Professional Documents
Culture Documents
Prof K KARUNAMURTHY
SMBS/VIT Chennai
Prof K Karunamurthy / VIT
CONTENTS
Recap
Formulation of LPP
Subject to
a11x1+a12x2+.a1nxn(<,=,>)b1
a21x1+a22x2+.a2nxn(<,=,>)b2
.
.
.
.
Objective function
am1x1+am2x2+.amnxn(<,=,>)bm
and
x1,x2,x3.xn >0
STRUCTURED
CONSTRAINTS
NON-NEGATIVITY CONSTRAINTS
Formulation of LPP
Problem 1. Berger Paint manufactures both exterior and interior paints from
two raw materials C1 and C2. The following data provides the details:
Tons of raw material per ton of
Exterior paint
Interior paint
Max
availability
(ton)
Raw Material
C1
24
Raw material
C2
5000
4000
A survey indicates that the daily demand for interior paint cannot exceed that
for exterior paint by more than 1 ton. Also, the maximum demand for interior
paint is 2 tons. Berger paint wants to determine the optimum product mix of
interior and exterior paints that maximizes the total daily profit.
Prof K Karunamurthy / VIT
Formulation of LPP
Max.Z = 5000x1 + 4000 x2
Subject to
6 x1 4 x2 24
x1 2 x2 6
x2 x1 1
Where
x2 2
x1 , x2 0
Formulation of LPP
Problem 2. Three products are made from Lakshmi industries. These
products are processed on three different machines. The time required to
manufacture one unit of each of the three products and the daily capacity
of the three machines are
Time per unit (min)
Machine
Machine
capacity
(minutes/
day)
Product 1
Product 2
Product 3
M1
440
M2
470
M3
430
Formulation of LPP
Max.Z 4 x1 3 x2 6 x3
subject to,
2 x1 3x2 2 x3 440
+3x3 470
4 x1
2 x1 5 x2
where
x1 , x2 ,x3
430
0.
Formulation of LPP
Problem 3. A company desires to utilize the excess capacity of lathe, shaper
and milling machine to make the products A, B, and C. The time
availability/month of these machines are
Time required (hrs)
Product
Lathe
Shaper
Milling
Machine
Available
hours/month
200
100
180
Formulation of LPP
Max.Z 20 x1 16 x2 12 x3
subject to,
6x1 2 x2 3x3 200
100
2x1 +2x2
4x1
where
3x3 180
x1 , x2 ,x3
0.
Formulation of LPP
Problem 4. The manager of an oil refinery must decide on the optimal mix
of two possible blending processes of which the inputs and outputs per
production run are as follows.
Inputs (Units)
Outputs (Units)
Process
Arabian
Crude
Iraqi
Crude
Petrol
(Superior)
Petrol
( Ordinary)
10
10
16
12
15
12
12
The availability of the two varieties of crude is limited to the extent of 400
units and 450 units per day. The market demand indicates that at least 200
units and 240 units of superior and ordinary quality of petrol is required
per day. The profitability analysis indicate that process A contributes Rs
18,000/day while the process B contributes Rs24,000/day. Determine the
number of production runs of process A and process B to maximize the
companys profit. Formulate the LPP.
Formulation of LPP
Max Z = 18000 X1 + 24000 X4
Subject to
10X1 + 12X2 400
6X1 + 15X2 450
10X1 + 12X2 200
16X1 + 12X2 240
Where X1, X2 0
Prof K Karunamurthy / VIT
Formulation of LPP
Problem 5. A person wants to fulfill his daily requirements of
protein, fat and carbohydrates at the minimum cost. The choice is
to be made from four different types of foods. The yields per unit of
these foods are given below,
Food Type
Protein
Fat
Carbohydrates
Cost / Unit
(Rs)
45
40
85
65
Minimum
Requirement
800
200
700
Formulation of LPP
= 451 + 402 + 853 + 654
Subject to,
31 + 42 + 83 + 64 800
21 + 22 + 73 + 54 200
61 + 42 + 73 + 44 700
Where 1 , 2 , 3 , 4 0