Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question 1

Table (1)

Immediate
A small project activities and related information are given in table Activity
predecessor(s)
(1).
A
a) Develop the AOA, AON, TSN
B
b) Calculate ES,LS,LS, AND LF and Find the critical path using
C
AON network
D
B
c) Find Gantt chart for each
E
A, D
d) Consider calendar date, the project starts Saturday, first of the
F
C
month and Friday is holiday. Draw the bar chart and
G
E, F
determine the project finish date and needed working days
e) Considering the constraints of ZZBD 3,2, FSCF 2, SSFG 4, SFEG 3; Determine:
i. Network data of forward and backward calculations and Total Float (TF)
ii. Critical path of the network. How it is differ from question 3b?
f) Develop load diagram of the resource, and find
i.
average daily requirement;
ii.
Critical Index
iii.
Effectiveness value
iv.
use Burgess Algorithm to level resource

Time,
days

Manpower

Equipment

E1

E1

E2

10

E2

E3

E4

E5

Solution
a)

AOA

AON

E, 3
2

A
,

A, 2
B, 5

D, 10

START

E
,

B
,

D
,

C
,

F,
6

G
,

C, 1
F, 6

G, 8

a) TSN
1

10

11

12

13

14

15

16

17

18

19

20

21

22

A,2
B,5
C,1

D,10

E,3

F,6

G,8

23

24

25

26

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

b) AON and critical path [carry calculation]


0

2
A
2

13
0

START
0
0

B
5

0
11
Activity
Free Float
Total Float

A
13
13

15

D
1

15

15

1
C
1

E
3

18

18

18

18

12
C
11
11

G
8

26

7
F
6

12

B
0
0

26

D
0
0

18
E
0
0

F
11
11

G
0
0

c) Gantt chart
T
B
D
E
G
A
C
F

01

02

03
B

04

05

06

07

08

09

10

11

12

13

13

15

16

17

18

19

20

21

22

23

24

24

26

CRITICAL
E

E
S

A
C

L
S

A
C

d) Calendar schedule
July
1
F

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

M
B

D
E
G

A
C
F

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

FORWARD PASS
Initial Time

EF FF D
Activity A: ESA=0; EFA= ESA+DA=0+2=2; ------------------------------------------------------------------------------ij
j
i

ESi SFij D j
Activity B: ESB=0; EFB= ESB+DB=0+5=5; ------------------------------------------------------------------------------[2]EF j ES j D j

e) Solution with constraint (lag times)


EF FS
i
ij

Forward pass:---------------------------------------------------------------------------------------------[1]ES j Max ( all i ) ESi SSij

Activity C: ESC=0; EFC= ESC+DC=0+1=1; -------------------------------------------------------------------------------

Activity D: ESD=ESB+SSBD=0+3=3 OR EFB+FFBD-DD=5+2-10=0 Then ESD=3; EFD= ESD+DD=3+10=13-Activity E: ESE=13; EFE= ESE+DE=13+3=16---------------------------------------------------------------------------Activity F: ESF=EFC+FSCF=1+2=3; EFF= ESF+DF=3+6=9----------------------------------------------------------Activity G: ESG=ESE+SFEG-DG=13+4-8=9 OR ESF+SSFG=3+4=7 Then ESG=9; EFG= ESG+DG=9+8=17---BACKWARD PASS
Backward pass: --------------------------------------------------------------------------------------------

Terminal Time

Activity G: LFG= EFG =17; LSG= LFG - DG =17-8=9; ----------------------------------------------------------------- LS FS

Activity F: LFF=LSG-SSFG+DF =9-4+6=11; LSF= LFF DF =11-6=5-----------------------------------------------[3]LFi Min( all j ) LF j FFij


j

ij

LS SS D
Activity E: LFE=LFG-SFEG+DE =17-4+3=16; LSE= LFE DE =16-3=13-------------------------------------------ij
i
j

LF j SFij Di
Activity D: LFD=13; LSD= LFD DD =13-10=3; ------------------------------------------------------------------------[4]LSi LFi Di

Activity C: LFC= LFF-FSCF = 10-2=8; LSC= LFC DC=8-1=7-------------------------------------------------------Activity B: LFB=LSD-SSBD+DB=3-3+5=5 OR LFD-FFBD=13-2=11 Then LFB=5; LSB= LFB DB =5-5=0----Activity A: LFA=13; LSA= LFA DA =13-2=11; -------------------------------------------------------------------0

