Professional Documents
Culture Documents
NETWORK
PARSONS BRINCKERHOFF
Tunnel Systems
Fire
Table
andofLife
Contents
Safety
NETWORK
Tunnel Systems
INTRODUCTION
VENTILATION SYSTEMS
Using Quantified Risk Assessment to Inform
Ventilation System Responses
Kate Hunt ............................................................................23
A Risk-Based Approach to Jet Fan Optimisation
Anthony Ridley ....................................................................26
Cost-Effective Ventilation System for a Light Rail
Transit Project
Silas Li, Andrew Louie ........................................................30
Meeting the Challenges of Smoke Duct Fan Selection
for Australian Road Tunnels
Chris Chen ...........................................................................34
Analysis Considering the Conversion of an Existing Road
Tunnel Transverse Ventilation System to Transit Use
Jesse Harder, Andrew Louie, Vamsidhar Palaparthy,
Silas Li...................................................................................37
Long Road Tunnels and Portal Emission Control
Argun Bagis, Duncan Saunsbury ......................................41
Merging Emergency Ventilation System Sound Power
and Pressure Drop Calculations
Michael MacNiven ..............................................................44
Cost-Effective Power Supply Scheme for Tunnel
Booster Fans in Long Tunnels
CC Cheung, Steven Lai ......................................................48
Air Purification System for a Road Tunnel Project
Cathy Kam, Chris Ma, Steven Lai .....................................51
PRESSURE TRANSIENT
Elimination of Portal Flares
Kenneth J. Harris, Bobby J. Melvin, Steve Gleaton ..........52
Comparison of 3-D and 1-D CFD Simulation Approach
for Aerodynamic Effects in a HSR Tunnel System
Dicken KH Wu, Rambo RB Ye ............................................55
LIGHTING
The Modernization of Tunnel Lighting and Controls:
Technology, Challenges, and Cost of Implementing a
Tunnel LED Lighting System
Christopher J. Leone, Jonathan T. Weaver,
Kimberly Molloy ..................................................................89
For decades, Parsons Brinckerhoff has been at the forefront of providing innovative tunnel systems solutions
to our clients. In 1973 at the First International Symposium on Aerodynamics and Ventilation of Vehicle Tunnels in Canterbury England, attended by representatives
from 26 different countries, a paper was presented on
the Subway Environmental Simulation (SES) program codeveloped by the late William D. Kennedy. That paper led
directly to a contract for the design of an extension to
the Hong Kong Metro and, out of that project, Parsons
Brinckerhoffs Hong Kong office was established. Over
40 years later in 2015, Dr. Norman Rhodes of Parsons
Brinckerhoff will chair the 2015 16th International Symposium on Aerodynamics, Ventilation, & Fire in Tunnels
to be held in Seattle.
Fire and
Introduction
Introduction
Life Safety
NETWORK
See Pioneering New Technology: PBs Innovation in M&E Analysis and Design, (Network #34, Spring 1996) for three articles on the Memorial
Tunnel Fire Ventilation Test Program, at the time the most comprehensive full-scale fire ventilation testing undertaken.
Fire andIntroduction
Life Safety
NETWORK
present and future. Parsons Brinckerhoff is involved
in a program to evaluate connected vehicle technology. The potential for connected vehicles to interact
with tunnel systems is limitless. Imagine a tunnel ventilation system that automatically regulates its airflow
based on the number and type of vehicles travelling
through the tunnel or a deluge system putting out a
vehicle fire without waiting for a tunnel operator to respond to the emergency.
Standards such as NFPA 130, Standard for Fixed Guideway Transit and Passenger Rail Systems,2 or NFPA 502,
Standard for Road Tunnels, Bridges, and Other Limited
Access Highways, have been a cornerstone guiding the
design of tunnel systems for the last few decades. In
many countries, these have been used as the de-facto
international standards shaping the design of tunnel solutions globally.
In the United States, Parsons Brinckerhoff has been central in shaping the direction of both NFPA 130 and NFPA
502 through active committee participation and chairmanship. Perhaps the most significant development
in recent years is the change from purely prescriptive
standards to standards that allow performance-based
approaches. For example, NFPA 130 states: Nothing in
this standard is intended to prevent or discourage the
use of new methods, materials, or devices, provided that
sufficient technical data are submitted to the authority
having jurisdiction (AHJ) to demonstrate that the new
method, material, or device is equivalent or superior to
the requirements of this standard with respect to fire
performance and life safety.
The change from prescriptive to performance-based
designs has led to a situation where designers can
exercise a greater level of flexibility and innovation in
providing solutions for our clients. For example, previous standards prescribed a fan inlet temperature that
had to be met without regard to the actual temperature
that a fan inlet may experience in a fire. The current
standards require that designers analyze the actual fan
inlet temperatures that would be experienced for the
type of fire that could be realized in relation to the specific rolling stock for that system. Another example is
NFPA 130 (2014) and NFPA 502 (2014), National Fire Protection Association, www.nfpa.org
High speed rail projects frequently involve long tunnels and long distances between stations. Parsons
Brinckerhoff can draw on global and local experience
to provide solutions for unique challenges such as
analyzing the pressure waves associated with high
speed trains (see article by Wu and Ye) and providing
cost-effective tunnel ventilation and fire and life safety strategies to accommodate the extended egress
distances of long tunnels.
For 18 articles on many aspects of this multidisciplinary project including 5 articles on tunnel mechanical and electrical systems, see Linking Two
Continents: The Marmaray Project, Network #65, June 2007, pp 1-58.
Fire andIntroduction
Life Safety
techniques, including using the latest inspection and asset management technologies, to efficiently assess existing tunnel infrastructure (see articles by Stevens and
VanDeRee; and by Portuguez and Moolin). Following the
assessment, our performance-based methodologies are
used to develop innovative upgrades that provide a level
of safety equivalent to code-compliant solutions and that
minimize or eliminate interruptions to tunnel operations.
NETWORK
Fire andIntroduction
Life Safety
NETWORK
with the UKs Climate Projections group (UKCP), developing a new toolset such as DYNAMO to address a developing market (see Dr. Jolyon Thompsons article in this
issue, a version of which won the 2014 Parsons Brinckerhoff Emerging Professionals Technical Paper competition), developing sustainable designs through the use of
innovative cooling techniques such as groundwater cooling or embedded liners, using the latest risk-based techniques to optimise designs and operations (see articles
in this issue by Kate Hunt and Anthony Ridley), or introducing world-class high speed rail to the UK, our team of
engineers is at the forefront of innovation.
Parsons Brinckerhoff continues to retain its high profile in
tunnel systems capability through many of the major projects being undertaken. Parsons Brinckerhoffs in-depth
knowledge and internationally renowned global team is
able to deliver technical excellence to clients across all
geographies and all sectors. As we engage with WSP,
the challenge in the Europe, Middle East, and North Africa regions is to enhance our service offering across a
broader range of sectors, to embrace the many exciting
opportunities available, and to continue to provide our
clients with the technical excellence they rightly expect of
Parsons Brinckerhoff.
New challenges in tunnel systems. Nowadays, exceptionally long tunnels with large cross-sectional areas
and/or multi-purpose tunnels create new challenges
to engineers. Parsons Brinckerhoff has participated in
the following design of tunnel systems for several special tunnel projects in China:
the 18km long (11 mile) Zhong Nam Shan Tunnel with
very long ventilation shafts, more than 500 meter
(1640 feet);
the 6km long (3.7 mile) Chongming road tunnel which
links Shanghai to the out-lying Chongming Island and
has an upper deck for vehicular traffic and a lower for
the metro line;
the 2km long (1.2 mile) Fuxing East Road Tunnel in
Shanghai which also has an upper deck and a lower
deck both of which are used for vehicular traffic; and
the Macau Sai Van Bridge which has an upper deck
used for vehicular traffic and an enclosed lower deck
used for light rail operation (normal condition) and vehicular tunnel operation (during typhoon conditions).
Value engineering and cost effective design. Parsons
Brinckerhoff has developed various value engineering
schemes and creative approaches to achieve cost effective design for our clients and provide a better environment for the people. These schemes include:
the use of combined ventilation shafts instead of individual ventilation shafts to reduce the constraint on the
station planning and the size of aboveground structures
(Suzhou metro);
the use of a centralized chilled water system to reduce
the overall spatial requirement and result in a more energy-saving system (Tsuen Wan Line in Hong Kong);
the use of higher voltage to supply the power for tun-
Fire andIntroduction
Life Safety
NETWORK
Fire andIntroduction
Life Safety
NETWORK
8.0 $ Billion
Forecast
Brisbane
Underground (QLD)
M4 East (NSW)
Toowoomba Range Second Crossing (QLD)
Lane Cove
Tunnel (NSW)
2.0
East-West Link
Eastern Section (VIC)
CityLink Western (VIC)
M1 to M2
Link (NSW)
Cross
City Tunnel
(NSW)
03
05
Year ended June
East-West
Link
Western
Section
(VIC)
M5 East (NSW)
North-South Bypass
Tunnel (QLD)
East Link (VIC)
0.0
East-West
Link (QLD)
4.0
M4 South (NSW)
07
09
11
13
15
17
19
21
23
Figure 1 Major road and rail projects with tunnel components (value of work done)
currently being planned along the east coast of Australia, with the west coast expecting some movement as
well with the planning of an extension to the existing
metro system.
John Munro
Director, M&E
New York, NY, US
Kate Hunt
Service Leader, Tunnel Ventilation &
Fire Engineering (RMS), Rail & Transit
Godalming, UK
Argun Bagis
Principal Engineer, Tunnel Systems
Australia, New Zealand
Fire andIntroduction
Life Safety
NETWORK
Fire Tunnel
and Life
Systems
Safety
NETWORK
William D. Kennedy, an internationally recognized expert in tunnel ventilation, died in June 2012. During a 46year career with Parsons Brinckerhoff, he was instrumental in the development of tunnel ventilation systems
for road and rail tunnels worldwide. His reputation in tunnel ventilation was recognized in March 2012 by the
International Symposium on Tunnel Safety and Security, which awarded him its 2012 Achievement Award,
citing his long and illustrious career in ventilation engineering of tunnels and calling his lifetime body of work
a shining example of wedding practice and theory in the design of tunnels.
This abstract is condensed from a paper that was originally prepared for the 2006 APTA Rail Conference and
has been updated to reflect the current 2014 version of NFPA 130.
10
Introduction
Based on earlier emergency ventilation studies, it was
concluded that the maximum cross-passage spacing
should be such that those downstream of the fire could
evacuate to a point of safety within the time that it
takes for the floor of a train car to burn through (which
leads to flashover of the entire train car).
This leads to the conclusion that increasing the car-floor
burn-through time would allow greater tunnel-to-tunnel
cross-passage spacing and possibly reduce costs. This
is suggested in NFPA 130 (Section 8.5.1.3.2(1)). Another
possibility is wider walkways or cross-passage doors to
speed passenger movement away from the fire site.
It also leads to the inference that an interior or post-flashover fire should not be allowed to stop a train in a tunnel.
Driver override should allow the movement of the train
to the nearest station even if a passenger activates the
emergency brake. The analysis for this paper assumes
that this is the circumstance and that the only fire that
will stop a train in a tunnel is a below-car fire that critically
damages the propulsion system or derails the train.
Therefore, when calculating the minimum car-floor burnthrough time required, 10 minutes (15-5) should be
added to the evacuation time. This does not include any
allowance for modeling accuracy.
Some observations
Downstream
595' (181 m)
Under-Car Fire
W
X
Upstream
X
(200, 300, 400, 500, 600, 700, and 800 feet)
(61, 91, 122,152, 183, 213, to 244 meters)
W= Constructed Walkway Width (36, 38, 40, 42, 44, 46, 48, 50, 52, and 54 inches)
(914, 965, 1016, 1067, 1118, 1168, 1219, 1270, 1321, to 1372 mm)
"SIMULEX Users Manual"; 1998, Integrated Environmental Solutions, Limited; 141 St. James Road, Glasgow G4 0LT, Scotland.
William D. Kennedy, Norris A. Harvey, and Silas K. Li, Simulation of Escape from Rail Tunnels Using SIMULEX, American Public Transportation
Association (APTA), Boston, Massachusetts, June 2001.
NETWORK
11
12
NETWORK
Conclusion
A performance-based approach for estimating evacuation times downstream from a tunnel fire site and minimum car-floor burn-through times has been presented.
It allows the trade-off among cross-passage spacing,
car-floor burn-through time, and walkway and cross-passage door width. For existing systems with fixed cross-
Historically, the disappointing results of the Ofenegg Tunnel fire tests (1965, Switzerland) had a negative impact on
sprinkler application in tunnels. The tests, which employed
pools of aircraft fuel, led to the view that visibility was
much reduced by the sprinkler systems and hot steam
was generated that could cause scalding at long distances
from the fire. The steam production also displaced smoke
more quickly causing temperatures to be higher than without sprinklers. After extinguishment the fuel continued to
evaporate, reaching critical concentrations within about 20
minutes. Subsequent deflagrations occurred that created
air velocities of up to 30 meters per second.
It was the impact of this experience that was reflected
in the World Road Association (PIARC) recommendations
which, between 1983 (World Road Congress in Sydney)
and 2004, consistently advised against the installation
of fixed fire fighting systems (FFFS) in road tunnels, and
this position was reflected in US standards.
One of the factors that maintained this attitude against
the application of FFFS in tunnels was the fire sizes generally used. The fire sizes chosen on which to base the
design were relatively small20 to 30 MWtypical of
a bus or truck fire. Such fires were regarded as manageable and ventilation systems were sized to control
smoke for such events.
Several severe road tunnel fires - the Mont Blanc Tunnel
(France/Italy, 1999), the Tauern Tunnel (Austria, 1999),
the St. Gotthard Tunnel (Switzerland, 2001), and the Frejus Tunnel (France/Italy, 2005) - resulted in loss of life,
injury, and infrastructure damage that were far more extensive than if they had occurred on surface roadways.
These fire incidents demonstrated that fire sizes could
be much larger than 20-30 MW and completely changed
the perception of the design fire size. Since then the
maximum design fires utilized in tunnel design have increased as much as tenfold in some cases. These re-
cent incidents have emphasized the need for further improvement to be made in tunnel fire management; the
FFFS is one technique that is actively being promoted.
Types of FFFS
Several types of FFFS have been used in road tunnels
worldwide:
Sprinkler/spray (water deluge) systems, based on dense
water jets consisting of large-size droplets;
Water mist systems, based on very fine water droplets;
and
Foam water suppression systems.
