Spare parts

Contractor B shall provide with his tender, for the equipment in Contract B, a complete
priced list of spare parts, in Schedule HH. The list shall be developed on an estimated usage basis and
supporting data from existing plants shall be provided to substantiate the spares holding and usage
proposed.
The priced list of spares shall include a recommended stockholding to cover all initial
inventory, planned maintenance and strategic reserves up to and including the first 2 years of operation
from plant takeover.
Contractor B shall provide all the commissioning consumables and spares up to take over
of the works.

4.10

Special tools and lifting devices

Contractor B shall supply, for the equipment in Contract B, a complete set of any special
tools and other equipment necessary for the dismantling, work storage, re-erection and adjustment of
any part of the plant. Tools shall be provided in new condition, adequately labelled to their use and
contained in stout and suitable padlocked boxes.
Any special lifting devices/slings required shall be provided and clearly marked by
embossed labels which show safe working loads. Test Certificates shall be provided where applicable.
Suitable lifting equipment shall be provided to facilitate removal and maintenance of plant
and equipment. Lifting devices shall be designed in accordance with the latest editions of the relevant
ISO standard or equivalent. All electrical and mechanical functions shall be tested before despatch
from the manufacturers works. Operational and overload tests shall be carried out on site.
Suitable lay down areas and methods of retrieving the equipment should be included to
support the integrated approach to the crane facilities.

4.11

Warranty engineer

A warranty engineer shall be located on site for a period of one (1) year following the date
of Takeover to cover the equipment in Contract B. The warranty engineer shall have not less than eight
years experience of power plants similar to the Facility and shall act proactively to ensure the best
performance and availability of the plant is achieved. A CV for the proposed engineer shall be
submitted for approval prior to him taking up the appointment.
The Contract shall include for all travelling, accommodation and subsistence costs of the
engineer and for his replacement by a similarly experienced engineer during periods of leave or longterm sickness. The replacement engineer shall be to approval. Such approval shall not be
unreasonably withheld.
The warranty engineer shall be available on site between 0800 1700 hours Saturday to
Thursday, and available for callout duty outside of these hours.

Page 39 of 330

PTS # 06EG902 - PROJECT-B, VOL-2


CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT

The warranty engineering shall be responsible for the following throughout the warranty
period:
i.

Ensuring that the O&M operator is operating and maintaining the entire plant in
accordance with the manufacturers instructions, and notifying the Owner (SEC)
and the O&M operator of any shortcomings.

ii.

Providing technical advice and support to the O&M operator.

iii.

Monitoring the performance and availability of the plant.

iv.

Assisting with troubleshooting.

v.

Acting as liaison with Contractor Bs head office for the clearance of any defects
existing on Takeover or occurring during the warranty period, to ensure that they
are cleared promptly.

The Owner (SEC) will monitor the performance of the warranty engineer. Should his
performance be unsatisfactory, Contractor B shall provide a replacement engineer to the satisfaction of
the Owner (SEC).

Page 40 of 330

PTS # 06EG902 - PROJECT-B, VOL-2


CONSTRUCTION OF QURAYYAH OPEN CYCLE POWER PLANT