a}

Figure

Force on a conductor in a Magnetic Field

.The wire tends to move, in the direction motion cutting the lines as shown above
in {b} it is on this effect that the operation of an electric motor depends. Both
explained the principle of electric motor.
.If a current is passed through a coil of wire suspended in a magnetic field as
shown at {a}, the action on each side of the coil is to cause rotational in the
direction shown.
.when the coil passed the vertical position {b}, a change in the direction of the
current is necessary if rotation is to continue in the same direction.

.If a conductor is moved across the line of force in a magnetic field, a current will
be generated in it. The direction of movement of conductor and the current flow
as shown in figure below explained the Principle of the Dynamo, the machine by
which electricity is mostly generated.
Details of the principle are illustrated below;

Figure

Dynamo principle

For the direction of rotation shown at {a} current will flow in the coil as shown ;
as the coil approaches the vertical position{b}, the current dies away because, in
the position, the conductors are not cutting the line of force , but are running
parallel to them. In position {c} the direction of flow is revered, and is at its
maximum with the coil in the horizontal direction, dying away to zero in
position {d} .this type of output is known as alternating Current.

WEEK 2 Clay Brick


Procedure:
In manufacturing of clay bricks, it is usual first to grind the clay with water
to reduce it to the required plasticity for molding. Sometimes two or more
types of clays are mixed in order to produce a more suitable material. The
plastic clay is then molded into bricks, which are dried and then burned at
a high temperature (about 850 1,1000c) in kilns. The burning process
hardens the clay and gives the bricks the strength and durability required.

WEEK 3
Hand - Made Bricks:
Bricks are moulded by hand from clay which contains sufficient
water to render it thoroughly plastic, and the finished product
usually has a high porosity (about 28 - 35 percent). Their
durability is, however, quite satisfactory except where
temperature of burning are not high enough. Under - burned
bricks may be recognized by their lightness in colour and lack
of ring when stucks, and should not be used for building
work. Hand made bricks are usually sand faced, since the
moulds are dusted with sand to prevent the clay sticking. This
gives to the bricks a surface texture which contributes greatly to
their good appearance.

WEEK 4
Pressed Bricks Experiment

Plastic type: The strongest of all clay bricks are made by


moulding under high pressure. Porosities as low as 8 percent
may be obtained by this means, and the bricks are afterward
burned at a temperature sufficiently high to give them a
vitreous surface.

Semi - Dry or Semi Plastic type: Bricks are also moulded by


repeated pressing of clay containing minimum water content.
High moulding pressures are generally used but high density is
not always achieved. In fact, English example of this type of
brick frequently have porosities greater than 25 per cent,
though this may be due to the nature of the clays used rather
than to the process itself. The low moisture content allows
considerable economies to be achieved in burning, and also
much reduces volume and shape change during burning;
semi-dry bricks are notable for their regularity of size and
shape.

WEEk 5
Determination of Crushing Strength of Bricks
Procedure;
Three whole bricks should be selectee from each batch to be tested
and the overall dimensions of each bed face (see Fig. Week5) of
each brick measured to the nearest 300mm. The area of the face
having the smaller area is taken as the area of the brick for
calculating the compressive strength.

Bricks without frogs are immersed in water for three days before
testing.

Bed Face

Figure Week5

Bricks with frogs are immersed in water for twenty-four hours. They
are then removed from the water, allowed to drain for about five
minutes, wiped free from surplus moisture, and their frogs filled
with mortar composed of 1 part by weight of Portland cement to 1

parts of sand. The bricks are stored under the damp sacks for twentyfour hours and afterwards in water until tested seven days after the
frogs have been filled.
The bricks are crushed between sheets of 3-ply wood 3mm thick.

A very large-capacity testing machine is necessary to crush whole


bricks of the stronger types. If the capacity of the machine available is
limited to 100 tons or to a lower value, the strengths of bricks may be
compared by tests on quarter-bricks, the frogs being filled as required
for whole bricks. The strengths obtained will be lower than if whole
bricks were tested.

The strength of bricks is dependent mainly on method of molding


and on burning temperature, high strengths being associated with
low porosity and high burning temperatures.

WEEK6 STRENGTH TESTS ON LIMES


Mix 300 gram. of hydrated lime with 195ml

of water for five

minutes. Mix the putty thoroughly with 900 gram of standard cement
testing sand, and fill six 4 in x 1-in 1-in moulds. The moulds should
be filled by pressing with the thumbs and smoothed off with a palate
knife. The specimens are stored in moulds in moist air in a slightly
warmed oven (250c) for twenty eight days. They are then removed
from moulds and stored in water half an hour before being tested
transversely on a 3-in span.
This experiment may be carried out using hydrated limes of the
following types
a.

non hydraulic

b.

semi hydraulic

c.

hydraulic and

d.

75 per cent. Non hydraulic lime: 25 per cent Portland cement

e.

