You are on page 1of 52

DOCUMENT SUBMISSION STATUS: FOR APPROVAL

00

09-07-2013

For Construction

SS

RSR

AK

PB

08-04-2013

Issued for Approval

SS

RSR

AK

PA

02-04-2013

ABB Internal Review

SS

RSR

AK

REV

DATE

DESCRIPTION

PREPARED

CHKD

APPD

OWNER

EPC CONTRACTOR

EPC CONTRACTORS CONSULTANT

ENGINEERING &CONSTRUCTION

PP-IMECO Consortium
PROJECT TITLE

KDL 120MW COMBINED CYLE POWER PLANT PROJECT

SUB-CONTRACTOR

ABB

ABB PTE LTD.

DOCUMENT TITLE

PROTECTION COORDINATION STUDY

REV

DOCUMENT NO

210014-P7002-E02-0042-00

00

DATE

09-07-2013

PAGES

ABB

DocumentTitle

DocumentNo.

ProtectionCoordinationStudy

210014P7002E020042

Rev

Date

Page

00

09072013

2of6

CONTENTS

Cl. No

Description

Page No.

1.0

Intent

2.0

References

3.0

Exclusion

4.0

Relay Settings and Coordination

5.0

Conclusion

6.0

Annexure

ABB

DocumentTitle
ProtectionCoordinationStudy

DocumentNo.

Rev

Date

Page

00

09072013

3of6

210014P7002E020042

1.0

INTENT
This document covers the following calculations and studies for KDL 120 MW Gas Fired
Combined Cycle Power Plant (CCPP), Indonesia.

i.

Relay Settings and Coordination for 6 kV Switchgear

ii.

Relay / Release setting and coordination for 400V Switchgear

iii. Motor Protection for MV Motors


iv. Thermal Overload Relay Settings for LV Motors
v.

2.0

Earth Leakage Protection for LV System

REFERENCES:
a. Equipment Sizing and System Studies 210014-P7002-E02- 0001-00
b. All Equipment Data Sheet & FAT Report
c.

IEEE 399 1997 Recommended Practice for industrial and commercial Power
System Analysis

3.0

EXCLUSIONS
a. Generator Protection
b. Generator Transformer Protection
c.

150 kV Switchyard Protection

Items b & c above are covered in 150 kV Substation Protection Setting Calculation 21004
P7001 E15 0001. Item a is not in ABB Scope.

4.0

RELAY SETTINGS AND COORDINATION


Relay settings for the equipment is divided into three groups for easy understanding and
coordination purpose:
1. Over current, Short Circuit & Earth fault protection and coordination
2. Equipment Protection Motor Thermal Overload protection (MV & LV Motors)
3. Earth Leakage Protection
Left out Items like transformer restricted earth fault protection, under voltage protection and
Synchrocheck are also covered at the end.

4.1

Over current, Short Circuit & Earth fault protection and coordination
Overload & short circuit are the frequent type faults in any power system and it is protected by
Over current, Short circuit & earth fault protection. Considering the probability of failure of
protective equipment, backup protection is also required. This backup protection should wait the
primary protection to clear fault and will isolate the fault only when primary protection fails to trip.

ABB

DocumentTitle
ProtectionCoordinationStudy

DocumentNo.
210014P7002E020042

Rev

Date

Page

00

09072013

4of6

Relay Coordination Methodology

The primary and backup relay pairs are identified using the network topology and relay
locations as inputs.

The primary fault current and the backup fault currents are determined.

For a given CT secondary rating, different plug setting steps (pick up currents) that are
available., the plug setting for phase and earth relays is selected. It is based on the maximum
load current flowing through the protective device and unbalance factor.

The selection of TMS is the most involved task in this process and that is where the actual
primary/backup coordination occurs. Before coordination is attempted, each relay is set to its
minimum TMS. The operating time of the primary relay for close in fault is determined. If this
new TMS is greater than old TMS, the actual TMS is made equal to new TMS and again the
process is repeated. An iterative method is employed whereby several passes are made
through the list of relays. Because of the inverse nature of the relay characteristic, these
iterations converge rapidly. The procedure is same for both phase and earth fault protection.
This is enabled by changing the plug setting and primary backup relay current depending on
the type of protection.

The over-current relay coordination is done such that the relays should operate for all short
circuits in its own zone and provide backup protection for short circuit in immediately
adjoining system elements in the downstream, if the relay in that adjoining system fails to
operate.

Assumptions & Consideration

250 ms discrimination time is considered for primary and backup relays.

Minimum time discrimination = Circuit breaker opening time + Relay Overshoot +


safety margin + Relay & CT error margin

Circuit breaker opening time = 45 ms


Relay Overshoot = 20 ms
Safety margin = 50 ms
Relay & CT error margin = 100 ms

Minimum Time Discrimination required = 45 + 20 + 50 + 100 ms


= 215 ms
Hence 250 ms discrimination is considered.

ABB

DocumentTitle
ProtectionCoordinationStudy

DocumentNo.
210014P7002E020042

Rev

Date

Page

00

09072013

5of6

No discrimination is considered between the primary and back-up relay pairs, which are
located on the same power system element (transformer primary side, secondary side and
cables) however where setting margins permit, discrimination is provided.

Plug settings of phase fault relays are computed based on the maximum load current.

An unbalance factor of 0.1 (10% unbalance) has been considered to compute the plug
settings of earth fault relays.

4.2

Equipment protection Motor Thermal Overload Protection


Motor Thermal overload protection settings are provided based on 110% of the full load current
for LV motors. The efficiency and power factor are assumed and hence full load current may vary
with actual full load current. Hence setting shall be provided based on the Name Plate details of
the motor at site.
For MV motors TOR settings based on 105% of the full load current for MV motors. Locked rotors
protection and permissible Cold and Warm start are provided based on the MV motor Data sheet.

4.3

Earth Leakage Protection


Earth leakage protection is to ensure the human safety during earth leakage. Earth leakage
settings for downstream end equipments like motors & DBs shall be 300 mA with instantaneous
trip. If upstream Earth leakage relay is available setting of 1 A with 300 ms shall be adopted if it is
to be coordinated with downstream.

4.4

Restricted Earth Fault Protection, Synchronism Check & Under Voltage Protection
Settings for Restricted earth fault protection, Synchronism Check & Under voltage protection are
provided in Annexure 6.

Results
The results of the over current and earth fault relay coordination study is presented in this section.
The recommended phase and earth fault relay settings for 6 kV & 400 V System is presented in
Annexure 1. MV & LV motor protection settings are provided in Annexure 2 & 3 respectively.
Earth Leakage relay settings are provided in Annexure 4.

