Professional Documents
Culture Documents
SCHEDULE"A"
CONTRACT NO.
Title
16.
A-19
15.6
A-19
Changes
A-20
CHANGE ORDER
A-20
16.2
A-20
16.3
A-21
16.4
A-21
16.5
A-21
A-21
A-21
A-22
A-22
"16.6
16.7
17.1
17.2
A-22
17.3
A-22
17.3.1
A-22
17.3.2
A-23
A-22
17.4
A-23
17.5
17.6
A-25
A-25
17.7
17.8
17.9
A-25
17.7.1
A-25
17.7.2
A-25
17.7.3
A-26
A-26
17.8.1
A-26
17.8.2
17.8.3
A-26
A-27
18.
Page
15.5
16.1
17.
30621090/00
A-27
A-27
A-28
A-28
18.1
Warranty Coverage
A-28
18.2
Warranty Duration
A-29
18.2.1
18.2.2
A-29
A-31
A-32
18.3
18.4
A-33
18.5
A-33
18.6
A-33
TC-4
Construction of Qurayyah Open Cycle Power Plant- Schedule A
---~---~------
-------------------------
9- ~..)4Slt
~.!1~ :a.s..,.Mt
CONTRACT NO.
SCHEDULE "A"
17.7.3
30621090/00
Final Acceptance of each Power Plant Unit (Power Plant Unit Final
Acceptance) shall be achieved when:
17.8.2
17.8.1.1
17.8.1.2
17.8.1.3
17.8.1.4
17.8.1.5
17.8.1.6
17.8.2.2
17.8.2.3
A-26
SCHEDULE "A"
17.11
CONTRACT NO.
30621090/00
The SELLER's warranties and remedy of defects for the EQUIPMENT it shall provide and
which CONTRACTOR shall install, test and commission under this CONTRACT are set
forth in the PURCHASE CONTRACT. This Paragraph 18 of Schedule "A" describes the
CONTRACTOR's warranty obligations with respect to the materials and equipment it
shall provide and the WORK it shall perform under this CONTRACT.
18.1
Warrantv Coverage
CONTRACTOR warrants:
18.1.1
18.1.2
18.1.3
that the materials for the PROJECT shall be merchantable, fit for the
purposes of generating electric power when operated in
A-28
~~i
;: ~ ..... :..:!
CONTRACT NO.
SCHEDULE "A"
30621090/00
18.2
18.1.4
that the fabrication of all parts, systems and units of the PROJECT
shall be free of defects in workmanship and in accordance with the
designs, drawings, and specifications prepared by CONTRACTOR and
with good and efficient fabrication and craft practices, and
18.1.5
Warranty Duration
18.2.1
18.2.1.1
18.2.1.2
18.2.1.3
18.2.1.4
A-29
g
~!
_ _ _ _ _ _ _ r.!~
/::_:;.J
SCHEDULE"A"
CONTRACT NO.
30621090/00
18.2.1.6
..
18.2.1.8
18.2.1.9
A-30
Construction of Qurayyah Open Cycle Power Plant- Schedule A
=-
~~
----------~------~
9-
SCHEDULE "A"
CONTRACT NO.
30621090/00
18.2.2
18.2.2.2
18.2.2.3
9-~~~~~~;as~,
SCHEDULE "A"
CONTRACT NO.
30621090/00
reinstall with new element, any part/system of the NonPower Plant Facility which, under the specified use and
proper maintenance by COMPANY, proved defective
during the warranty period, provided COMPANY gives
CONTRACTOR prompt written notice and satisfactory
proof of such defect.
18.2.2.4
18.2.2.5
:.::
,.
18.3
18.2.2.6
18.2.2.7
18.2.2.8
A-32
;,_
;:..
~-
r.-~':
".::.::.:.:
9-l:1~ ~~~;as~,
Saudi Electricity Company
SCHEDULE "A"
CONTRACT NO.