2
A
2

11
0

START
0
0

B
5

D
10

0
7

Activity
Free Float
Total Float

A
11
11

B
0
0

13
13

13

13

13

1
C
1

C
7
7

16

17
G
8

17

9
F
6

D
0
0

E
3

16

11

E
0
0

F
2
2

G
0
0

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

f) Resource and leveling


TI
BDEGACFTI
R

R
R2

01

02

03
B

04

05

06

07

08

09

10

11

12

13

13

15

16

17

18

19

20

21

22

23

24

24

CRITICAL
E
G

E
S

A
C
F
0
1
6

0
3
8
2
4
6
4

02
10

16

3
6

10
0

0
4
8
3
2
6
4

0
5
8
4
0
6
4

06

07

08

09

10

11

12

13

13

15

16

17

18

19

20

21

22

23

24

24

26

48

56

59

62

65

68

71

74

77

80

84

88

92

95

98

3
10
1

3
10
4

3
10
7

3
11
0

3
11
3

3
11
6

64

64

16

16

16

9
64
8

R2

T
B
D
E
G
A
C
F
TI
R

R
R2

26

01

02

03
B

04

05

06

07

08

09

10

11

12

13

13

15

16

17

18

19

20

21

22

23

24

24

26

CRITICAL
E
G

L
S

A
C
F

0
1
3

0
2
3

0
3
3

0
4
3
1
2

0
5
3
1
5

0
6
3
1
8

0
7
3
2
1

0
8
3
2
4

0
9
3
2
7

1
0
3
3
0

1
1
3
3
3

1
2
4
3
7
1
6

1
3
8
4
5
6
4

13

15

10

10

55

65

10
0

10
0

1
6
9
7
4
8
1

1
7
9
8
3
8
1

1
8
9
9
2
8
1

1
9
3
9
5

2
0
3
9
8

21

22

23

24

24

26

3
10
1

3
10
4

3
10
7

3
11
0

3
11
3

3
11
6

R2

69
4

12

120

No. of Resources (Men)

Accumalative Resource (man)

140

100
80
60

ES
T

40

LS
T

20

ES
T

10
8

LS
T

6
4
2
0

0
0

10

20

30

10

15

20

25

30

Time, Day

Time, Days

Figure 1 Man Load histogram (Earliest & Latest


Start

Figure 2 man power requirement


4

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Analysis
, =

( )
116
=
= .
()
26

= 2 = (4.462)2 26 = .
2

648
= 0.98
26

=
Load
TI
BDEGACF-

01

TI
R
R
R2

01
3
3
9

694
= 1.013
26

leveled
02

03
B

04

05

06

07

08

09

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

24

26

CRITICAL
E
G

A
C
F
02
3
6
9

03
3
9
9

04
3
12
9

05
3
15
9

06
3
18
9

07
5
23
25

08
5
28
25

09
4
32
16

10
8
40
64

11
8
48
64

12
8
56
64

13
8
64
64

14
8
72
64

15
8
80
64

16
4
84
16

17
4
88
16

18
4
92
16

19
3
95
9

20
3
98
9

21
3
101
9

22
3
104
9

23
3
107
9

24
24
3
3
110 113
9
9
R2

624
=
= 0.961
26
2

No. of Resources (Men)

12
LEVELING

ES
T

10
8
6

LS
T

4
2
0
0

10

15

20

Time, Day

Figure 3 Load Histograms

25

30

26
3
116
9
624

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question 2
A small project activities and related information are given in table.
1. Develop the AOA, AON, TSN
2. Calculate network times and Find the critical path using AON network
3. Find Gantt charts
4. Considering the constraints of ZZAD 3,2, SFDF 2, FSFH 2, SSGI 2; ZZHI 2,1Determine:
a. Network data of forward and backward calculations and Total Float (TF)
b. Critical path of the network.
5. Develop load diagram of the resource, and find
a. average daily requirement;
b. Critical Index
c. Effectiveness value
d. use Burgess Algorithm to level resource

Solution Q1 -16
J, 15

AOA network
F, 6

I, 14

H, 14

1
0

1
2

B, 4

A, 4

D, 7

C, 4

G, 7

K, 10

AON network

E, 7

J, 15

B,4

FSFH 2

F, 6

ZZHI 2,1
H, 14

SFDF 2
ZZAD 3,2
A,4

1
1

D,7

C,4

I, 14
SSGI 2

G, 7

E, 7

K,10

END

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 3 3 4 4 4 4 4 4
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