Phase relay & earth relay curves for typical feeders are given in Annexure -5. These curves show
minimum discrimination of 250 ms is maintained between primary and backup relays. From the
curves it is observed that the equipments (Transformer, Cables etc) are protected for short circuit
& overload. Curves also indicate that there is no nuisance tripping for transformer inrush and
motor starting.

Three phase faults and Single line to ground faults are simulated at various locations and the
operating sequence of relays are verified. No uncoordinated tripping or inadvertent relay tripping
is reported. All relays operated as per coordination requirements.

ABB

DocumentTitle
ProtectionCoordinationStudy

DocumentNo.
210014P7002E020042

Rev

Date

Page

00

09072013

6of6

5.0

CONCLUSION

Optimal settings for both over current and earth fault relays are provided.

From the sequence of operation, it is observed that relays isolate the faulty equipments as
early as possible and minimise the damage. Clear discrimination is maintained between
primary and backup relays.

6.0

From the various curves it is observed that the protection tripping are coordinated perfectly.

ANNEXURE
1. Recommended Phase & Earth Relay Settings
2. MV Motor Protection settings
3. LV Motor Protection Settings
4. Earth Leakage Relay Settings
5. Over current & Earth fault Relay curves for typical MV feeders
6. Restricted Earth Fault Protection, Synchronism Check and Under Voltage Protection
settings

ANNEXURE 1:
Recommended Phase & Earth Relay
Settings

KDL

RelaySettings
RelaySettingsKDL
Sl.No

SWGR

FeederName

Relay

Make

OverCurrentRelaySettings

CTRatio

EarthfaultRelaySettings

6kVSwitchgearBusA

Incomer36.5MVA

REF615

ABB

800/1

0.86

0.05

LTI

Ip>>
Stage1
2.25

6kVSwitchgearBusA

CrankingMotor1

REM615

ABB

100/1

0.57

EI

0.04

0.055

0.05

NI

0.55

0.04

6kVSwitchgearBusA

AuxTrafo13MVA

REF615

ABB

350/1

0.9

0.65

EI

13

0.04

0.1

0.05

NI

0.8

0.04

6kVSwitchgearBusA

AuxTrafo13MVALVSide

REF615

ABB

5000/5

0.9

0.68

EI

0.1

0.26

NI

1150kW

6kVSwitchgearBusA

FuelGasCompressorMotor1

REM615

ABB

200/1

0.7

2.2

LTI

0.04

0.075

0.05

NI

0.75

0.04

500kW

6kVSwitchgearBusA

HRSGFeedWaterPump1A

REM615

ABB

100/1

0.45

EI

0.04

0.05

0.05

NI

0.45

0.04

500kW

6kVSwitchgearBusA

HRSGFeedWaterPump2A

REM615

ABB

100/1

0.45

EI

0.04

0.05

0.05

NI

0.45

0.04

350kW

6kVSwitchgearBusA

SeaWaterCWPump01

REM615

ABB

100/1

0.55

0.6

EI

0.04

0.055

0.05

NI

0.55

0.04

6kVSwitchgearBusA

Incomer16.5MVA

REF542+

ABB

800/1

0.86

0.05

LTI

0.1

0.08

NI

Disabled

10

6kVSwitchgearBusA

Incomer16.5MVA

REF610

ABB

800/1

0.1

0.1

NI

Disabled

Buscoupler

REF542+

ABB

800/1

0.86

0.05

LTI

Disabled

0.1

0.08

NI

Disabled

0.86

0.05

LTI

Disabled

0.1

0.08

NI

Disabled

0.1

0.1

NI

Disabled

450kW

11

Ip>

TDS

Curve

T>>
Stage1
0.4

Ie>

TDS

Curve

0.1

0.08

NI

Disabled

Disabled

NA

Ie>>

Te>>

Disabled

Disabled

12

6kVSwitchgearBusB

Incomer26.5MVA

REF542+

ABB

800/1

13

6kVSwitchgearBusB

Incomer26.5MVA

REF610

ABB

800/1

1150kW

14

6kVSwitchgearBusB

FuelGasCompressorMotorB

REM615

ABB

200/1

0.7

2.2

LTI

0.04

0.075

0.05

NI

0.75

0.04

450kW

15

6kVSwitchgearBusB

CrankingMotor2

REM615

ABB

100/1

0.57

EI

0.04

0.055

0.05

NI

0.55

0.04

16

6kVSwitchgearBusB

AuxTrafo23MVA

REF615

ABB

350/1

0.9

0.65

EI

13

0.04

0.1

0.05

NI

0.8

0.04

17

6kVSwitchgearBusB

AuxTrafo23MVALVSide

REF615

ABB

5000/5

0.9

0.68

EI

0.1

0.26

NI

500kW

18

6kVSwitchgearBusB

HRSGFeedWaterPump1B

REM615

ABB

100/1

0.45

EI

0.04

0.05

0.05

NI

0.45

0.04

500kW

19

6kVSwitchgearBusB

HRSGFeedWaterPump2B

REM615

ABB

100/1

0.45

EI

0.04

0.05

0.05

NI

0.45

0.04

350kW

20

6kVSwitchgearBusB

SeaWaterCWPump02

REM615

ABB

100/1

0.55

0.6

EI

0.04

0.055

0.05

NI

0.55

0.04

21

6kVSwitchgearBusB

SeaWaterCWPump03

REM615

ABB

100/1

0.55

0.6

EI

0.04

0.055

0.05

NI

0.55

0.04

688A

0.5

VI

1800A

0.4

NA

2300A

0.8

NA

NA

Disabled

Disabled

ExistingSwitchgear
1

6kVExistingSwitchgear

ToKDLnewPP6kVSwitchgear

Siemens

600/5

6kVExistingSwitchgear

Incomer

Siemens

2000/5

NA

LEGEND:
In

ABB

Relayratedcurrent

Note:

Ip>

PhaseOvercurrentpickup

EI

ExtremelyInverse

TDS

TimeDialSetting(k)

LTI

LongTimeInverse

Ip>>

PhaseInstantaneouspickup

NI

NormalInverse

T>>

Instantaneoustimedelay

SI

StandardInverse

Ie>

EarthOvercurrentpickup

Ie>>

EarthInstantaneouspickup

Te>>

InstantaneoustimedelayforEarthFault

ExistingswitchgearsettingsareprovidedKDLinSitemeetingDt21.06.2013.Graphsareprovidedtoverifythe
settings