Water sprinkler type FFFS have been installed in road
tunnels of significant length for many years in Japan and
Australia. Tunnels that have water deluge fixed fire fighting systems installed can also be found in the United
States, Norway, Canada, and Sweden. These have been
found to be effective in preventing fire spread and enhancing cooling of the tunnel structure. In 1999, two fires
occurred in the underwater tunnels of the Tokyo Metropolitan Expressway and the FFFS helped control the fires
so firefighters could approach and eventually extinguish
the fires. The deluge system in Sydney Harbor Tunnel in
Australia is reported to have worked well during a van fire
in 2004. Another example is the Burnley Tunnel fire in
2007; the deluge system was activated quickly and this
was deemed by firefighters to have kept the fire under
control. Based on this experience, and the development
of alternative types of FFFS, PIARC re-evaluated its position with regard to FFFS and at the same time the European Community undertook research programs to examine
fire suppression and the impact of larger design fires.
Several relevant European research programs, including
UPTUN (Multinational European Research Project) and
the SOLIT (Safety of Life in Tunnels) Project, have demonstrated through independent tunnel fire tests that, with
early activation, high pressure water mist systems can be
effective in controlling potential 200 MW solid fuel fires
Introduction
NETWORK
13
NETWORK
and 200 MW diesel oil pool fires. The water mist systems
have been installed in the A86 tunnel in Paris, the M30
tunnel in Madrid, the Roertunnel and the Tunnel Swalmen
in the Netherlands, and other tunnels in Europe.
Therefore, FFFS are now increasingly being considered
in the design of tunnel systems worldwide. This position
is also reflected in changes to the recent NFPA 502 and
PIARC documentation.
14
Piping Network
Proportioning
Controller
CAF Generation
Water
Releasing Controller
Air
Piping Network
Mixing Chamber
Foam Concentrate
Nozzles
Alarm Check
Valve
Main Control
Valve
Water Supply
Bladder
Tank
CAF
Nozzles
Conclusion
The FFFS is also being considered in road tunnels to reduce the size of the ventilation system required. When
authorities prepare to permit all types of traffic, such as
dangerous goods or heavy goods vehicles, to cope with increasing economic activities, mitigation options that can
combat 200 - 300 MW fires would be necessary for tunnels, as recommended by NFPA 502 and most European
standards. Without FFFS, large fires (such as 200 - 300
MW) dictate the need for a very powerful ventilation system, increasing space requirements and adding significant cost. In addition, FFFS, unlike a ventilation system,
can provide benefits for firefighting, tunnel system protection, and operational continuity.
Although the benefits of FFFS are clear, many design issues
remain, such as: the reduction in the design fire size with the
inclusion of the FFFS and the subsequent reduction in ventilation requirements; the impact of the FFFS on the structural
protection system; the performance of the FFFS under operational conditions that have not been tested in the tunnel
fire experiments; and the impact of the FFFS on the overall
tunnel safety concept and operation procedures.
The most reliable method available to date for those unsolved design questions is full-scale testing, but that is
extremely expensive and impractical for new or existing
tunnels. A computational fluid dynamics (CFD) fire modeling approach is an alternative and holds great promise
once a reasonable correlation between numerical simulations and full-scale tests has been achieved.
References
Haerter, Fire Tests in the Ofenegg-Tunnel in 1965,
International Symposium on Catastrophic Tunnel
Fires, Boros, Sweden, November 2003.
For longer tunnels, the use of foam-water fire suppression systems may be challenging:
NETWORK
15
NETWORK
Introduction
Fires that occur in road tunnels can grow rapidly and
reach very high heat release rates. As a result, road
tunnels are designed with mitigation technology and
procedures to help reduce the detrimental effects that
can occur.
The main goals of the mitigation measures are to:
Provide a tenable environment for motorist evacuation;
Assist firefighters with their operations; and
Maintain the structural integrity of the tunnel.
A fixed fire fighting system (FFFS) is one type of mitigation measure implemented to help achieve these goals.
The major components of the FFFS include water delivery infrastructure (pumps, pipes, valves, and nozzles
divided into separate zones for water delivery) and also
components for water removal (drainage, pumps, pipes,
water treatment).
A FFFS is typically installed to help reduce the fire growth
rate and air/smoke temperature, which helps to prolong
occupant tenability and provides structural protection.
Proper integration of the FFFS with other tunnel fire-life
safety systems is essential to achieve the FFFS goals.
179
178
16
The first important question in FFFS integration is whether or not the tunnel has a full-time operator. In many tunnels with FFFS, a full-time operator is present. In this article the integration question is considered in the context
of a full-time operator being present, but it is noted that if
an operator is not present there will be different integration considerations. Tunnel systems and functions that
require particular attention for integration with a FFFS,
with full-time operator present, include:
Closed circuit television (CCTV);
Ventilation systems;
Egress provisions;
Drainage;
Fire alarm systems, control systems, heat detection
systems; and
Traffic and operations.
Fixed camera
Tunnel wall
Roadway
Application
criterion is 8 kg/
2
m in one minute
AIRFLOW
9.00
8.00
FFFS Zone
FFFS Zone
7.00
NETWORK
6.00
5.00
4.00
Jet fans
Water overshooting zone of application
(overshoot by up to 15m)
Jet fans
Water not reaching entire zone of
application (up to 5m of a zone missed)
3.00
2.00
1.00
0.00
17
NETWORK
fire site. The fuel draining away from the fire site would
be unshielded by vehicles and so it will typically be suppressed, if it is burning, prior to exiting the FFFS zone.
Flame traps in the drainage system are sometimes used
to prevent a secondary fire moving through the drain
pipe network.
18
Conclusion
An FFFS is a useful fire safety tool for a road tunnel. Good
integration of the FFFS with other tunnel systems and functions, using the principles outlined above, assists in bringing to fruition its purported benefits for tunnel fire safety.
In addition to the engineered systems, it is important that
the tunnel operator is well-trained and that tunnel systems
are well-maintained to assure good performance.
Matt Bilson is a Principal Technical Specialist in the field of
tunnel ventilation and fire-life safety in the New York office of
Parsons Brinckerhoff.
Sal Marsico is a Mechanical Engineer in the field of tunnel
ventilation and fire-life safety in the New York office of Parsons
Brinckerhoff.
Introduction
INCIDENT AND
MODE ID
A fire or other emergency situation in a tunnel environment can be a serious threat to human life and the infrastructure. One of the main tasks of the fire-life safety
(FLS) engineer is to develop a response strategy to
manage or prevent such events. The strategy will frequently rely on many sub-systems such as ventilation,
lighting and signage, traffic management, alarms, operator responses and coordination, and communication
with emergency services agencies (e.g., the fire department). The harmonious and correct operation of the subsystems is essential to protecting life and infrastructure
during an incident; clear and concise system integration
is needed to achieve this goal.
Incident ID
(as per the
operators
incident
response plans)
Requirements and
Architecture
Trafc
Devices
Automatic
Communications
Escalation
Modes
Lighting/
Signs
Fixed Fire
Fighting System
Operation and
Maintenance
System Verication
and Validation
Detail
Integration Test
and Verication
Detailed Design
Manual
Implementation
Time
Concept
SUB-SYSTEM
RESPONSES
Ventilation
DETECTION
METHODS AND
LOCATION
NETWORK
19
NETWORK
Case Study An Urban Road Tunnel
To illustrate the FMT concept, a virtual case
study of an urban road tunnel several kilometers long is used. For the present discussion
the tunnel is taken to have the following principal system features:
Unidirectional traffic;
Longitudinal ventilation;
Egress points at 200 meter spacing (to an
adjacent tunnel);
CCTV system;
Fixed fire fighting system;
Communications (phones, public address),
lighting, traffic controls; and
Full-time tunnel operator.
Response
Sub-systems available
Operator
Human-machine interface.
Trafc
management
Ventilation
Lighting
Detection and
alarms
initiate and direct evacuation.
public address, variable
The ventilation system plays a major role in
message signs, CCTV,
life-safety, directing smoke downstream of
and heat detectors.
the fire so that people upstream are protectFixed re
Activate system in the correct
Valves and pumps, and
ed (see Figure 3). However, the ventilation
ghting
location.
CCTV for identication.
system
system alone will not necessarily produce
a favorable outcome; a successful outcome
needs several provisions to operate correctly. Table 1 Sub-system response for a road tunnel fire
During a major incident, ventilation operation
During an emergency an operators capacity to
is only one of several important steps that need to be
perform sophisticated system adjustments may be
taken, as explained in Table 1.
limited by the enormous flow of information among
the operator, the motorists, and the emergency
Overcoming Operational Complexity The FMT and a
agencies. An operators attention becomes focused
One Button Response
on specific events and as a result may fail to take into
Table 1 outlines a number of sub-systems required
account the broader situation, a condition referred to
to operate during an emergency, and a major tunnel
as attention tunneling.
will typically have a full-time and well-trained operator.
Emergencies do not occur frequently and so the operator
However, it is not reasonable to expect the operator
has limited practice at performing the required actions.
to manually perform all of the actions required for the
Emergency situations are high stress events within the
following reasons:
control room. Designers of the systems need to be
mindful of the possibility for an operator to lock up
Operators are typically not engineers and therefore not
which could further delay the correct response.
versed in tunnel systems design.
Egress: back up
the tunnel and via exit
20
System
Fire
Fire-Life
Safety and
Ventilation
Concept Design
Operator Emergency
Services Occupants
Control
System
Design
FUNCTIONAL
MODE TABLE
Systems
(Detection, Alarm,
Egress, Trafc Light,
Lighting, Ventilation)
FUNCTIONAL
MODE TABLE
Mechanical
Design
Electrical
Design
Generating a one button response requires that all stakeholders in the emergency response system are aware of
the realistic information available during an emergency situation and the order of actions to be taken. As fire-life safety
engineers, it is our responsibility not only to define the spectrum of data and available actions, but also to define the
data with language, terminology, and structured presentation that is easily communicated and understood by other
stakeholders. This task is challenging but not out of reach.
Comment
For example, with a well-designed FMT and incident response plan, during a fire in a road tunnel the operator would need to answer some basic questions at each
stage in order to then activate the physical tunnel systems. Table 3 provides a simplified account of the response stages, questions, and system actions.
The outline of questions in Table 3 minimizes the amount
of information that the operator must give, thus reducing the time it takes for a response and maximizing the
chances that the correct system actions will be taken
and all the essential sub-systems will be activated.
Trafc Devices Incident Tunnel
Egress
Devices
Ventilation
Manual
Auto
Escalation
mode
Upstream
from
incident
Dstream
from
incident
Portal
Lights, PA,
VMS
Jet fans
Suspected
re
CCTV
Heat
sensor
Mode 2
Stop trafc
Exit
with
caution
Stop trafc
N/A
On,
emergency
mode
Conrmed
re
Operator
N/A
N/A
Stop trafc
Exit
with
caution
Stop trafc
On,
egress
mode
On,
emergency
mode
Incidents and
Response Plans
NETWORK
Table 2 Functional mode table example (showing a limited number of incidents and devices)
21
NETWORK
Stage of response
3. Conrm incident?
Secondary
evacuation required
Is evacuation required?
Tertiary xed re
ghting required
The operator may need to make adjustments later, possibly manual adjustments, but with this framework the
initial response and activation of critical systems for firelife safety are certain.
22
Conclusion
A well-integrated tunnel system will provide better functionality at all stages of a project including planning,
implementation, commissioning, training, and operation.
The FMT is a tool to assist with integrating the key stakeholders in the tunnel system design process including
the operator, the designer, people who use the facility,
the implementation staff, and emergency services. One
of the greatest advantages of the approach is that it
can be used to simplify the operators actions during an
emergency, thereby improving the chances of a favorable
outcome and greatly contributing to public safety.
As a leading consultant in fire-life safety engineering,
Parsons Brinckerhoff is well placed to improve the delivery and perception of fire-life safety training and operation within tunnels for our clients. The FMT can help to
achieve this and provide a safer road or rail facility.
Matt Bilson is a Principal Technical Specialist in the field of
tunnel ventilation and fire-life safety in the New York office of
Parsons Brinckerhoff.
Andrew Gouge is a Senior Controls Engineer in the field of tunnel
ventilation and fire-life safety. He left Parsons Brinckerhoff in
2014 to pursue an MBA.
Abstract
Ventilation
Fire Tunnel
and
Water
Life
Systems
Systems
Safety
Power
NETWORK
23
Ventilation
Fire and Life
Systems
Safety
NETWORK
Event
Small in-car re
Large in-car re
Small under-car /
tunnel re
Large under-car /
tunnel re
33.3%
33.3%
33.3%
33.3%
IT 99.8%
AT 99.8%
TT 99.8%
IT 99%
AT Null
TT Null
IT 95%
AT Null
TT Null
IT 66.5%
AT Null
TT Null
25%
25%
25%
25%
IT = 10% or Null
IT = 5% or 50%
IT = 10% or Null
IT = 5% or 50%
AT & TT = 5% or Null
AT & TT = 5% or Null
IT as appropriate
Null
96.367%
96.367%
96.367%
96.367%
85%
85%
85%
85%
96.7%
96.7%
96.7%
96.7%
IT = 3
AT = 0
TT = 0
IT = 1400
AT = 1050
TT = 700
IT = 3
AT = 0
TT = 0
IT = 1400
AT = 1050
TT = 700
AT & TT 0% or 100%
as appropriate
As appropriate
AT & TT 0% or 100%
as appropriate
Critical velocity the air flow required to prevent smoke from moving upstream of the fire location.
24
Direction of travel
critical
velocity
met
Scenario
No
Change
Switch
Off
NonOptimal
Optimal
2.34
2.60
2.60
2.60
Small undercar/track/
tunnel re
26.35
29.27
30.90
30.90
Large in-car re
(determined arson event)
1.21
1.27
1.27
0.46
Large undercar/track/
tunnel re
29.24
30.78
32.49
4.28
Ventilation
Fire and Life
Systems
Safety
NETWORK
Direction of travel
critical
velocity
met
critical
velocity
met
Scenario
No
Change
Switch
Off
NonOptimal
Optimal
2.34
2.60
2.60
2.60
Small undercar/track/
tunnel re
26.35
29.27
30.90
30.90
Large in-car re
(determined arson event)
118.97
125.23
125.23
0.46
Large undercar/track/
tunnel re
98.35
103.53
105.24
4.28
Direction of travel
critical
velocity
lost
critical
velocity
met
critical
velocity
met
Scenario
No
Change
Switch
Off
NonOptimal
Optimal
2.34
2.60
2.60
2.60
Small undercar/track/
tunnel re
26.35
29.27
30.90
30.90
Large in-car re
(determined arson event)
197.48
207.87
187.88
0.68
Large undercar/track/
tunnel re
144.42
152.02
153.73
8.58
Recommended actions
2 or more
2 or more
When there is one train in a ventilation section, the optimal smoke control mode should be determined based
on the fire location along the train and the drivers intended direction of evacuation. When there is more than
one train in the ventilation section, trains in front of the
incident train should be driven forward at low speed, out
of the ventilation section. The preferred direction of ventilation should then be forward, to avoid passing smoke
25
Ventilation
Fire and Life
Systems
Safety
NETWORK
Introduction
In addition to providing adequate air quality and maintaining temperatures within acceptable limits, tunnel ventilation systems need to be designed to move smoke in
the event of a fire with a good level of confidence. Wind
and other meteorological forces can negatively affect the
performance of the ventilation system, but for how much
wind force should the system be designed?
