DREDGING WORKS AND CONSTRUCTION OF

TWO CONTAINER BERTHS


AT
RAS AL KHAIR

METHOD STATEMENT
FOR DREDGING & RECLAMATION WORKS

DATE: RAMADAN 1435H

CONTENTS

DREDGING WORKS AND CONSTRUCTION OF


TWO CONTAINER BERTHS
AT
RAS AL KHAIR
Item

1.

Page
No.

List of Key Personnel

General Project Details

3.

Method of Construction

4.

APPENDIX A

2.

5.

Method Statement indicating Compliance


with all Clauses of Specification

APPENDIX B

Photographs of Equipment

1. LIST OF KEY PERSONNEL

Title

Name

Telephone No.

Project Manager

Dredging Engineer

Dredger Master

Technical Office Engineer

Safety Engineer

Port Control

VHF Channel 67/19

0515187877

SEAPA Resident Engineer

Mehdi

0551918151

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized Contracting


Company Ltd.
Ramadan 1435H
Page 3 of 61

Project
Manager

Dredger
Master

Technician
Mechanic

Dredger
Operator

Divers
Seaman

Heavy Duty
Operator

Civil
Foreman

Mechanical
Chief
Engineer
Reclamation
Engineer

Secretary

Laboratory
Technician

Technician
Electrical
Mechanic

Laboratory
Helper

Civil
Foreman

Welder
Pipe fitter
Labor

Heavy Duty
Driver

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 4 of 61

2. GENERAL PROJECT DETAILS

1. General

The Ports Authority is developing the Port of Ras Al Khair. The marine part of this
development is the construction of the following works:

Remaining 185m of Berth 8 to complete the East West line of the berths

A Roll on Roll off berth at junction of Berths 8 & 9.

Two Container Berths 330LM each

Dredging of Basin alongside to a depth of -15.00

Reclamation of all areas behind the quaywall and the West lagoon.

Edge Protection works at the south-west end of Berth 10.

Removal of core rockfill and armour from existing bund.

2. Method Statement
Under the terms of the contract a Method Statement is required to be submitted for
Dredging & Reclamation works of the contract.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 5 of 61

(Contd. from previous page)

Description of Works

Works included in this Method Statement are as follows:

a) Dredging of basin up to depth -15.00 .

b) Dredging of trench to depth -18.50 for Berth 8 and Roll on Roll off Berth.

c) Dredging of trench to depth -20.00 for Berths 9 & 10.

d) Reclamation of storage area behind quaywalls.

e) Reclamation of lagoon area west of the existing road.

f)

Provision of surcharge in various Storage Areas as required and


directed by the Engineer.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 7 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 8 of 61

METHOD OF CONSTRUCTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.

Survey
Boreholes & Testing
Permits from Govt. Agencies
Contractors Working Area
Equipment utilized for Dredging & Reclamation
Construction Schedule
Dredging Calculations
Sequence of Works
Reporting & Information
Monitoring
Risk Analysis & Mitigation
Compaction requirements for Reclamation
Contractors Comments

1. SURVEY
The Survey Points and Bench Marks provided by the Ports will be utilized for the project.
Other points will be established for convenience of checking, and will be submitted to the
Engineer for approval before usage.
Topographic and Hydrographic surveys will be carried out in the presence of the Engineers
representatives. Arrangements for spot checking (soundings) shall also be made to ensure
matters remain under check.
Multi beam echo sounder will be employed for all hydrographic survey work.
Prior to commencement of dredging, a number of runs by the echo-sounder will establish
the presence of any obstruction on the sea-bed.
envisaged that this should be a problem.

As the Port is a new port it is not

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 9 of 61

Tide Gauges, wind sock etc. will be provided to ensure all weather parameters are known
during the dredging operations.

2. BOREHOLES & TESTING

A local firm will be engaged after obtaining approval from the Ports and all necessary information
obtained.
From the borehole information provided at tender stage, material appears to be good, suitable
material for reclamation.
However it appears that no boreholes were taken in the Basin Area. At least two boreholes wll
be taken in the Basin Area up to -18.00 or as directed by the Engineer to confirm suitability of
material.
Daily testing or as required at the change of dredged materials will be carried out in the presence
of the Engineers Representative and commensurate action taken as regards the suitability of the

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 10 of 61

material for reclamation purposes. Any poor material encountered will be dumped in the Spoil
Area.
After completing the Soil Investigations, if the results differ appreciably from that shown at the
tender stage, appropriate adjustments will be made to the Method Statement, to the approval of
the Engineer.