KDL

RelaySettings

RelaySettings(400VLoadCenter)forKDL00BFA01
Recommendedsettings
Sl.No

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

Groundfault

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

Ie>>

Te>>

LoadCentre

HRSGMCC1

ACB

ABB

E2S08WMP

PR121/PLSI

800

0.4

48

10

0.4

Disabled

LoadCentre

GTG2MCC

ACB

ABB

E2S08WMP

PR121/PLSI

800

12

0.3

Disabled

LoadCentre

GTG1MCC

ACB

ABB

E2S08WMP

PR121/PLSI

800

12

0.3

Disabled

LoadCentre

CEPPumpA

ACB

ABB

E2S10WMP

PR122/PLSIG

800

0.5

12

0.2

0.1

LoadCentre

EssentialMCC

ACB

ABB

E2S10WMP

PR121/PLSI

1000

36

0.4

Disabled

LoadCentre

UtilityMCC1

ACB

ABB

E2S20WMP

PR121/PLSI

2000

12

0.4

Disabled

LoadCentre

Incomer1

ACB

ABB

E6H63WMP

LoadCentre

Buscoupler

ACB

ABB

E6H63WMP

Disabled

0.1

0.6

LoadCentre

Incomer2

ACB

ABB

E6H63WMP

10

LoadCentre

UtilityMCC2

ACB

ABB

E2S20WMP

PR121/PLSI

2000

12

Disabled

11

LoadCentre

CEPPumpB

ACB

ABB

E2S10WMP

PR122/PLSI

800

0.5

12

0.2

0.1

12

LoadCentre

GTG2MCC

ACB

ABB

E2S08WMP

PR121/PLSI

800

12

0.3

Disabled

13

LoadCentre

GTG1MCC

ACB

ABB

E2S08WMP

PR121/PLSI

800

12

0.3

Disabled

14

LoadCentre

HRSGMCC2

ACB

ABB

E2S08WMP

PR121/PLSI

800

0.4

48

10

0.4

Disabled

REFRelaySettingsareprovidedalongwithMVFeeders
PR121/PLSIG

6300

0.9

HRSGMCC1&2,400APlugisused.

12

0.6

REFRelaySettingsareprovidedalongwithMVFeeders

Note

ABB

ShortTime(ST)

424.53471

0.4
Disabled

KDL

RelaySettings

RelaySettings(400VHRSGMCC)forKDL01BFA02&02BFA02
Recommendedsettings
Sl.No

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

ShortTime(ST)

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

HRSGMCC1

Incomer

MCCB

ABB

T2S160FF160

PR221/PLS/I

160

6.5

0.25

Disabled

HRSGMCC1

PreheaterRCP1

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

HRSGMCC2

Incomer

MCCB

ABB

T2S160FF160

PR221/PLS/I

160

6.5

0.25

Disabled

HRSGMCC2

PreheaterRCP2

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

ABB

KDL

RelaySettings

RelaySettings(400VUtilityMCC1)forKDL00BFA02
Recommendedsettings
Sl.No

ABB

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

ShortTime(ST)

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

UtilityMCC1

GasCompressoraferCooler
FanA

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

UtilityMCC1

DMWaterMakeupPump

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

UtilityMCC1

ClosedCircuitCWP1

MCCB

ABB

T4H250FF160

PR221I

160

6.5

UtilityMCC1

DC&UPSSystem1

MCCB

ABB

T5H400FF400

PR221/PLS/I

400

0.52

5.5

UtilityMCC1

DMWatertransferPump

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

UtilityMCC1

WorkshopDP

MCCB

ABB

T4H250FF200

TMA

200

1(200A)

10(2000A)

UtilityMCC1

AirCompressorPanel

MCCB

ABB

T4H250FF200

TMA

200

1(200A)

10(2000A)

UtilityMCC1

MLDB

MCCB

ABB

T5H400FF400

PR221/PLS/I

400

0.6

12

5.5

0.25

Disabled

UtilityMCC1

PlantACDB

MCCB

ABB

T5H400FF400

PR221/PLS/I

400

12

5.5

0.25

Disabled

10

UtilityMCC1

AuxSeaWaterCoolingPump
A

MCCB

ABB

T4H250FF250

PR221I

250

5.5

11

UtilityMCC1

Incomer

ACB

ABB

E2S20WMP

PR121/PLSI

2000

0.75

12

0.3

Disabled

KDL

RelaySettings

RelaySettings(400VUtilityMCC2)forKDL00BFA03
Recommendedsettings
Sl.No

ABB

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

ShortTime(ST)

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

UtilityMCC2 GasCompressoraferCoolerFanB

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

UtilityMCC2

DMWaterMakeupPump

MCCB

ABB

T2H160FF52

MA

52

Min(312A)

UtilityMCC2

ClosedCircuitCWP2

MCCB

ABB

T4H250FF160

PR221I

160

6.5

UtilityMCC2

DC&UPSSystem2

MCCB

ABB

T5H400FF400

PR221/PLS/I

400

0.52

5.5

UtilityMCC2

DMWatertransferPump

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

UtilityMCC2

AirCompressorPanel

MCCB

ABB

T4H250FF200

TMA

200

1(200A)

10(2000A)

UtilityMCC2

FireSystemPanel

MCCB

ABB

T4H250FF250

PR221/PLS/I

250

1(250A)

5.5

0.25

Disabled

UtilityMCC2

ACDB@SwydCR

MCCB

ABB

T5H400FF400

PR221/PLS/I

400

1(400A)

12

5.5

0.25

Disabled

UtilityMCC2

AuxSeaWaterCoolingPumpB

MCCB

ABB

T4H250FF250

PR221I

250

5.5

10

UtilityMCC2

Incomer

ACB

ABB

E2S20WMP

PR121/PLSI

2000

0.75

12

0.3

Disabled

KDL

RelaySettings

RelaySettings(400VSTMCC)forKDL03BFA01
Recommendedsettings
Sl.No

ABB

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

ShortTime(ST)

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

STMCC

JackingOilPump1

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

STMCC

JackingOilPump2

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

STMCC

HPOilPump1

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

STMCC

HPOilPump2

MCCB

ABB

T2H160FF32

MA

32

Min(192A)

STMCC

incomer

MCCB

ABB

T4H250FF250

PR221/PLS/I

250

1(250A)

12

7.5

0.1

Disabled

STMCC

AuxOilPump

MCCB

ABB

T2H160FF80

MA

80

Min(480A)

KDL

RelaySettings

RelaySettings(400VEssentialMCC)forKDL
Recommendedsettings
Sl.No

ABB

MCC

FeederName

Protection

Make

Model

Release

Rating
(A)

LongTime(LT)

ShortTime(ST)