30621090/00
18.5
18.6
Subcontracts
19.1
Any subcontract for the performance of any portion of the WORK shall be
procured only after CONTRACTOR has received written authorization from
COMPANY to subcontract that portion of the WORK. If not already
accomplished prior to the effective date of the CONTRACT, then promptly
thereafter, CONTRACTOR shaH submit to COMPANY REPRESENTATIVE for
COMPANY's approval, the CONTRACTOR's subcontracting plan. This
subcontracting plan shall specifically identify those portions of the WORK that
CONTRACTOR proposes to subcontract. In procuring subcontracts/
CONTRACTOR shall select SUBCONTRACTOR solely on the basis of financial and
technical considerations.
This Paragraph shall be limited to major subcontracts and SUBCONTRACTORS
included in CONTRACTOR's list of major subcontractors which shall be deemed
approved by the COMPANY with the effectiveness of the CONTRACT.
19.2
19.2.1
A-33
Construction of Qurayyah Open Cycle Power Plant- Schedule A
~:;
'}.~
--'--'-------~
41-\.;1~ ~~~~:as~,
CONTRACT NO.
SCHEDULE "A"
20.9
30621090/00
Consequential Damages
CONTRACTOR, its agents and SUBCONTRACTORS, shall not be liable in any
event to COMPANY nor shall COMPANY be liable to CONTRACTOR, Its agents
and SUBCONTRACTORS, for any indirect, special, consequential losses or
damages including, but not limited to, loss of profit or products, whether such
liability is based, or claimed to be based upon any breach of either party's
obligations under the CONTRACT, or whether such liability is based, or claimed
to be based, upon any negligent act or omission of a party, its personnel,
agents, appointed representatives or SUBCONTRACTOR.
20.10
Maxjmum liability
Except as provided in Paragraph 20.7 and notwithstanding anything contained
elsewhere in this CONTRACT to the contrary, the total liability of CONTRACTOR
and his SUBCONTRACTORS to COMPANY under this CONTRACT shall not
exceed the amount of the CONTRACT Price set forth in Paragraph 1.1 of
Schedule "C" as may be modified from time to time. All liabilities under this
CONTRACT shall terminate four (4) years from Final Acceptance of the WORK
except for the warranty liabilities contained in Paragraphs 18.3 and 18.6 of
Schedule "A".
21.
Insurance
21.1
Coverage
Comprehensive General Uability Insurance coverage with limits
of no less than twenty million Saudi Riyals (SR 20,000,000)
per occurrence for bodily injury, death or property damage
during the performance of the WORK. CONTRACTOR represents
and warrants that the aforesaid insurance covers, without
limitation, loss of, or damage to COMPANY's other property for
which CONTRACTOR is responsible pursuant to Paragraph 20.5 of
this Schedule "A".
b)
Term
CONTRACTOR shall carry and maintain this insurance in full force
at all times from the effective date of the CONTRACT through the
Preliminary Acceptance of all the PROJECT PORTIONS and
thereafter during the Warranty Period, and until CONTRACTOR has
fully demobilized from the WORK SITE.
c)
COMPANY as Additional
A-37
Construction of Qurayyah Open Cycle Power Plant- Schedule A
CONTRACT NO.
SCHEDULE "A"
30621090/00
Coverage
CONTRACTOR's All Risk Insurance (CAR) coverage for the entire
PROJECT. The sum insured per occurrence shall be no less than
the total CONTRACT Price or replacement cost of the PROJECT
and the cost of removing debris following an insured loss.
b)
c)
Term
CONTRACTOR shall carry and maintain this. insurance in full force
at all times from the effective date of the CONTRACT through the
Preliminary Acceptance of all the PROJECT PORTIONS and
thereafter during the Warranty Period, and until CONTRACTOR has
fully demobilized from the WORK SITE.
