PRESNTED TO
Sir Hallar Memon
COURSE NAME
ERP AAD
COURSE I.D
PROGRAM
Bs-ERP (Spring)
PRESENTED BY
Mati-Ur-Rehman(58615)
Shahrukh Ali (58617)
Waqar Aziz (58628)
Page | 1
PROJECT CHARTER
Table of Contents
NTRODUCTION - ................................................................................................................ 3
HUMUN RESOURCE MANAGEMENT - ................................................................................. 3
IMPORTANCE OF HRM - ..................................................................................................... 4
OBJECTIVES OF THE PROJECT CHARTER - .........................................................................5
ORGANIZATION SCOPE -.................................................................................................... 6
IMPLEMETATION SCOPE - .................................................................................................. 6
IMPLEMENTATION STRATERGY - ........................................................................................ 6
PROJECT MANAGEMENT - .................................................................................................. 7
EXECUTIVE STEERING COMMITTEE.................................................................................... 7
INFRASTRUCTURE.............................................................................................................. 8
PROJECT DELIVERABLES PLAN........................................................................................... 8
Page | 2
PROJECT CHARTER
Page | 3
PROJECT CHARTER
-- This document is the Project Charter for one of the ERP Module,
Human Resource Management. At MSW Enterprises (Mati-Ur-Rehman,
Shahrukh Ali, Waqar Aziz).
-- This Project Charter is a formal deliverables that will be
generated by various activities required to complete the Project. The
responsibility to approve the following Project Charter will be done by
Sir.Hallar Memon (Head)
-- This Project Charter defines the Objectives of the Project
Charter, Organizational Scope, Implementation Scope, Roles and
Responsibilities and e.t.c. The Project would serve according to the
budget, time constraints, resources and strandard agreed upon for the
project.
Page | 4
PROJECT CHARTER
Page | 5
PROJECT CHARTER
Page | 6
PROJECT CHARTER
Page | 7
PROJECT CHARTER
Page | 8
PROJECT CHARTER
Page | 9
PROJECT CHARTER
Page | 10
PROJECT CHARTER
Page | 11
PROJECT CHARTER
Page | 12
PROJECT CHARTER
Page | 13
PROJECT CHARTER
Page | 14
PROJECT CHARTER
The following services would be provided at the time and after the
Implementation,
-- Understanding the existing system and the development of the
HRM Module Business Blueprint.
-- Installation of the Human Resource Module.
-- Maintenance for the first three problems would be free.
-- Resolving issues/bugs ASAP.
-- Hands on the Module (Training).
Page | 15
PROJECT CHARTER
Page | 16
PROJECT CHARTER
Page | 17
PROJECT CHARTER
Page | 18
PROJECT CHARTER
Page | 19
PROJECT CHARTER
Page | 20
PROJECT CHARTER
Page | 21
PROJECT CHARTER
Page | 22
PROJECT CHARTER
Page | 23
PROJECT CHARTER
Page | 24
PROJECT CHARTER
Task Name
Preparatio
n of Project
Charter
Submission
of Project
Charter
Creating
Blueprint
for HRM
Module
Installation
of HRM
Module
Go Live
Duration
1 Days
Start Date
04/10/2015
0 Days
05/10/2015
05/10/2015
5 Days
06/10/2015
11/110/2015 Shahrukh
Ali, Mati-UrRehman
2 Days
12/10/2015
14/10/2015
2 Days
15/10/2015
17/10/2015
Demo
0 Days
18/10/2015
18/10/2015
Waqar Aziz
Mati-UrRehman,
Waqar Aziz
Shahruh Ali,
Mati-UrRehman
Mati-UrRehman,
Shahrukh
Ali, Waqar
Aziz
Page | 25