Professional Documents
Culture Documents
com
ScienceDirect
International Journal of Project Management 32 (2014) 850 860
www.elsevier.com/locate/ijproman
Abstract
Construction cost overrun is a common problem in construction industries. The objective of this research is to extract the key cost-inuencing
factors with new concept and methods to help control the expenditure. Hence, this research adopts the Modied Delphi Method (MDM) with 2
groups and 2 rounds and Kawakita Jiro method (KJ) to consolidate the experts' opinions and identify and rank the key factors that affect project
costs. Ninety cost-inuencing factors are collected from literary review and interviews with experts with practical cost control experiences in the
construction companies (Group 1). The KJ method is used to consolidate these factors into 4 categories and down to a total of 42 factors. 2 rounds
of questionnaires are then conducted to lter the key factors. In order to verify views of those in the rst group, Group 2 consists of experienced
experts from the public sectors, consulting rms and construction companies as a comparison. Results of the analysis indicate that there are 16 key
cost-inuencing factors. Severity Index computation was then adopted to rank these key cost-inuencing factors. The study renders that clearly
dened scope of project in the contract and cost control are the major determinants for cost overrun.
2013 Elsevier Ltd. APM and IPMA. All rights reserved.
Keywords: Cost-inuencing factors; Cost control; Modied Delphi Method; KJ method
1. Introduction
It's customary in construction industries to win projects with
the lowest bids. Therefore, without controlling key costinfluencing factors, construction companies will not be able to
control the expenditure effectively, which will in turn increase
project costs and affect overall profit. In fact, construction cost
overrun is a common problem in construction industries.
Flyvbjerg et al. (2002) pointed out that historically, large
construction projects have been plagued by cost and schedule
overruns. Shane et al. (2009) stated that final project costs have
been higher than the cost estimates prepared in too many
cases. Doloi (2011) brought up that cost overrun is a chronic
problem for most projects. Love et al. (2013) calculated cost
851
4. Research methodology
4.1. KJ method
The KJ method is a qualitative technique developed by
Kawakita Jiro in 1953. It adopts the bottom-up sorting process
and is very useful for classifying data. It is used to organize data
into useful categories, or in other words, transform data into
Literary Review
Group 2
First round
First round
Questionnaire Analysis
Questionnaire Analysis
Second round
Second round
Questionnaire Analysis
Filter the key factors
Rank the key factors
Conclusion and Recommendations
852
853
Climate factor
Political environment
The fluctuations in commodity price is too great
Geology, topography
Scope of
of contract
contract
The level of demand on quality
Contract types
Project quality
Contract dispute (unclear drawings or guidelines/regulations)
Modifications to the scope of construction
Scale of construction
User demand
Structure type
Project type
Project location
854
Project risks
Project
risks
Protest
Stagnant project
Neighbor protests
Policy change
Delayed procurement
Labor protests
Design modifications
Occupational hazards
The gap between the construction plan and the reality is too great
Material management
Procurement contract
Subcontractor's valuation
Cost control
Personnel training
Project manager's capability
Budget exceptions
Labor attendance
Coordination among
the team members
Practical experience
the lack of experience for this type of project
Construction methods
855
Table 1.1
First round results environmental and circumstantial influence.
6.2. Analysis
Factor
Group 1
Group 2
4.00
4.00
4.42
1.10
0.70
0.80
0.60
0.30
0.50
4.09
4.09
4.18
0.70
0.8
0.6
0.30
0.8
0.3
2.92
3.83
0.80
0.90
0.10
0.60
3.64
3.55
1.2
0.8
1.3
0.5
4.58
0.50
0.50
4.55
0.5
0.5
3.58
0.90
0.50
3.27
1.1
0.8
3.67
0.90
0.60
3.82
0.9
0.8
3.88
0.83
0.46
3.90
0.83
0.66
Table 1.2
First round results scope of contract.
Factor
Group 1
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.75
3.33
3.75
3.83
4.33
4.58
0.40
0.90
0.70
0.80
0.60
0.50
0.10
0.50
0.10
0.10
0.50
0.50
4.55
3.73
3.82
3.82
4.09
4.09
0.7
0.7
0.7
0.7
0.9
0.5
0.5
0.3
0.5
0
1
0
4.58
4.42
4.20
0.50
0.60
0.63
0.50
0.50
0.35
4.45
4.09
4.08
0.5
0.9
0.70
0.5
0.5
0.41
Table 1.3
First round results project risks.
Factor
Group 1
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
Design modifications
Protest
The client's financial capability
Stagnant project
Occupational hazards
Inadequate project listing
The vendors/contractors/subcontractors went bankrupted
Inadequate construction techniques
The gap between the construction plan and the reality is too great.