d)
COMPANY
as Additional
Professionallndemnitv Insurance
CONTRACTOR shall effect and maintain [a single project] Professional
Indemnity insurance from the effective date of this CONTRACT until the
date three (3) years from Final Acceptance of the WORK in the names
of the CONTRACTOR, its SUBCONTRACTORS and consultants to
indemnify them in respect of their legal liability for claims made against
them during the period of insurance for any negligent act, error or
omission by the CONTRACTOR, its SUBCONTRACTORS and consultants
in the conduct and execution of their professional activities and duties
relating the design and/or supervision of installation and/or testing and
commissioning of the WORK. This insurance shall be in the amount of
SR: 2,000,000 in respect of each claim and SR: 20,000,000 in the
aggregate for all claims during the period of insurance, and shall be
subject to worldwide jurisdiction. The deductible shall not exceed SR:
25,000 in respect of each claim or such other amount, which the
COMPANY, acting reasonably, may approve in writing.
21.1.4
A-38
Construction of Qurayyah Open Cycle Power Plant- Schedule A
---------------------
-----------" -----~-~='-:'*
~,,f:"
~]
~~
~
~~~~jj~,~~
Saudi Electricity Company
SCHEDULE "A"
CONTRACT NO.
30621090/00
final certificates from the Directorate of Zakah and Income Tax as well as the
General Organization of Social Insurance (GOSI) which confirm that all
applicable Zakah and CONTRACTOR income tax obligations have been paid by
CONTRACTOR through the previous Hijra year period.
These certificates shalt be delivered to:
The Manager
Controller's Department
Eastern Operating Area
Saudi Electricity Company
Room 2-215E, SEC-EOA Headquarters
P. 0. Box 5190, Dammam 31422
Kingdom of Saudi Arabia
31.
Taxes
31.1
Payment of Taxes
Withholding Tax
Bank Guarantee
32.1
Jo.z:?;r
A-49
Construction of Qurayyah Open Cycle Power Plant- Schedule A
f.
'
. ~f);(~::~~;;;ff:g~g:
fSC)
f:_,\';.}l
~~K.;..
~~
SCHEDULE"A"
CONTRACT NO.
30621090/00
33.
CONTRACTOR shall ensure that Its Commercial Registration (CR) or License is valid
throughout the entire duration of the CONTRACT and any extension(s) thereof. In the
event that its CR or License expires during the duration of the CONTRACT and any
extenslon(s) thereof, CONTRACTOR shafl submit to COMPANY a copy of its application
form or proof for renewal prior to the expiration of its CR or License and shall submit
its new or renewed CR or License within forty-five (45) days after the expiration of its
previous CR or License. Failure by CONTRACTOR to submit such document may cause
COMPANY to withhold its invoices until its new or renewed CR or License is submitted
to COMPANY.
34.
CONTBACT language
General Provisions
36.
CONTRACTOR warrants that the WORK does not infringe any patent rights, copyrights,
trademarks, or trade secrets owned or controlled by any Third Party, either in the
country of manufacture or use. CONTRACTOR agrees to defend, indemnify and hold
COMPANY harmless against any and all liability, loss or expense arising out of patent,
copyright, trademark infringement or trade secret misappropriation claim relating to
the WORK.
A-50
Construction of Qurayyah Open Cycle Power Plant- Schedule A
_________ I
2.
2.1
General
This Specification calls for the erection of gas turbine power plant and associated
equipment and the design and supply of supporting services which shall initially be installed in open
cycle configuration with the intention to convert to combined cycle at a later date. The design shall be
modern, well proven, safe, economically attractive both in capital cost and running cost and offering a
high availability with low forced outage rate. The plant shall be fully automated and require minimum
operator intervention for normal operation. Contractor B shall comply with the Specification unless
compliance would for any reason put at risk safety, reliability and economy due to deviation from
standard practice of Contractor B. However, the intent of the Specification shall always be complied
with.
Any deviations from the Specification shall be clearly identified in Schedule FF, which shall
be completed and returned as part of the Tender.