Groundfault

Instantaneous

Ip>

Tripcurve

Ip>

Tripcurve

Ip>>

Ie>>

Te>>

EssentialMCC

incomer

ACB

ABB

E2S12WMP

PR121/PLSIG

1200

0.85

24

0.3

Disabled

0.2

0.4

EssentialMCC

500kVADG

ACB

ABB

E2S12WMP

PR121/PLSIG

1200

0.7

24

0.4

Disabled

0.2

0.4

EssentialMCC

DC&UPSBypass

MCCB

ABB

T4H250FF200

TMA

200

1(200A)

5(1000A)

EssentialMCC

STMCC

ACB

ABB

E2S08WMP

PR121/PLSI

800

0.4

48

0.2

Disabled

KDL

RelaySettings
RelaySettings(ACDB)forKDL
Sl.No
1

ABB

MCC
ACDB

FeederName Protection
Incomer

MCCB

Relay
MicomP111

OverCurrentRelaySettings

EarthfaultRelaySettings

Rating
(A)

Ip>

TDS

Curve

Ip>>
Stage1

T>>
Stage1

Ie>

TDS

Curve

Ie>>

T>>

400

0.45

LTI

0.2

0.1

0.3

SI

0.8

0.2

ANNEXURE 2:
MV Motor Protection settings

Equipment protection Motor Protection


Jam Protection:
The stalled motor protection JAMPTOC is used for protecting the motor in stall or
mechanical jam situations during the running state.
Sl.No

Property

Setting

Operation

On

StartValue

2.5

OperateDelay
Time

ResetDelayTime

100

Motor Start Up Supervision: STTPMSU:


Maximum no. of starts limits shall be programmed into REM 615 relay as below. Cumulative
time limit and counter red rate has been calculated based on the REM 615 relay Technical
manual.

Starting
Capacity Timeat80%
kW
Vtins
(t)

Maximum
allowed
No.ofHot
start
(n)

Duration
during
whichmax.
noof
startups
made

Cumulative
timelimit

Counter
RedRate

Sl.No

Motor

SeaWaterPump

355

CrankingMotor

450

4.8

0.96

FuelGas
Compressor

1100

5.6

1.12

HRSGFeedPump

355

2.5(at85%
Voltage)

STTPMSU1:

Sl.No

Parameter

Sea Water Pump

Cranking Motor

Operation

On

On

Fuel Gas

HRSG Feed

Compressor

Pump

On

On

Page 1 of 4

Fuel Gas

HRSG Feed

Compressor

Pump

IIT

IIT

IIT

0.96

1.12

Cumulative time limit

Emer Start Red Rate

20

20

20

20

Restart Inhibit time

Motor Standstill A

0.1

0.1

0.1

0.1

Sl.No

Parameter

Sea Water Pump

Cranking Motor

Operation Mode

IIT

Counter Red Rate

Setting Group 1
1

Start detection A

0.75

0.75

0.6

Motor Start up A

2.5

3.1

Motor start up time

2.5

4.8

5.6

Lock rotor time

22

12

16

Str Over delay time

100 ms

100 ms

100 ms

100 ms

Thermal Overload Protection for Motor: MPTTR:


The motor thermal overload protection function MPTTR protects the electric motors from
overheating. MPTTR models the thermal behavior of motor on the basis of the measured load
current and disconnects the motor when the thermal content reaches 100 percent. The thermal
overload conditions are the most often encountered abnormal conditions in industrial motor
applications. The thermal overload conditions are typically the result of an abnormal rise in
the motor running current, which produces an increase in the thermal dissipation of the motor
and temperature or reduces cooling. MPTTR prevents an electric motor from drawing
excessive current and overheating, which causes the premature insulation failures of the
windings and, in worst cases, burning out of the motors.
The following thermal overload settings are recommended for motor feeders.

Page 2 of 4

Sl.No

Parameter

Value

Overload factor

1.05

Alarm Thermal Value

90

Restart thermal Value

40

Negative Seq Fact

Weighting factor

50

Time constant normal

320

Time constant start

320

Time constant stop

500

Env Temperature Mode

1 (FLC only)

Non Group settings:


Fuel Gas

HRSG Feed

Compressor

Pump

0.51

0.65

0.4

80

80

80

Sl.No

Parameter

Sea Water Pump

Cranking Motor

Rated Current

0.48

Initial Thermal Value

80

Negative sequence overcurrent Protection for Motor: MNSPTOC:


The unbalance protection based on the negative-sequence current function MNSPTOC
protects electric motors from phase unbalance. A small voltage unbalance can produce a large
negative sequence current flow in the motor. For example, a 5 percent voltage unbalance
produces a stator negative sequence current of 30 percent of the full load current, which can
severely heat the motor. MNSPTOC detects the large negative sequence current and
disconnects the motor.

Page 3 of 4

Sl.No

Parameter

Value

Start Value

0.08

Operating curve Type

15 (IEC Def Time)

Operate delay time

500 ms

Voltage Protection
In addition to above protection settings, Under voltage and overvoltage protection settings are
recommended for the feeders as below:
Over Voltage
Sl.No

Parameter

Value

Start Value

1.2

Operating curve Type

15 (IEC Def Time)

Operate delay time

2000 ms

Under Voltage
Sl.No

Parameter

Value

Start Value

0.8

Operating curve Type

15 (IEC Def Time)

Operate delay time

2000 ms

Page 4 of 4

ANNEXURE 3:
LV Motor Protection Settings

LV Motor Thermal Overload Relay Settings


Sl.No

Motor Capacity
in kW

pf

eff

FLA

OLR

Range

0.37

0.7

0.8

0.95

TA 25 DU 1.4

1 - 1.4

0.55

0.8

0.8

1.24

TA 25 DU 1.8

1.3 - 1.8

1.3

0.75

0.8

0.8

1.69

TA 25 DU 2.4

1.7 - 2.4

1.7

1.5

0.8

0.8

3.38

TA 25 DU 4

2.8 - 4

3.4

2.2

0.8

0.8

4.96

TA 25 DU 5

4.5 - 6.5

0.8

0.8

6.77

TA 25 DU 8.5

6 - 8.5

0.8

0.8

9.02

TA 25 DU 11

7.5 - 11

9.5

3.7

0.8

0.8

8.34

TA 25 DU 11

7.5 - 11

8.5

5.5

0.8

0.8

12.40

TA 25 DU 14

10 - 14.

