Federal Register / Vol. 71, No.

242 / Monday, December 18, 2006 / Notices 75769

be used to support the span. Other from GGNRA). Written comments will Regional Director, Pacific West Region.
bridge alternatives considered in the be accepted online at http:// Subsequently, the official responsible
Draft EIS/EIR include: Alternative BR1 parkplanning.nps.gov/goga (click on the for implementing the approved wetland
(50-foot-long bridge with a raised road); project title and follow instructions), or and restoration plan will be the General
Alternative BR2 (50-foot-long bridge by sending a letter addressed as follows: Superintendent, Golden Gate National
with a low road); Alternative BR3 (150- Superintendent, Golden Gate National Recreation Area.
foot-long bridge with raised road); and Recreation Area, Fort Mason, Building Dated: October 3, 2006.
Alternative BR4 (266- to 300-foot-long 201, San Francisco, CA 94123 (Attn:
Patricia L. Neubacher,
bridge with highest road). Muir Beach Creek and Wetland
Scoping and Public Involvement: Acting Regional Director, Pacific West Region.
Restoration). Two public meetings will
Between December 2002 and December be scheduled to hear comments on the [FR Doc. 06–9748 Filed 12–15–06; 8:45 am]
2004, 17 public meetings were held, as Draft EIS/EIR, approximately 30 days BILLING CODE 4312–FN–M
well as a variety of site visits and after publication of this notice in the
meetings with representatives of various Federal Register. Please visit the project
agencies. On December 3, 2002, a Notice Web site (noted above) to learn more DEPARTMENT OF THE INTERIOR
of Intent (NOI) to prepare an about the project, planning process, and
Environmental Impact Statement was Bureau of Reclamation
the confirmed dates and time for the
published in the Federal Register, public meetings. Questions regarding New Melones Lake Project Resource
beginning the formal scoping process for this project may also be directed at any Management Plan/Environmental
the project. The NOI identified goals for time to Steve Ortega (415) 561–4841 or Impact Statement (RMP/EIS), Calaveras
the project, and public scoping meetings via e-mail at steve_ortega@nps.gov. and Tuolumne Counties, CA
were held on October 22, October 29, All comments are maintained in the
and November 2, 2002, with a site visit administrative record and will be AGENCY: Bureau of Reclamation,
for the public held on November 9, available for public review at GGNRA Interior.
2002, to solicit input on the project and headquarters. Please note our practice is
ACTION: Notice of intent to prepare an
its potential impacts. Following these to make comments, including names,
RMP/EIS and notice of public meetings.
meetings, a Big Lagoon Working Group home addresses, home phone numbers,
consisting of interested individuals, and e-mail addresses of respondents, SUMMARY: Pursuant to the National
agencies, and organizations was formed available for public review. Individual Environmental Policy Act (NEPA), the
to help develop project alternatives. The respondents may request that we Reclamation Act of 1902, the
working group convened regularly in withhold their names and/or home Reclamation Project Act of 1939, and
meetings that were open to the public. addresses, etc., but if you wish us to the Reclamation Recreation
In addition, two alternatives workshops consider withholding this information Management Act of 1992, the Bureau of
were held for the public on September you must state this prominently at the Reclamation (Reclamation) proposes to
30 and October 4, 2003. The results of beginning of your comments. In prepare an integrated RMP/EIS for the
those workshops, as well as a more addition, you must present a rationale New Melones Lake Project. Reclamation
detailed summary of the scoping for withholding this information. This is the lead federal agency for NEPA. The
process, are presented in the rationale must demonstrate that
RMP process is designed to evaluate
Alternatives Public Workshops Report disclosure would constitute a clearly
current and future resource conditions
(NPS 2004). Finally, Marin County unwarranted invasion of privacy.
for a management area and to analyze
circulated a Notice of Preparation of an Unsupported assertions will not meet
whether updated or new management
Environmental Impact Report on April this burden. In the absence of
actions are necessary to attain desired
27, 2004, soliciting comments on the exceptional, documentable
long-term goals.
specific issues to be included in the circumstances, this information will be
scope of CEQA environmental review. released. We will always make The public is invited to participate in
All of these activities informed the submissions from organizations or the planning process by submitting
alternatives formulation process. businesses, and from individuals comments during the scoping period
Comments: Copies of the Draft EIS/ identifying themselves as and the public comment period on the
EIR will be sent to affected Federal, representatives of or officials of draft RMP/EIS. Other opportunities to
Tribal, State and local government organizations or businesses, available participate will be described during the
agencies, to interested parties, and those for public inspection in their entirety. public scoping meetings.
requesting copies. Paper and digital Decision Process: Following the DATES: Reclamation will host a series of
copies (compact disc) of the document analysis of all comments received three public scoping meetings to solicit
will also be available at park concerning the Draft EIS/EIR, at this input on the development of
headquarters and at local libraries. The time it is anticipated that the Final EIS/ alternatives, concerns, and issues to be
complete document will be posted on EIR would be completed in spring 2007. addressed in the RMP/EIS. The meeting
the GGNRA’s Web site (http:// The availability of the final documents dates and times are:
www.nps.gov/goga) and on NPS’s will be announced in the Federal • Monday, January 29, 2007, 6:30 to
Planning, Environment and Public Register, and also publicized via local 8:30 p.m., Sonora, CA,
Comment Web site (http:// and regional press media, direct • Tuesday, January 30, 2007, 6:30 to
parkplanning.nps.gov/goga). All written mailings, and Web site postings. Not 8:30 p.m., Angels Camp, CA,
comments must be postmarked or sooner than thirty days after the
• Wednesday, January 31, 2007, 6:30
transmitted no later than 75 days from distribution of the Final EIS/EIR, a
to 8:30 p.m., Manteca, CA.
the date of EPA’s notice of filing Record of Decision may be executed (at
jlentini on PROD1PC65 with NOTICES