Material shortage or supply delay
Average
4.33
3.75
4.42
4.42
4.67
4.17
3.75
4.08
4.42
4.58
4.26
0.70
0.70
0.60
0.50
0.50
0.70
0.60
0.80
0.80
0.60
0.65
0.50
0.50
0.50
0.50
0.50
0.50
0.50
0.60
0.50
0.50
0.51
3.91
4.55
3.91
4.00
4.45
4.00
4.36
4.55
4.45
4.73
4.29
0.9
0.7
0.8
0.6
0.5
0.9
0.9
0.5
0.7
0.6
0.71
0.5
0.5
0
0
0.5
0.3
0.5
0.5
0.5
0
0.33
856
Table 1.4
First round results management and technique.
Factor
Group 1
Cost control
Project control meeting
Labor attendance
Carry out supervision/monitoring
Project valuation does not match the collected payment.
Whether the high-level management decentralizes the power.
Staff/personnel training
Regular budget update
Job site safety and sanitation/health management
Budget exceptions
Material management
Practical experience
Procurement contract
Time management
The project manager's capability
Project team (coordination capability and the understanding
of operational procedure)
Average
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.75
4.00
3.67
4.17
4.08
4.50
4.08
3.75
4.33
3.83
4.17
4.33
4.50
4.50
4.67
4.58
0.40
0.70
0.70
0.70
0.60
0.50
0.60
1.00
0.90
0.70
0.60
0.50
0.50
0.50
0.50
0.50
0.10
0.30
0.50
0.50
0.10
0.50
0.10
0.60
1.00
0.50
0.10
0.50
0.50
0.50
0.50
0.50
4.64
4.18
3.91
4.18
4.36
4.09
3.91
4.09
3.91
3.91
4.18
4.64
4.18
4.18
4.36
4.45
0.5
0.6
0.7
0.6
0.9
0.7
0.8
0.8
0.5
0.5
0.8
0.5
1.1
0.7
0.9
0.7
0.5
0.3
0
0.3
0.5
0.3
0
0.3
0
0
0.5
0.5
0.5
0.5
0.5
0.5
4.24
0.62
0.43
4.21
0.72
0.34
and gave the rating of 5. The mean for Group 2 is 4.00 with a
standard deviation of 0.7 and a quartile range of 0.5. 3 of the 11
panel members gave the maximum value of 5, and 3 gave the
value of 3. Members in Group 2 are from different sectors.
Although they each hold a different view, with a mean of 4.00,
the group still thinks that factor A-4 holds certain influence
over construction costs. Figs. 7 and 8 show the comparison of
the standard deviation and quartile range between the two
groups. It is shown that the standard deviation for factor C-2
from Group 1, Material Shortage or Supply Delay, is 0.9, the
Table 2.1
Second round results environmental and circumstantial influence.
Factor
Climate factor
Natural disaster
Geology, topography
Political environment
High fluctuation in labor cost
High fluctuation in commodity price
Gross domestic products (GDP)
Interest rate on bank loans
Average
Group 1
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.00
3.75
4.33
3.00
3.33
4.92
3.00
3.67
3.75
0.60
0.4
0.6
0.7
0.7
0.3
0.6
0.7
0.58
0.00
0.1
0.5
0.3
0.5
0
0
0.5
0.24
4.27
4.27
4.09
3.55
3.36
4.00
3.18
3.55
3.78
0.40
0.4
0.7
0.8
0.6
0.7
0.7
0.7
0.63
0.30
0.3
0.3
0.5
0.5
0.5
0.5
0.5
0.43
Table 2.2
Second round results scope of contract.
Factor
Group 1
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.83
3.33
3.83
3.58
4.25
4.08
0.4
0.6
0.8
0.9
0.6
0.6
0
0.5
0.1
0.5
0.5
0.1
4.64
3.64
3.64
3.55
4.45
4.36
0.5
0.8
0.6
0.7
0.7
0.6
0.5
0.5
0.5
0.5
0.5
0.5
4.83
4.42
4.15
0.4
0.6
0.61
0
0.5
0.28
4.45
4.27
4.13
0.7
0.9
0.69
0.5
0.5
0.50
857
Table 2.3
Second round results project risks.
Factor
Group 1
Design modifications
Protest
The client's financial capability
Stagnant project
Occupational hazards
Inadequate project listing
The vendors/contractors/subcontractors went bankrupted
Inadequate construction techniques
The gap between the construction plan and the reality is too great.