12.5

10

9.3

0.8

0.8

20.97

TA 25 DU 25

18 - 25

21

11

11

0.8

0.8

24.81

TA 25 DU 25

18 -25

25

12

15

0.8

0.9

30.07

TA 75 DU 32

22 - 32

32

13

37

0.85

0.8

78.54

TA 25 DU 4

2.8 - 4

110/4

14

55

0.85

0.9

103.78

TA 25 DU 4

2.8 - 4

3.8

110/4

15

75

0.9

0.9

133.65

TA 25 DU 1.4

2.8 - 4

145/4

LEGEND:
eff

efficiency

pf

Power Factor

FLA Full Load Amps


OLR Over Load Relay
CT Current Transformer

Setting CT Ratio

Note
The efficiency and power factor are assumed and hence full
load current may vary with actual full load current. Hence
setting shall be provided based on the Name Plate details of
the motor at site.

ANNEXURE 4:
Earth Leakage Relay Settings

Earth Leakage Relay Settings


Sl.No

Motor Capacity
Protection Make
in kW

Model

Current

Time

0.37

ELR

ABB

RD3

0.3

0.55

ELR

ABB

RD3

0.3

0.75

ELR

ABB

RD3

0.3

1.5

ELR

ABB

RD3

0.3

2.2

ELR

ABB

RD3

0.3

ELR

ABB

RD3

0.3

ELR

ABB

RD3

0.3

3.7

ELR

ABB

RD3

0.3

5.5

ELR

ABB

RD3

0.3

10

9.3

ELR

ABB

RD3

0.3

11

11

ELR

ABB

RD3

0.3

12

15

ELR

ABB

RD3

0.3

13

37

ELR

ABB

RD3

0.3

14

55

ELR

ABB

RD3

0.3

15

75

ELR

ABB

RD3

0.3

ANNEXURE 5:
Over current & Earth fault Relay
curves for typical MV feeders

Amps X 100 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

500

500

300

Relay1 - P
OC1

100

ABB
REF 542plus
CT Ratio 800:5
Long Time Inverse
Pickup = 0.86 (0.05 - 40 xCT Sec)
Time Dial = 0.05
3x = 3 s, 5x = 1.5 s, 8x = 0.857 s

50

300

CB9

6 kV SWITHGEAR1

CB14

Relay2

100

Cable8
1-3/C 240

50

30

30

T2
3 MVA

10

10

Cable8 - P

1 - 3/C 240 mm
Copper XLPE
Tc = 90C
Plotted - 1 x 3/C 240 mm
1

.5

.5

Relay2 - P
OC1

.3

.3

ABB
REF 615
CT Ratio 350:5
IEC - Extremely Inverse
Pickup = 0.9 (0.3 - 5 xCT Sec)
Time Dial = 0.65
3x = 6.5 s, 5x = 2.17 s, 8x = 0.825 s
Inst = 13 (0.5 - 35 xCT Sec)
Time Delay = 0.04 s

.1

.05

T2
3 MVA (Secondary) 7.83 %Z
Delta-Wye Solid Grd
.1

T2
Inrush

.05
Relay1 - 3P

.03

.03

Relay2 - 3P

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 100 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

Incomer - OG
Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

Relay1

Amps 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

500

500

Relay1

300

300

CB9

6 kV SWITHGEAR1

CB14

100

10

50

30

T2
3 MVA

10

.5

.5

Relay2 - G
OC1

.3

.3

ABB
REF 615
CT Ratio 350:5
IEC - Normal Inverse
Pickup = 10 (1 - 100 xCT Sec)
Time Dial = 0.05
3x = 0.315 s, 5x = 0.214 s, 8x = 0.165 s
Inst = 80 (5 - 400 xCT Sec)
Time Delay = 0.04 s

.1

.05

.1

.05

.03

.03

Relay1 - LG
Relay2
G - LG

.01

.01
.5

10

30

50

100

300

500

1K

Amps 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

Incomer - OG
Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Ground

Seconds

Seconds

1-3/C 240

ABB
REF 542plus
CT Ratio 800:5
Normal Inverse
Pickup = 0.1 (0.05 - 40 xCT Sec)
Time Dial = 0.08
3x = 0.504 s, 5x = 0.342 s, 8x = 0.264 s

30

100

Cable8

Relay1 - N
OC1

50

Relay2

Amps X 10 Grid Bus (Nom. kV=150, Plot Ref. kV=150)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

01MBA10GT001
46/46/6.5 MVA

500

500

300

300
CB2

Relay10

Bus4

01MBA10GT001

01MBA10
37.64 MW

46 MVA (Secondary) 11.834 %Z


Wye Solid Grd-Delta-Wye Resistor Grd
Curve Shift = 1

100

Cable25

100

2-3/C 240

50

Relay1

50

CB9

6 kV SWITHGEAR1

30

30

10

10

2 - 3/C 240 mm
Copper XLPE
Tc = 90C
Plotted - 2 x 3/C 240 mm

.5

.5

Relay1 - P
OC1

.3

.3

ABB
REF 542plus
CT Ratio 800:5
Long Time Inverse
Pickup = 0.86 (0.05 - 40 xCT Sec)
Time Dial = 0.05
3x = 3 s, 5x = 1.5 s, 8x = 0.857 s

.1

.05

.1

01MBA10GT001
Inrush

.05

.03

.03

Relay1 - 3P

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 10 Grid Bus (Nom. kV=150, Plot Ref. kV=150)

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

GSUT Damage Curve


Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

Cable25 - P
5

Amps Bus4 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

01MBA10GT001
46/46/6.5 MVA

500

500

300

300
CB2

Relay10

Bus4

01MBA10
37.64 MW
Cable25

Relay10 - G - 51
OC1

100

100

2-3/C 240

50

30

Relay1

50

CB9

6 kV SWITHGEAR1

30

10

10

.5

.5

.3

.3

Relay1 - N
OC1
ABB
REF 542plus
CT Ratio 800:5
Normal Inverse
Pickup = 0.1 (0.05 - 40 xCT Sec)
Time Dial = 0.08
3x = 0.504 s, 5x = 0.342 s, 8x = 0.264 s

.1

.05

.03

.1

.05

.03

Relay1 - -LG
Relay10
G - LG

.01

.01
.5

10

30

50

100

300

500

Amps Bus4 (Nom. kV=6, Plot Ref. kV=6)

1K

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

GSUT Damage Curve


Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Ground

Seconds

Seconds

ABB
REF 610
CT Ratio 800:5
IEC - Normal Inverse
Pickup = 10 (1 - 100 xCT Sec)
Time Dial = 0.1
3x = 0.63 s, 5x = 0.428 s, 8x = 0.33 s

CB11
Open

Relay6

I>

Cable4
1-3/C 150

Bus8

Cranking Motor 1
450 kW

CB11
Open

Relay6

I>

Cable4
1-3/C 150

Bus8

Cranking Motor 1
450 kW

Amps X 100 6 kV SWITHGEAR2 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K
1K