published in the Federal Register (as this time it is anticipated a ADDRESSES: Scoping meetings will be
soon as this occurs, the confirmed close recommended decision would be held at:
of the comment period will be posted on developed in summer 2007). As a • Sonora at the Sonora Union High
the Web sites noted above, and listed in delegated EIS the approving official School Cafeteria, 251, South Barretta
all notification announcements sent responsible for the final decision is the Street, Sonora, CA,

VerDate Aug<31>2005 16:16 Dec 15, 2006 Jkt 211001 PO 00000 Frm 00062 Fmt 4703 Sfmt 4703 E:\FR\FM\18DEN1.SGM 18DEN1
75770 Federal Register / Vol. 71, No. 242 / Monday, December 18, 2006 / Notices

• Angels Camp at the Brett Harte This list is not exhaustive and may organizations or businesses, available
High School Library, 323 South Main, increase or change as a result of public for public inspection in their entirety.
Angels Camp, CA, response during the scoping period. Michael Nepstad,
• Manteca at the Manteca High
School Cafeteria, 450 East Yosemite Additional Information Acting Regional Environmental Officer, Mid-
Pacific Region.
Avenue, Manteca, CA. Persons needing reasonable [FR Doc. E6–21471 Filed 12–15–06; 8:45 am]
Written comments on the scope of the accommodations in order to attend and BILLING CODE 4310–MN–P
proposed RMP/EIS should be sent by participate in the public meeting should
close of business on February 16, 2007 contact Ms. Vasquez as soon as possible.
to: Ms. Elizabeth Vasquez, Natural In order to allow sufficient time to
Resource Specialist, Central California DEPARTMENT OF JUSTICE
process requests, please call no later
Area Office, U.S. Bureau of
than one week before the meeting. Office of Justice Programs
Reclamation, 7794 Folsom Dam Road,
Information regarding this proposed [OMB Number 1121–0094]
Folsom, CA 95630, or e-mail to
evasquez@mp.usbr.gov. action is available in alternative formats
upon request. Agency Information Collection
FOR FURTHER INFORMATION CONTACT: Ms.
During the meetings, Reclamation Activities: Proposed Collection;
Elizabeth Vasquez at 916–989–7192. Comments Requested
representatives will present an overview
SUPPLEMENTARY INFORMATION: In 1976,
of the project. Those attending the
during planning for construction of the ACTION: 30-Day notice of information
meeting will have the opportunity to collection under review:
New Melones Dam, a master plan was
created to manage the various resources submit comments, which Reclamation
available at New Melones Lake. This will consider in the development of Reinstatement of a previously
plan and a subsequent 1995 draft alternatives and for analysis of approved collection for which approval
resource management plan do not fulfill environmental issues that should be has expired:
the need for resource management addressed in the RMP and EIS. The Annual Survey of Jails.
planning, due to the age of the (Additional coordination meetings can The Department of Justice (DOJ),
documents, changes in visitor use over be arranged with responsible/ Office of Justice Programs, Bureau of
the last 30 years, and the accumulation cooperating agencies and with special Justice Statistics has submitted the
of more complete information about the interest groups upon request.) following information collection request
various resources managed by to the Office of Management and Budget
Letters describing the proposed action (OMB) for review and approval in
Reclamation as part of the New Melones and soliciting comments will be sent to
Lake Project. accordance with the Paperwork