3. PERMITS FROM GOVT. AGENCIES

As we will be working within the confines of a working Port, we envisage that there will be
no requirements of Permits or any permission to be taken from any Govt. Agency (Four
member committee etc.).
However, on our own, we will be taking care not to spoil the environment and will ensure
that whatever measures need to be taken are followed by all staff and equipment.
Any permit requirements from the Coast Guards or the Customs will be fulfilled to their
satisfaction.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 11 of 61

4. CONTRACTORS WORK AREA

A Contractors Work Area is shown in the Tender drawings which will be developed for the
production of the blocks.
A block loading jetty will be constructed at the required location where all mooring craft and
marine equipment will be parked when not in use or during inclement weather. Care will be
taken not to interrupt Port small craft traffic at Berth 4.
Diesel, the fuel for most marine craft will be brought in from land after taking permission from the
required Customs and Coast Guards authorities.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

5.

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 12 of 61

* EQUIPMENT UTILIZED FOR DREDGING & RECLAMATION

1.

Dredger
IHC Beaver 65 DDSP
(Modified by IHC)

Dredging depth:
Cutter Power:
Delivery Pipeline:
Dredger Pump:

22m.
700 KW
650mm dia.
. HP

2.

Tug Boat
IHC Delta Multicraft
1400 DMC 1400

Power:
Speed:
Bollard pull:

609 HP
8 knots
7T

3.

Survey Boat

4.

Pilot Boat

5.

Hopper Barge

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 13 of 61

Self propelled barge


6.

Pipeline 650mm dia.

Length:

7.

Pontoons
Backhoe

8.

Bulldozers

9.

Shovel

10.

Grader

Caterpillar

11.

Steel Roller

Volvo

12.

Other Equipment:

Tide Gauge
GPS
Wind sock
Silt curtains, booms etc.

m.

Doosan

* Note: Photographs of marine equipment included in Appendix B

6. CONSTRUCTION SCHEDULE

The Construction Schedule for all works is enclosed.

It can be seen that dredging

westwards in the line of Berth 8 up to a depth of -15.00 is the first activity to be


undertaken.
The same dredger will be employed to form the trench up to -18.50 after which blockwork
placing for the quaywall could commence.
As there are no interface requirements with any other contractor, we do not foresee any
problem in continuing with the dredging and blockwork installation on the rest of the
quaywalls as programmed.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

The stages of construction are shown on Page No. 14.

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 14 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized Contracting


Company Ltd.
Ramadan 1435H
Page 14 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 15 of 61

7. DREDGING CALCULATIONS

Total volume to be dredged

2,125,540 cu.m.

Assume period required

15 months

Volume of dredging/month

141,703 cu.m./month

Rate of Dredging, assuming 20 days/month work

7,085 cu.m./day

Note that the dredger is provided with pumps, situated below water level on the ladder, hence is
capable to carry out dredging operations up to -22.00 satisfactorily.
i.e. one dredger is capable to carry out all dredging works of the contract. However, should the
need arise for a grab dredger for cutting the trench or for removal of hard material in the Basin,
we have arrangements for deploying a grab dredger.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 16 of 61

8. SEQUENCE OF WORK
The sequence of work will be as follows:
1. IN-SURVEY
2. DREDGING
a) Berth 8 & Ro Ro

Dredging up to -15.00 in the line of the trench.


Dredging of trench up to -18.50 .
Approval from Consultant for proceeding with quaywall construction.

b) Berths 9 & 10

Dredging up -15.00 in the line of the trench


Dredging of trench up to -20.00 .
Approval from Consultant for proceeding with quaywall construction.

c) Basin
Dredging up to -15.00 .
3. OUT SURVEY
4. RECLAMATION
Prior to any reclamation the following works need to be carried out:
a. Removal of rockfill underlayer and core from rear of Berth 8 and its storage.
b. Removal of rockfill underlayer and core from the rear of Berths 9 & 10 and its
storage.
c.

