Professional Documents
Culture Documents
Page 1
TABLE OF CONTENT:
INTRODUCTION:..........................................................................................................2
CASE STUDIES ............................................................................................................4
SPECIFICATION OF SW COMPONENTS:........................................................................................... 4
SPECIFICATION OF OPERATING CONDITIONS:............................................................................... 4
SPECIFICATION OF CALCULATION TOOL:....................................................................................... 5
Page 2
INTRODUCTION:
The co-operation between DESMI, APV and Grontmij Carl Bro was established more
than a year ago due to the increased demands for reduction of the CO2 emission to
the environment.
The co-operation between the pump supplier, the heat exchange supplier, and the
system designer was initiated with a view to trying to optimise auxiliary service
systems on board ships by combining the designers knowledge and the practical
experience of the two suppliers. The optimisations were centred on reducing the
needed power for the pump and in that way reducing the CO2 emission to the
environment.
The cooperation partners first focused on the seawater (SW) cooling system, being
one of the parts in an ordinary central cooling water system. The chosen vessel type is
a bulk carrier, which is very familiar to almost all, and in that way the conclusion of the
studies in this report can easily be adopted to optimising projects at existing vessels
and of course to optimising all new-building projects.
Page 3
Page 4
CASE STUDIES
SPECIFICATION OF SW COMPONENTS:
The case studies have been divided in different steps to illustrate the progress in the
project. These steps have been named as follows:
CASE STUDY NO. 1: Calculation of the existing final design including the
existing pumps and coolers.
CASE STUDY NO. 2: Same as case study No. 1 but with a new optimised
pump.
CASE STUDY NO. 3: Calculation with a new cooler based on 2x50% instead
of 2x65% cooling capacity, please see explanation later.
New optimised pump, corresponding to the new
coolers, has been used.
CASE STUDY NO. 4: Calculations with optimised coolers in respect of lowpressure drop. New optimised pumps, corresponding to
the new coolers, have been used.
Filter:
Running time
for pumps:
Pipes:
Calculation:
32 deg.C
36 deg.C
2.5 m above base line
6.0 m above base line
3.5 m above base line
9.5 m above base line
7.0 m
Page 5
Page 6
Coolers:
Page 7
The operator tries to keep each of the pumps at the 230 m3/h operation point.
To ensure this it is necessary to throttle the discharge valves or insert an
orifice due to the fact that the system pressure is lower than the specified
operation point at 3.0 barg.
In this scenario the mechanical power in the duty point of each of the running
pumps is 25.85 kW which corresponds to the below per year / pump:
Fuel consumption (ts/year/pump):
CO2 emission (ts/year):
Running cost (USD/year):
51.30
159.6
32,807.0
ref. calculation in appendix 1 page 2
1-2
The operator lets each of the pumps run at the system pressure. The pump is
very close to run out of its curve and delivers approx. 321 m3/h SW at 2,4bar.
In this scenario the pumps mechanical power in the duty point is 29.09 kW
which corresponds to the below per year / pump:
Fuel consumption (ts/year/pump):
CO2 emission (ts/year):
Running cost (USD/year):
57.70
179,6
36,919.0
ref. calculation in appendix 1 page 2
Page 8
SPECIFICATION OF SW COMPONENTS:
Pumps:
Coolers:
19.60
61.0
12,545.0
ref. calculation in appendix 1 page 2
66%
Page 9
SPECIFICATION OF SW COMPONENTS:
Pumps:
Coolers:
13.48
42.0
8,630.0
ref. calculation in appendix 1 page 2
77%
31%
Page 10
Case 4-2
Pumps:
Coolers:
Case 4-3
Pumps:
Coolers:
Case 4-4
Pumps:
Coolers:
Case 4-5
Pumps:
Coolers:
Case 4-6
Pumps:
Coolers:
Page 11
91%
73%
60%
It has to be mentioned that a cooler with a very low pressure drop is a larger cooler
and of course in that way a more expensive cooler. The increased initial installation
costs will afterwards be compared to the operational costs.
Case Study No. 4
Accumulated Running Cost + Installation Cost
700.000
Case
Case
Case
Case
Case
Case
600.000
500.000
4-1
4-2
4-3
4-4
4-5
4-6
USD
400.000
300.000
200.000
100.000
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Year
Page 12
OVERALL CONCLUSION:
The pressure drop of the cooler is essential. The cooler is the component in the
sea water system causing the highest resistance, and consequently it has a
significant impact on the overall system pressure and in that way facilitates the
installation of smaller pumps. Therefore the chosen cooler pressure drop should
be specified very clearly, when purchasing departments are purchasing the
coolers.