1 2 3 4 5 6 7 8 9

J, 15

B, 4

TSN network

A, 4

D, 7

F, 6

H, 14

G, 7

E, 7
C, 4

I, 14

K, 10

Solution Q1 -2ES

TF

LS

23

Act
LS

22

LF

30

15

45

11

17

CR@CS
4

11

11

17

11

11

18

17

18

D
7

11

27

17

31

31

14

24

31

25

24

31

17

18

K
35

35

Critical Path activities: A-D-F-H-I


Project duration Time =45 weeks
7

10

45

45

C
31

0
H

17

45

31

14

45

END
45

45

45

King Saud University


Civil Engineering Department

Selected Problems Solution

GE 404 Engineering Management


Summer semester 1433/ 1434H

Solution Q1 -31 2 3 4 5 6 7 8 9

1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 3 3 4 4 4 4 4 4
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

A
D
F
H
I
B
J
E
G
C
K

EST GANTT CHART

1 2 3 4 5 6 7 8 9

1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 3 3 4 4 4 4 4 4
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

A
D
F
H
I
B
J
E
G
C
K

LST GANTT CHART

Solution Q1 -4 Solution with constraint


Forward pass:
Activity A: ESA=0; EFA= ESA+DA=0+4=4;
FORWARD PASS
Activity B: ESB=4; EFB= ESB+DB=4+4=8;
Initial Time
Activity C: ESC=4; EFC= ESC+DC=4+4=8;
EF FS

Activity D: ESD=ESA+SSAD=0+3=3 OR EFA+FFAD-DD=4+2-7=0


i
ij

Then
ESD=3; EFD= ESD+DD=3+7=10;
[1]ES j Max ( all i ) ESi SSij
Activity E: ESE= EFD =10; EFE= ESE+DE=10+7=17;
EF FF D
Activity F: ESF=ESD+SFDF-DF=3+2-6=0 OR EFB= 8;
ij
j
i

Then
ESF=8; EFF= ESF+DF=8+6=14;
ESi SFij D j
Activity J: ESJ= EFB= 8; EFJ= ESJ+DJ=8+15=23;
[2]EF j ES j D j
Activity G: ESG= EFE=17; EFG= ESG+DG=17+7=24;
Activity K: ESK= EFC=8; EFK= ESK+DK=8+10=18;
Activity H: ESH=EFF+FSFH=14+2=16; EFF= ESF+DF=16+14=30;
Activity I: ESI=ESH+SSHI=16+2=18 OR EFH+FFHI-DI=30+1-14=17 OR ESG+SSGI=17+2=19
Then
ESI=19; EFI= ESI+DI=19+14=33;

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Backward pass:
BACKWARD PASS
Activity I: LFI= EFI =33; LSI= LFI DI =33-14=19;
Activity J: LFJ= EFI =33; LSJ= LFJ DJ =33-15=18;
Terminal Time
Activity K: LFK= EFK=33; LSK= LFK- DK =33-10=23;
LS FS

j
ij
Activity H: LFH=LSI-SSHI+DH=19-2+14=31 OR LFI-FFHI=33-1=32

[3]LFi Min( all j ) LF j FFij


Then
LFH=31; LSH= LFH DH =31-14=17
LS SS D
Activity G: LFG=LSI-SSGI+DG =19-2+7=24; LSG= LFG DG =24-7=17
ij
i
j

Activity F: LFF= LSH-FSFH = 17-2=15; LSF= LFF DF=15-6=9


LF j SFij Di
Activity E: LFE= LSG =17; LSE= LFE- DE=17-7=10;
Activity C: LFC= LSG =17; LSC= LFC- DC=17-4=13;
[4]LSi LFi Di
Activity B: LFB= LSF =9; LSB= LFB- DB=9-4=5;
Activity E: LFD=LFE-SFDE+DD=17-2+7=22; OR LFD = LSE=10;
Then
LFD=10; LSD=LFE DE =10-7=3
Activity H: LFA=LSD-SSAD+DA=3-3+4=4 OR LFD-FFAD=10-2=8 OR LSJ=18 OR LSC=13
Then
LFA=4; LSA= LFA DA =4-4=0