Material shortage or supply delay
Average
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.33
3.33
4.67
4.17
4.75
4.08
3.33
3.92
4.33
4.33
4.13
0.6
0.6
0.5
0.9
0.4
0.8
0.9
0.5
0.7
0.9
0.68
0.5
0.1
0.5
0.5
0.1
0.6
0.5
0
0.5
0.5
0.38
3.91
4.45
3.82
4.18
4.00
3.82
4.00
4.55
4.64
4.64
4.20
0.9
0.5
0.6
0.6
0.7
0.7
0.9
0.8
0.6
0.6
0.69
0.5
0.5
0.3
0.3
0.5
0
0.3
0.3
0.3
0.3
0.33
wi
Table 2.4
Second round results management and technique.
Factor
Cost control
Project control meeting
Labor attendance
Carry out supervision/monitoring
Project valuation does not match the collected payment.
Whether the high-level management decentralizes the power.
Staff/personnel training
Regular budget update
Job site safety and sanitation/health management
Budget exceptions
Material management
Practical experience
Procurement contract
Time management
The project manager's capability
Project team (coordination capability
and the understanding of operational procedure)
Average
Group 1
Group 2
Mean
Standard deviation
Quartile ranges
Mean
Standard deviation
Quartile ranges
4.83
3.92
3.25
3.83
4.08
4.08
3.50
3.50
4.00
3.58
4.17
4.50
4.42
4.50
4.42
4.42
0.4
0.3
0.4
0.6
0.6
0.8
0.6
1
0.7
1
0.6
0.6
0.6
0.6
0.6
0.6
0
0
0.1
0.1
0.1
0.6
0.5
0.5
0.3
0.6
0.1
0.5
0.5
0.5
0.5
0.5
4.64
4.00
3.55
3.82
4.55
4.09
3.73
4.00
3.82
3.55
3.91
4.27
4.09
4.36
4.00
4.27
0.5
0.7
0.7
0.7
0.5
0.8
0.7
0.6
0.9
0.5
0.3
0.4
0.5
0.5
1
0.6
0.5
0.5
0.5
0
0.5
0.3
0.3
0
0.8
0.5
0
0.3
0
0.5
0.8
0.5
4.08
0.62
0.35
4.05
0.62
0.38
858
Table 3
Mean SI for the categories with key cost influencing factors.
Category
D-6
Factor
5.00
D-4
0.40
D-3
B-1
D-2
D-1
B-3
C-2
B-4
C-1
Fig. 7. Radar chart for standard deviation comparison between the two groups.
A-2
0.50
A-2
0.40
D-5
A-3
A-3
0.30
D-4
A-4
0.20
A-4
0.10
1.00
Group 1
0.00
B-1
D-2
D-1
Group 1
0.00
D-3
B-1
Group 2
B-2
B-3
C-2
Group 2
B-2
D-6
2.00
D-3
Group 1
0.00
3.00
D-4
A-4
0.20
A-1
4.00
D-5
A-3
0.60
A-1
D-6
A-2
0.80
D-5
1.00
B-4
C-1
Fig. 6. Radar chart for mean comparison between the two groups.
D-2
Group 2
B-2
B-3
D-1
C-2
B-4
C-1
Fig. 8. Radar chart for quartile range comparison between the two groups.
Factor
7. Conclusion
SI
Rank
(Severity Index)
859
94.78
94.78
93.04
1
2
89.57
89.57
3
3
89.57
88.70
87.83
86.96
86.96
86.96
3
4
5
6
6
6
86.09
85.22
84.35
82.61
80.00
8
9
10
11
Table 5
Effect of cost-influencing factors on public construction and common duct projects.
Category
Contract stipulated
costs (NT$)
Increase/
Details (factors)
decrease (NT$)
Public
construction
project
740,870,943
8,520,717
Common duct
project
186,310,553
3,376,191
1. For items whose actual quantities cannot be confirmed during the planning and design stage, the
contract stipulated that the payment schedule is based on actual completion. Examples include grit
chambers, road pavement and compressed concrete paving units, which were significantly reduced from
the original estimate. (B-1)
2. Fully implement cost control and regularly review the required quantity and construction costs. (D-1)
1. Contract omissions. (B-3)
2. Design changes due to site conditions. (B-2, C-1)
3. Unfamiliarity with local culture, which affected the design of the manhole cover. The client intervened
later on for the redesign. (C-1)
4. The drilling indicated inconsistency with current conditions. Additional backfill required. (C-1)
5. Poor control over the transfer schedule and unclearly defined responsibility resulted in theft finished
installations. (D-5, D-6)
6. Project redo due to poor construction quality. (B-4)
860
RII
SI
Acknowledgments
The author would like to thank all participating experts,
especially Kuang-Hu Cheng, former worksite director of Land
Consolidation Engineering Bureau and Yu-Ming Liu, senior
engineer with CECI Engineering Consultants, without their
valuable contributions this research would not have been
possible. Moreover, the authors would like to acknowledge the
reviewers for contributing helpful suggestions and insightful
comments, which greatly improved the quality of this paper.