The rock armour, underlayer etc. of the West Breakwater (besides the Lagoon)
will be removed and stored at the location required by the Ports.

d. A further layer and geotextile will be provided before reclamation will proceed in
the area.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 17 of 61

8. SEQUENCE OF WORKS (Contd.)

e. Filling the area behind Berth 8.


f.

All excess dredged material at this stage ill be diverted to the West Lagoon area.

g. Filling the area behind Berths 9 & 10 up to bund.


h. After completion of blockwall, provision of rear rockfill, filter, geotextile etc.
complete the reclamation up to the sand bund *.
Stages I V
Drawings included in Appendix B show the various stages of dredging and reclamation.

* Note: Sand bund will be of coarse material and will not in any way alter the characteristics of
the fill.

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 18 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 19 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 20 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 21 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 22 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company
Ltd.
Ramadan 1435H
Page 23 of 61

9. REPORTING & INFORMATION


Daily Reports will be submitted to the Engineer.
Photographs of work in progress will be submitted together with the Weekly Reports.
An In-survey will be carried out in the presence of the Engineers Representative and the
sheets signed for records.
An Out-survey will be carried out in the presence of the Engineers Representative suitable
for submission by the Ports to the mariners.
The dredger and all support vessels will remain in constant contact by radio with the
Harbour Master to ensure none of the Port incoming or outgoing vessels are interrupted by
the operations.
24 hour operation is envisaged for all dredging and reclamation work.

10. MONITORING
Constant monitoring of the following parameters will be carried out:

Turbidity
Movement of silt
Water quality.

Please note that the temperature of the water may be higher in the basin due to the presence of
the Maaden outfall. The water may be saltier too.
Consequently, care will be taken regarding concrete for the structures, steelwork, slope protection
rock etc. to ensure that they stand well to the additionally aggressive conditions found in the
Basin. It is expected that the temperature and salinity of the Basin may reduce after dredging has
been carried out as a larger body of water will be available for dispersion.

11. RISK ANALYSIS AND MITIGATION


The Harbour appears to be well protected where the dredging works and reclamation
works are to take place. Large current/waves cannot enter the harbor as breakwaters

shield the Port from the North and the North-west winds. The lagoon is totally protected
from the west and the north sides. Little mitigation measures need to be carried out in this
respect.
Interference with shipping is also foreseen to be minimum as all work is to the west of the
existing shipping berths and traffic. Only small boats, vessels visiting Berth 4 will need to
be diverted slightly when the final dredging up to -15.00 in the basin will be carried out.
This should be simply straightforward and should not pose any problem or would require
mitigation measures.
Any risk to environment shall be mitigated by ensuring there are no leaks in the joints of
the discharge pipes.
If dredging operations result in silt/sedimentation finding its way into the adjacent basin,
silt curtains will be provided to ensure that it is kept to a minimum.
As the Western Lagoon is on the other side of the main road leading to the Aluminium
Berths 5, 6 & 7, alternative roads will be provided if the permanent road will be closed for
traffic. Alternatively if the Port allow ramps with mild slopes will be provided to ensure
passage of heavily loaded trucks without difficulty.

There will be some interface

requirement with the contractor CHEC who has constructed a temporary road west of the
Main Road on which they will be moving their Armour Blocks made available from the
North Breakwater.
All marine staff will be provided with life jackets, life buoys and rafts will be available for
any emergency.

11. RISK ANALYSIS AND MITIGATION (Contd..)

Adequate beacons, buoys etc. will be provided for the dredging operations to eliminate
chances of collision. Flood Lighting will be provided such that it would not confuse the

shipping. All vessels shall be equipped with VHF phones and mobile telephones to ensure
rapid communication.
We understand that a number of days will be lost for the dredging operation because of
dusty and windy weather. All marine craft will be parked safety during such conditions and
the Ports kept well-informed of their positions.
Care will be taken in the sequence of reclamation that tail water never gets trapped.
Overflow weirs etc. will be constantly provided and monitored to ensure discharge of
excess water.

12. COMPACTION REQUIREMENTS FOR RECLAMATION

From the materials indicated to be dredged and used for reclamation, it appears that the
required densities will be reached without resorting to either Dynamic Compaction or
Vibroflotation.