Any new and additional equipment supplied under this Contract shall be designed and
selected to ensure high reliability and availability of the complete plant with low forced outage rates and
minimal maintenance over the lifetime of the power station, which shall be defined as 40 years.
An appropriate level of redundancy shall be included in each new system; the Works shall
be designed so that no single auxiliary plant failure shall result in the total loss of the unit generating
capability. In this context, it is required that with agreed exceptions, all unit auxiliaries will be provided
with at least one installed spare (N+1). For the station auxiliaries, no single equipment failure shall
result in any loss of station generating capability.
Prototype plant will not be acceptable, and plant that is offered with limited operating
experience must be fully supported by manufacturers warranties and indemnities.
2.2
Unit rating
The gas turbine units, rated at the site ambient condition given in Schedule AA, shall meet
the nominal power requirement range of 1900 MW 80 MW open cycle and shall be installed to
provide 500 MW available generation by 1 June 2008 and further 350/400 MW available by 1 August
2008, and with a further 1016 MW, 40 MW open cycle plant to be available for generation by 1 June
2009. The CIF delivery dates for the gas turbine units, generator transformers, unit transformers and
IPBs shall be as stated in Schedule BB.
The gas turbine generators shall be suitable for outdoor installation and conversion to
combined cycle operation 3+1 configuration at a later date.
The guarantee and warranty for the gas turbines and associated equipment shall be the
responsibility of the gas turbine generator supplier Contractor A without exception. The guarantee and
warranty for any new and additional equipment supplied under this Contract shall be the responsibility
of Contractor B and in the event that any other requirements of this Specification are in conflict with
Contractor Bs ability to meet the performance requirements contained in Schedule CC1, such
exceptions shall be identified. It is the intent that the gas turbine supplier supplies his standard
modular gas turbine design to the maximum extent possible.
Page 3 of 330
4.9
Spare parts
Contractor B shall provide with his tender, for the equipment in Contract B, a complete
priced list of spare parts, in Schedule HH. The list shall be developed on an estimated usage basis and
supporting data from existing plants shall be provided to substantiate the spares holding and usage
proposed.
The priced list of spares shall include a recommended stockholding to cover all initial
inventory, planned maintenance and strategic reserves up to and including the first 2 years of operation
from plant takeover.
Contractor B shall provide all the commissioning consumables and spares up to take over
of the works.
4.10
Contractor B shall supply, for the equipment in Contract B, a complete set of any special
tools and other equipment necessary for the dismantling, work storage, re-erection and adjustment of
any part of the plant. Tools shall be provided in new condition, adequately labelled to their use and
contained in stout and suitable padlocked boxes.
Any special lifting devices/slings required shall be provided and clearly marked by
embossed labels which show safe working loads. Test Certificates shall be provided where applicable.
Suitable lifting equipment shall be provided to facilitate removal and maintenance of plant
and equipment. Lifting devices shall be designed in accordance with the latest editions of the relevant
ISO standard or equivalent. All electrical and mechanical functions shall be tested before despatch
from the manufacturers works. Operational and overload tests shall be carried out on site.
Suitable lay down areas and methods of retrieving the equipment should be included to
support the integrated approach to the crane facilities.
4.11
Warranty engineer
A warranty engineer shall be located on site for a period of one (1) year following the date
of Takeover to cover the equipment in Contract B. The warranty engineer shall have not less than eight
years experience of power plants similar to the Facility and shall act proactively to ensure the best
performance and availability of the plant is achieved. A CV for the proposed engineer shall be
submitted for approval prior to him taking up the appointment.
The Contract shall include for all travelling, accommodation and subsistence costs of the
engineer and for his replacement by a similarly experienced engineer during periods of leave or longterm sickness. The replacement engineer shall be to approval. Such approval shall not be
unreasonably withheld.