26
Methodology
An event tree was generated to consider the probability of
various scenarios (see Figure 1). Each branch or scenario
of the event tree had an overall predicted event frequency
and consequence assigned. This was subsequently used to
estimate risk.
A tunnel fire frequency rate was estimated through interpretation of statistical data from the UKs Railway Safety
and Standards Board. Various probabilities were then
assigned to each scenario.
Bulk-flow simulations were undertaken using the Subway Environment Simulation (SES)2 software for three
representative tunnels. This provided information about
the tunnel air flow rate for every different configuration
of ventilation mode, train location, fire heat release rate,
Each event path required an evaluation of consequences to passengers. The consequence analysis was broken down into two constituent parts:
Critical velocity the air flow required to prevent smoke from moving upstream of the fire location.
Subway Environmental Design Handbook. Volume II. Subway Environment Simulation Computer Program (SES). Part 1. Prepared by Parsons
Brinckerhoff as part of a joint venture for the U.S. Department of Transportation, in 1975.
1
2
Common
Tunnel fire
Ventilation
frequency with cause failure mode achieved
consequence
No
Design
Fire
magnitude
Wind direction
7MW
Adverse
Consequence*final
event frequency
10%
1%
Ventilation
Fire and Life
Systems
Safety
NETWORK
0.1%
0.01%
Beneficial
All
1MW
30MW
Base
Fail
SUM
Yes
Results
The results of the consequence analysis can be seen in
Figure 2.
It is evident that for the larger fires simulated there is always a base equivalent fatality rate of approximately 55
persons. This represents the inherent consequence involved with longitudinal ventilation systems; there is a risk
that passengers may be located downstream of the fire
location. To minimise passenger numbers downstream of
the fire, the ventilation direction is decided by the fire location. To model a condition where an average number
of passengers were downstream of the fire, the fire was
set to be a quarter of the length down the train. As the
percentage of critical velocity achieved reduces, the backlayering of the smoke advances. This process is illustrated
in Figure 3. The jump in the predicted number of equivalent
fatalities from 55 to 250 as seen in Figure 2 was due to
the back layering of smoke past an upstream passenger
exit (illustrated by scenario C in Figure 3).
Figure 1 - Event tree (dotted arrows represent uncompleted branches of the tree, only one complete branch is fully shown)
27
350.0
300.0
Equivalent Fatalities
Ventilation
Fire and Life
Systems
Safety
NETWORK
250.0
30MW
200.0
7MW
150.0
1MW
100.0
50.0
0.0
0%
20%
40%
60%
80%
100%
% Critical Velocity
Figure 2 - Predicted relationship between percent of critical velocity achieved and total passenger fatalities and weighted injuries for
different fire magnitudes.
a) CV is achieved
28
LEGEND
Ventilation
direction
Walkway
Train
Train/
Tunnel exit
Fire
Untenable
conditions
Evacuation
route
Figure 3 - Illustration of evacuation scenarios: a) CV is achieved, b) CV not achieved but no additional passenger fatalities (60-100% CV), c)
CV not achieved and resulted in additional passenger fatalities (<60% CV).
Risk analysis
The UK rail industry has acceptance criteria for the
probability of injury for individuals as well as methods
to evaluate the so called societal risk that can occur for low-frequency high-consequence events such as
tunnel fires.
The risk to an individual passenger was predicted to be
1 in 240,000,000orders of magnitude lower than the
broadly acceptable limit of 1 in 1,000,000 in the UK.
Societal risk was evaluated using frequency/severity
(FN) curves where the value plotted on the y-axis is
the cumulative frequency of experiencing N (passenger
Ventilation
Fire and Life
Systems
Safety
NETWORK
1.E+00
1.E-01
Frequency (yr-1)
1.E-02
1.E-03
1.E-04
Inherent
Longitudinal
risk
Wind risk
1.E-05
1.E-06
1.E-07
0.10
1.00
10.00
Fatality Weighted Injuries
System
failure
100.00
1000.00
1.E+00
1.E-01
1.E-03
1.E-04
1.E-05
1.E-06
1.E-07
0.10
1.00
10.00
100.00
Fatality Weighted Injuries
short tunnels societal risk
UK railway societal risk 2013
1000.00
Figure 5 - Societal risk with the removal of human error from the operation of the ventilation systems.
Conclusions
It was concluded that the fire hazard could be managed so
far as is reasonably practicable with the proposed ventilation approach of using the spare jet fan to also overcome
wind forces. There was no strong case for adding further
jet fans to reduce the risk. Eighteen (18) jet fans were
eliminated from the ventilation system design, potentially
saving many millions of pounds.
Frequency (yr-1)
1.E-02
29
Ventilation
Fire and Life
Systems
Safety
NETWORK
Figure 2 shows the airflow schematic for the original ventilation concept with two ventilation systems:
30
tunnel ventilation system includes four uni-directional fans each delivering 250,000 cfm (125 m/s).
The original station design consists of ventilation fan
plants located directly over the trainways at the ends of
the station platform. There is a large atrium in the middle
of the station where station ventilation dampers connect
the station ventilation fans to the atrium area via dampers in the fan room level walls. At the ends of the station,
there are tunnel ventilation dampers located in the ceiling
of the trainway that connect the trainway region to the tunnel ventilation fans.
Fire Dynamics Simulator (FDS) Version 5.5.3, 2010, (CFD Software), Building and Research Laboratory, National Institute of Standards and
Technology (NIST), 100 Bureau Drive, Stop 8600, Gaithersburg, MD 20899-8600, USA.
2
NFPA 130, "Standard for Fixed Guideway Transit and Passenger Rail Systems", 2010 Edition, published by the National Fire Protection Association, 1 Batterymarch Park, Quincy, MA 02269-9101, USA, August 2009.
Ventilation
Fire and Life
Systems
Safety
NETWORK
Street Level
Mezzaninie Level
Platform Level
Tunnel Ventilation
Dampers (typ.)
Trainway
(below)
Station Ventilation
Dampers (Typ)
Mezzanine
To Outside
LEGEND
Tunnel
Ventilation System
Station
Ventilation System
Tunnel Ventilation
Dampers (typ.)
Trainway
(below)
Mezzanine
To Outside
To Outside
Ventilation Shaft
to Outside
Station Ventilation Dampers (typ.)
LEGEND
Tunnel
Ventilation System
Station
Ventilation System
To Outside
Ventilation Shaft
to Outside
31
Ventilation
Fire and Life
Systems
Safety
NETWORK
Emergency Exits
Original
Vent
Concept
Stairs to Mezzanine
Emergency Exits
30.0
Platform
Fire Car
4
minutes
27.0
Modied
Vent
Concept
24.0
21.0
Original
Vent
Concept
6
minutes
18.0
15.0
Modied
Vent
Concept
12.0
9.00
Original
Vent
Concept
32
20
minutes
6.00
3.00
Modied
Vent
Concept
0.00
fans are activated two minutes after the fire starts, and
reach full operational capacity after 180 seconds.
criterion. Un-shaded regions are within the visibility criteria, while regions that are shaded violate the criteria.
Conclusion
The CFD results were presented to the authority having
jurisdictions (AHJ). The AHJ approved the modified ventilation concept with the elimination of station ventilation
fans. The modified ventilation design saved approximately US$6 million in mechanical and electrical costs, in addition to lowered maintenance costs due to less equipment. Additional savings were realized by the elimination
of fan room space and ventilation shafts.
The CFD analysis also provided insight into key station
design elements that impact the effectiveness of the ventilation system. For this type of station, the large atrium
functions as a smoke reservoir and locating the smoke
Ventilation
Fire and Life
Systems
Safety
NETWORK
33
Ventilation
Fire and Life
Systems
Safety
NETWORK
Introduction
Parsons Brinckerhoff has been involved in the detailed
design work on some recently completed major Australian road tunnels. A number of these unidirectional traffic tunnels, including the M7 Clem Jones Tunnel (Clem
7), Brisbanes Airport Link Tunnel, and Legacy Way (under construction), employ a combined longitudinal and
distributed smoke extraction ventilation (smoke duct)
system for fire emergencies. This type of system can result in unique tunnel ventilation fan duty requirements.
This article describes the challenges and analysis approaches to account for a wide range of parameters that
can affect the fan requirements, including:
Case A: 50% and 50% split of total airow at pressure loss of P1a=P2a
Path 1 with duct
pressure loss P1a
Smoke duct
Critical velocity
Case B: 30% and 70% split of total airow at pressure loss of P1b=P2b
Path 1 with duct
pressure loss P1b
Smoke duct
Critical velocity
34
with leakage
10% increase
10%
increase
without leakage
1000m
( 3300 ft.)
Ventilation
Fire and Life
Systems
Safety
NETWORK
Figure 2 - Effect of air leakage in ducts for both pressure and flow
35
70%
ow
50%
ow
Pressure (force/area)
Ventilation
Fire and Life
Systems
Safety
NETWORK
30%
ow
Pa
Case B
Path 1
Legend
Required duties
Fan curves
Case A
Path
1&2
System curves
Potential Fan
curve for covering
all duty cases of 30%
Case B to 70% of total airow
Path 2
Pb
(Two identical fans)
Flow rate (volume/time)
The resulting fan duties for the two cases are shown
parametrically in Figure 4 and show that the fan duty
points vary considerably even when only two fire locations are considered. When assessing, many locations will need to be considered along with the varying
fire size. The analysis is an iterative process. This
will determine a range of fan duty limits. Practically,
the final fan selection is based on the need for the
fans to cover all possible fan duty points that may
be encountered during operation. The fans ultimately
selected will generate flows in excess of the required
flows for many cases which will need to be considered
and accounted for. Generally for smoke extraction duties, excess of design performance requirements is
not an issue.
36
Pressure (force/area)
Case B
Path 1
Case A
P1a=P2a
Case B
Case A
Path
1&2
50%
Required duty
System curve
30%
P1b=P2b
0%
Legend
70%
100%
Conclusion
The process of sizing smoke ducts and determining the
smoke extraction fan requirements is technically challenging, involving factors from many tunnel design disciplines, interactions of thermodynamics and fluid dynamics, and physical constraints. Fan requirements for the
smoke extraction system are based on the possible fan
duty points the system will encounter during operation.
Designs undertaken by Parsons Brinckerhoff have demonstrated the viability of smoke extraction systems for
long road tunnels, by determining the necessary fan requirements and smoke duct requirements to achieve the
required capacity. The design analysis and research the
team has undertaken will benefit future smoke extraction system designs for long road tunnels, by ensuring
that the installed systems can perform to their intended
purposes and capacities. However, the actual performances of such systems are also dependent on the
constructors final system design, the equipment suppliers, and the installers performance based on their
project contractual obligations. The completed smoke
extraction systems installed in the Clem7 and Airport
Link tunnels are currently in service.
Chris Chen is a Mechanical Engineer who has worked on various road and rail tunnel projects, including Airport Link in Brisbane, as part of Parsons Brinckerhoffs tunnel systems team
in Australia.
Ventilation
Fire and Life
Systems
Safety
NETWORK
by Jesse Harder, Sacramento, CA, US, +1-916-567-2512, harderjl@pbworld.com; Andrew Louie, New York, NY, US,
+1-212-631-3767, louiea@pbworld.com; Vamsidhar Palaparthy, New York, NY, US, +1-212-465-5521, Palaparthy@
pbworld.com; Silas Li, New York, NY, US +1-212-465-5217, lisilas@pbworld.com
dard for fully transverse ventilation system design for many decades to come.
37
Ventilation
Fire and Life
Systems
Safety
NETWORK
for 10 and 20 MW fires from the findings of the MTFVTP,
it would appear that some variation of extraction ventilation could control the smoke generated. However, road
tunnel ventilation systems, like those considered for reuse in the East Link extension, were designed to the 100
cubic feet per minute per lane foot criteria. In MTFVTP
findings, this criterion was not sufficient for many emergency fire scenarios.
center tunnels into a light rail transit (LRT) trainway connecting Seattle to Bellevue (see Figure 3).
In 2013, Parsons Brinkerhoff performed extensive ventilation analysis in support of the East Link project final design, investigating the ventilation system design
for two existing road tunnels in the Seattle area, the
Mount Baker Ridge Tunnel and the Mercer Island Lid
Tunnel. The analysis specifically considered modifications to the existing fully-transverse road tunnel ventilation systems to determine the feasibility of reusing it
for the new LRT trainway.
38
West Portal
East Portal
Ext. Coeff
Ventilation
Fire and Life
Systems
Safety
NETWORK
Ext. Coeff
Exhaust Damper 1
Exhaust Damper 2
250 feet
Fire Car
Zone 2
ct
t Du
aus
Exh
t
Duc
ply
p
u
S
East Portal
Zone 1
Zone 3
West Portal
Motor-Operated
Damper Connection
to Fan Plant (typ.)
Zone 4
West Portal
39
Ventilation
Fire and Life
Systems
Safety
NETWORK
feet (22.3 square meters) in the suspended ceiling
to extract smoke and hot gases from the incident fire
zone (see Figure 7). This system controlled smoke
spread for the duration of egress (12 minutes) with
increased fan capacity, but the option was rejected
due to concerns about the structural impact on the
existing tunnel.
Longitudinal System (Jet Fans) install 14 jet fans
(12 fans operating - analysis considered 1 fan out
of service and 1 fan out due to fire) along the tunnel
walls providing longitudinal ventilation and protecting
the egress path indefinitely (see Figure 8).
Conclusion
Converting an existing fully-transverse road tunnel ventilation system to transit use is feasible but presents
many challenges to the designer. Based on CFD analysis of the East Link tunnels for the stated fire size, the
following parameters significantly affect the ventilation
system performance:
40
Ventilation
Fire and Life
Systems
Safety
NETWORK
Exhaust
System
Reversible Jet Fans
Fresh Air
Fresh Air
Piston Effect
Unidirectional trafc
Exit Portal
Entry Portal
Vitiated Air
Figure 2 - Point extraction for portal emission control fully reversible jet fans shown
41
Ventilation
Fire and Life
Systems
Safety
NETWORK
longer tunnels requiring greater exhaust capacity. Figure 2
schematically shows the location of the exhaust system
within the context of the tunnel and associated ventilation
equipment. The capacity of the exhaust system needs to
be sufficient to capture both the main tunnel airflow and
the additional fresh air inflow through the exit portal.