ES

TF

LS
8

Act
LS

10

23

LF

18

15

33
ZZHI 2, 1

CR@CS
4

B
5

A
0

FSFH 2

16

30

10

10

15

17

14

17

17

10

10

31

24

G
17

17

24

15

18

C
13

23

17

Critical Path activities: A-D-E-G-I


Project duration Time =33 weeks

10

33

33

19

33

14

33

END

SSGI 2

19

SFDF 2

D
4

14

ZZAD 3, 2
0

33

33

33

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Solution Q1 -51 2 3 4 5 6 7 8 9

A
D
F
H
I
B
J
E
G
C
K

1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 3 3 4 4 4 4 4 4
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

4 4 4 4

EST GANTT CHART


3 3 3 3 3 3 3
4 4 4 4 4 4
5 5 5 5 5 5 5 5 5 5 5 5 5 5
5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 2 2 2
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
5 5 5 5 5 5 5
4 4 4 4 4 4 4
3 3 3 3
2 2 2 2 2 2 2 2 2 2

R 4 4 4 4 8 8 8 8 8 8 8 14 14 14 14 14 14 15 12 12 12 12 12 9 9 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
R 4 8 12 16 24 32 40 48 56 64 72 86 100 114 128 142 156 171 183 195 207 219 231 240 249 254 259 264 269 274 279 284 289 294 299 304 309 314 319 324 329 334 339 344 349
R2 16 16 16 16 64 64 64 64 64 64 64 196 196 196 196 196 196 225 144 144 144 144 144 81 81 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
R2 16 32 48 64 128 192 256 320 384 448 512 708 904 1100 1296 1492 1688 1913 2057 2201 2345 2489 2633 2714 2795 2820 2845 2870 2895 2920 2945 2970 2995 3020 3045 3070 3095 3120 3145 3170 3195 3220 3245 3270 3295

R2

1 2 3 4 5 6 7 8 9

A
D
F
H
I
B
J
E
G
C
K
R
R
R2
R2

3295

1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 2 3 3 4 4 4 4 4 4
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5

4 4 4 4

LST GANTT CHART


3 3 3 3 3 3 3
4 4 4 4 4 4
5 5 5 5 5 5 5 5 5 5 5 5 5 5
5 5 5 5 5 5 5 5 5 5 5 5 5 5
2 2 2 2
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
5 5 5 5 5 5 5
4 4 4 4 4 4 4
3 3 3 3
2 2 2 2 2 2 2 2 2 2

4 4 4 4 3 3 3 5 5 5 5 4 4 4 4 4 4 10 10 10 10 10 10 10 9 9 9 9 9 9 12 11 11 11 11 10 10 10 10 10 10 10 10 10 10
4 8 12 16 19 22 25 30 35 40 45 49 53 57 61 65 69 79 89 99 109 119 129 139 148 157 166 175 184 193 205 216 227 238 249 259 269 279 289 299 309 319 329 339 349
16 16 16 16 9 9 9 25 25 25 25 16 16 16 16 16 16 100 100 100 100 100 100 100 81 81 81 81 81 81 144 121 121 121 121 100 100 100 100 100 100 100 100 100 100
16 32 48 64 73 82 91 116 141 166 191 207 223 239 255 271 287 387 487 587 687 787 887 987 1068 1149 1230 1311 1392 1473 1617 1738 1859 1980 2101 2201 2301 2401 2501 2601 2701 2801 2901 3001 3101

R2

10

3101

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question 8
Consider the time-scaled network given below.
a) Draw the corresponding AON network showing each activity four timings and total float.
b) For Developed load diagram of the resource for EST below, find
i. Average daily requirement
ii. Effectiveness value
iii. Critical Index
c) Perform the resource leveling in order to keep the resource uniform with resource constraint of 5 and find
i. Average daily requirement
ii. Effectiveness value
iii. Critical Index
d) Comment on the budget costing before and after leveling of resources,
Period, week