The warranty engineer shall be available on site between 0800 1700 hours Saturday to
Thursday, and available for callout duty outside of these hours.
Page 39 of 330
The warranty engineering shall be responsible for the following throughout the warranty
period:
i.
Ensuring that the O&M operator is operating and maintaining the entire plant in
accordance with the manufacturers instructions, and notifying the Owner (SEC)
and the O&M operator of any shortcomings.
ii.
iii.
iv.
v.
Acting as liaison with Contractor Bs head office for the clearance of any defects
existing on Takeover or occurring during the warranty period, to ensure that they
are cleared promptly.
The Owner (SEC) will monitor the performance of the warranty engineer. Should his
performance be unsatisfactory, Contractor B shall provide a replacement engineer to the satisfaction of
the Owner (SEC).
Page 40 of 330
s.
t.
Separating funnels.
u. Volumetric flasks.
v.
Reagent bottle.
w. Funnels.
6.4.8.5
x.
y.
Reagents
A complete listing of all reagents required for the analytical equipment, reagents for manual
analysis, standard reference solutions, and others required for a complete functioning laboratory shall
be provided for Owner (SEC) review. The reagents shall be of the required purity for the instruments
and as required by ASTM test methods. The listing shall include the reagent name, and quantity
recommended. Sufficient reagents shall be furnished for 2 years of operation after the warranty period.
Contractor B shall advise the Owner (SEC) of reagents with shelf lives shorter than the warranty period
plus 2 year period.
6.4.8.6
Ancillary equipment
Analytical balance
b)
Electronic balance
c)
Calibration masses
d)
e)
f)
Balance desiccators
g)
Centrifuge, oil
h)
Muffle furnace
i)
j)
Three-beam balance
k)
6.4.8.8
Equipment furnished shall be provided with all required accessories and spare parts
sufficient for 2 years of operation after the warranty period.
6.4.9
A site effluent disposal system for 15 gas turbine open cycle configuration is required to
ensure that all potentially contaminated wastes generated by the construction, operation and
maintenance of the power station shall be controlled in accordance with World Bank guidelines and
local legislation. This layout and arrangement of the waste water system shall take into account the
requirement to extend the system for combined cycle conversion.
Effluent from the drains of the laboratory, battery room, plant and chemical dosing drains
shall also be suitably treated.
Surface water with the potential of oil contamination shall be directed to an oil/water
separator prior to discharge. All waste oil shall be collected for off-site disposal.
Gas turbine compressor wash effluent shall be segregated and stored at a suitable location
for off-site disposal.
Sampling and instrumentation shall be included in the final discharge to ensure compliance
with the requirements of relevant legislation. As a minimum, this shall include equipment to measure
flow, temperature and pH. Provision to take a manual sample shall be provided. Discharge of
wastewater outside agreed limits shall be prevented by the control system.
For Qurayyah OCGT plant no discharge sewer is available, the final effluent disposal shall
be routed to an evaporation pond. Two 100 per cent evaporation ponds shall be provided for the
OCGT plant installation and the proposed site layout should take into account the requirement to
construction additional evaporation pond(s) for the combined cycle plant conversion. Details of the
proposed discharge system shall be provided within the Tender.
For further details of the site waste water systems, refer to Section 9 of this Specification.
6.4.9.1
A packaged sewage treatment plant shall be provided to cater for the total foul water
treatment requirements of the station, with adequate margins, under all conditions of operation. The
plant shall be complete with sanitary drainage piping, manholes and grease traps required for
conveying sewage, comminutor and bar screen, pre-engineered activated sludge modules, chlorination
equipment, treated sewage holding facility, treated sewage transfer pump sets, interconnecting piping
valves and supports, associated instruments and controls, associated electrical work, associated civil
work and all tanks shall be fitted with access ladders, platforms, vents and access ports. Level and
contents gauges shall be located for operational convenience.
The plant shall be capable of treating 300 litres per day of raw sewage per person during
normal operation together with a provision for peak demand at 2.5 times normal operational flow.