Aerodynamic efficiencies can be improved by augmenting
the exhaust system capacity with jet fans within the tunnel to control tunnel and portal airflows (see Figure 3).
In a unidirectional tunnel the aerodynamic drag of the
vehicles moving in one direction creates a piston effect
which generates air flow in the direction of traffic. In a
simple longitudinal ventilated tunnel without portal emission control, the piston effect is utilised with the jet fans
augmenting the flow when required. When portal emissions are to be controlled, jet fans are often utilised to
retard the traffic piston effect along the length of the tunnel, to reduce the required extraction system capacity just
prior to the exit portal. The number of jet fans needed to
operate at any one time is dependent upon a number of
factors including the ventilation system exhaust rate, the
traffic speed, the fleet vehicle profile, the tunnel geometry,
and the capacity of the jet fans.
42
In order to ensure that portal emission control is maintained, it is also important to consider the short-term
transient effects that fluctuations in the traffic volume,
profile, or speed can have on the portal inflow condition.
The tunnel exit section is typically short in length with the
air within that section having a relatively low inertia making it susceptible to short-term fluctuations due to traffic. A short-term increase in the number of heavy goods
vehicles travelling through the tunnel in a convoy could
generate a piston effect sufficient to not only reduce the
portal inflow but also create an outflow condition.
Air Flow
Ram
Exit P
ortal
Exit
Ventilation
Fire and Life
Systems
Safety
Exit Ramp
Trafc Flow
Exit Portal
NETWORK
Extraction
System
Wider considerations
It has been shown that there are engineering solutions
available for the control of emissions through tunnel exit
portals. However, we recommend that a holistic approach
be taken prior to committing to a portal emission control
ventilation strategy and that it not be carried out in isolation from other disciplines.
The use of jet fans to control in-tunnel airflow and exhaust fans to extract the air from the tunnel is a relatively
costly strategy, considering that the fans may be required
to operate on a 24-hour basis, depending on the traffic
and air quality limits. The decision to go ahead with portal emission control should be undertaken with support
from air quality assessment, dispersion modelling, power
demand, and future climate change projections on power
cost, carbon emissions, community consultation, and
whole-of-life assessment.
Relaxing portal emission control during off-peak, shoulder, and night time operation should also be considered,
provided that portal emissions are monitored, ambient air
quality limits strictly observed, and community consultation and subsequent buy-in is obtained.
Argun Bagis is a Principal Mechanical Engineer at Parsons
Brinckerhoff, with over 18 years engineering experience,
primarily in the transportation infrastructure industry.
Duncan Saunsbury is a Mechanical Engineer with over 3 years
of experience specialising in tunnel ventilation, fire, and life
safety. Originally based in the UK, he has worked on tunnel
projects worldwide including in the US, Europe, Middle East,
Australia and New Zealand.
43
Ventilation
Fire and Life
Systems
Safety
NETWORK
Introduction/Overview
44
North
Emergency
Vent
Shaft
South
Emergency
Vent
Shaft#1
North
Emergency
Vent
Shaft #2
Reversible
Emergency
Fan (TYP)
EMFN-5
Fan Damper
(TYP)
EMFN-7
EMFN-2
EMFN-4
EMFN-6
EMFN-1
EMFD-3
Push/Pull
Push/Pull
Push/Pull
Track
Damper
(TYF)
South Bound
Tunnel
U-District
Station
North Bound
Tunnel
Roosevelt
Station
SB Portal
from
Northgate
Station
NB Portal
from
Northgate
Station
EXHAUST / INTAKE
Ventilation
Fire and Life
Systems
Safety
NETWORK
EFAN
EFAN
PUSH / PULL
Pressure Loss/Silencer
Pressure loss through the silencer may be given
by manufacturers data (IAC Type L Sound
Attenuator), however, the pressure loss is taken
by SMACNA pg 9.10. The ow rate for this type
of system is considered a medium attenuator.
Lz : = 7. ft.
Q
ft.
Vs : = f
= 1875 .
min
As
Pf := 0.3 in
z
Length of Silencer
Face Velocity
Pressure Loss
(SMACNA pg 9.10)
45
Ventilation
Fire and Life
Systems
Safety
NETWORK
Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) has published that pressure loss is
a function of velocity. Similarly, a pressure loss is to be
calculated for every ductwork component along the highest
resistance pathway.
the flow path. After each component has been evaluated for pressure loss, the total summation is used to
evaluate the fan brake horsepower. The fan sound power
is evaluated from the total pressure loss as shown by
Equation 3 (Reference 2).
Sound
In conjunction with the pressure term, a sound power
component is considered for all segments in which
sound is either regenerated or attenuated. The sound
reduction or absorption is defined as the insertion loss
(IL). When sound travels through a duct component such
as a silencer an insertion loss occurs.
Equation 3
Equation 1 describes the sound power after a component loss where Lw1 is the sound power level before the
component loss and Lw2 is sound power level after the
component loss (Reference 2). The insertion loss reduction is calculated over each of eight frequency bands
which range from 63Hz to 8000Hz. The human ear is
only sensitive to this range of frequencies.
Equation 1
When calculating the total sound power at the receptor, each component is evaluated from the fan to each
receptor location. In other words, the fan sound power
calculated from Equation 3 is taken to be reduced
from the insertion component by Equation 1. For components with regeneration, the total sound is combined using Equation 2. Sound power, which is a measure of the sound intensity, must then be converted to
sound pressure or the power component that directly
affects the ear drum. The sound pressure levels are
evaluated for the receptors, typically in a tunnel, station, or ambient locations.
Example
46
A silencer insertion loss and regeneration values for a silencer are available from manufacturers' data for each of
the eight frequency band levels in both the forward and
reverse fan direction. Insertion loss can be determined
for any component in the system. Sheet Metal and Air
Conditioning Contractors' National Association (SMACNA)
provides methods to calculate insertion and regeneration
values for various types of ductwork components.
Total Pressure/Sound
The total pressure loss of the ventilation system is determined by a summation of losses for components along
SOUND POWER
PROVIDED AT
TUNNEL DAMPER
AT CEILING
OF PLATFORM
LEVEL (TYP)
Ventilation
Fire and Life
Systems
Safety
NETWORK
ADD ACOUSITCAL
MATERIAL TO
WALLS
SOUND POWER
FOR SINGLE
ATRIUM DAMPER
STAIR-6
SOUND PATHWAY
Conclusion
Traditionally, pressure loss analysis has received more attention in the design of tunnel ventilation systems than
sound analysis. In recent years, environmental policy, regulatory requirements, and space constraints are making
it more important to understand sound mitigation. This
methodology of combining sound and pressure simultaneously in the design of ventilation systems provides an
efficient tool for understanding how both sound and pressure are influenced by each system component. In addition
to demonstrating compliance with the regulatory requirements, the method provides a means to explore other options more efficiently than before. It allows for an optimum
design that minimizes motor power requirements, meets
sound requirements, and minimizes space requirements.
References
1. Idelchick, I.E., Handbook of Hydraulic Resistance. 4th
Edition.
2. HVAC Sound and Vibration Manual. s.l. : Sheet Metal
and Air Conditioning Contractors' National Association, First Edition Dec. 2004.
3. HVAC Systems Duct Design. s.l. : Sheet Metal and Air
Conditioning Contractors' National Association, Third
Edition 1990.
Michael MacNiven is a Senior Mechanical Engineer with a technical background in HVAC, piping, and fire life/safety systems
along with large scale tunnel emergency ventilation systems.
SOUND POWER
PROVIDED AT
AMBIENT AT TOP
OF SHAFT
47
Ventilation
Fire and Life
Systems
Safety
NETWORK
In general, tunnel booster fans are powered from a motor control center (MCC) and operated at a low voltage of
about 400V. However, if the fans are not located near the
power supply, it becomes necessary to run long cables to
the tunnel booster fans, which leads to:
48
Examples of Solutions
Some projects in Hong Kong, India, and Singapore have
considered or adopted this approach of using tunnel
booster fans of increased voltages of 660V (i.e., 3 x
380V), or 690V (i.e., 3 x 400V) as appropriate1 (using
step-up transformers inside the MCC rooms). This nominal voltage boost approach will reduce the nominal operating currents of the tunnel booster fans proportionally;
however, the percentage voltage drop along the feeder
will be reduced with the square of the nominal voltage
boost, which in turn results in significantly reduced feeder cable sizes for the same voltage drop requirements,
and therefore results in significant savings for the overall
feeder cabling costs.
To illustrate this approach/solution, it is assumed a tunnel project in Singapore has tunnel booster fans (45kW
each) with an average cabling distance2 of over 200 metres (656 feet) from the MCC room. For this situation, two
schemes were considered:
Note: In the US the nominal voltage of a fan motor is relatively standardized (3-phase 208V, 480V, 575V, 2400V, etc.) and normally cannot
be customized as stated in this paper.
2
Average cabling distance = Total cable length / Number of tunnel booster fans.
MCC 3
(400V)
MCC 1
(400V)
Cost Considerations
MCC 2
(400V)
MCC 4
(690V)
Other Considerations
Cabling System
The cost saving as illustrated in Figure 3 is 7.6
percent, based on the adoption of low smoke zero
Description
Scheme 1
Cost (US$)
Scheme 2
Cost (US$
Power cables to
tunnel booster fans
$736,000
$427,000
$54,000
MCC (400V)
$266,000
$199,000
MCC (690V)
$210,000
$480,000
$480,000
Total:
$1,482,000
$1,370,000
MCC 3
(400V)
MCC 1
(400V)
MCC 2
(400V)
Overall Savings
(by using Scheme 2):
$112,000
(Cost Saving of 7.6% using Scheme 2)
Ventilation
Fire and Life
Systems
Safety
NETWORK
49
Ventilation
Fire and Life
Systems
Safety
NETWORK
halogen (LSOH3) type fire resistant cables. This is
generally a cabling requirement for emergency/life
safety systems of all underground tunnel installations
in Singapore. In Singapore and Hong Kong, where the
low voltage (LV) power distribution system is rated
at 230V/400V and 220V/380V respectively, the
standard LV cable (Uo/U) is rated at 600V/1000V.
Energy Savings/Efficiency
From a viewpoint of energy savings, VVVF drives can
be considered for many fan/motor installations. VVVF
drives can achieve a very steady current ramping for different fan speeds to suit different air flow requirements.
As the energy consumption for a fan with VVVF drive is
in direct proportion to the speed, the energy savings will
be generally as shown in Figure 4.
Speed
100%
90%
80%
70%
60%
50%
Energy
Consumed
100%
73%
51%
34%
22%
13%
In the US, the acronym for low smoke zero halogen is LSZH.
50
Recommendation
Technically, the use of a step-up boost transformer or
autotransformer for tunnel booster fans requires more
distribution equipment and more space to accommodate the plant. If the tunnel booster fans are too close
to the MCC (e.g., within 200 metres) and the fan quantity is small (e.g., four fans), it will not be worthwhile
to consider the use of a higher supply voltage cable
distribution system.
Parsons Brinckerhoff successfully has applied the abovementioned cost saving scheme to various road tunnels
and metro projects.
Ventilation
Fire and Life
Systems
Safety
NETWORK
51
WaterFire
Resource
Pressure
and Life
Transient
Planning
Safety
NETWORK
The expertise of Parsons Brinckerhoff in tunnel aerodynamics was utilized in eliminating an expensive and
complicating featureflared tunnel portalsindicated
by preliminary engineering for Sound Transit's Northgate
Link Extension tunnel in the state of Washington. The
analysis performed also provided an additional benefit,
eliminating some station ventilation shafts that were initially perceived to be required.
Portal Flares
52
sure changes that occur, the air flow through the station
elements is estimated and compared to the design criteria requirements.
The Subway Environmental Design Handbook1 (SEDH) is
the reference source. The equations and expressions in
the calculation describe the effects of pressure transients
caused by train movement into and within enclosed spaces. These transients can place large loadings on trains
and wayside facilities and can cause passenger discomfort, particularly ear discomfort due to pressure.
The SEDH criteria for changes of pressure inside a train
are: if the pressure change exceeds 2.78 inches water
column (0.69 kPa), then the rate of pressure change
should be less than 1.67 inches (0.42 kPa) per second. These are the same as the project design criteria. These requirements reflect passenger comfort for
subway operations involving frequent pressure changes
due to portals, vent shafts, and other discontinuities in
metropolitan underground transit operations.
There are no standard criteria for exterior pressure
changes; however, they do represent cyclical loads that
must be accounted for on tunnel surfaces, particularly
doors, ductwork, and other large metal surfaces. Special
construction, reinforcing, or other treatment is usually
necessary to handle these cyclical loading conditions.
In addition to the pressure changes from train passage
described above, acoustic waves are generated at discontinuities such as portals, vent shafts, and tunnel shape
changes. These waves are generated at the discontinuity
location, travel at the speed of sound along the tunnel,
and are then reflected back and continued forward. The
reflected wave passes over the train providing a pressure
spike. These are all evaluated with respect to the project/
SEDH criteria.
Subway Environmental Design Handbook (Vol. 1 & 2), prepared by Parsons Brinckerhoff as part of a joint venture for the U.S. Department of
Transportation, publication date 1975.
Location
Pressure Change
(inches water
column) (kPa)
Rate of Change
(inches water column)
(kPa) per second
Nose
at portal entry
3.91* (0.97)
0.94 (0.23)
3.909
= 2.468
1.441
= 3.408
-2
0
2000
North Portal
Nose
at tail crossing
portal entry
-2.47 (-0.62)
Nose
transiting tunnel
-3.41* (-0.85)
n/a
-0.05 (-0.01)
-1.967
4000
6000
8000
Distance in subway (feet)
Roosevelt Station
In. wc
3.909
2.468
1.441
3.408
1.967
kPa
0.97
0.61
0.36
0.85
0.49
0.50
1.00
-1.5
Tail
transiting tunnel
Tail
at nose exit into station
Tail
at exit into station
-1.81
-2.54 (-0.63)
n/a
Pressure (inches water)
Tail
at portal entry
-2
= 1.86
-2.5
-1.24 (-0.31)
0.11 (0.03)
1.86 (0.46)
n/a
n/a
n/a
= -1.24
-2.54
-3
-3.5
-4
0
2000
North Portal
-3.78
6000
-3.67
= 0.11
4000
Distance in subway (feet)
Roosevelt Station
8000
In. wc
2.54
1.24
3.78
1.86
3.67
1.81
1.5
2.5
3.5
kPa
0.63
0.31
0.94
0.94
0.46
0.91
0.45
0.50
0.63
0.75
0.83
1.00
Calculation Results
Fire
Pressure
and Life
Transient
Safety
NETWORK
53
6
Pressure (inches water)
Fire
Pressure
and Life
Transient
Safety
NETWORK
5.26
4
2
0
-0.02
-2
0
2000
North Portal
4000
6000
8000
Distance in Subway (feet) Roosevelt Station
In. wc
7.72
5.26
0.02
kPa
1.92
1.31
0.00
0.50
1.00
1.50
2.00
0.80
-0.01
-1
-1.12
-2
-2.49
-3
0
2000
North Portal
4000
6000
8000
Distance in subway (feet)
Roosevelt Station
In.