1K

Relay5 - P
OC1

500

Relay5

ABB - New
REM 615
CT Ratio 200:1
IEEE - Long Time Inverse
Pickup = 0.7 (0.1 - 5 xCT Sec)
Time Dial = 2.2
3x = 8.92 s, 5x = 6.19 s, 8x = 4.86 s
Inst = 5 (0.1 - 40 xCT Sec)
Time Delay = 0.04 s

300

100

50

500

CB23

300

I>

Cable18

100

1-3/C 120
50

Bus26

30

30

Fuel Gas Compressor 2-Hot


10

10

Fuel Gas Compressor 2


1100 kW

.5

.5

.3

.3

Fuel Gas Compressor 2-80%


1100 KW

Fuel Gas Compressor 2-100%

.1

.1

1100 KW

Cable18
1 - 3/C 120 mm
Copper XLPE
Tc = 90C

.05
.03

.05
.03

Relay5 - 3P

.01
.5

10

30

50

100

300

500

1K

Amps X 100 6 kV SWITHGEAR2 (Nom. kV=6, Plot Ref. kV=6)


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

Fuel Gas Comp

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-03-2013
ABBGLOBAL
Base
Phase

3K

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

Stall = 12 sec

Amps 6 kV SWITHGEAR2 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K
1K

1K

500

500

CB23
Relay5

300

300

I>

Cable18

100

100

1-3/C 120
50

50

Bus26

30

10

10

Fuel Gas Compressor 2


1100 kW

.5

.5

Relay5 - N
OC1

.3

.3

ABB - New
REM 615
CT Ratio 200:1
Normal Inverse
Pickup = 0.075 (0.05 - 5 xCT Sec)
Time Dial = 0.05
3x = 0.315 s, 5x = 0.214 s, 8x = 0.165 s
Inst = 0.75 (0.05 - 40 xCT Sec)
Time Delay = 0.04 s

.1

.05

.1

.05

.03

.03
Relay5 - LG

.01
.5

10

30

50

100

300

500

1K

Amps 6 kV SWITHGEAR2 (Nom. kV=6, Plot Ref. kV=6)


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

Fuel Gas Comp

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-03-2013
ABBGLOBAL
Base
Ground

3K

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

30

Amps X 10 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)


.5

10

1K

30

50

100

300

500

1K

3K

5K

Relay3 - P
OC1

500

100

50

500

CB12

ABB - New
REM 615
CT Ratio 100:1
Extremely Inverse
Pickup = 0.45 (0.05 - 40 xCT Sec)
Time Dial = 1
3x = 10 s, 5x = 3.33 s, 8x = 1.27 s
Inst = 3 (0.1 - 40 xCT Sec)
Time Delay = 0.04 s

300

10K
1K

Relay3

300

I>

Cable7
1-3/C 120

100

Bus12

50

30

30

HRSG Feed Pump1

10

355 kW

HRSG Feed Pump1-Hot


Stall = 16 sec
1

HRSG Feed Pump1-85%


355 KW

.5

.5

.3

.3

Cable7
1 - 3/C 120 mm
Copper XLPE
Tc = 90C

.1

.1

.05

.05

.03

.03

HRSG Feed Pump1-100%


355 KW

Relay3 - 3P

.01
.5

10

30

50

100

300

500

1K

3K

5K

.01
10K

Amps X 10 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)ETAP Star 7.5.0C


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

HRSG Feed Pump

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-03-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

10

Amps 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

1K

500

10K
1K

500

CB12
Relay3

300

300

I>

Cable7
1-3/C 120

100

100

Bus12

50

50

30

30

HRSG Feed Pump1

10

355 kW

Relay3 - N
OC1
ABB - New
REM 615
CT Ratio 100:1
Normal Inverse
Pickup = 0.05 (0.05 - 5 xCT Sec)
Time Dial = 0.05
3x = 0.315 s, 5x = 0.214 s, 8x = 0.165 s
Inst = 0.45 (0.05 - 40 xCT Sec)
Time Delay = 0.04 s

.5
.3

.5
.3

.1

.1

.05

.05

.03

.03
Relay3 - LG

.01
.5

10

30

50

100

300

500

1K

Amps 6 kV SWITHGEAR1 (Nom. kV=6, Plot Ref. kV=6)


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

HRSG Feed Pump

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-03-2013
ABBGLOBAL
Base
Ground

3K

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

10

CB10
Relay4

I>

Cable1
1-3/C 120

Bus5

Main Sea Water Pump1


355 kW

CB10
Relay4

I>

Cable1
1-3/C 120

Bus5

Main Sea Water Pump1


355 kW

6 kV SWITHGEAR1

CB14

Relay2

Cable8
1-3/C 240

T2
3 MVA

Relay9

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

Relay9 - G
OC1

500

300

ABB
REF 615
CT Ratio 5000:5
IEC - Normal Inverse
Pickup = 10 (1 - 100 xCT Sec)
Time Dial = 0.26
3x = 1.64 s, 5x = 1.11 s, 8x = 0.857 s

100

500

6 kV SWITHGEAR1

CB14

300

Relay2

Cable8
1-3/C 240

T2
3 MVA

100

Relay9

50

30

30

10

10

.5

Relay2 - G
OC1

.5

.3

ABB
REF 615
CT Ratio 350:5
IEC - Normal Inverse
Pickup = 10 (1 - 100 xCT Sec)
Time Dial = 0.05
3x = 0.315 s, 5x = 0.214 s, 8x = 0.165 s
Inst = 80 (5 - 400 xCT Sec)
Time Delay = 0.04 s

.3

.1

.05

.1

.05

.03

.03

Relay2 - G - LG

Relay9 - G - LG

.01

.01
.5

10

30

50

100

300

500

1K

3K

5K

10K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ETAP Star 12.0.0C

ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

3 MVA Trafo

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Ground

Seconds

Seconds

50

Amps X 100 Bus26 (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

Relay5 - P
OC1

500

Relay14

300

100

500

ABB - New
REM 615
CT Ratio 200:1
IEEE - Long Time Inverse
Pickup = 0.7 (0.1 - 5 xCT Sec)
Time Dial = 2.2
3x = 8.92 s, 5x = 6.19 s, 8x = 4.86 s
Inst = 5 (0.1 - 40 xCT Sec)
Time Delay = 0.04 s

CB41

Open

300
CB23
Relay5

I>

Cable18

100

1-3/C 120

Bus26

50

50

30

30

Fuel Gas Compressor 2


1100 kW

10

Relay14 - P
OC1

ABB
REF 542plus
CT Ratio 800:5
Long Time Inverse
Pickup = 0.86 (0.05 - 40 xCT Sec)
Time Dial = 0.05
3x = 3 s, 5x = 1.5 s, 8x = 0.857 s