01

02

03

04

05

06

07

09

10

12

13

14

15

16

17

18

19

20

21

22

23

H
3@1500SR
J
2@500SR

F
3@2000SR

C
3@2500SR
D
2@1000SR

Resources, R
Budget, Cs,
1000SR

11

E
3@1000SR

B
2@500SR

A
5@2000SR

08

I
2@2500SR

K
3@2000SR

G
2@1000SR

3.5

2.5

2.5

2.5

2.5

14

a) AON
3

B
12
0

30

A
0

10

15 15

21

21

23

14

14

19

19

23

14

11

14

G
9

21

18

18

2
19

17

C
3

14

Critical Path activities: A-C-F-I-K


Project duration Time =23 weeks
11

19

23

END

K
19

23

23

23

23

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

b) Load diagrams
Period, week

01

02

03

A
5@2000

04

05

06

07

01
5
5
25

10

11

12

13

14

15

16

17

2@500SR

3@1000SR

3@1500SR

18

19

20

21

22

23

J
2@500SR
K

3@2500S

3@2000SR

2@2500SR

3@2000SR

2@1000SR

week
R
R
R2

09

Resources, R
Budget, Cs,
1000SR

08

2@1000SR

4.5

2.5

2.5

2.5

2.5

11
5
70
25

12
5
73
9

13
5
76
9

14
5
79
9

15
5
84
25

16
5
89
25

17
5
94
25

18
2
96
4

19
2
98
4

20
5
103
25

21
5
108
25

02
5
10
25

03
5
15
25

04
5
22
49

05
7
29
49

06
7
36
49

07
5
41
25

08
6
49
64

09
6
57
64

10
8
65
64

Analysis

23
3
114
9

642

= . =

642
=
=
= .

565.153

Comments

No. of Recourses

10

,
( )
114
=
=
()
23
= .
= 2 = (4.957)2 23

8
6
4
2
0
0

1- Load histogram shows resource variations


through the time.
2- The average resources required to be leveled is
>= 5
3- available resources only 5 at any time, then

Hence, when available resource is 5; Then,


= 2 = (5)2 23 = =
=

22
3
111
9
R2

.
= .

12

10
20
Project Duration

30

King Saud University


Civil Engineering Department

Selected Problems Solution

GE 404 Engineering Management


Summer semester 1433/ 1434H

c) Resource leveling
Arrange according LST (A, C, D, B, F, G, E , I, H, K, J)
EAS
OSS
A

5 5 5

3 3 3 3

2 2 2

2 2 2

3 3 3 3 3

2 2 2

3 3 3

2 2 2 2 2

3 3 3

3 3 3 3

2 2

WEEK 1 2 3 4 5 6 7 8 9 10 11 12
5 5 5 5 5 5 5 5 5 5 5 5
- - - 2 2 2 2 3 3 2 2 2

R
R
R2

5 5

R2=

532

13
5
2

14 15 16 17 18 19 20 21 22 23 24 25 26
5 5 5 5 5 5 5 5 5 5 5
2 2 2 2 3 3 2 2 2 2 2

5 5 5 5 5 5

5 5 3 3

10

15

20

25

30

35 40 45 50 55 60 65 70 75 80 85 90 95

98

103 108 111 114

25

25

25

25

25

25 25 25 25 25 25 25 25 25 25 25 25 25

25

Analysis

No. of Resources

10
8
6
4
2
0
0

10
15
Project Duration, week

R (without resource limit)


, =

25

( )
114
=
= .
()
24

= 2 = (4.75)2 24 = . =
.
=
= .

13

20

25

R (with resource limit=5)

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Comments
1-

Load histogram shows resource variations reduced by leveling through the time.

d) Budgeted Cost
Week
Budget, Cs 1000SR
(Without resource level)
Cumulative Cs
Budget, Cs 1000SR
(With resource level=5)
Cumulative Cs

10

11

12

13

14

15

16

17

18 19

20

21

22

23

4.5

2.5 2.5

2.5

2.5

9 13 17 20.5 23.5 26.5 30.5 33.5 36.5 39.5 42.5 46.5 50.5 54.5 57 59.5 62 64.5 66.5 68.5

6 9.5 13 16.5 19.5 22 24.5 27.5 30.5 33.5 36.5 39.5 43 46.5 50

4.5

2.5 2.5
54

2.5

2.5

Cumulative budgeted cost, 1oooSR

60
50
Cumulative
Cs1000SR(Without
resource level)

30

Cumulative Cs1000SR(With
resource level=5)

20
10
0
0

10
15
20
Project Duration, week

25

Figure 4 Cumulative Budgeted Cost


Comment:
Since the duration is extended when resources is limited to 5, this is resulted in small reduction of budgeted cost
over periods.