0.01
2.49
1.12
0.80
kPa
0.00
0.62
0.28
0.20
0.25
0.50
0.75
1.00
Piston effect refers to the forced air flow inside a tunnel caused by moving vehicles.
For other previous Network articles by Bob Melvin, see Mitigating Pressure Effects in High Speed Rail Tunnels, Network #60, June 2005, pp
90-91, 95; and Geometric Enhancement of Fire Size in Road Tunnels, with Joe Gonzalez, Network #70, November 2009, pp 15-17.
2
3
54
Conclusion
Fire
Pressure
and Life
Transient
Safety
NETWORK
Usually, the aerodynamic analysis of a high-speed railway tunnel system can be done by using a highly efficient one-dimensional (1-D) computational fluid dynamics (CFD) simulation program such as ThermoTun.
However, the pressure wave propagation and airflow
speed inside some complicated geometries, such as
an underground station, plenum, and vent shaft, may
no longer be 1-D in nature, and so we investigated the
possibility of three-dimensional (3-D) CFD as a suitable
method to be adopted.
South
Portal
462m
Monitoring Point
South
Shaft
9m
542m
North
Portal
1633m
12.25m
75.9m
8m
Introduction
3m
Area: 75.9m2
Length: 1633m
Vent Shaft:
Area: 12m2
Length: 12m
Area: 10m2
Length: 236m
Full-scale flow measurements in a tunnel airshaft, A. Vardy, 12th International Symposium on the Aerodynamics and Ventilation of Vehicle
Tunnels, Organized by BHRA Fluid Engineering, Portoroz, Slovenia, 2006, p. 343
2
http://www.thermotun.com/airshaft
3
FLUENT Version 14 User Guide, Chapter 11, Modelling Flows Using Sliding and Deforming Meshes
1
55
Fire
Pressure
and Life
Transient
Safety
NETWORK
approach, the mesh quality and quantity, and also the
required computer resource, could be controlled. Figure
2 illustrates the general concept of this CFD technique.
Layers of meshes removed
Moving Domain
Mesh Interface
Stationary Domain
56
Apart from the numerical methods adopted, the boundary conditions used are as follows:
The ideal gas law to account for the air compressibility, i.e., the relationship between
absolute pressure, temperature, and density;
Ambient condition: absolute pressure at 95802.79 Pa (13.89 psi) and at 287.15K
(also as initial condition for the whole domain);
Density-based, spatial, and temporal implicit solver;
Green-Gauss Node-based for gradient interpolation;
Second order discretization for flow;
Flux type: Roe flux-difference-splitting (FDS) scheme;
Implicit time stepping with time step around 0.0013 second;
Initial air speed = 0 meters per second (m/s) for the whole domain;
Initial train location = 50 metres from south portal; and
Train speeds: north bound 177.5 kph (110.29 mph) and 204 kph (126.76 mph).
Prediction and validation on the sonic boom by a high-speed train entering a tunnel, Yoon, T.S., Institute of Advanced Aerospace Technology,
School of Mechanical and Aerospace Engineering, College of Engineering, Seoul National University, Journal of Sound and Vibration (2001)
247(2), pp. 195-211
5
Numerical and Experimental Investigation of Wave Dynamics Processes in High-Speed Train / Tunnels, Jiang Zonglin, ACTA MECHANICA
SINICA (English Series), Vol. 18, No. 3, June 2002.
4
The 3-D CFD simulations were conducted on a high performance workstation supporting 24-CPU parallel processing. The nominal time required for each time step
of 0.0013 seconds is around 20 seconds. For the train
to run from the starting position to the other end of the
tunnel, the total travelling time required for speeds of
177.5kph and 204kph is 40 seconds and 35 seconds
respectively. And the computer time required is 171
hours and 150 hours respectively. Unfortunately, due
to the limited computer resources available, the complete train entry and exit could not be simulated. Only
12 seconds and 17.5 seconds of simulations were
conducted for 177.5kph and 204kph train speeds respectively. The total simulation time required for these
two cases using the same workstation is approximately
one week.
Fire
Pressure
and Life
Transient
Safety
NETWORK
Point B
Point A
10
12
-200
Pt-B (CFD)
-400
Pt-A (CFD)
-600
400
200
0
0
9 10 11 12 13 14 15 16 17
-200
Apart from the numerical values, it is clear from the figures that the 3-D CFD simulation approach could predict
the major pressure wave peaks and troughs correctly at
their time of occurrence. However, the 3-D CFD simulation
approach appears to underpredict the positive pressurization before the train nears the measurement point but
Train Speed
-400
Pt-B (CFD)
-600
177.5kph
204kph
Exp.
Exp.
2050
3280
492
667
554
769
57
Fire
Pressure
and Life
Transient
Safety
NETWORK
overpredicts the negative pressurization after the initial
stage of the train passed through the measurement point
(Figure 7). After that the variations in magnitude appear
to be less regular.
It is clear from Table 1 that the pressure gradients (important for sonic boom generation) and first peak values
are overpredicted by CFD and the second peak values
are underpredicted.
Pt-C (Measurement)
400
200
Pt-D (ThermoTun)
0
10
-200
-500
800
600
400
200
0
Pt-D (ThermoTun)
0
10
-200
-400
-600
-800
177.5kph
204kph
Exp.
CFD Results
Exp.
CFD Results
492
667
554
769
58
-400
ThermoTun
software is
for studying
pressure waves
within high
speed train tunnels. Since ThermoTun is a 1-D
approach, some
Figure 8 - Cisalpino ETR 470
natural disadvantages that may affect the accuracy are raised below:
500
Even with the use of the latest high performance parallel processing technique, the overall progress of 3-D CFD
simulation is very slow. The computational resources and
time span required also prohibit the use of the 3-D CFD
method as a design tool for high-speed railway aerodynamics analysis. The 1-D ThermoTun approach cost less
to run the same scenario compared to 3-D. Although the
ThermoTun simulation amplifies the pressure peak, for
design applications this can be treated as a safety factor.
In short, with more numerical method refinement and enhancement of computer speed and capacity, 3-D CFD is
expected to perform more accurately and provide more
detail when simulating tunnel pressure waves. However,
with the current computational resources and the time
span required, the 3-D CFD approach cannot achieve
more accuracy within reasonable time and cost. It is concluded that 1-D ThermoTun is the best choice for engineering design purposes under current technology.
Dr. Dicken K.H. Wu specializes in computational fluid dynamics (CFD) simulations and various types of computer simulation analysis. He has designed pressure comfort control systems for high-speed subway systems in Hong Kong, Mainland
China, and Taiwan.7
Rambo RB Ye was formerly a specialist in simulation methods at
Parsons Brinckerhoff.
Aerodynamic design of underground station with high-speed train passing, D.K.H. WU, 13th International Symposium on the Aerodynamics
and Ventilation of Vehicle Tunnels, Organized by BHRA Fluid Engineering, 2009. An abstract of the same paper is in Network #70, November
2009, p 26.
7
For a previous Network article by Dicken Wu and YF Pin about FLUENT, see New and Efficient Techniques for Modeling and Meshing with FLUENT and FDS, in The Engineers Crystal Ball, Network #70, November 2009, pp 4-6.
6
Fire
Pressure
and Life
Transient
Safety
NETWORK
59
Climate Change
Fire Tunnel
and
Water
Stormwater
Life
Resiliency
Systems
Safety
Power
NETWORK
Parsons Brinckerhoff has been providing engineering support to London Underground, the Buenos Aires Metro
(Subterrneo de Buenos Aires), and the proposed UK High
Speed 2 project in identifying, understanding, and overcoming the challenges associated with warming railways.
The Challenges
60
Mitigating Heat
Energy efficiency is first and foremost a measure that
can be employed to take on the challenges; this tackles
the heat release at its source. Optimizing rolling stock
and traction power specifications, train speed operating
profiles, and maximizing regenerative braking1 receptivity
all play a major role in reducing temperatures, as well as
reducing energy usage. For example, it might be preferable to provide more motored axles on the train to allow
more regenerative braking (the number of motored axles
might otherwise be rated on acceleration requirements
alone). Such energy efficiency was an important part of
the scope of work for London Underground where Parsons Brinckerhoff played a key role in the optimisation of
Regenerative braking is when the train motors are used to slow the train down. When they work in this way the motors act as generators,
providing energy back to the traction power system for use by other trains. Without this technology the braking energy would be released as heat.
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
61
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
25mm diameter pipe
200mm below the surface
of a 300mm thick liner and
spaced at 350mm centres
Figure 4 - Thermal analysis of the heat recovery potential for pipework embedded into a 300mm tunnel liner with a soil depth of 20m
Re-using Heat
62
Sustainability may be further improved by heat recovery. For example, a heat exchanger in the tunnel may
capture the heat from the tunnel, and a water circuit
transfers the heat to the heat-sink side of a heat pump.
The heat-source side of the heat pump may be connected to a third partys building or small-scale district
heating system, again by a water circuit, and provided
with monitoring systems to record the amount of heat
captured and utilised. Capturing the heat from the tunnel in a cost-effective manner remains a key challenge.
Parsons Brinckerhoff has been involved in the investigation of several technologies including tunnel cooling
pipes2, pipework embedded within the tunnel liner (see
Figure 4), and the location of air source heat pumps in
exhaust air plenums. For High Speed 2 we have developed a finite difference model of tunnel wall heat transfer and airflow within the tunnel (called Dynamo, see
article in this issue on Dynamo by Jolyon Thompson)
and are looking at the most cost effective way to re-use
the heat from these tunnels.
A Sustainable Outcome
Sustainability is a key factor in railway cooling, and in the
broadest possible sense. Social sustainability can be
enhanced by providing the temperature control to support railway capacity upgrades that improve the quality
of life for transit users and city dwellers. Environmental
sustainability can be enhanced by reducing heat release
in the railway through increased energy efficiency and
low energy cooling methods such as groundwater cooling
systems. Economic sustainability can be enhanced by
optimising the cooling provisions and customer benefits
to minimize whole-life costs with a demonstrable benefit
to cost ratio. Parsons Brinckerhoff has an enviable track
record in balancing these sustainability needs.
Mark Gilbey is EAME Head of Discipline for Tunnel Ventilation. He
is a Mechanical Engineer and has worked for Parsons Brinckerhoff
since 1998 in Hong Kong, US, and the UK.
For the abstract of a previous article by Ting, Drake, and Gilbey on CFD Estimation of Heat Transfer Enhancement on a Cooling Pipe in Underground Railway Tunnels, see Network #70, November 2009, p 42.
The Subway Environment Simulation (SES) software program was co-developed by Parsons Brinckerhoff for the
US Department of Transportation in the 1970s. It allows
engineers to mathematically model aspects of the subway
environment on a second-by-second basis and continues
to be regarded as an industry standard tool in the field of
tunnel ventilation. SES is used worldwide for a variety of
underground construction and tunnel applications, including
high speed rail, commuter rail, metros, freight tunnels, road
tunnels, and cable tunnels. A supplement to the SES has
been developed by Parsons Brinckerhoff to enhance the capabilities of SES and to meet specific requirements of other
tunnel system projects. This supplement is called Dynamo.
Dynamo is a one-dimensional (1-D) model of a single
length of tunnel which can simulate the effects of a ventilation shaft connected at any point along the length of
the tunnel. Dynamo predicts the thermofluid interactions
DYNAMO
Parsons Brinckerhoff created a calculation tool to estimate the annual temperatures of long tunnels and with the
ability to calculate the heat transfer from heat recovery mechanisms such as embedded liners and tunnel cooling
pipes. The tool is named Dynamo.
Dynamo uses a similar set of modelling assumptions to SES and therefore a single Dynamo file can and may need
to take input from several SES simulations to account for variations in fan, train operations, or other significant
variations in the system. The most significant difference is in the treatment of the deep heat sink effect through
the surrounding soil. Dynamo uses a fully transient finite difference approach to allow thermal evolutions to be
calculated in response to the tunnel environment, allowing complete year profiles to be developed.
Dynamo uses an energy balance approach to determine the thermofluid interactions. The energy balance is at the
core of the flexible Dynamo methodology. Any technology or system which can be formulated into an energy effect
upon the system (input, output, or storage) can be included.
Dynamo is a modular program which enables additional functions to be easily added and tested. All that the
function requires is to be formulated to add to the energy balance in the correct manner. Examples of technology
systems that have been added in this manner include cooling pipes and embedded tunnel liners.
A Newtonian fluid is any fluid that exhibits a viscosity that remains constant regardless of any external stress that is placed upon it. This could
include mixing or a sudden application of force. A Newtonian fluid can change viscosity if the temperature or pressure changes. The fluid would
still be regarded as Newtonian providing the viscosity remained constant at these new temperatures or pressures.
Introduction
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
63
Previously a two-stage approach using an initial SES simulation supplemented with an Excel calculation sheet
would be used. This required iteration between the two
models to get the final result. If the cooling pipes loop
and return to the portal-based cooling plants, this would
result in a circular formula within the Excel analysis. The
calculation therefore required a macro to control the
process. The system was then iterated to ensure the
accuracy of the calculation. The calculation process was
thus bespoke to the situation and would need adjusting
before it could be used with another tunnel layout option
and it also took several days to complete.
Dynamo, in contrast, can be set up to evaluate the system in an integrated way. Since the only source of air
flow is that generated by the fan against a constant resistance, the ventilation rate is also constant. The Dynamo analysis took less than four hours to set up, check,
and simulate.