Fuel Gas Compressor 2-Hot

.5

.5

Fuel Gas Compressor 2-80%


.3

.3

Fuel Gas Compressor 2-100%


.1

.1

.05

.05

.03

.03

Relay14- -3P
Relay5
3P

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 100 Bus26 (Nom. kV=6, Plot Ref. kV=6)

Meghnaghat
Project:
Location:
Contract:
Engineer:
Filename:

3K

Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

Gas Compressor
Starting

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA

5K

07-10-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

10

Amps X 100 Existing SWGR (Nom. kV=6, Plot Ref. kV=6)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K
Relay16

Relay16 - P
OC1

500

I>

Siemens
7SJ551
CT Ratio 2000:5
Inst = 1.15 (1 - 10 xCT Sec)
Time Delay = 0.8 s

300

500

Existing SWGR

300

Relay15

I>

Cable27
2-3/C 240

100

100
Relay14

50

CB41

50

Open

6 kV SWITHGEAR1

30

30

Relay15 - P
Siemens
7SJ45
CT Ratio 600:5
IEC - Very Inverse
Pickup = 1.15 (0.5 - 4 xCT Sec)
Time Dial = 0.5
3x = 3.38 s, 5x = 1.69 s, 8x = 0.964 s
Inst = 3 (2 - 20 xCT Sec)
Time Delay = 0.4 s

10

.5

.5

Relay14 - P
OC1

.3

.3

ABB
REF 542plus
CT Ratio 800:5
Long Time Inverse
Pickup = 0.86 (0.05 - 40 xCT Sec)
Time Dial = 0.05
3x = 3 s, 5x = 1.5 s, 8x = 0.857 s
Inst = 2.25 (0.05 - 40 xCT Sec)
Time Delay = 0.4 s

.1

.05

.1

.05

.03

.03

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 100 Existing SWGR (Nom. kV=6, Plot Ref. kV=6)

Meghnaghat
Project:
Location:
Contract:
Engineer:
Filename:

3K

Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

Existing switchgear
Coord

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA

5K

07-10-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

10

Amps X 100 GTG - 1 MCC MAIN (Nom. kV=0.4, Plot Ref. kV=0.4)
.5

10

30

50

100

300

500

1K

3K

5K

1K

10K
1K

500

500
LOAD CENTRE 1

300

CB29

ABB SACE PR121


Frame = 1200 Plug = 800 Amps
LT Pickup = 1 (800 Amps)
LT Band = 12
ST Pickup = 5 (4000 Amps)
ST Band = 0.3 (I^x)t = OUT

100

50

Cable2

100

2-4/C 300

50

CB53
GTG - 1 MCC MAIN

30

30

10

10

CB53
ABB SACE PR112
Sensor = 400
LT Pickup = 1 (400 Amps)
LT Band = 12
ST Pickup = 6 (2400 Amps)
ST Band = 0.1 (I^x)t = OUT
Inst. Pickup = 15 (6000 Amps)

.5
.3

.5
.3

Cable2

.1

.1

.05

.05

.03

.03

.01
.5

10

30

50

100

300

500

1K

3K

Amps X 100 GTG - 1 MCC MAIN (Nom. kV=0.4, Plot Ref. kV=0.4)
ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

LC - GT MCC

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

300

CB29

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

500

500
LOAD CENTRE 1

CB34
300

300

ABB SACE PR121


Frame = 2000 Plug = 2000 Amps
LT Pickup = 1 (2000 Amps)
LT Band = 12
ST Pickup = 4 (8000 Amps)
ST Band = 0.4 (I^x)t = OUT

100

CB34

Cable11
3-4/C 300

100

50

50
CB44

30

30
Utility MCC1

10

10

CB44
3

ABB SACE PR121


Frame = 2000 Plug = 2000 Amps
LT Pickup = 0.75 (1500 Amps)
LT Band = 12
ST Pickup = 3 (6000 Amps)
ST Band = 0.3 (I^x)t = OUT

Cable11 - P

.5

.5

.3

.3

.1

.1

CB42
ABB SACE PR221 (T5)
Sensor = 400
LT Pickup = 1 (400 Amps)
LT Band = 12s
ST Pickup = 5.5 (2200 Amps)
ST Band = 0.25s (I^x)t = IN
Override = 5000 Amps

.05
.03

.01
.5

10

.05
CB34 - 3P
.03

CB44 - 3P
.01
30

50

100

300

500

1K

3K

5K

10K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ETAP Star 12.0.0C

ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

LC - Utility MCC ACDB

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KD

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

CB42

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K
1K

1K

500

500

Relay9

300

300

CB16
100

100

LOAD CENTRE 1
50

50

30

30

CB34

CB34
ABB SACE PR121
Frame = 2000 Plug = 2000 Amps
LT Pickup = 1 (2000 Amps)
LT Band = 12
ST Pickup = 4 (8000 Amps)
ST Band = 0.4 (I^x)t = OUT

10

.5

.5

Relay9 - P
OC1

.3

.3

ABB
REF 615
CT Ratio 5000:5
IEC - Extremely Inverse
Pickup = 0.9 (0.3 - 5 xCT Sec)
Time Dial = 0.68
3x = 6.8 s, 5x = 2.27 s, 8x = 0.863 s

.1

.05

.1
Relay9 - 3P
.05
CB34 - 3P

.03

.03

CB16 - 3P

CB16
.01
.5

10

30

50

100

300

500

1K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

LC IC & OG

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

3K

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

10

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

500

500

CB33

300

300

100

100

Cable12

CEP-Hot

50

50

2-3/C 240

Stall = 12 sec
30

30

CEP-80%

Bus14

10

10

CEP
200 kW

CEP-100%

200 KW
.5

.5

Cable12 - P

.3

.3

CB33
ABB SACE PR121
Frame = 800 Plug = 800 Amps
LT Pickup = 0.5 (400 Amps)
LT Band = 12
Inst. Pickup = 4 (3200 Amps)

.1

.05

.1

.05

.03

.03
CB33 - 3P

.01

.01
.5

10

30

50

100

300

500

1K

3K

5K

10K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ETAP Star 12.0.0C

ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

CEP.

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

200 KW

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

500

500

CB33

300

300

100

100

Cable12
50

50

2-3/C 240

30

30

10

10

CEP
200 kW

CB33
ABB SACE PR121
Frame = 800 Plug = 800 Amps
Ground Pickup = 0.2 (160 Amps)
Ground Band = 0.1 (I^x)t = OUT

.5

.5

.3

.3

.1

.1

.05

.05

.03

.03
CB33 - LG

.01

.01
.5

10

30

50

100

300

500

1K

3K

5K

10K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ETAP Star 12.0.0C

ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

CEP.