14

58 59.5 62 64.5 66.5 68.5

70

40

24

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question 12 (Crushing)
Development of a new version of software is
Tome, weeks
Cost, $
considered by a software company. The activities Activities Predecessor(s) Normal Crash Normal Crash
necessary for completion of the project are given
A
4
3
2000
2600
in the following table (1)
B
2
1
2200
2800
C
3
3
500
500
(a) What is the project completion date?
D
A
8
4
2300
2600
(b) What is the total cost required to completing
E
B
6
3
900
1200
this project on normal time?
F
C
3
2
3000
4200
(c) If it is required to reduce the completion time
G
D, E
4
2
1400
2000
by one week, which activity should be
crashed? , and how much will this increase the total cost increase?
(d) What is the maximum time that can be crashed? How much would cost increase?

Solution
(a) Project completion time 16
(Critical Path Activities ADG)

A,
4

(b) Total cost on normal duration time =


normal cost of activities = $12,300

START

(c) Crash one week

D,
8

B,
2

E,
6

C,
3

F,
3

G,
4

Find cost slope


Activity

(X)
Normal Time Crash Time

(Y)
Crash $Normal $

A
B
C
D
E
F
G

1
1
0
4
3
1
2

600
600
0
300
300
1,200
600

Crash activity (D) by one week at extra cost of $75


(d) Maximum time to be crashed
Activity Crash Cost
D
4
$300
G
2
600
A
1
600
E
1
100
7 weeks $1,600

15

Cost Slope=(Y/X);
$/time
600
600

75
100
1,200
300

END

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question 13 (financing)
Consider data for a small project given in Table below. Revenue is paid to the contractor every 6 months
according to completed quantities of work. Assume that markup is 10% of total project cost and is uniformly
distributed over the work.
Assume also that work of each activity is uniformly distributed over its duration.
a. Draw on a scale the project cumulative cost and revenue curves according to ES timings.
b. Draw on the diagram produced in a) above effect of receipt of 10% of total revenue as an advance
payment. This payment will be deducted from each periodic revenue by the same percentage.

Solution
B,
6

1A,
12

Activity Predecessor(s) Duration, Months Monthly cost, SR1000


A
12
20
B
A
6
60
C
A
12
60
D
B,C
6
50

D,
6

C,
12

Project completion time 30 ; (Critical Path Activities ACD)


2- Activity Cost distribution
TIME

10

12

14

16

A-20

18

20

22

24

26

C-60

28

30

D-50

B-60

ACC.
COST

0040

0080

0120

0160

0200

0240

0480

0720

0960

1080

1200

1320

1420

3- Revenue calculation
4- Total payment = 1620*(1+0.1) x 1000=(1620+162) x 1000 =1782 x 1000
Advanced payment = 0.1*1782 x 1000 =178.2 x 1000
Revenue every 6 months =
Month
0
6
12
18
24
30

R= Revenue =(Cost*1.1),
1000 SR

Adj. Revenue = 0.9 R, 1000


SR

120(1.1)=132
240(1.1)=264
960(1.1)=1056
1320(1.1)=1452
1620(1.1)=1782

118.8
237.6
950.4
1306.8
1603.8

16

Cumulative Revenue,
1000 SR
178.2
118.8+178.2=297.0
237.6+178.2=415.8
950.4+178.2=1128.6
1306.8+178.2=1485.0
1603.8+178.2=1782.0

1520

1620

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

5- Graph presentations

1800
1600

Cash out= Cost

1200
1000
Adj. Revenue

800
600

Revenue

400
200
0
0

10

15
20
Project Duration, weeks

25

Figure 5 Cumulative Cash Flow

300

Adj. Revenue

100

Cash, 1000 SR

Project Cash, 1000 SR

1400

-100 0

10

20

-300
-500
-700

Revenue

Project Duration, weeks


Figure 6 Net Cash Flow

17

30

30

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question17 (project control)


A small engineering project has budgeted cost of each activity as shown
Table (1b) Project status
in Table (15a). The budgeted cost of each activity is assumed to be
th Activity % completed Expense to date,
uniformly distributed over its duration. Project status at the end of the 15
1000 SR
day, is given the table (15b). The actual cost of work performed (ACWP)
A
100
4.2
at the end of day 15 = 20200 SR
B
60
3.0
Table (1a). Activity budgeted cost
Activity
A
B
C
Budgeted cost (SR) 4000 6000 2000

D
8000

E
7000

F
6000

G
9000

H
4000

Calculate the CV, SV, CPI, SPI, and % overrun (underrun); BAC, EAC;
comment on progress of works.