60
7000
50
6000
5000
30
4000
3000
20
2000
10
1000
18000
17700
17400
17100
16800
16500
16200
15900
15600
15300
15000
14700
14400
14100
13800
13500
13200
12900
12600
12300
12000
11100
11700
11400
10800
10500
9600
9300
9000
8700
8400
8100
7800
7500
7200
6900
6600
6300
6000
64
5700
5400
5100
4800
4500
4200
3900
3600
3300
3000
2700
2400
2100
1800
900
1500
1200
600
300
0
0
Temperature (C)
40
Time (hours)
10200
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
60
7000
50
Time (hours)
40
5000
30
4000
3000
20
2000
10
Temperature (C)
6000
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
1000
18000
17700
17400
17100
16800
16500
16200
15900
15600
15300
15000
14700
14400
14100
13800
13500
13200
12900
12600
12300
12000
11100
11700
11400
10800
9600
10500
9300
10200
9000
8700
8400
8100
7800
7500
7200
6900
6600
6300
6000
5700
5400
5100
4800
4500
4200
3900
3600
3300
3000
2700
2400
2100
1800
900
1500
1200
600
300
0
0
60
7000
50
Time (hours)
40
5000
30
4000
3000
20
2000
10
1000
13420
13115
12810
12505
12200
11895
11590
11285
10980
10675
10370
10065
9760
9456
9150
8845
8540
8235
7930
7625
7320
7015
6710
6405
6100
5795
5490
5185
4800
4575
4500
4270
3965
3660
3355
3050
2745
2440
2135
1830
1525
1220
915
610
305
0
0
Temperature (C)
6000
In a recent project, a 13.5 kilometre (8-mile) long highspeed rail tunnel was analysed using SES and predicted
to be at a significantly elevated temperature over a substantial length of the tunnel during summer. To allow the
tunnel to meet the design criteria, a cooling system was
proposed and designed with a total peak cooling capacity of approximately 4MW.
65
60000
50000
80000
70000
60000
50000
40000
30000
20000
10000
0
40000
30000
20000
10000
Climate Change
Fire and Life
Resiliency
Safety
NETWORK
20
15
50
100
150
10
200
250
Time (hrs)
5
300
350
66
Conclusion
Two examples of Dynamo usage have been provided in
this article. Dynamo has been shown to be capable of
supplementing SES predictions in some areas which enhances the analysis capabilities of Parsons Brinckerhoff.
References
Subway Environmental Simulation User Manual, 2003,
prepared for the U.S. Dept. of Transportation
Thompson J.A., Missenden J.F., Gilbey M.J. and Maidment G.G., Response of wall heat transfer to steady and
transient flows along a cylindrical cavity, Int. Symp. Aero.
& Vent. Vehicle Tunnels, New Brunswick 2009
Jolyon Thompson is a Senior Tunnel Engineer in the UK office
with a PhD in sustainable cooling of underground railways. He
has a keen interest in heat recovery and improving the sustainability of tunnels through holistic design and was the lead developer of the DYNAMO analysis tool.
Facility Description
The Brooklyn Battery Tunnel (see Figure 1) crosses New
York Harbor, connecting Brooklyn and lower Manhattan.
The tunnel consists of two adjacent tubes, the east and
west tubes, each approximately 9,000 feet long making
it the longest continuous underwater vehicular tunnel
in North America. Construction of the tunnel began in
the 1940s but was suspended during the Second World
War. The tunnel was opened to traffic on May 25, 1950
and now carries over 50,000 vehicles per day.
NETWORK
Security
Elevators
Electrical Distribution
Compressed Air
Communications
Carbon-Monoxide (CO)
Monitoring
Tunnel Drainage
Tunnel Ventilation
Building Lighting
SCADA/PLC
Hoisting-Mechanical
Heating, Ventilation,
and Air Conditioning
The database includes structural, architectural, mechanical, and electrical components this article is focused
on the tunnel systems which include:
67
NETWORK
Database Architecture
The database of tunnel tubes and plazas includes an inventory of 65 different structural, mechanical, and electrical element types. These element types were inventoried
by location with over 23,000 uniquely identified database
elements or entries resulting. The database identifies
over 150 element types housed in the buildings.
These elements are defined by:
Asset Identifies tube, plaza, building, or pedestrian
bridge;
Discipline Structural, Mechanical, Electrical, or
Architectural;
System Various tunnel and building systems; and
Location
- Tubes - subdivided by wall marker stationing; then
Construction Type - cut and cover steel bent, cut
and cover concrete, light cast iron ring, heavy cast
iron ring; and then Level - exhaust duct, roadway,
fresh air duct;
- Plazas - subdivided by expansion joints;
- Buildings - subdivided by floor/(sub) levels; and
- Pedestrian Bridge - subdivided by bents.
See Figure 2 for a sample listing of element types.
The comprehensive database also provides the following:
Identification of element-level electrical and mechanical
deficiency types for use in future inspections;
Identification of element level deficiencies observed during the 2012 inspection with links to photographs of
conditions;
The ability to sort and search the data within the database to facilitate condition management and reporting;
The ability to summarize condition ratings, deficiency
types, and quantities of deficiencies;
Installation year, age, and expected service life
Parsons Brinckerhoff worked with the TBTA, to identify
the estimated service life. Data from Federal Transit
Administration (FTA) assumptions regarding useful life
for effective cost comparisons was considered as well
68
Database Worksheets
The database was developed in coordination with the
client using Microsoft Office Excel 2007. This format
was chosen in order to create an asset management
tool that is commonly understood by the engineering
staff that would be working with the system. The Excel
spreadsheets provide ease in the creation and manipulation of the large amount of data through simple functions such as sorting and filtering, and provide the ability
to produce reports summarizing filtered and sorted data
through pivot tables.
Different groups of worksheets make up the Brooklyn
Battery Tunnels database:
Support/Reference worksheets;
Master-Administrator Only worksheet;
End-User Database worksheets;
Database Expansion worksheets; and
Summary worksheet(s).
Support/Reference worksheets
These worksheets are the source of defined and known
information contained in the Master-Administrator Only
worksheets. These include: a summary of the repair/
rehabilitation projects and the coding used to define the
element level that is inventoried and rated, along with
the deficiency types applicable to each element.
The Support/Reference worksheets standardize the
terminology throughout the databases and minimize
manual work during database updates by simplifying the
steps for modifying or expanding the current range of
data in the databases. The vast majority of the current
System
Element
Structural
Tunnel Ventilation
Acoustic Bafe
Structural
Tunnel Ventilation
Structural
Tunnel Ventilation
Structural
Tunnel Ventilation
Structural
Tunnel Ventilation
Structural
Tunnel Ventilation
Damper Door
Mechanical
Tunnel Ventilation
Mechanical
Tunnel Ventilation
Fan
Mechanical
Tunnel Ventilation
Fan Housing
Mechanical
Tunnel Ventilation
Fan Shaft
Mechanical
Tunnel Ventilation
Fan Motor
Mechanical
Tunnel Ventilation
Electrical
Tunnel Ventilation
Electrical
Tunnel Ventilation
Electrical
Tunnel Ventilation
Power Capacitor
Discipline
NETWORK
Figure 4 - Filter worksheet with elements associated with the tunnel fireline
69
NETWORK
Figure 5 - Pivot Table worksheet showing query of the tunnel drainage system
70
Summary worksheets
These worksheets are provided for the tunnel systems
and sum each elements total quantity and the elements
quantity per rating value, and quantity per deficiency type.
The east and west tubes of the Brooklyn Battery Tunnel
are tallied separately. Therefore the condition rating of
various tunnel elements can be reviewed per query.
Conclusion
The asset management database is an essential tool that
can be used on a day-to-day basis or when scheduling and
budgeting projects that will maintain the facility in a state
of good repair. Within the database there are several worksheets that can be used to manage the various assets.
Some are better suited for reports while other worksheets
are better suited for obtaining data for monitoring the asset
condition. Each worksheet aids in obtaining the necessary
data, in the desired format, to make an informed decision.
During the aftermath of Superstorm Sandy, the database was used to determine replacement quantities
for items damaged in submerged sections of the tubes
(water filled approximately 6,000 feet of the 9,000
foot-long tunnel) and in the flooded sublevels of the
buildings, and to obtain pertinent sump pump information. Its use during the operational response to that
storm in 2012 contributed to the east tube reopening
to limited bus service after 13 days and the west tube
soon afterwards.
Introduce a new SCADA platform and new programmable logic controllers (PLCs) which will communicate via
the clients converged Ethernet network;
Initially connect SCADA to existing mechanical and electrical equipment in both tunnels for tunnel environmental control (ventilation, lighting, dewatering, etc.);
Expand the system at a later date to connect to new
traffic management equipment (signage, barriers, etc.)
that is planned;
Latterly expand to take control of the emergency refuge
areas installed in the 1930s tunnel, a four-lane single
bore tunnel;
Interface with other tunnel management systems,
such as the automatic incident detection system, in
order to deliver improved connectivity to the operation of the tunnels;
Challenges
The clients primary objective is to ensure the safe and secure operation of the tunnels. Whilst a multitude of factors
play a part in this, the security of the new control system
is an important element and the requirement that the new
SCADA and PLCs migrate onto the clients converged Ethernet network becomes relevant. This network has both operational uses (the management of road tunnels and bus,
rail, and ferry terminals) and business uses (office and enterprise IT for staff). Therefore a traditional separation and
isolation of the control system is not straightforward.
The challenge is specifying security requirements at the
outset. This needs to happen ahead of the design work
that will identify how the control system is integrated on
the converged network, and these requirements will need
to remain relevant as the control system is upgraded over
the next four years. Equally, whilst the SCADA system integrator will hold overall responsibility for the SCADA system
design, the client - through its IT department will be involved in the design and delivery of the communications,
server, and workstation environment. Here there is a need
to ensure that a secure system can be implemented and
to identify which party will be responsible for delivering the
various elements of this.
Our solution to this challenge has been to specify, within the SCADA system technical specification, adher-
NETWORK
71
NETWORK
ence to two international standards, ISO/IEC 27000
and IEC 62443.
Conclusion
Work on implementing the SCADA programme is now
underway. It is at the initial concept design stage and
the high-level design necessary for the full SCADA
system as envisioned is being explored. To this end
the application of the IEC 62443 standard is coming
into play. Although experience applying the standard
across all parties is still in its infancy, we are learning valuable lessons as we go. For example, one such
lesson is what we are calling our levelling layers into
zones lesson.
This lesson, put simply, is to ensure that there is a mutual understanding and use of terminology among all
stakeholders. This is a common lesson in collaborative
work and in this case is not one that reflects negatively
on the standard itself, which is well constructed and
clear. Rather the distinct uses of relatively interchangeable words such as level, layer, and zone within
the specification are recognised and highlighted for
the stakeholders. Whilst seemingly a minor point, the
current design work needs to correctly define a logical segmentation of the control system in order to build
defence in depth1 (in this instance, segmenting the system into zones within the operational level, a level that
corresponds to layers 0 to 4 of the standards reference
model you see the potential for confusion if words are
interchanged when communicating).
To conclude, where other security guidance gives
equally valuable insight into good practice, the IEC
62443 series of standards also helps in the development of a security management system that meets
the needs of a SCADA control system. Further, as the
standards build on guidance of ISO/IEC 27000 the
resulting security approach may integrate better with
an organisations information security management
system, helping an organisations IT and automation
control functions to more effectively collaborate on securing a SCADA control system. Whilst the full suite of
the IEC 62443 series of standards is not yet complete
and its application is in its infancy, we are seeing that
this standard does form a valuable point of reference
on security when specifying, developing, and ultimately
maintaining a tunnel SCADA control system.
Peter Massheder is a Principal Engineer with 26 years of experience in delivering automation, computing, and ecommerce solutions to clients across the utilities, transport, environment, and
banking sectors.
Defence in depth is a concept in which multiple layers of security controls are built into an information technology system rather than relying
on a single layer of security control. Its purpose is to provide more than one line of defence in case any one layer fails.
72
caused by the passing of heavy vehicles. Since vibration can negatively affect devices and their connections,
hardened enclosures should be considered. Prior to
commencing detailed design of the new CCTV system,
the following design criteria needed to be addressed:
Coverage (including sensor type, lenses, aspect ratio,
and camera angles);
Mounting; and
Communication System.
Coverage
It is extremely important to identify the right locations for
CCTV cameras and associated equipment panels. Cameras should be located to provide a clear line of sight
with minimal obstructions. Tunnel cameras used in low
light conditions should be located such that the main
view is with the camera looking away from bright light.
This is because video images in bright light taken from
low light vantage points tend to appear washed out.
Where changeable message signs (CMS) are installed,
cameras should be located so that the message of an
adjacent CMS can be read. This allows for visual verification of CMS status.
Parsons Brinckerhoff was engaged to design a new digital IP CCTV (internet protocol closed circuit television)
system, replacing the existing analog system whilst
maintaining the existing operation.
The tunnels existing CCTV system is an analog system, with fixed cameras providing continuous views of
the tunnel to tunnel operators in the control room. In
other words, each camera provides a separate feed on
a screen (four cameras per screen) in the control room.
Parsons Brinckerhoff was engaged by a client to undertake remedial and resilience design work on a tunnel
in the US that serves as an important thoroughfare for
motor vehicles and was flooded in a storm.
NETWORK
73
74
NETWORK
Mounting
Three camera mounting hardware mechanisms were
analyzed for the tunnel installation:
wall-mounted hardware with short arm;
ceiling-mounted hardware; and
surface-mounted camera enclosure.
Most camera manufactures have wall and ceiling hardware accessories but a surface camera enclosure would
require a special order.
Communication System
Migrating from an analog CCTV system to a digital IPbased system enables the tunnel controllers to gain a
level of efficiency and control not previously available in
overall operations. However, doing so requires a communication network to transmit the CCTV camera footage to
the tunnel control center. On this project, various network
types (star and ring topology) were considered based on
ease of maintenance, redundancy, and resilience.
A star topology is when each edge switch (switches in the
field equipment panels) is connected to a central switch,
typically in a control room. A ring topology is where each
edge switch is connected to next and previous edge
switch, forming a large ring. This option provides redundancy in that, if one of the switches were damaged, communication to downstream switches can be established
through the other side of the ring.
For the maintenance department, a star topology was
preferred because it meant that all of the back-end equipment would be located in one central location. This means
In Closing
CCTV systems are integral to the safe operation and
control of roadway tunnels. While CCTV technology can
be fairly simple, the tunnel environment, maintenance,
project requirements, and number of cameras can make
the CCTV system design complex. This approach to CCTV
system design is recommended for other projects to facilitate maintenance, whilst providing a robust system that
can be verified through simulation prior to construction.
Ryan Williams is a Senior Systems Engineer in our New York City
office, having spent the last 8 years with Parsons Brinckerhoff in
Australia. He is a registered professional engineer with chartered
status and has substantial experience in transport and communication projects.