Figures for one pump:
Fuel cons./ CO2 emission Case Study 1-2 (ts/year):
Fuel cons./ CO2 emission Case Study 3 (ts/year):
Fuel cons./ CO2 emission Case Study 4-1(ts/year):
57.70 / 179.6
13.48 / 42.0
5.33 / 16.6
10.000,00
Case 1-2
8.000,00
TONS
Case 3
Case 4-1
6.000,00
4.000,00
2.000,00
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Year
Page 13
2.000.000
Case 1-2
Case 3
USD
1.500.000
Case 4-1
1.000.000
500.000
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Year
Accumulated Cost
Let the pump specification be open until the pipe system has been
designed in detail, so that all components are well known, e.g. location
of equipment, pipe length, quantity of bends etc. In that way the pump
can be optimised to exactly fit the system pressure.
Page 14
Page 15
Granskoven 8
DK-2600 Glostrup
Denmark
Karsten Elland
Project Manager
Industry, Marine & Environment
Phone: +45 4348 6060
E-mail: karsten.elland@grontmij-carlbro.dk
Heat Transfer
Platinvej 8
DK-6000 Kolding
Denmark
Kim Koldskov
Sales Manager
Global Marine Division
Phone: +45 7027 8444
E-mail: Kim.Koldskov@apv.com
Tagholm 1
DK-9400 Nrresundby
Denmark
Henrik Mrkholt
Sales Director
Phone: +45 9632 8128
E-mail: hms@desmi.com
Appendix 1
Calculation Documents
1.
2.
3.
4.
29,09
57,69
179,63
36.919
2x65%
COOLER
25,85
51,26
159,63
32.807
3,114
93%
95%
365
200
640
NEW PUMP
BASE PUMP
BASE PUMP
2x65% COOLER
NEW PUMP
CASE
STUDY 3
NEW PUMP
CASE
STUDY 4-1
NEW PUMP
CASE
STUDY 4-2
NEW PUMP
CASE
STUDY 4-3
NEW PUMP
CASE
STUDY 4-4
NEW PUMP
CASE
STUDY 4-5
NEW PUMP
CASE
STUDY 4-6
PAGE NO. 2
9,89
19,60
61,04
12.545
6,80
13,48
41,99
8.630
2,69
5,33
16,61
3.414
3,46
6,86
21,37
4.391
4,11
8,15
25,38
5.216
4,66
9,24
28,78
5.914
5,21
10,33
32,17
6.612
5,84
11,57
36,03
7.405
2x65% COOLER 2x50% COOLER 2x50% COOLER 2x50% COOLER 2x50% COOLER 2x50% COOLER 2x50% COOLER 2x50% COOLER
0.2 dP
0.3 dP
0.4 dP
0.5 dP
0.6 dP
0.7 dP
CASE
STUDY 2
CASE
STUDY 1-2
CASE
STUDY 1-1
Date: 14-09-2008
563.01
M/E LO COOLER +
562.03
JACKET WATER COOLER
411.01
M/E SCAVENGER AIR COOLER
431.01
A/E 1 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
431.02
A/E 2 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
431.03
A/E 3 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
312.01
REFR. COMPRESSOR UNIT FOR A/C PLANT
312.02
REFR. COMPRESSOR UNIT FOR A/C PLANT
355.01
PROVISON COOLING COMPRESSOR
355.02
PROVISON COOLING COMPRESSOR
314.03
REFR. COMP. FOR A/S UNIT GALLEY
314.02
REFR. COMP. FOR A/S UNIT ENG. CONTR. ROOM
682.01
STEAM DUMP COOLER
562.07
SAMPLE COOLER
423.03
SHAFT BEARING
461.01
STARTING AIR COMPRESSOR
461.02
STARTING AIR COMPRESSOR
TOTAL REQUIREMENT:
TOTAL LT FLOW:
TOTAL SW FLOW:
FW TEMP OUTLET OF COOLERS:
FW TEMP INLET TO COOLERS:
SW TEMP INLET TO COOLERS:
SW TEMP OUTLET OF COOLERS:
COOL. REQ. FOR EACH COOLER:
LT FLOW FOR EACH COOLER:
SW FLOW FOR EACH COOLER:
[%]
100%
100%
100%
90%
90%
0%
75%
75%
75%
75%
75%
75%
50%
0%
100%
50%
0%
65%
[kW]
700
1240
3000
420
420
420
196
196
9,5
9,5
17,8
17,2
998
2
1,7
16,7
16,7
[kW]
700,0
1240,0
3000,0
378,0
378,0
0,0
147,0
147,0
7,1
7,1
13,4
12,9
499,0
0,0
1,7
8,4
0,0
6540
437
460
36,0
49,0
32,0
48,0
4251
437
460
LOAD HEAT
HEAT
DISS. DISS. AT
LOAD
615-00-1
SPEC.