As the dredged material appears to be more in quantity than the reclamation area volumes,
it is expected that surcharge will need to be placed on all areas. This in itself will provide
the long term consolidation required for either the Lagoon Area or the Port Storage Areas.
Areas behind the wharf which are subject to more stringent requirements will be carried out
by the future construction contractor of the Container Terminal.
Homogeneity of fill will be ensured by constant movement of the dredged material by
bulldozers. Fine material pockets will not be allowed to form that may lower the quality
requirements of the fill.
Should densities not be achieved for any reason above water levels, 10T rollers will be
provided to compact the fill in layers to give the required compaction in the Storage Areas.

13. CONTRACTORS COMMENTS

a) Surcharge
From preliminary calculations it appears that there will be more dredged material than what is
required for reclamation. Should the quantity of dredging exceed the allocated BOQ quantity,
we assume that a Change Order will be provided as all quantities are subject to

remeasurement. Consequently, surcharge will have to be provided in the reclamation areas


which will induce settlement and consolidation of the fill in the long run.
As the surcharge will be in the wind direction, some form of treatment would be required at
the top of the surcharge to ensure that it does not blow itself into the basin or other areas of
the Port.
b) Filling of West Breakwater
Before filling could commence in the Lagoon area, the eastern side of the breakwater will
need to be provided with a layer of filter and geotextile. Apparently there is no provision for
this work in the contract BOQ.

APPENDIX A

METHOD STATEMENT INDICATING


COMPLIANCE WITH ALL CLAUSES OF
SPECIFICATION

(C)4

DREDGING AND RECLAMATION

(C)4.1

Dredging
All

Dr
ac
ba
ag

Rates for
dredging all
materials

(C)4.1.2
The removal of rubbish, foreign object or obstructions
found on the seabed.

No

Obstacles

(C)4.1.3
In order to prevent damage to his plant and equipment, it
is recommended that the Contractor should locate and remove such
obstructions before beginning dredging.

No

Plant and
methods

(C)4.1.4
The plant and methods used for dredging shall be subject
to the prior
approval of the Engineer, but such approval shall not relieve the
Contractor of his responsibility for ensuring that his plant and
methods are suitable, efficient and sufficient for the works, nor of any
other of his responsibilities under the Contract.

De
at
(w
dr
a
wo
Da

The method of dredging and transporting material shall be


such as to obviate any deposition of material navigable channels or
berths. In the event of unavoidable spillage occurring to such an
extent that siltation of any navigable channel or berth occurs, the
Contractor shall, at his own expense, immediately restore the affected
channel or berth to its original depth to the satisfaction of the Ports
and the Engineer.

No
th
its
re
em
do

General

(C)4.1.1. The area to be dredged is shown in the Drawings.


dredging shall be to the profiles shown in the Drawings.

Program
me to be
flexible

(C)4.1.5
The programme of dredging must be flexible. It may need
to be varied to meet the working needs of the Port and the
construction programme, or for any other reason considered
necessary by the Engineer. Meetings shall be held with the Engineer
or any other party, as and when required by the Engineer, to arrange
a suitable programme.

(C)4.1.6
Tolerances
and
limitations

(C)4.1.7

No
de
qu
ex
re

Not used.
The tolerances and limitations of dredging are as follows:-

(a) Quaywall foundation trench.


The finished trench profile shall not, at any point, be shallower than the design
profile shown in the Drawings, neither shall it be deeper than the design profile
by more than 250mm, nor wider than the design profile by more than 500mm (on
each side). Should these tolerances be exceeded, except on the written
instructions of the Engineer, the Contractor shall, at his own expense, backfill
over cut areas in accordance with the Engineers instructions.
(b) Quay-Side
Within 30 metres of the quay face, the Contractor shall not over-dredge by more
than 250mm below the design profile. Should such over-dredging occur, the
Contractor shall, at his own expense, backfill to the design profile with approved
material.

Side
slopes

(C)4.1.8
The side slopes to the boundaries of the prescribed dredging areas
and the side slopes to the quay-wall foundation trench shall be dredged in
accordance with the design profiles shown in the Drawings, or to whatever other
such profiles as the Engineer may decide, having regard to the nature of the
materials present. Alternatively, if approved by the Engineer, a series of benches
equivalent to the exhibited side slope may be dredged, and any such benching
shall be deemed to be a side slope for the purpose of this Clause.