Surface-Mounted Enclosure
Figure 4 shows the wallmounted dome camera
option. The camera inside
the dome enclosure is adjustable to the angle with
an optimum view. This
Camera
option provides enough
height to minimize view
obstruction by large trucks
and buses. The height
also allows for easy installation. Finally, this type
of mounting will result
in minimal damage from
maintenance and wash
trucks, but limits camera
selection options as few
fixed cameras are manufactured with this mount. Figure 4 - Typical Surface-Mount
NETWORK
75
NETWORK
Background
The Shatin to Central Link (SCL) is one of the ten largest
infrastructure projects being constructed in Hong Kong.
It is a 17 kilometre territory-wide strategic railway corridor with ten stations. The project is linked with a number
of existing railways, forming two strategic railway corridors: the East West Corridor and the North South
Corridor as shown in Figure 1.
The East West Corridor is formed by the Ma On Shan
Line (the proposed Tai Wai to Hung Hom Section of the
SCL) and the existing West Rail Line. Upon completion,
passengers will be able to travel between Tuen Mun in
the west and Wu Kai Sha in the east without interchanging (transferring) trains.
Lok Ma Chau
Lo Wu
Wu Kai Sha
East Rail Line
Tuen Mun
Tai Wai
Ma On Shan Line
Diamond Hill
Shatin to Central Link
(Tai Wai to Hung Horn Section)
Hung Horn
Admiralty
76
Challenges
NETWORK
77
NETWORK
AC/DC
INTERCHANGE
STATION
DC OHL Network
DC FEEDER
SUBSTATION
DC RAIL NETWORK
DIODE
EARTH
STRAY
CURRENT
STRAY
CURRENT
DC STRAY CURRENT
RETURN PATHS
CONNECT TO STATION
STRUCTURE AND OTHER
METALLIC PARTS
78
Circuit A
Train
positioned at
middle of rail
section
Voltage (V)
0.25
0.2
0.15
Circuit B
Train
positioned at
250m from
interchange
station
0.1
0.05
-3.89E-15
0
0.24
0.48
0.72
0.96
1.44
1.2
1.68
1.92
2.16
2.4
Distance (km)
Figure 4 - Potential Shift vs. Train Positions with Rail-to-Earth Resistance Decayed to 15 ohm/km per track
Interchange
station
Estimated
Maximum
Potential Shift at
Station Structure
(all at RTE1 = 15
ohm/km per track)
DIH
ADM
HOM
Recommended Mitigation
Measures against
Stray Current Corrosion
Platform Screen
Door (PSD)
Other Metallic
Equipment
Provide insulation
or isolation
between PSD and
civil structure
Provide
insulation or
isolation for
other metallic
equipment from
structure
Conclusion
This article addresses the impacts of coexistence of
AC and DC traction systems at the underground interchange stations of the Shatin to Central Link in Hong
Kong and describes the approach taken to quantify the
impacts. It was noted that at the time of conducting
the study, there were very limited references on this
subject, in particular on its quantitative analysis. Conservative assumptions on the train positions and injection currents were made in the analysis in consultation
with the railway operator for a more realistic estimate
of the worst case.
Results of the analysis indicated that DC stray current
corrosion was less of a concern at the interchange stations. However, for asset protection and good practice,
0.3
NETWORK
79
NETWORK
AC/DC
INTERCHANGE
STATION
DC OHL NETWORK
NORMAL PATH
FOR DC TRAIN
CURRENT
REGENERATION
AC/DC
INTERCHANGE
STATION
MOTORING
DC FEEDER
SUBTATION
DC RAIL NETWORK
DIODE
EARTH
DC TRACTION
SYSTEM
STATION
EARTH
OVPD
OPERATED
DC EARTHING NETWORK
(CABLE ARMOUR/FCRW)
STATION
EARTH
AC TRACTION
SYSTEM
AC OHL NETWORK
AC FEEDER
SUBTATION
AC RAIL NETWORK
AC EARTHING NETWORK
(AEW/EARTH STRAP/
FIRE HYDRANT)
STATION
EARTH
STATION
EARTH
80
it was recommended to the client that mitigation measures be implemented. With regard to the DC current
flowing through the AC train-borne transformer and AC
traction transformer, results of the quantitative analysis
indicated that this requires careful attention and monitoring of the DC current flows in the AC traction equipment, as saturation of the transformer core by the DC
current will bring adverse impacts to the transformers.
Moving forward, in future application of the analysis
Introduction
Construction and
Fire Tunnel
Rehabilitation
andStormwater
Life
Systems
Safety
NETWORK
81
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
be done per NFPA 25, the inspector has a responsibility
to verify compliance with required standards. In cases
where inspectors are not present for required periodic
testing, reviewing the test report records is the only
means to determine the owners compliance with applicable regulations.
Site and Area Scouting
Site scouting visits serve an important role that of seeing the current general condition of a tunnel. Structural
damage, improperly supported or damaged equipment,
and inoperable life safety systems can be reasons for
an inspection to be postponed or canceled until repairs
are made.
There may also be environmental issues that impede inspection efforts. Dead animals, animal waste, excessive
dirt or debris, and standing water are only a few issues
that pose hazards to personnel and should be corrected
before inspections are performed.
82
Ventilation
Tunnel ventilation was originally designed to remove noxious vehicle fumes, however, it was discovered that a
ventilation system, if properly designed, could also remove smoke from an in-tunnel fire. The most common
types of powered tunnel ventilation systems are longitudinal, transverse, and semi-transverse. The distinct differences of these systems require special access and
experience in order to be evaluated properly. Ventilation
systems inspections may include airflow rate measurements, fan and fan drive system conditional evaluations,
duct inspections, and damper operational testing.
Fan operation may be initiated manually, or automatically if sensing systems are installed. Fans may be axial
or centrifugal, direct drive, gearbox driven, or belt driven.
Fans that are not directly coupled to the motors also
have shafts and bearings. All these components need to
be inspected. Often, special vibration analysis vendors
are used to quantify potentially damaging vibrations
from out-of-balance fans. Ventilation fans can produce
wind velocities that exceed 90 miles per hour (MPH),
and move volumes of air that exceed 350,000 cubic
feet per minute (CFM).
Carbon Monoxide Sensing Systems
Some tunnels have sensing systems to detect high levels of carbon monoxide (CO). These sensing systems
may provide alarms and initiate operation of the ventilation systems. Inspections of CO monitoring systems
require specialized training, equipment, and span gases
and are normally performed by the owners maintenance
staff or an outside vendor.
Dampers
Dampers can alter the exhaust and supply of air relative to zones in the tunnel, improving the effectiveness
of removing smoke and providing a safe egress route.
There are several different types of damper operating
systems and inspectors need to be familiar with gears,
chains and sprockets, hydraulics and pneumatics, and
Fans
Different ventilation systems employ different types of
fans. Longitudinal systems use high velocity, low volume
jet fans mounted inside the tunnel (see Figure 1). Transverse and semi-transverse systems use high volume
fans connected to ducts that distribute exhaust, and
sometimes supply, air flows to strategic locations (see
Figure 2). The equipment for transverse tunnel ventilations systems can be quite large.
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
83
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
level sensors for turning the pumps on and off. Most dewatering systems have hydrocarbon-sensing equipment.
Inspections of these systems involve running pumps
(pumping water if possible), gauging pump flow rates, and
visually scrutinizing the condition of pumps, valves, piping,
sumps, and water collection grates and gutters. Flammable gases may also be used to test hydrocarbon sensors.
Inspecting and testing tunnel electrical systems are important to verify the systems are functioning properly.
84
Recommendations
The Simplex control system did not keep each foam pump
running to the low level sensor on the tank, nor did the system
start the lag pump if the lead pump failed to start.
Balancing damper D-120 did not actuate the fully open position
limit switch when it was fully open.
Adjust the fully open limit switch for balancing damper D-120
so the damper position indicates correctly in the control room.
The tunnel ceiling mounted axial type jet fan motor inspection
cover had two broken fasteners.
Experienced tunnel inspectors should be capable of inspecting and evaluating a tunnel control system, only
requiring assistance from the owners control systems
operations personnel.
Conclusion
Some basics for inspecting tunnel mechanical and
electrical systems are presented. The main purpose
of inspecting tunnels is to note deficiencies and communicate findings to the owner. The owner can then
use this information to budget and schedule needed
repairs or modifications to correct the deficiencies.
ConstructionFire
andand
Rehabilitation
Life Safety
Findings
NETWORK
85
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
Introduction
The Waterview Connection is the largest road project ever
undertaken in New Zealand. At a cost of NZ$1.4 billion
(approximately US$1.2 billion), it involves building a 4.8 kilometre (3.0 miles) long six-lane motorway to link two highways and complete Aucklands Western Ring Route. The
highway includes a 2.5 kilometre (1.6 miles) long twin-tube
tunnel, with three-lanes in each tunnel, bored by a 14.4
metre (47.2 feet) diameter tunnel boring machine (TBM).
The twin-tube design includes cross-passages which connect the tubes, house mechanical and electrical (M&E)
systems, and provide escape paths in emergencies.
Parsons Brinckerhoff is a member of the Well-Connected Alliance, which is both delivering the project, and
operating and maintaining the facility for 10 years after
opening. This project structure gave all parties an interest in cost-effective design for both construction and
maintenance.
The tunnel's vertical alignment has a low-point, requiring a sump and mechanical drainage system to remove
TUNNEL INVERT
SERVICES TUNNEL
Figure 1 - Tunnel Cross Section
86
UM
TS
OIN
E
WP
LO CKAG
GE
PA
DRAIN FROM
RISING MAIN
KA
PAC
RT
LVE
CU
PAVEMENT
CONNECTION
MINIMUM SL
CROSS PASSAGE
LOW POINT SUMP
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
D450 PAVEMENT
DRAIN
DN100 SOUTHBOUND
TUNNEL INVERT
CULVERT FLOOR DRAIN
D250 PAVEMENT
DRAIN
CROSS PASSAGE
The sump was designed as a 5.7 metre (18.7 feet) diameter vertical shaft located under the floor of the crosspassage at the low-point. To avoid backflow through the
invert drainage pipes into the service tunnel, the sump
high water level was set below the level of the tunnel
invert. This high water level, combined with the required
sump storage, resulted in a sump shaft design depth
of approximately 12 metres (39.4 feet) under the crosspassage floor.
Proposed redesign
Reasons for redesign
The concept design provided several construction
challenges:
Time and cost in constructing a deep shaft;
Technical difficulty in penetrating the tunnel lining for
the large drainage pipe; and
87
ConstructionFire
andand
Rehabilitation
Life Safety
NETWORK
The new sump shape also raised the top water level well
above the tunnel invert, meaning the invert drain could
no longer connect directly to the sump. Some form of
pumping was therefore needed for the seepage flows
in the invert. The revised proposal therefore included
a small pump in the services tunnel, operated by float
switches, to automatically pump collected water to the
main sump.
Operation and maintenance considerations
The service tunnel is a 2.5 kilometre (1.6 mile) tunnel within a tunnel, running below the road surface with
entry points only at the ends. As a result, access to the
service tunnel requires procedures similar to a confined
space, including a dedicated ventilation system, a minimum of two people, and radio contact with the surface
at all times.
Due to these restrictions, the operations and maintenance (O&M) strategy was to minimise equipment that
required servicing in the service tunnel. This challenged
the proposed sump redesign, as any pumping equipment
in the service tunnel would conflict with the O&M strategy.
Final design
88
Fire Tunnel
andStormwater
Life
Lighting
Systems
Safety
NETWORK
Until recently, lighting equipment was limited to fully enclosed luminaires utilizing fluorescent, metal halide, and
high pressure sodium lamps. These sources are bright,
have a long life, and are robust enough to withstand the
harsh environment of a tunnel. Light emitting diode (LED)
technology provides an alternative that has significantly
improved in longevity and adaptability. Traditional high intensity discharge (HID) systems utilizing high pressure
sodium or metal halide lamps require the least number
of luminaires as the light output available from each luminaire is high. Fluorescent systems require more luminaires, and are often supplemented with the higher wattage HID sources. LED fixtures have a steadily increased
light output and control and are now comparable in intensity to the HID. Tunnel luminaires are expensive, and LED
luminaires have the highest initial cost.
Controlling a tunnel lighting system is necessary to ensure that the amount of artificial illumination is in tune
with the outside daylight conditions. If it is sunny or
cloudy throughout the day, or from dawn to dusk, the
lighting control system will switch luminaires off and on
as needed or dim the supplemental lighting in the threshold and transition zones of the tunnel. Both switching
and dimming control systems utilize either an intelligent
photocell or a special camera that records luminance
levels outside of each portal. Another reason for lighting
control is simply for energy savings.
89
NETWORK
adapt to LEDs. As a solid state source, the very definition of lamp life has been modified to correctly model
sources that may well run for 11 years. Also a challenge
is the rapidly evolving LED chips that make it increasingly
difficult for manufacturers to test their fixtures life expectancy. The Illuminating Engineering Society of North
America (IESNA) has developed several technical manuals for LED luminaire manufacturers to follow which include a procedure for the manufacturers to interpolate
an expected life of their products.
Traditionally the evaluation of lighting products is based
on a separate test for the lamps and luminaires, but with
LED luminaires the test has to be completed on the whole
package because the LEDs rely on the luminaire for heat
dissipation which affects the lumen output and life. The lumen maintenance of a LED luminaire must also be tested;
this is the method for measuring the lumen depreciation
from the LEDs original light output. LEDs do not typically
burnout; a degradation of their light output occurs continuously to a point where they are beyond their useful light
output. Methods have been developed by the IESNA to
measure the lumen maintenance and to estimate the life
of the project based on the measured results.
90
were developing LED luminaires that could finally withstand the environment of a vehicular tunnel. Parsons
Brinckerhoff carried out a cost and performance comparison of the HPS and LED luminaires. The conclusion
was that the LED system would have a substantially
lower life cycle cost.
Conclusion
LED luminaires are suitable for the tunnel environment
and will be more widely used in the future. There is a demand for LED as a lighting solution from tunnel owners
and operators as a way of reducing operating and maintenance costs for a project, while embracing a leading
edge technology. This demand will put pressure on the
engineer to fully understand the challenges of LEDs while
pushing manufacturers to produce durable, reliable, and
consistent products. A rigorous testing procedure should
be an integral part of the tunnel luminaire specification.
In addition, a warranty that covers the luminaires needs
to be in place for a significant portion of the anticipated
life of the light engine in the luminaire, considered by
Parsons Brinckerhoff to be 10 years.