COOL.
COOL.
WATER
FLOW
INLET
TEMP.
PAGE NO. 3
Page: 1 / 1
TOL.
Date: 14-09-2008
563.01
M/E LO COOLER +
562.03
JACKET WATER COOLER
411.01
M/E SCAVENGER AIR COOLER
431.01
A/E 1 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
431.02
A/E 2 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
431.03
A/E 3 TOTAL (LO, JACK. W. AND SCAV. AIR COOLER)
312.01
REFR. COMPRESSOR UNIT FOR A/C PLANT
312.02
REFR. COMPRESSOR UNIT FOR A/C PLANT
355.01
PROVISON COOLING COMPRESSOR
355.02
PROVISON COOLING COMPRESSOR
314.03
REFR. COMP. FOR A/S UNIT GALLEY
314.02
REFR. COMP. FOR A/S UNIT ENG. CONTR. ROOM
682.01
STEAM DUMP COOLER
562.07
SAMPLE COOLER
423.03
SHAFT BEARING
461.01
STARTING AIR COMPRESSOR
461.02
STARTING AIR COMPRESSOR
TOTAL REQUIREMENT:
TOTAL LT FLOW:
TOTAL SW FLOW:
FW TEMP OUTLET OF COOLERS:
FW TEMP INLET TO COOLERS:
SW TEMP INLET TO COOLERS:
SW TEMP OUTLET OF COOLERS:
COOL. REQ. FOR EACH COOLER:
LT FLOW FOR EACH COOLER:
SW FLOW FOR EACH COOLER:
[%]
100%
100%
100%
90%
90%
0%
75%
75%
75%
75%
75%
75%
50%
0%
100%
50%
0%
50%
[kW]
700
1240
3000
420
420
420
196
196
9,5
9,5
17,8
17,2
998
2
1,7
16,7
16,7
[kW]
700,0
1240,0
3000,0
378,0
378,0
0,0
147,0
147,0
7,1
7,1
13,4
12,9
499,0
0,0
1,7
8,4
0,0
6540
437
460
36,0
49,0
32,0
48,0
3270
437
460
LOAD HEAT
HEAT
DISS. DISS. AT
LOAD
615-00-2
SPEC.
COOL.
COOL.
WATER
FLOW
INLET
TEMP.
PAGE NO. 4
Page: 1 / 1
TOL.
ORIFICE INSERTED
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 465,723 m3/h
Temperature = 48,6 C
Case 1-1:
SW cooling system
PAGE NO. 5
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 650,938 m3/h
Temperature = 43,9 C
Case 1-2:
SW cooling system
PAGE NO. 6
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 459,766 m3/h
Temperature = 48,9 C
Case 2:
SW cooling system
PAGE NO. 7
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 407,362 m3/h
Temperature = 46,6 C
Case 3:
SW cooling system
PAGE NO. 8
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 359,945 m3/h
Temperature = 48,6 C
Case 4-1:
SW cooling system
PAGE NO. 9
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 363,943 m3/h
Temperature = 48,4 C
Case 4-2:
SW cooling system
PAGE NO. 10
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 363,203 m3/h
Temperature = 48,4 C
Case 4-3:
SW cooling system
PAGE NO. 11
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 363,479 m3/h
Temperature = 48,4 C
Case 4-4:
SW cooling system
PAGE NO. 12
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 362,921 m3/h
Temperature = 48,5 C
Case 4-5:
SW cooling system
PAGE NO. 13
Pressure = 1 m Fluid g
Elevation = 6 m
Unique Name = Overboard
Flow = 364,041 m3/h
Temperature = 48,4 C
Case 4-6:
SW cooling system
PAGE NO. 14
Member of
Green Ship of the Future