Agr
to f

Disposal
of dredged
material

(C)4.1.9
If dredged material is suitable for use as reclamation fill (as
specified in (C)4.2.4), it shall be deposited in areas to be reclaimed. If it is not
suitable for this purpose, it shall be dumped, in accordance with the Engineers
instructions, in the approved spoil ground shown in the Drawings.

Dre
will
coo

Disposal of
dredged
material
(Contd.)

Before tendering, the Contractor shall satisfy himself as to the


distance between areas to be dredged and the spoil ground and reclamation
areas and shall include in his rates and prices for dredging for the conveyance
of dredged material from any part of the areas to be dredged to any part of the
spoil ground or reclamation areas. No claim will be entertained in respect of
length of haul between the dredged areas and the spoil grounds specified
herein.

No

Should the dredged material be utilized for reclaiming the western


lagoon, the contractor must ensure that his operations do not disrupt Maaden
Aluminium Companys and Port traffic to Berths 5-7.

No

No dredged spoil shall be dumped in any area other than the


specified spoil ground or such other spoil ground as may subsequently be
directed by the Engineer. The Contractor shall hold the Ports indemnified
against any claim that may be made against it through the Contractors default
in this respect.

No

The rates for dredging and disposal of material shall include for all
temporary moorings, stages, pipe work, sluices, temporary bunding and any
other works necessary for carrying out the work in an efficient manner.
No
simultaneou
s discharge

(C)4.1.10

Surveys of
dredging
areas

(C)4.1.11 Prescribed dredging areas shall be surveyed from time to time


during and after dredging operations, as specified below or as required by the
Engineer, for the purposes of measurement or for any other reason. The cost
of all such surveys will be deemed to be included in the Contractors rates and
prices for dredging.

Ag

Not used.

Unless otherwise specified or required by the Engineer, surveys shall be made


using a suitable launch fitted with an approved echo sounder and positioning
shall be made by using approved electronic location equipment. For this
purpose, the Contractor shall provide operators who have been trained by the
supplier of the equipment and certified as capable of such duties.

Jo
co
qu

No

Surveys
of
dredging
areas
(Contd)

Bar calibration or the echo sounding equipment shall be carried


out prior to the commencement of each days surveying and at such other
times as the Engineer may direct and the corrections shall be agreed between
the Contractor and the Engineer.

Not

Surveys
of
foundation
trench

(C)4.1.12 The method of survey of the quay-wall foundation trench after


completion, or alleged completion, shall consist of close-centred spot
soundings to provide cross-sections at regular intervals. The techniques used
and the frequency of soundings and cross-sections shall be to the approval of
the Engineer. Notwithstanding any such approval, the techniques and
frequencies shall be amended if required by the Engineer as the work
proceeds. For the purpose of this Clause, the foundation trench shall be
deemed to include for all dredged side slopes or benches, and the surveys
shall also be extended for an approved distance on each side of the trench.

Agr

Joint
surveys

(C)4.1.13 Before dredging commences, the Contractor and the Engineer


shall jointly make survey of all areas which are to be dredged and all areas in
which reclamation is to be placed. The method and frequency of sounding
shall be to the Engineers approval. The Contractor shall prepare a drawing
showing the agreed levels, and this shall be signed by the Contractor and the
Engineer. On the basis of the agreed drawing, the Contractor shall prepare
drawings showing sections through these areas, all to the Engineers
satisfaction.

In-s
Con
Eng

Unless otherwise specified or required by the Engineer, the survey procedure


described in Clause (C)4.1.11 above shall be repeated for all interim and final
measurements, and the quantities determined by difference, but with due
regard to over-dredged material (see Clause (C)4.1.17).

Agr

Payment

(C)4.1.14 Payment for dredging will be made under the appropriate items in
the Bills of Quantities, and the quantities shall be determined in accordance
with Clauses (C)4.1.11 to (C)4.1.13 for the following:(a)
the sum of net volumes of materials dredged from
prescribed dredging areas and deposited in reclamation areas, as
specified.