8.
8.1
Introduction
This Section describes the technical requirements for the supply and installation of
instrumentation and control (I&C) for the open cycle power plant. All I&C equipment necessary to allow
the safe and efficient operation of the power plant shall be supplied, installed, commissioned and
tested.
Gas turbine generators (GTGs) and ancillary equipment, a hydrogen plant and ancillary
equipment and a CEMS system together with all associated I&C equipment and systems will be
supplied under a separate contact by Contractor A. Contractor B will be responsible for interfacing to
and/or integrating these I&C systems into the DCS and other control/monitoring systems being supplied
to provide an integrated system for the control and monitoring of the power plant.
The DCS will provide control, monitoring, alarming, trending, logging, archiving and data
acquisition and storage for the gas turbines and associated equipment for each combined cycle block.
A consistent control, instrumentation and data acquisition philosophy shall be applied
throughout the power plant. The objective shall be to standardize all equipment, wherever possible,
throughout the power plant in order to rationalize operation, maintenance and reduce spare parts. In
general, all equipment shall be of modern compact design, incorporating proven technology and
supplied from one composite range as marketed by a reputable international manufacturer. The DCS
Vendor shall be from a short list of reputed manufacturers approved by SEC.
The hardware and software for DCS shall be the latest available at the time of system
installation. The latest system software version shall be made available for all units prior to the
completion of warranty period so as to have an identical and latest software version for all systems of
the plant.
Contractor B shall be responsible for liaising with Contractor A and Owner (SEC) to obtain
all data and information necessary to allow for the design, build and commission of his I&C systems,
DCS and interfaces required to connect to Contractor As equipment and SEC existing equipment.
8.2
Scope of supply
The extent of supply described shall be the minimum necessary to achieve the required
objectives and shall consist of, as a minimum, the following:
a.
Complete control, protection and monitoring systems for the plant being provided
including the fuel systems, gas detection, fire detection, common services and
auxiliary equipment.
b.
Interfaces to and integration into the DCS and other control and monitoring systems
of equipment provided by Contractor A.
10.6
Non-conformances
The witness of any inspection and tests by the Engineer/Owner (SEC) of any components
or lots thereof does not relieve Contractor B of any responsibility whatever regarding defects or other
failures which may be found before the end of the warranty period.
10.7
At the end of each visit to a manufacturer to carry out quality control activity, the Engineers
Representative will complete a Quality Control Record and hand one copy to a responsible
representative of the Manufacturer.
The Quality Control Record (QCR) will identify the item inspected, the stage of
manufacture, and the nature of the QC carried out, and will list all points which require remedial action
by the manufacturer, before the subject item can be released.
When each item of equipment is ready for despatch from the place of manufacture and the
Engineer/Owner (SEC) has verified compliance with specified requirements up to that point, a Quality
Control Certificate will be issued to Contractor B.
The Quality Control Certificate (QCC) will identify the item to which it applies and will
release that item from the Engineers control only. The QCC does not constitute any form of
acceptance of the item by either the Engineer or the Owner (SEC).
Contractor B shall provide a Certificate of Conformance confirming compliance with the
Contract requirements and as detailed in the manufacturing record data book.
Sets of all test records, test certificates and performance curves, whether or not they have
been witnessed by the Engineer, shall be supplied for all tests carried out in accordance with the
provisions of this Contract.
Sets of all test certificates shall be endorsed with sufficient information to identify the
material or equipment to which the certificates refer, and shall carry in the top right hand corner the
following reference:
Owners name
Project title
Engineers reference number.
All test documentation shall be in the English language.
No materials or equipment shall be shipped to the site until all tests, analysis and
inspections have been made and Contractor B's Certificate of Conformance has been reviewed and
released by the Engineer/Owner (SEC) or unless otherwise agreed by the Engineer/Owner (SEC)
10.8