C
D
E
F
G
H

100
80
100
80
0
0
Total

1.6
5.0
7.2
4.2
0
0
25.2

Solution
Project Cost Control
Activity

Budgeted (scheduled) Cost,


1000 SR

A
B
C
D
E
F
G
H
Total

4
6
2
8
7
6
9
4
46

% completed
100
60
100
80
100
80
0
0

To date value
Estimated Cost,
1000 SR
4*1.0=4
6*0.6=3.6
2
8*0.8= 6.4
7
6*0.8=4.8
0
0
BCWP = 27.8

Expense to date,
1000 SR
4.2
3.0
1.6
5.0
7.2
4.2
0
0
ACWP = 25.2

(Over /Under) Run


Cost, 1000 SR
+0.2
-0.6
-0.4
-1.4
+0.2
-0.6
0
0
-2.4 (under-Run)

Using Equations
BCWS (SR) =20,200
BCWP (SR) = 4000 + 6000 (0.6) + 2000 + 8000(0.8) + 7000 + 6000 (0.8) = 27,800
ACWP (SR) = 4200 + 3000 + 1600 + 5000 + 7200 + 4200 = 25,200
CV (SR) = BCWP ACWP = 27800-25200=+2600 Over Budget
SV (SR) = BCWP BCWS = 27,800-20,200=+7,600 Ahead of the schedule
BAC (SR) = 4000 + 6000 + 2000 + 8000 + 7000 + 6000 +9000 + 4000 = 46,000
EAC (SR) = (ACWP/ BCWP) BAC = (25,200/27,800)*46,000= 41,697.84
ETC (SR) = EAC ACWP =41,697.84-25,200= 16,497.84
% overrun or underrun = (ACWP-BCWP)/BCWP =(25,200-27,800)/ 27,800= -9.35% underrun

Comment:
1- Expenses are less than estimated and project is under control.

18

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Question18 (Crashing & project control)


Table (15) gives the work activities of a project and its related data.
Table (16a) project activity data
Normal Schedule Crashed Schedule
Activity Predecessor (s) Time, Cost,
Time, Cost,
week 10,000 SR week 10,000 SR
A
4
2.0
2
5.0
B
6
3.0
3
9.0
C
A
4
4.5
2
10.0
D
A, B
6
2.5
4
10.0
E
D
2
0.5
1
1.0
F
E
13
13.0
8
25.0
G
E
1
1.5
1
1.5
H
C, G
20
6.0
10
23.5
I
F
9
7.0
5
16.0
Total
40.0
101.0

Table (16b) Project status


% completed Expense to date,
Activity
10,000 SR
A
100
2.6
B
100
5.0
C
100
3.0
D
100
5.0
E
100
0.7
F
40
5.6
G
100
0.7
H
25
2.0
I
0
0
Total
24.6

a) Determine EST, LST, TF schedule for each work activity at normal activity duration.
b) Determine a minimum schedule to complete the project within 26 weeks, what will be the required budget?
c) Consider that the project is scheduled according earliest time schedule for normal activity duration, only

246,000 SR has been spent and the project status as shown in table (3b). Determine the project is ahead or
behind schedule and the amount it is over or under budget. Suggest corrective actions in case that the project
is behind schedule or over budget.

Solution (a)
AON network
A, 4

C, 4

H, 20
G, 1

STAR

FINIS

B, 6

D, 6

E, 2

Critical Path activities: B-D-E-F-I


Project duration Time =36 Weeks

19

F, 13

I, 9

King Saud University


Civil Engineering Department

GE 404 Engineering Management


Summer semester 1433/ 1434H

Selected Problems Solution

Time Schedule analysis for Project normal activity duration


Activity Predecessor (s)
A
B
C
D
E
F
G
H
I

A
A, B
D
E
E
C, G
F

Forward pass Backward pass


Normal
Time, week ES LS
LS
LF
4
0
4
2
6
6
0
6
0
6
4
4
8
12
16
6
6
12
6
12
2
12
14
12
14
13
14
27
14
27
1
14
15
15
16
20
15
35
16
36
9
27
36
27
36

Slack, (LS_ES)=
TF
2
0
8
0
0
0
1
1
0

On Critical
Path
yes
yes
yes
yes

yes

Solution (b) Crashing


Activity

Cycle
#
0
1
2
3
4

Predecessor (s)