Agr

Ag
(b)
the sum of net volumes of materials dredged from
prescribed dredging areas and dumped in the spoil ground or
elsewhere, as specified.
No payment will be made for dredging per se, in borrow areas, or
elsewhere as specified, for the purpose of winning reclamation fill.

Siltation,
inflow etc

(C)4.1.15 Payment for dredging any one area will be made once only. Until
all dredging and reclamation has been completed to the Engineers
satisfaction, the Contractor shall remain responsible for the removal from
dredged areas of any subsequent influx of materials, whether this be caused
by siltation, sedimentation, inflow, collapse of side slopes, discharge or
deposition, or any other cause, irrespective of whether or not this may be
directly attributable to the Contractors operations.
When required to do so by the Engineer, the Contractor shall
determine the depth of siltation (the term shall be taken to include the influx of
silt or mud, however caused) in any specified area, at any time after dredging.
The method, which shall be to the approval of the Engineer, shall enable such
deposits to be differentiated from the underlying materials where, in the
opinion of the Engineer, this is reasonably possible.

No

(C)4.1.16 The Engineer will give monthly certificates on account of sums


which may become payable. Interim measurements will be based on
either:-

Interim
measurement
s
a)

agreed joint surveys, as specified in Clause (C)4.1.13 or

A
b)

agreed net volumes of material dredged during the month to which


the Certificate relates.

Over-dredging

(C)4.1.17 Payment will not be made for any material dredged from below
or outside of the design profiles shown in the Drawings, or any other such
profiles as the Engineer may from time to time direct, and the volume of
any such material shall be deducted from the total volume dredged to
determine the net volume for which payment is due.

Final
measurement

(C)4.1.18 On completion, or alleged completion, of dredging in any


particular area, the survey procedures specified in Clause (C)4.1.11 to
(C)4.1.13 above shall be repeated. If it is found that the required profile
has not been attained, or the required slopes not properly formed, the
Contractor shall further deepen, extend or correct such areas as
necessary, all to the satisfaction of the Engineer. A further joint survey of
the area shall then be made for the purpose of final measurement. A
deduction shall be made, in accordance with Clause (C)4.1.17, for
material dredged from below or outside of the required profile.

Final sweep of
dredged areas

(C)4.1.19 On completion of all dredging and reclamation, the Contractor


shall sweep the whole of the dredged area, using equipment approved by
the Engineer, to ensure that no high spots or obstruction remains. If any
such high spots or obstructions are revealed, the Contractor shall remove
them at his own expense.

A
o
b

Weekly
returns

(C)4.1.20 The Contractor shall, at the end of each week, submit to the
Engineers Representative in duplicate, and in such form as the Engineer shall
require, a return of the measurements of materials dredged.

Rates to be
inclusive

(C)4.1.21 All costs in connection with the provision and maintenance, in


good working order, of all necessary plant and equipment necessary for
dredging will be deemed to be included in the rates and prices in the priced
Bills of Quantities.

(C)4.2
General

Reclamation

(C)4.2.1
The area to be reclaimed is shown in the Drawings. All
reclamation shall be carried out to the lines and levels shown in the Drawings,
unless otherwise directed by the Engineer.
The levels shown in the Drawings shall be deemed to be those
required at the end of the Maintenance Period. The Contractor shall make
allowance, therefore, for settlement of the reclamation fill after placement.
This shall be done by initially placing the fill levels higher than those shown in
the Drawings and the magnitude of this allowance shall be agreed between
the Contractor and the Engineer (or otherwise determined by the Engineer) on
the basis of all available data. Fill above water level shall be laid and
compacted in 300mm thick layers and shall be compacted to 75% Relative
Density. The density tests shall be carried out on a 50m grid.
The Contractor shall allow in his rates and prices entered in the
priced Bills of Quantities for the additional material required to allow for
settlement.

Source of
reclamation
material

(C)4.2.2
The source material provided for reclamation filling shall consist of
material arising from any source always that both the source and quality of the
material are to the approval of the Engineer. Any such approval of source
material given by the Engineer shall not relieve the Contractor of his full
responsibility for ensuring that the finished reclamation satisfies all the
requirements of this Specification.

A
ou
be
ma

Fil

Ag

Th
wil
fro

Samples for
approval

(C)4.2.3
The Contractor shall submit any such samples of the reclamation
fill source material as are required from time to time by the Engineer for the
purpose of approval.