Portland cement. The quantity of water used may have to be


varied to suit the requirements of different materials

WEEK 7 EXPERIMENT; EFFECT OF GRADING OF AGGREGATE ON THE


PROPERTIES OF CONCRETE
Mixes are prepared consisting in each case of 1 part (by weight) of cement and 6
parts aggregate. (48.5kg of cement and 20.1kg) of aggregate give a quantity
soluble for making one 4 in cube. In different mixes, the proportions of fine and
coarse aggregate are varied, in table 11 are given mixes whose proportion
provide
Table 11
Proportions by weight
Mix

Cement

Sand

Gravel

A suitable range for observation of the effects of grading of aggregate on the


properties of concrete. Each mix is gauged with sufficient water to produce a
plastic, workable mix, an attempt being made to produce mixes of comparable

workability. The amount of water required for each mix is carefully noted and
the character of each mix is examined by working it with a trowel. A test
specimen is then made from mix, care being taken to compact the concrete
thoroughly, and its crushing strength determined after seven days or other
convenient interval. A typical set of result from the experiment are given in the
following table.
Table 12
Effect of aggregate grading on concrete properties
Mix

Water content percentage by weight of Crushing strength at seven days


cement

lb. per square inch

86

280

73

88

66

1,480

60

2,220

49

1,760

40

730

It will be observed that, as the proportion of fine aggregate in the mix increase,
so also does the amount of mixing water required. Also mixes E and F, deficient
in sand , will be found to work very harshly, and no amount of added water will
make them plastic. Mixes, A,. B and C on the other hand, provided sufficient
water is added, give very attractive mixes, plastic and workable. From the
appearance of the cubes and the crushing test results, mix F will be seen to be
very porous, and not very strong; mix E though still porous, should give good

strength. The other mixes appear satisfactorily dense, but the strength will fall off
rapidly from mix D, which should give good strength not very different from
mix E, to mix A, whose strength will probably be even lower than that of F
whose appearance is so unpromising.

WEEK 8
TITLE: SLUMP TEST
OBJECTIVE:
To assess the workability of concrete.
Apparatus:
Truncated conical mould 100mm diameter at the top, 200mm at the
bottom and 300mm height.
Steel tamping rod 16mm diameter, 600mm long rounded at one end,
Diagram:

Figure: slump cone


Theory:
The slump is the difference between the height of concrete before
removing a slump cone and after removing it.

Procedure:

1.

The inside of the mould should be cleaned before each test


and the mould placed on a hard, flat, impervious surface.

2.

The mould should be filled in three layers of concrete of


approximately equal depth. Each layer is rode with 25 stokes
of the rounded end of the tamping rod; after the top layer
has been rode, the surface of the concrete is struck off level
with the top of the mould with a trowel or the rod. Any
spillage is cleaned away from around the base of the mould,
and the mould is then lifted vertically from the concrete.

3.

The slump is the difference between the height of the


concrete before and the greatest height after the removal of
the mould. If any specimen collapses or shears off laterally,
the test should be repeated with another sample of the same
concrete; if in the repeat test, the specimen should again
shear; the slump should be recorded together with the fact
that the specimen sheared.

4.

If after the slump measurement has babe completed, the side


of the concrete is tapped with a rod, a well-proportioned

cohesive mix will gradually slump further but a harsh no


cohesive mix is likely to collapse.

WEEK 9 Title: compacting factor test


Objectives:
This test is a more sensitive method of measuring the workability of
concrete than the slump test, as it is designed to give a figure as a
measure of workability for any kind of concrete mix made with
aggregate not over 38mm maximum size.
Apparatus:
Compacting factor apparatus
Hand scoop
Balance capable of weighing 7kg and accuracy 1g
Trowel;
Diagram

Figure: compacting factor apparatus


Theory:
Included in procedure:
Procedure:
1.

The doors of the hoppers are closed and the lower cylinder is
fixed centrally in position and covered.

2.

The top hoppers filled with the sample of concrete of this


hopper is released and the concrete is allowed to fall into the
lower hopper; than the concrete is similarly released from
the lower hopper and fall into the cylinder. Cohesive mixes
have a tendency to stick in one or both of the hoppers, and, if
this happens, the concrete may be helped through by
pushing a rod gently into the concrete from the top.

3.

The excess concrete is struck off by two trowels working


inwards and the full cylinder then removed and weighed,
giving the partially compacted weight.

4.

The cylinder is emptied ad refilled in layers approximately


50mm deep and heavily rammed or vibrated (if of low
workability), and completely filled. The concrete in the
cylinder is again weighed.

Compacting factor (CF) =

1st net weight


2nd net weight

A higher value indicates greater workability.

WEEK 10 Title: V.B Consistometer test


Objective:
This test can be regarded as an extension of the slump test which
is performed in the same apparatus, being the first part of this test.
Apparatus:
a.