B
C
D
E
F
G

A
A, B
D
E
E

H
I

C, G
F

Activity to
Shorten

Can Be
Shortened

E
B, A
I, H
D

1
3, 2
4, 10
2

X=(Normal Crash)
Time, week

Week
Shortened

Y=(Normal crash)
Cost, 10,000 SR

Cost Slope =Y/X,


10,000 SR

2
3
2
2
1
5

3.0
6.0
5.5
7.5
0.5
12.0

1.5
2.0
2.75
3.75
0.5
2.4

10
4

17.5
9

1.75
2.25

Cost per week,


10,000 SR

1
0.5
3, 1
2, 1.5
4, 3
2.25, 1.75
2
3.75
Total extra cost paid, 10,000SR
Project budget,10,000 SR

Cost for Cycle,


10,000 SR
0.5
6+1.5=7.5
9+5.25=14.25
7.5
29.75
40+29.75=69.75

Project
Duration
36
35
32
28

Time Schedule analysis for Project after crashing


Forward pass Backward pass Slack, (LS_ES)=
Activity
Activity Predecessor (s)
Time, week
TF
ES
LS
LS
LF
A
3
0
3
0
3
0
B
3
0
3
0
3
0
C
A
4
3
7
5
9
2
D
A, B
4
3
7
3
7
0
E
D
1
7
8
7
8
0
F
E
13
8
21
8
21
0
G
E
1
8
9
8
9
0
H
C, G
17
9
26
9
26
0
I
F
5
21
26
21
26
0

20

New activity
duration time, week
1
3, 3
5, 17
4

On Critical Path
yes
yes
yes
yes
yes
yes
yes
yes

King Saud University


Civil Engineering Department

Selected Problems Solution

GE 404 Engineering Management


Summer semester 1433/ 1434H

Critical Activities; A, B, D, E, F, G, H, I
Project Duration =26 WEEKS
Number OF Critical path = 4
Budget =697,500 SR

Solution (c) Project control


Activity

Predecessor
(s)

A
B
C
D
E
F
G
H
I

A
A, B
D
E
E
C, G
F

project cost control Report


Normal Schedule
To date values
Time, Cost (scheduled),
%
Cost (estimated),
Expense to
Cost
week
10,000 SR
completed
10,000 SR
date, 10,000 SR overrun/underrun,10,000SR
4
2.0
100
2.0
2.6
+0.6
6
3.0
100
3.0
5.0
+2.0
4
4.5
100
4.5
3.0
-1.5
6
2.5
100
2.5
5.0
+2.5
2
0.5
100
0.5
0.7
+0.2
13
13.0
40
13*0.4=5.2
5.6
+.4
1
1.5
100
1.5
0.7
-0.8
20
6.0
25
6*0.25=1.5
2.0
+.5
9
7.0
0
7*0=0
0
0
Total
40.0
BCWP = 20.7
ACWP = 24.6
Over-run = +3.9

OR
BCWS (SR) =24.6 x 104
BCWP (SR) = (2 + 3 + 4.5 + 2.5 + 0.5 + 13*0.4+ 1.5 + 6*0.25) = 20.7 x 104
ACWP (SR) = (2.6 + 5 + 3 + 5 + 0.7 + 5.6 + 0.7 + 2) = 24.6 x 104
CV (SR) = BCWP ACWP = 20.7 x 104-24.6 x 104=-3.9 x 104 under Budget
SV (SR) = BCWP BCWS = 20.7 x 104-24.6 x 104 =-3.9 x 104 behind the schedule
BAC (SR) = (2 + 3 + 4.5 + 2.5 + 0.5 + 13+1.5 + 6 + 7) = 40 x 104
EAC (SR) = (ACWP/ BCWP) BAC = (24.6 x 104 /20.7 x 104)* 40 x 104= 47.54 x 104
ETC (SR) = EAC ACWP =47.54 x 104-24.6 x 104 = 22.94 x 104
% overrun or underrun = (ACWP-BCWP)/BCWP =(24.6 x 104 -20.7 x 104)/ 20.7 x 104= 18.84% Over-run

Comments:
1- The project is found to be behind schedule / experiencing cost over-run.
2- The experienced cost over-run or delay is lost causes due to not meeting project deadlines or budgets.
3- Action should be taken for cost saving, (a) in case the project behind schedule, expediting some activity
at extra cost may be possible; (b) in case over budget, non-critical activities are evaluated for cost saving.,
(c) in case of fund reduction causing delay, evaluating project duration time is evaluated and may require
to be extended.