Reclamatio
n fill grading
above chart
datum

(C)4.2.4.2 All material deposited in the reclamation for use as reclamation


fill above chart datum shall consist of naturally occurring soils and rock
fragments and shall have a grading curve wholly within the limits shown
graphically in Figure 2 below. The principal limits are as follows:

La
co
sa

(C)4.2.5
The placement of reclamation fill shall be carried out in such a
manner that segregation of material is limited and that specified gradings are
satisfied throughout the as-placed material.

Bu
m
ac
m

Unsuitable
material

(C)4.2.6 Any material not complying with the requirements of the


Specification, or any other such requirements as the Engineer may from time
to time stipulate, shall be deemed unsuitable and shall be rejected. Material
so rejected shall be removed from the Site and replaced with suitable
reclamation fill all at the Contractors expense.

Programm
e to be
flexible

(C)4.2.7 The programme of reclamation shall be flexible. It may need to be


varied to meet the working requirements of the Port and the construction
programme, or for any other reason considered necessary by the Engineer.
Meetings shall be held with the Engineer, or any other party, as and when
required by the Engineer to arrange as suitable programme.

Clearance
of seabed

(C)4.2.8 Before depositing any reclamation fill, the Contractor shall remove
all vegetable matter, foreign objects and any other substances on the seabed
which, in the opinion of the Engineer, could have an adverse effect on the
Works. The cost of such removal shall be deemed to be included in the rates
and prices entered by the Contractor in the Priced Bills of Quantities.

No
ou
rep
La
qu

Segregation
to be
minimized

Pumping

(C)4.2.9 If pumping plant is utilized, it shall be capable of placing reclamation


fill to any level as directed by the Engineer in any part of the reclamation. This
includes the placement of reclamation fill as a surcharge to levels higher than
the finished levels shown on the drawings, as described in Clause (C)4.2.14 of
this Specification.

Th
to h

Su
as
in
Bo
nec

Distance to
borrow
areas

(C)4.2.10 Before tendering the Contractor shall satisfy himself as to the


distance between any borrow area and the reclamation area. He shall include
in his rates and prices for the conveyance of material from any part of any
borrow area to any part of the reclamation area and no claim will be
entertained in respect of length of haul.

Transport
of
reclamatio
n fill

(C)4.2.11 Subject to the requirements of this Specification, the fill material


shall be discharged into the reclamation area by whatever means the
Contractor considers most suitable, including dumping and/or pumping
through floating pipelines, provided always that his methods are to the
approval of the Engineer. Whilst depositing into a reclamation area material
dredged from the prescribed dredging area, the Contractor shall not
simultaneously discharge into the same area material originally won from a
borrow area.

Fil
the
by
wh
da
wil

Method
statement
with tender

(C)4.2.12 The Contractor shall, at the time of tendering, submit to the


Engineer an outline description of the methods he proposes to use to convey
and discharge material for reclamation.

Me
su

Method of
reclamatio
n

(C)4.2.13 Reclamation will be performed by placing of material (if suitable)


dredged from the prescribed dredging area shown on the Drawings or as
instructed by the Engineer.

Temporary
surcharge

(C)4.2.14 As and where directed by the Engineer, additional material shall be


placed as a temporary surcharge to pre-load the reclamation fill. The extent,
level and duration of all surcharge loading will be decided by the Engineer,
normally on the basis of soils tests and instrumentation, and the work shall be
carried out strictly in accordance with the Engineers instructions.
Joint surveys shall be made in accordance with Clause (C)4.2.17 of this
Specification, as and when necessary for measurement purposes.

Fo
w
w

Disposal
of
surcharg
e
material

(C)4.2.15 The surcharge material shall, when decided by the Engineer, be


removed and carted away. Unless otherwise approved by the Engineer, all
surcharge material shall comply with Specification Clause (C)4.2.4.

No

Joint surveys shall be made, in accordance with Clause (C)4.2.17 of this


Specification, as and when necessary for measurement purposes.