the appropriate federal, state, and local Reduction Act of 1995. The proposed
The RMP process is designed to agencies and to private organizations information collected is published to
evaluate current and future resource and citizens who have expressed an obtain comments from the public and
conditions for a management area and to interest or who are known to have an affected agencies. The proposed
analyze whether updated or new interest in this proposal. information collected was previously
management actions are necessary to
Comments received in response to published in the Federal Register
attain desired long-term goals. All
this notice will become part of the Volume 71, Number 200, page 61071, on
proposed management actions will be
administrative record and are subject to October 17, 2006, allowing a 30 day
incorporated into a single document
public inspection. Our practice is to comment period. The purpose of this
that will guide management of
make comments, including names, notice is to allow for an additional 30
biological, social, and physical
home addresses, home phone numbers, days for public comment until January
resources and, when implemented, will
and email addresses of respondents, 17, 2007. This process is conducted in
result in the desired conditions for the
available for public review. Individual accordance with 5 CFR 1320.10.
management area. The associated EIS
Written comments and/or suggestions
will assess the potential effects of respondents may request that we
regarding the items contained in this
current management actions as well as withhold their names and/or home
notice, especially the estimated public
those proposed under the action addresses, etc., but if you wish us to burden or associated response time,
alternatives. The final RMP/EIS will consider withholding this information, should be directed to The Officer of
reflect the alternative that is deemed you must state this prominently at the Management and Budget, Officer of
most preferable given the range of beginning of your comments. In Information and Regulatory Affairs,
resources to be managed and the addition, you must present a rationale Attention Department of Justice Desk
management tools available to for withholding this information. This Officer, Washington DC 20503.
Reclamation. rationale must demonstrate that Additionally, comments may be
Reclamation has developed a disclosure would constitute a clearly submitted to OMB via facsimile to (202)
preliminary list of management issues to unwarranted invasion of privacy. 395–7285.
be addressed in the RMP/EIS. These Unsupported assertions will not meet Request written comments and
items include: this burden. In the absence of suggestions from the public and affected
• Public health and safety; exceptional, documentable agencies concerning the proposed
• Recreational use; circumstances, this information will be collection of information are
• Interest groups; released. We will always make encouraged. Your comments should
• Traffic and transportation; submissions from organizations or address one or more of the following
jlentini on PROD1PC65 with NOTICES

• Cultural and archaeological businesses, and from individuals four points:


resources; identifying themselves as (1) Evaluate whether the proposed
• Land use, including historic and representatives or officials of collection of information is necessary
proposed rights-of-way; and for the proper performance of the
• Sensitive species and habitats. functions of the agency, including

VerDate Aug<31>2005 16:16 Dec 15, 2006 Jkt 211001 PO 00000 Frm 00063 Fmt 4703 Sfmt 4703 E:\FR\FM\18DEN1.SGM 18DEN1