Consistometer (see figure) consisting of a vibrating table T,


on which is fixed a cylinder container C. A slump cone S (of
size as for slump which rest centrally in the container. A
funnel F is held on a; swivel arm A, for filling with concrete.
On the swivel arm on the opposite side is a rod R, holding a

transporatent disc D, with a weight w (270g) including the


rod and disc).
b.

Tamping road, 16mm diameter, 600mm long.

c.

Stop watch accuracy 0.5s.

Diagram

Figure: V-B Consistometer


Theory:
Included in the procedure
Procedure;

1.

The cone is filled with concrete as for the slump test. The set
screw G is loosened and the funnel is swung to one side. The
surface of the concrete is struck off. The mould is removed
carefully and the slump is measured if required. This can be
done when the disc is swung round into position and
lowered down the rod just to touch the slump concrete. The
slump may be read off the rod scale.

2.

With the arm fixed in this position, holding the disc resting
on the concrete and with stop watch ready, thee watch is
started the instant that vibration is begun; and the watch is
stopped at the moment the concrete has been fully
compacted as compacted as observed through the disc, i.e
when the disc is fully covered underneath with cement
grout. The result is the time in seconds recorded to nearest
0.5s being expressed as V-B degrees.

An approximate guide to compacting factors, slump, and vebe


degrees suitable for concrete for different purposes are given in
the following table:

The presence of salt salts out and coagulates the colidal particles
which may be present, and which otherwise would remain in
suspension in the water layer.

WEEK 11
DETERMINATION OF THE STRENGTH OF CONCRETE
After the casting of concrete, the concrete should be cured for 7 days -14 days.
.To demonstrates to student how Schmidt Hammer is used to determine the strength of
concrete on site.
.the lower pitch sound indicates that the strength of the concrete is low.
.The higher pitch sound gives the higher strength of concrete.
Week. 12
Title:
SOUNDNESS OF CEMENT TEST
Objectives: To Determine the Soundness of cement test.
Apparatus: le chatelier apparatus
Diagram
Procedure

mix10gofcementwiththequantityofwaterrequiredtogiveapasteofstandard
consistency,vigorouslyfor240sonanonporoussurfacebymeansoftwotrowels.
Placethemouldononeglassplateandfillitwiththepastetakingcaretokeepthesplit
ofthemouldgentlyclosedwhilethisoperationisbeingperformed.
Coverthemouldwithotherglass,uponwhichasmallweightisplaced.
Immersethewholeimmediatelyinwateratatemperatureof20+10Candleavethese
fortwentyfourhours.
Removethemouldfromthewaterthenmeasurethedistanceseparatingtheindicator
pointstothenearest0.5mm.
Immersethewholeandbringthewatertoboilin2530minutesandkeepboilingfor
1hour.
Removethemouldfromthewatertocool.
Measurethedistanceseparatingtheindicatorpointtothenearest0.5mm.

Result

The difference between the two measurements represents the expansion of the
cement to the nearest 1mm

Week 13
FIELD SETTING TEST TO DETERMINE SILT CONTENT
Prepare an approximately 1m solution of common salt by dissolving 2.5g of sodium
chloride in 250ml of tap water. Pour 50ml of this solution into a 250ml measuring
cylinder and then add sand until the volume of sand is about 100ml; add more of the salt
solution until the total volume in the measuring cylinder is 150ml. Placing the palm of
the hand over the open end of the cylinder, shake vigorously, place on a level bench, tap
until the sand surface is level. Allow to stand for three hours. Record the height of the
sand, and of the silt above it.
Calculate the percentage of silt present.
Report on the suitability of the sand as fine aggregates in the preparation of
concrete.
Note: the presence of salt out and coagulates the colloidal particles which may be present
and which otherwise would remain suspension in the water layer.

WEEK 14
Title: Soundness of Cement Test.
Objective:

To determine Soundness of Cement

Apparatus:

Le Chatelier Apparatus

See week 7 for the theoretical explanation of this test.

Mix 10g of cement with quantity of water required to give a paste standard
consistency vigorously for 240s on a non porous surface by means of two trowels.

Place the mould on one glass plate and fill it with paste taken care to keep the
split of the mould gently closed while this operation is being performed.

Cover the mould with other glass, upon which a small weight is placed.

Immerse the whole immediately in water at a temperature of 20 10C and leave


these for twenty four hours.

Remove the mould from the water then measure the distance separating the
indicator points to the nearest 0.5mm.

Immerse the whole and bring the water to boil in 25 30 minutes and keep
boiling for 1hour.

Remove the mould from the water to cool.

Measure the distance separating the indicator point to the nearest 0.5mm.

Result
The difference between the two measurements represents the expansion of the
cement to the nearest 1mm

WEEK 15. STUDENTSEXCURSION.


Pictures on excursion from Ajaokuta steel rolling mill at Kogi state, Nigeria.

The process of the production is described by the arrows.

You might also like