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Ground

Seconds

Seconds

Bus14

Amps X 100 Utility MCC1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

1K

Relay7 - P
OC1

500

Utility MCC1

100

50

500

CB42

AREVA
P111
CT Ratio 400:5
IEC - Long Time Inverse
Pickup = 1 (0.1 - 25 xCT Sec)
Time Dial = 0.45
3x = 27 s, 5x = 13.5 s, 8x = 7.71 s
Inst = 5 (0.5 - 40 xCT Sec)
Time Delay = 0.2 s

300

10K
1K

300
Cable31
3-1/C 120

100

50

Relay7

I>

30

30

ACDB

10

10

CB42
3

ABB SACE PR221 (T5)


Sensor = 400
LT Pickup = 1 (400 Amps)
LT Band = 12s
ST Pickup = 5.5 (2200 Amps)
ST Band = 0.25s (I^x)t = IN
Override = 5000 Amps

.5
.3

ABB
T3
Size = 150 Amps
Thermal Trip = Fixed
Magnetic Trip = Fixed

.1

.5
.3

Cable31

CB43

.1

.05

.05

.03

.03

.01
.5

10

30

50

100

300

500

1K

3K

Amps X 100 Utility MCC1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

Utility MCC - ACDB

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.OTI

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

5K

.01
10K

ETAP Star 7.5.0C

Seconds

Seconds

CB43

Amps X 100 STG MCC (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

CB50
500

500

ABB SACE PR121


Frame = 800 Plug = 800 Amps
LT Pickup = 0.4 (320 Amps)
LT Band = 48
ST Pickup = 5 (4000 Amps)
ST Band = 0.2 (I^x)t = OUT

300

Essential MCC

300
CB50

100

100

Cable42
1-4/C 120

50

50
CB20
STG MCC

30

30

CB28

10

10

ABB SACE PR221 (T4)


Sensor = 250
LT Pickup = 1 (250 Amps)
LT Band = 12s
ST Pickup = 7.5 (1875 Amps)
ST Band = 0.1s (I^x)t = IN
Override = 3000 Amps

.5

.5

.3

.3

Cable42 - P
CB28
ABB
T3
Size = 125 Amps
Thermal Trip = Fixed
Magnetic Trip = Fixed

.1

.05

.1

.05

.03

.03

CB50 - 3P

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 100 STG MCC (Nom. kV=0.4, Plot Ref. kV=0.4)

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

Ess MCC - STG MCC


Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

CB20

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K

LOAD CENTRE 1

500

500
LOAD CENTRE 1

300

300
CB31

Cable5
2-4/C 300

100

100
CB51
Essential MCC

50

50

30

30

Cable5 - P
2 - 4/C 300 mm
Copper XLPE
Tc = 90C
Plotted - 2 x 4/C 300 mm

10

Test PR121 New


Frame = 1000 Plug = 1000 Amps
LT Pickup = 1 (1000 Amps)
LT Band = 36
ST Pickup = 6 (6000 Amps)
ST Band = 0.4 (I^x)t = OUT

.5

.5

.3

.3

CB51

.1

.1

ABB SACE PR121


Frame = 1200 Plug = 1200 Amps
LT Pickup = 0.85 (1020 Amps)
LT Band = 24
ST Pickup = 5 (6000 Amps)
ST Band = 0.3 (I^x)t = OUT

.05

.03

.05

.03

CB51CB31
- 3P - 3P

.01

.01
.5

10

30

50

100

300

500

1K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)

3K

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination\rc\KDL LV.

Date:
SN:
Rev:
Fault:

10K

ETAP Star 12.0.0C

LC - Essential MCC
Project:
Location:
Contract:
Engineer:
Filename:

5K

06-14-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

CB31
5

10

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


.5

10

30

50

100

300

500

1K

3K

5K

10K

1K

1K
LOAD CENTRE 1

CB49

500

500

Test SACE PR221 (T2)


Sensor = 160
ST Pickup = 6.5 (1040 Amps)
ST Band = 0.25s (I^x)t = IN
Override = 2000 Amps

300

CB32

300

Cable10
1-4/C 120

100

100
CB49
HRSG MCC 1

50

50

30

30

CB32

10

ABB SACE PR121


Frame = 800 Plug = 400 Amps
LT Pickup = 0.4 (160 Amps)
LT Band = 48
ST Pickup = 10 (4000 Amps)
ST Band = 0.4 (I^x)t = OUT

5
3

5
3

.5

.5

.3

.3

.1

.1

.05

.05

CB32 - 3P

.03

.03
CB49 - 3P

.01

.01
.5

10

30

50

100

300

500

1K

3K

5K

10K

Amps X 100 LOAD CENTRE 1 (Nom. kV=0.4, Plot Ref. kV=0.4)


ETAP Star 12.0.0C

ABB Global
Project:
Location:
Contract:
Engineer:
Filename:

HRSG

120 MW Combine Cycle GT Power


CILEGON BANTEN INDONESIA
Selvakumar S
C:\0 Projects\KDL\Relay Coordination

Date:
SN:
Rev:
Fault:

04-05-2013
ABBGLOBAL
Base
Phase

Seconds

Seconds

10

ANNEXURE 6:
Restricted Earth Fault Protection,
Synchronism Check and Under
Voltage Protection

RestrictedEarthFaultProtection:
Sl.No

Parameter

Values

Unit

SetValue

ReferencenominalCurrent

1100000

800

Unbiasedregionthreshold

0.050.5

Ir

0.1

Unbiasedregionlimit

0.011

Ir

0.5

Slightlybiasedregionslope

0.012

0.7

Slightlybiasedregionslope

0.012

Ir

1.25

Heavilybiasedregionslope

0.11

Relayoperateangle

60180

Deg

75

Time

0.04100

0.04

SynchronismCheck:
Sl.No

Parameter

Values

Unit

SetValue

DeltaVoltage

0.020.4

Pu

0.05

DeltaPhase

550

Deg

10

Time

0.21000

100

Sl.No

Parameter

Values

Unit

SetValue

LowestVoltage=0used

StartValueU<,U<<

0.11.2

pu

0.8

Time

4030000

ms

5000

StartValueU<,U<<<

0.11.2

pu

0.7

Time

1530000

ms

2000

UnderVoltage

Note:
SettingsforundervoltageandSynchronismcheckarebasedonourexperience.Settingshallbe
modifiedtomeetthelocalregulationsandoperationalrequirements.

You might also like