Method
of
payment

(C)4.2.16 Payment for reclamation will be as follows:

Measure
-ments

(C)4.2.17 Before the placing, in any area, of material obtained from borrow
areas, the Contractor and the Engineer shall make a joint survey and the
results shall be recorded on a drawing showing the agreed levels, which shall
be signed by the Contractor and the Engineer or his Representative. The
total as-placed volume of reclamation which will be required to reclaim any
area shall be calculated using levels shown in this drawing and the finally
required reclamation levels.

For material dredged from the prescribed area shown on the


Drawings or as instructed by the Engineer, payment will only be made for
dredging as described in Clause (C)4.1.14. No additional payment will be
made for reclamation.

Unless approved by the Engineer, the Contractor shall not place


material dredged from the prescribed dredging area upon material obtained
from borrow areas. If such placing shall be approved, sufficient joint surveys
shall be made to enable the volume of material from the prescribed dredging
area which has been placed to be calculated and this volume shall be
deducted from the volume of reclamation determined as described above.

No

M
t
s
c

MeasureMents
(Contd)

Reclamation areas shall be surveyed from time to time before,


during and after reclamation, as specified above or as required by the
Engineer, for the purposes of measurement or for any other reason. The
cost of all such surveys will be deemed to be included in the Contractors
rates and prices for reclamation.

Weekly
returns

(C)4.2.18 The Contractor shall, at the end of each week, submit to the
Engineers Representative in duplicate, and in such form as the Engineer
shall require, a return of the measurements of reclamation materials placed.

Rates to be
inclusive

(C)4.2.19 All costs in connection with the provision and maintenance, in


good working order, of all necessary plant and equipment necessary for
raising the reclamation areas to the required levels will be deemed to be
included in the rates and prices in the priced Bills of Quantities.
The rates and prices shall also include for the costs of provision,
and subsequent removal, of all temporary culverts and sluices necessary for
the satisfactory completion of the reclamation in accordance with this
Specification.

Compactio
n to 75%
relative
density

(C)4.2.20 Where the reclamation fill is not subjected to surcharge loading,


all fill above Mean High Water Springs Level shall be thoroughly compacted
in layers by vibratory rolling, or by other means to the Engineers approval,
such that the finished relative density of each layer is at least 75%. Relative
density Dr, shall be defined in terms of voids ratio, e, as follows:-

where emax and emin are determined using the procedures given in A.S.T.M.
Standard D2049 Test for relative density of cohesionless soils.

A
as
de

Testing of
samples

(C)4.2.21 Representative samples of the reclamation fill within its


upper 2 metres shall be tested in accordance with the Standard defined
in Clause (C)4.2.20 above to determine their maximum and minimum
voids ratios. Further samples shall be submitted to the Engineer if
required.

In-situ density
measurement
s

(C)4.2.22 The Contractor shall measure the in-situ dry density of the
compacted reclamation fill, at regular intervals as directed by the
Engineer, using the procedure given in BS 1377 Test 15(B). Tests will
be required by the Engineer at various levels within the upper 2 metres
of fill and the Contractor shall excavate shallow pits as necessary to
enable these tests to be made. Excavation of the last 200mm down to
test level shall be done carefully by hand to avoid disturbance of the soil
to be tested.

Testing
prior to
construction

(C)4.2.23 In-situ density tests shall also be made, in accordance with


the Engineers instructions, within the areas of buildings or other
structures prior to their construction. The maximum depth of such tests
below finished level will be 2 metres. (Where investigation to greater
depth, by instrumentation, boreholes or Dutch probes, is also required,
payment for these will be made under the items in the appropriate
section of the Bills of Quantities.

---------------- x X x ----------------

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H

Page No.:

Page 43 of 61

APPENDIX B

PHOTOGRAPHS OF EQUIPMENT

1.
2.
3.
4.

Dredger
Tug Boat
Pilot Boat
Any other

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 44 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 45 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 46 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 47 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 48 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 49 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 50 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 51 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 52 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 53 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 54 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 55 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 56 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 57 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 58 of 61

DREDGING WORKS AND


CONSTRUCTION OF
TWO CONTAINER
BERTHS AT
RAS AL KHAIR

METHOD STATEMENT
FOR
DREDGING AND
RECLAMATION WORKS

Issued by:
Date:
Page No.:

Rawabi Specialized
Contracting Company Ltd.
Ramadan 1435H
Page 59 of 61