Christopher Leone is a Lighting Engineer in the Boston office of
Parsons Brinckerhoff with 14 years of experience in tunnel and
roadway lighting. He is a current member of the IES Roadway
Lighting Committee.1
The 3,760 linear foot (1,146 meter) immersed tube tunnel will include two 12-foot (3.6-meter) travel lanes, two
2-foot (0.6-meter) shoulders, an escape corridor, high
walkway, and utility corridor.
For a previous Network article on lighting by Chris Leone, see Lighting a 3D World: Design and Analysis, Network #70, November 2009, pp
64-65,69.
NETWORK
91
Introduction
Analysis
Approximately 1158 meters (3800 feet) of the tunnel
consisted of segments immersed and buried below a
river with the elevation varying by as much as 18 meters
(60 feet). The two 6-inch piping systems of concern, a
FIRE SUPPRESSION
WATER MAINS
CORRIDOR
ROADWAY
CONCRETE
92
Fire
SESTunnel
and
and
Water
Stormwater
Life
Modeling
Systems
Safety
Power
NETWORK
Date
Daily Minimum,
C (F)
Daily Average,
C (F)
2-Day Average,
C (F)
3-Day Average,
C (F)
7-Day Average,
C (F)
18-Jan
1.11 (34)
2.63 (36.73)
3.97 (39.14)
0.80 (33.44)
-2.64 (27.25)
19-Jan
2.22 (36)
5.31 (41.55)
-0.11 (31.80)
-4.97 (23.05)
20-Jan
-15.61 (3.9)
-5.52 (22.06)
-10.11 (13.80)
-8.77 (16.21)
21-Jan
-19.39 (-2.9)
-14.70 (5.55)
-10.40 (13.28)
-7.65 (18.23)
22-Jan
-10.61 (12.9)
-6.10 (21.02)
-4.12 (24.58)
-2.06 (28.29)
23-Jan
-8.89 (16)
-2.14 (28.14)
-0.04 (31.92)
24-Jan
-3.89 (25)
2.06 (35.70)
Fire
SESand
andLife
Modeling
Safety
NETWORK
Discussion
Highest heat transfer rates would occur near tunnel portals where incoming air is coldest.
Material properties were assumed constant with temperature and direction.
Effective properties of backfill material assumed a fully
saturated state with 30 percent water.
Tunnel walls, ceiling, and floor were assumed to be the
same concrete material.
Tunnel section geometry and dimension were slightly
modified to minimize computational processing time.
0.6
W/mK
Density,
1700
kg/m
Specic heat, Cp
2.5
kJ/kgK
Concrete
B5A
T2
1.4
W/mK
Density,
2100
kg/m
Specic heat, Cp
0.88
kJ/kgK
T3
B5B
Thermal conductivity, k
B6
Source: The SFPE Handbook of Fire Protection Engineering, Fourth Edition, National Fire Protection Association, June 1995; and
Incropera F., Dewitt, D., Bergman, T., Lavine, A., Fundamentals of Heat and Mass Transfer. Wiley. 6th Ed. 2007
12.8C(55F)
Thermal conductivity, k
CORRIDOR
B5
Soil
12.8C(55F)
Figure 3 Locations of
Temperature Measurement
Roadway
-10C(14F)
BACKFILL
CONCRETE
93
94
2.00
0.00
-2.00
-4.00
-6.00
FDS Time, s
1,200,000
960,000
840,000
720,000
600,000
480,000
360,000
120,000
240,000
13.9 days
0
-8.00
1,080,000
Temperature, C
4.00
Legend
Temperature, C
6.00
4.00
T3
B5A
B5B
2.00
0.00
FDS Time, s
1,200,000
960,000
840,000
720,000
600,000
480,000
360,000
240,000
120,000
-4.00
1,080,000
13.9 days
-2.00
T2
T4
B5
B6
Legend
6.00
4.00
2.00
0.00
-2.00
-4.00
1,200,000
FDS Time, s
1,080,000
960,000
840,000
720,000
300,000
240,000
180,000
120,000
2.3 days
60,000
-6.00
-8.00
8.00
6.00
4.00
Legend
T3
B5A
B5B
2.00
0.00
-2.00
FDS Time, s
600,000
540,000
480,000
420,000
360,000
300,000
240,000
180,000
120,000
2.3 days
-4.00
60,000
For both cases considered, the corridor air temperature reaches freezing conditions after some length of
time. However, the length of time required for the air
temperature to reach 0C (32F) was longer than the
expected duration of the low temperatures assumed in
this calculation.
T2
T4
B5
B6
Legend
To further investigate the influence of ambient air temperatures on temperature within the corridor, a simulation was
run with the influent air flow temperature of -19.4C (-3F).
This temperature corresponds to the lowest recorded temperature since 1946 and is considered to be quite conservative. Figures 6 and 7 show the resulting interior corridor
walls and air temperatures, respectively. Similar to the
case with a -10C (14F) air flow, both the corridor walls
and the air began at ambient temperature and decreased
over time. For this case, the corridor air temperature reaches 0C (32F) after 2.3 days. Note that the one-day and
two-day average temperatures for this historic low were
-14.7C (5.6F) and -10.4C (13.3F), respectively.
6.00
8.00
Temperature, C
Temperature, C
Fire
SESand
andLife
Modeling
Safety
NETWORK
Incropera F., Dewitt, D., Bergman, T., Lavine, A., Fundamentals of Heat and Mass Transfer. Wiley. 6th Ed. 2007
Kusuda, T., Earth Temperature and Thermal Diffusivity
at Selected Stations in the United States. U.S. Department of the Army. 1965
Lapham, W.W., Use of Temperature Profiles Beneath
Streams to Determine Rates of Vertical Ground-Water
Flow and Vertical Hydraulic Conductivity, United States
Geological Survey Water-Supply Paper 2337, 1989
The SFPE Handbook of Fire Protection Engineering,
Fourth Edition, National Fire Protection Association,
June 1995
References
Calvache, M.L., Duque, C., Gomez Fontalva, J.M., Crespo, F., Processes Affecting Groundwater Temperature
Patterns in a Coastal Aquifer. International Journal of Environmental Science and Technology. 8, 223-236, 2011
Raylene Moreno is a Registered Professional Mechanical Engineer with experience in plumbing, fire protection, and heat transfer. She provides engineering design, analysis, and construction
support services on various rail and tunnel projects.
Fire
SESand
andLife
Modeling
Safety
Conclusion
NETWORK
95
Fire
SESand
andLife
Modeling
Safety
NETWORK
Introduction
Requirements for implementation of fixed fire fighting systems (FFFS) in road tunnels often include a full-scale test
or series of tests to be performed.
96
Flame
H 20
mw, ex
q
HW
m
Fuel (HT)
Hg
Legend
q - heat source or net ux
m - mass loss rate of the fuel
Hg - magnitude of the heat required to vaporize the fuel
HT - the fuel souce
HW - heat of gasication
mw, ex - critical water application rate
Computational modeling can be used to compare the effectiveness of water application rates for solid-fuel types
of fires, provided an accurate representation is made of
the items affecting heat flux (convection, radiation, surface cooling, water evaporation, etc.). Fuel can be defined in terms of a heat of combustion, reactions, products, and reaction rates. Selected material properties
can be determined from literature or testing. The primary
objective is to generate sufficient power from the fire to
simulate the design scenario. For most tests, wood and
plastic have been used as common sample fuels.
Computer Calibration
Fire Tests
In March 2012, LTA of Singapore conducted a series of
tests in the A86 Tunnel in Spain. These tests were performed with various standard drop nozzle configurations
and water application rates. Three in particular were of
interest for calibration purposes described in Table 1.
Activation Time
after 60 C
Target Ignited?
12
4 minutes
37.7
No
4 minutes
44.1
Unknown
Unknown
none
150
Yes
225
Model Values
Wood
Plastic
Total
Test Values
Volume (m3)/%
7.6/82
1.7/18
9.3
80/20
Mass (kg)/%
3,410/67
1,711/33
5,121
5,000
Energy (GJ)/%
58.0/61
37.6/39
95.6
99.2
Fire
SESand
andLife
Modeling
Safety
NETWORK
117
Computer Models
Computer models were developed in fire dynamics simulator (FDS) by the author for these three tests. The model
quantities and reported test values are tabulated and
summarized in Table 2. The grid size was chosen as a
cube with lengths of 0.125 meters, a value that has
been shown to give reasonable results in other simulations performed by the author.
Results
The results of the free-burning test show reasonable correlation between the model and the test for the heat release rate and gauge heat flux as indicated in Figure 2.
The modeled peak heat release rate is slightly higher than
the test. The growth rate is slightly faster than the test.
The extreme decay period is not considered significant
because the major effects of the fire have passed. The
modeled gauge heat flux is considerably more aggressive
Gas temperatures were compared in Figure 3. For the unsuppressed fire, the model shows reasonable correlation
with the test. For the suppressed fire, the model gas temperatures are lower than tested. However, both model and
test showed temperatures too high for tenable conditions
and low enough not to be a concern to the structural integrity. This is reasonable correlation for design purposes.
200
150
200
Model
100
50
Test Gauge
150
Model Gauge
100
Model Net
50
Test
0
0
0
500
1000
Time (sec)
1500
2000
500
1000
Time (sec)
1500
2000
97
1500
Deluge operation
400
Model Temp 5m
downstream of re
1000
Temperature (oC)
Temperature (oC)
Fire
SESand
andLife
Modeling
Safety
NETWORK
500
Model Temp 5m
downstream of re
300
200
100
500
1000
1500
Time (sec)
+L51 oMS1 +R51
2000
500
1000
1500
Time (sec)
+L51 oMS1 +R51
2000
Figure 3 Comparison of model and test results for unsuppressed and 12 millimeter/minute suppressed fire
50
120
110
45
100
Model
gauge
Model
40
90
60
Model
net
50
Heat ux 5m downstream of re
Deluge operation
2.0
30
20
Test
0
0
500
1000
1500
2000
1.5
1.0
Test
gauge
0.5
15
10
0
0
500
Time (sec)
Figure 4 Comparison of model and test results for 12 millimeter/minute suppressed fire
98
20
Deluge operation
40
10
25
1000
1500
Time (sec)
2000
30
70
35
80
of the suppressed test, the model showed higher values than the test, but still showed that spread to the
target fuel pile was prevented.
Conclusion
Full-scale testing of fire suppression systems is expensive. Computer modeling provides a cost-effective means
of demonstrating proposed system performance. The
fuel vaporization process is well-defined in fire science
and the computer models can be structured to utilize
this approach.
Comparison with a test is beneficial to calibrate the
model. For this reason, the LTA tests are a significant
milestone in providing a benchmark to compare model
results and their contribution to the knowledge of the
industry is extremely important.
Kenneth Harris has written a number of articles for Network including Hydraulic Modeling of Fire Protection Pipelines for the Westside Rail
Tunnel Network #34, Spring 1996, pp 24, 25.
The fire heat release rate (FHRR) and heat flux test results for the 12 millimeter/minute (mm/min) suppressed
fire, as shown in Figure 4, did not compare well at all. The
model heat release rate was calculated as considerably
higher than that tested. This is acceptable for design purposes, as the calculation indicates a higher value than
measured. The reverse would be problematic.
Fire
SESand
andLife
Modeling
Safety
NETWORK
99
Fire
SESand
andLife
Modeling
Safety
NETWORK
100
Silas Li is Manager of the Parsons Brinckerhoff Tunnel Ventilation Analysis Group and chairman of the NFPA 130 ventilation
task group. He has 29 years of experience in the design and
simulation modeling of fire/smoke management and ventilation
systems for numerous projects involving transit, rail and road
tunnels in seven countries.
Ting, Y S, et al., "CFD estimation of heat transfer enhancements on a cooling pipe in underground railway tunnels", 13th Annual Symposium on
Aerodynamics and Ventilation of Vehicle Tunnels, p. 629, BHR Group, 2009.
Fire
SESand
andLife
Modeling
Safety
NETWORK
101
Fire
SESand
andLife
Modeling
Safety
NETWORK
Background
Singapore
Metro Project
Waterside System
Airside System
Lighting System
Earthing System
Not Applicable
Sprinkler System
FH/HR System
Not Applicable
Not Applicable
Sanitary System
Drainage System
Electrical System
Not Applicable
Not Applicable
ELV System
TCSS System
Figure 1 - Systems in the BIM models for the Singapore and Hong
Kong projects include, but are not limited to, the above.
The Level of Development (LOD) is a reference to help the designer and owner specify BIM deliverables and get a clear picture of what will be
included in a BIM deliverable. It is defined and developed by the American Institute of Architects (AIA) for the AIA G202-2013 Building Information Modeling Protocol. At present there are six LOD levels (LOD 100, 200, 300, 350, 400, 500). LOD 100 300 are suitable for the design
stage, LOD 350 and 400 are suitable for construction stage, and LOD 500 is specific to the as-built model for owner.
102
Many resources are required to develop a standard library for M&E equipment and BIM standards for infrastructure projects. Information from suppliers of BIM
services and software for infrastructure projects is limited. Parsons Brinckerhoff is using BIM experience from
other projects in different regions to help develop and
recommend standards across various disciplines.
There are two major software options (Revit and AECOsim) being used for infrastructure projects. Usually, the
architect and the structural engineer will create an individual BIM model for buildings and another model for
tunnels. For some projects, Revit software is used for
developing the station or ventilation building BIM model
and AECOsim software is used for the tunnel model.
When integrating the building model and the tunnel model, it is difficult but important to ensure continuity of the
M&E services at the boundary between the two models,
as compatibility issues and information loss has been
experienced. Partnerships with Bentley and Autodesk
will help to overcome the above issues and help to drive
the software changes needed.
Some engineering calculation programs and numerical analyses are available as add-ons to BIM software.
Input parameters for design can be gotten directly
from the BIM model and the engineering calculation or
analysis can be performed automatically. However, the
results of these engineering calculation programs may
deviate from other commonly used commercial engineering calculation programs. As a result, further development of these add-on programs is expected from
the suppliers.
The computer hardware requirement for creating a BIM
model for MEP (mechanical/electrical/plumbing) design
exceeds that for other disciplines. The normal workstation cannot handle a BIM model for a large-scale infrastructure project and generally needs to be upgraded.
M&E BIM models contain many systems and sub-sys-
Fire
SESand
andLife
Modeling
Safety
NETWORK
103
NETWORK
Our Goal
The goal of Network is to promote technology transfer by featuring
articles that:
Tell readers about innovative developments.
Appeal to a broad range of readers.
Include only essential information in a readable format.
Encourage readers to contact authors for more information.
Network Format
104
Cover photo: Eurasia Road Tunnel (Istanbul Strait Road Tube Crossing), Tolga Togan