References
Chan, C.T.W., 2012. The principal factors affecting construction project
overhead expenses: an exploratory factor analysis approach. Constr.
Manage. Econ. 30 (10), 903914.
Chan, A.P.C., Yung, E.H.K., Lam, P.T.I., Tam, C.M., Cheung, S.O., 2001.
Application of Delphi method in selection of procurement systems for
construction projects. Constr. Manage. Econ. 19 (7), 699718.
Chang, A.S., 2002. Reasons for cost and schedule increase for engineering
design projects. J. Manage. Eng. 18 (1), 2936.
Chen, J.H., Hsu, S.C., 2008. Quantifying impact factors of corporate financing:
engineering consulting firms. J. Manage. Eng. 24 (2), 96104.
Cheng, Y.M., Leu, S.S., 2011. Integrating data mining with KJ method to
classify bridge construction defects. Expert Syst. Appl. 38 (6), 71437150.
Dissanayaka, S.M., Kumaraswamy, M.M., 1999. Evaluation of factors affecting
time and cost performance in Hong Kong building project. Eng. Constr.
Archit. Manage. 6 (3), 287298.
Doloi, H.K., 2011. Understanding stakeholders' perspective of cost estimation
in project management. Int. J. Proj. Manage. 29, 622636.
Doloi, H., 2013. Cost overruns and failure in project management: understanding
the roles of key stakeholders in construction projects. J. Constr. Eng. Manage.
139 (3), 267279.
Elhag, T.M.S., Boussabaine, A.H., Ballal, T.M.A., 2005. Critical determinants
of construction tendering costs: quantity surveyors standpoint. Int. J. Proj.
Manage. 23, 538545.
Elinwa, A.U., Buba, S.A., 1993. Construction cost factors in Nigeria. J. Constr.
Eng. Manage. 119 (4), 698713.
Flyvbjerg, Bent, Holm, Skamris, Mette, K., Buhl, Soren L., 2002. Underestimating costs in public works projects: error or lie? J. Am. Plan. Assoc.
68 (3), 279295.
Hallowell, M.R., Gambatese, J.A., 2010. Qualitative research: application of the
Delphi method to CEM research. J. Constr. Eng. Manage. 136 (1), 99107.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D., Harris, F.C., 1997. Factors
influencing construction time and cost overruns on high-rise projects in
Indonesia. Constr. Manage. Econ. 15, 8394.
Lance, D., 2006. Creating an Affinity Diagram. LL Decker Associates,
Inc.(Helping organizations change).
LCEB, 2004. Land Consolidation Engineering Bureau, Ministry of the Interior,
Expense Report, Regional Requisition for Taiwan High Speed Rail
Taoyuan Station.
LCEB, 2005. Land Consolidation Engineering Bureau, Ministry of the Interior,
Evaluation Report, Regional Requisition for Taiwan High Speed Rail
Taoyuan Station.
Love, P.E.D., Wang, X., Sing, C.P., Tiong, R.L.K., 2013. Determining the
probability of project cost overruns. J. Constr. Eng. Manage. 139 (3), 321330.
Ma, Z., Shao, C., Mac, S., Ye, Z., 2011. Constructing road safety performance
indicators using Fuzzy Delphi method and Grey Delphi method. Expert
Syst. Appl. 38, 15091514.
Murry, J.W., Hammons, J.O., 1955. Delphi: a versatile methodology for
conducting qualitative research. Rev. High. Educ. 18 (4), 423436.
Olawale, Y., Sun, M., 2013. PCIM: project control and inhibiting-factors
management model. J. Manage. Eng. 29 (1), 6070.
Plain, C., 2007. Build an affinity for KJ method. Qual. Prog. 40 (3), 88.
Rahman, I.A., Memon, A.H., Karim, A.T.A., 2013. Significant factors causing
cost overruns in large construction projects in Malaysia. J. Appl. Sci. 13 (2),
286293.
Shane, J.S.A., Molenaar, K.R., Anderson, S., Schexnayder, C., 2009. Construction project cost escalation factors. J. Manage. Eng. 25 (4), 221229.
Shash, A.A., 1993. Factors considered in tendering decisions by top UK
contractors. Constr. Manage. Econ. 11 (2), 111118.
Yeung, J.F.Y., Chan, A.P.C., Chan, D.W.M., 2009. Developing a performance
index for relationship-based construction projects in Australia: Delphi
study. J. Manage. Eng. 25 (2), 5968.
Zaphiris, P., Ghiawadwala, M., Mughal, S., 2005. Age-centered Researchbased Web Design Guidelines. Portland, Oregon, USA.